11
Reliability Policy Issues Reliability Policy Issues Committee Report to Members – Committee Report to Members –
2006 Annual Meeting2006 Annual Meeting
Presented by:Presented by:
Scott A. GuttingScott A. Gutting
RPIC ChairRPIC Chair
April 2006April 2006
Key Activities and Key Activities and AccomplishmentsAccomplishments
22
RPIC MembersRPIC Members
AESO – Diana PommenAESO – Diana Pommen PG&E – Kevin DassoPG&E – Kevin Dasso
ACC - Jerry SmithACC - Jerry Smith PSC – Robin KittelPSC – Robin Kittel
BPAT - Vickie VanZandtBPAT - Vickie VanZandt Mariner Consulting – John Mariner Consulting – John
StoutStout
CISO - Armie PerezCISO - Armie Perez REI – John MeyerREI – John Meyer
UAE - Scott GuttingUAE - Scott Gutting SCE – Gary TarpleeSCE – Gary Tarplee
SRP – David Areghini SRP – David Areghini IPUC - Marsha SmithIPUC - Marsha Smith
PAC - Mark MaherPAC - Mark Maher TANC – Richard FerreiraTANC – Richard Ferreira
NAD*- Jananne SharplessNAD*- Jananne Sharpless TSGT – Ken AndersonTSGT – Ken Anderson
NAD*- Tim NewtonNAD*- Tim Newton UCCS – Nancy KellyUCCS – Nancy Kelly
NMPRC - Prasad PotturiNMPRC - Prasad Potturi WECC – Louise McCarrenWECC – Louise McCarren
33
Key Activities and Key Activities and AccomplishmentsAccomplishments
• Top “10” RPIC Issues for 2005/06Top “10” RPIC Issues for 2005/06
• Response to WAG Requests of WECCResponse to WAG Requests of WECC
• Data Sharing & Confidentiality PoliciesData Sharing & Confidentiality Policies
• Transmission Expansion Planning EffortsTransmission Expansion Planning Efforts
• Reliability Centers – 5 Year Strategic PlanReliability Centers – 5 Year Strategic Plan
• Energy Act ImplementationEnergy Act Implementation
44
Top “10” RPIC Issues for Top “10” RPIC Issues for 2005/062005/06
• Data Sharing IssuesData Sharing Issues
• Resource Adequacy AssessmentResource Adequacy Assessment
• Transmission Expansion PlanningTransmission Expansion Planning
• WECC’s Role in Commercial IssuesWECC’s Role in Commercial Issues
• WECC/NERC RelationshipWECC/NERC Relationship
• Energy Act ImplementationEnergy Act Implementation
• Reliability Benchmarks/OTC ratings/FRR EffortsReliability Benchmarks/OTC ratings/FRR Efforts
• OtherOther
55
Data Sharing & Confidentiality Data Sharing & Confidentiality PoliciesPolicies
• Policy documents circulated to committees Policy documents circulated to committees
& members for comment& members for comment
• RPIC reviewed comments and RPIC reviewed comments and
recommended final policy in Decemberrecommended final policy in December
• Board approved new policy in DecemberBoard approved new policy in December
66
Transmission Expansion Transmission Expansion Planning in WECCPlanning in WECC
• WAG requested WECC address the issueWAG requested WECC address the issue
• RPIC “commissioned” white paperRPIC “commissioned” white paper
• White paper posted for member comment – Sept. – Jan.White paper posted for member comment – Sept. – Jan.
• RPIC recommend new board committee and charterRPIC recommend new board committee and charter
• RPIC sponsored Member workshop in FebruaryRPIC sponsored Member workshop in February
• Near unanimous member approval of RPIC Near unanimous member approval of RPIC
recommendationsrecommendations
• RPIC presents charter and committee recommendations to RPIC presents charter and committee recommendations to
Board in April 2006Board in April 2006
77
Recommended Transmission Recommended Transmission Expansion Planning Policy Expansion Planning Policy CommitteeCommittee
RECOMMENDED MEMBERS Company / Class
1 WECC Board Member Dave Areghini SRP / Class 12 WECC Board Member Scott Cauchois CORA / Class 43 PUC Representative Jerry Smith ACC / Class 54 Energy Office Representative: Grace Anderson CEC / Class 55 IRP Expert Mike Whatley SCE / Class 16 Wholesale Market Expert Mike Evans STGP / Class 37 Transmission Owner Marv Landauer BPA / Class 18 LSE Representative Alan Myers WPE / Class 29 Consumer Representative Harlow Peterson USE / Class 4
10 Environmental Representative Dian M. Grueneich CPUC / Class 511 Generator Owner Representative Gordon Dobson Mack PWX / Class 312 SWAT Robert Kondziolka SRP / Class 113 NTAC Chris Reese PSE / Class 114 STEP Robert Smith APS / Class 115 RMATS Mike DeWolf PAC / Class 116 CAISO Dariush Shirmohammadi CISO / Class 117 Colorado Planning Group Sandra Johnson PSC / Class 1
TEPPC
88
Reliability Centers 5 Year Reliability Centers 5 Year Strategic PlanStrategic Plan
• OC requested RPIC investigate RC policy issuesOC requested RPIC investigate RC policy issues
• RPIC created subcommittee to evaluate RC RPIC created subcommittee to evaluate RC
strategic issuesstrategic issues
• Subcommittee represents all member classes & Subcommittee represents all member classes &
regionsregions
• Subcommittee has drafted recommendations to Subcommittee has drafted recommendations to
be presented to Board in Aprilbe presented to Board in April
99
Other ItemsOther Items
• WAG Response - RA, Transmission Planning WAG Response - RA, Transmission Planning
and Commercial Issues came from WAG and Commercial Issues came from WAG
efforts. efforts.
• WECC role in commercial issues – MIC WECC role in commercial issues – MIC
outreach initiative in process. outreach initiative in process.
• Energy Act Implementation – activities Energy Act Implementation – activities
conducted by broader WECC “Ad Hoc” team conducted by broader WECC “Ad Hoc” team
1010
Member Comments & Member Comments &
Questions of RPICQuestions of RPIC