02 Mechanical

Embed Size (px)

DESCRIPTION

02 Mechanical

Citation preview

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 1

    INDEX

    Indicative Inspection & Test Plans

    SL. No.

    DESCRIPTION

    B. MECHANICAL WORKS

    I Under Ground Piping

    II Above Ground Piping/ Heater Coils

    III Storage Tanks

    IV Equipment Erection (Static)

    V Equipment Erection (Rotary)

    VI Crane (EOT/ HOT)

    VII Column Internals

    HEATER WORKS

    I Fired Heaters

    II Refractory & Insulation Works Fired Heaters

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 2

    HP : HOLD POINT.

    A point which requires inspection/verification and acceptance by Owner/ Consultant

    before any further processing is permitted. Contractor shall not process the activity

    beyond a Hold Point without written approval by Owner/ Consultant.

    W : WITNESS POINT.

    An activity which requires witnessing by Owner/ Consultant when activity is performed.

    Suppose, after proper notification has been provided, the contractor not obliged to

    hold further processing, if Owner/ Consultant is not available to witness the activity or

    does not provide the comments before the date notified.

    Rw : REVIEW of contractors documentation.

    S : SURVEILLANCE Inspection by Owner/ Consultant.

    Monitoring or making observations to verify whether or not material/ Items or services

    conform to specified requirements. Surveillance Activities may include audit,

    inspections, witness of testing, review of quality documentation & records, field visit,

    personnel qualifications etc.

    WC : 100% Examination by CONTRACTOR.

    NDT : NON DESTRUCTIVE TESTING.

    PWHT : POST WELD HEAT TREATMENT.

    NOTE :-

    Contractor to submit required formats and job procedures for each activity listed in ITPs and

    submit to Owner/ Consultant for approval. Responsibility for execution of the inspection/ testing

    is with the contractor. Owner/ Consultant only verify examination or testing done by the

    Contractor at important stages. Activities for which ITPs are not given, contractor to develop

    and get the same approved by Owner/ Consultant well before start of the work.

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 3

    I UNDER GROUND PIPING A PRIOR TO FABRICATION

    1 Incoming Material WC W

    2 Welding Filler Material Approval/ Qualification. WC HP

    3 WPS/ PQR WC HP

    4 Welder Performance Qualification. WC HP

    5 a NDT Procedure Qualification WC HP

    b PWHT Procedures Qualification (if any) WC HP

    6 Preparation of Sketches. WC S

    7 Joint Numbering. WC S

    8 Material traceability & transfer of heat nos. WC S

    B FABRICATION (SHOP & FIELD)

    1 Material as per piping class (check w.r.t. approved WC S Colour coding procedure).

    1 a Fit-up check WC S

    b Dimensional check WC S

    2 Pre-heat (if any). WC S

    3 Check for purity of purging/ shielding gas WC Rw/S

    4 Purging (if any) WC S

    5 Shielding rate (if any) WC S

    6 Basking of Electrodes WC S

    SL.

    NO. ACTIVITY CONTRACTOR PMC

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 4

    7 Interpass cleaning & temperature check WC S

    8 Visual check of completed welds WC S

    9 Monitoring of PWHT Cycle WC S

    10 Hardness Check WC S

    11 PT/MT WC S

    12 Radiography marking (for Random Radiography) WC W

    13 Radiography Interpretation WC HP

    14 Check shot for Radiography WC W C PROOF TESTING

    1 Procedure WC HP

    2 Correctness of Testing arrangements WC S

    3 Calibration of Pressure Gauges WC Rw

    4 R.F. Pad testing, if any WC W

    5 Positive Material Identification as per WC HP Specification after completion.

    6 Scrutiny of test packs for Mechanical WC HP & NDT Clearance(As per Annexure A)

    7 Air / Water Flushing (preliminary) WC W

    8 Pneumatic/ Hydro testing WC P 9 Draining of Water & Air drying WC S D LAYING

    1 Trench excavation and levels WC S

    2 Cleaning of pipe surface WC S

    3 Approval of wrapping/ coating material manufacturers WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 5

    4 Approval of agency for wrapping & coating WC HP

    5 Sample test of coating materials in approved laboratory WC Rw

    6 Procedure qualification for wrapping & coating WC HP

    7 Application of primer WC S

    8 Coal tar temperature WC S

    9 Coating and wrapping WC S

    10 Calibration of Holiday tester WC HP

    11 Holiday testing WC HP

    12 Thickness of coating WC HP

    13 Peel test WC HP

    14 Lifting arrangement WC S

    15 Lowering (levels & orientation of branches) WC S

    16 Checking of wrapping and coating for damages during WC HP lowering, their repair, holiday testing, etc.

    17 Back filling WC S

    18 Location, Brickwork, Plaster of valve pit WC S

    19 Top cover & finish of valve pit WC S E SYSTEM COMPLETION

    1 Tie in joins (As per Annexure - B) WC W

    2 Scrutiny of test packs for system testing

    (As per Annexure - C) WC W

    3 System testing WC W

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 6

    Inspection & Test Documents

    Review Test and Inspection Document HP Rw

    Abbreviations:

    NDT : Non Destructive Testing

    WPS : Welding Procedure Specifications

    U/G : Under Ground

    PT : Penetrant Testing

    MT : Magnetic Particle Testing

    PWHT : Post Weld Heat Treatment

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 7

    Plant: Report:

    Contractor: Area :

    Loop No.: Inch Metre

    Sketch No.: From: ____________ To : ____________

    Sr.No.

    Activity Check Clearance by Contractorwith Date & Sign

    Clearance by PMC with Date

    & Sign

    A MECHANICAL COMPLETION RECORD (U/G)

    1 Clearance for flushing & testing.

    1.a

    Mechanical clearance

    Conformity with drawing.

    1.b

    Welding & NDT clearance

    Material as per piping class

    Fit-up check

    Visual check of completed welds

    LPI checks

    RF pad testing

    2 Flushing & Pressure testing

    Medium

    Test pr. Kg /Sqcm

    3

    Coating and Wrapping

    Surface preparation

    Primer application

    Coating, wrapping and peel test

    Holiday check

    4

    Laying

    Trench leveling

    Lowering & checking for damages in wrapping & coating, their repair, holiday

    testing, etc.

    Backfilling

    Remarks:- Test loop sketches duly filled in to be enclosed with this (Jt.No., W.No. X SR. Chart No.

    Alongwith XR Films, SR Charts etc.)

    Review by Area Co-ordinator

    Sign. Date Name Designation

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 8

    INSPECTION REPORT FOR TIE IN JOINT

    (FOR UNDER GROUND PIPING)

    JOINT NO. REPORT NO.

    DATE

    A TTIME AT THE TIME OF FIT UP

    CLEARANCE BY

    DATE CONTRACTOR PMC

    B FIT UP

    C ROOT RUN DP

    D FINAL RUN DP

    E WELDER NO

    F RADIOGRAPHY

    G PWHT HARDNESS

    H RF PAD TESTING

    I CLEANING & PRIMING

    J COATING, WRAPPING & PEEL TEST

    K HOLIDY CHECKING

    L CHECKING FOR ANY DAMAGE IN

    WRAPPING & COATING AFTER

    LOWERING, THEIR REPAIR, HOLIDAY

    TESTING, ETC.

    M BACK FILLING

    Inspection at above stages has been carried out by concerned and found satisfactory.

    Contractor PMC Mechanical PMC Inspection

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 9

    Plant: Report:

    Contractor: Area:

    Loop No.: Inch Meter

    Sketch No.: From: ____________ To: ____________

    Sr.No.

    Activity Check Clearance by Contractorwith Date & Sign

    Clearance by PMC with Date

    & Sign

    A MECHANICAL COMPLETION RECORD (U/G)

    1 Clearance for flushing & testing.

    1.a

    Mechanical clearance

    Conformity with drawing.

    1.b

    Welding & NDT clearance

    Material as per piping class

    Fit-up check

    Visual check of completed welds

    LPI checks

    RF pad testing

    2 Flushing & Pressure testing

    Medium

    Test pr. Kg /Sqcm

    3

    Coating and Wrapping

    Surface preparation

    Primer application

    Coating, wrapping and peel test

    Holiday check

    4

    Laying

    Trench leveling

    Lowering & checking for damages in wrapping & coating, their repair, holiday

    testing, etc.

    Backfilling

    Remarks:- Test loop sketches duly filled in to be enclosed with this (Jt.No., W.No. X SR. Chart No.

    Alongwith XR Films, SR Charts etc.)

    Review by Area Co-ordinator

    Sign. Date Name Designation

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 10

    II ABOVE GROUND PIPING

    A PRIOR TO FABRICATION

    1 Incoming Material WC W

    2 Welding Filler Material Approval/ Qualification WC HP

    3 WPS/ PQR WC HP

    4 Welder Performance Qualification WC HP

    5 a NDT Procedure Qualification WC HP b PWHT Procedures Qualification WC HP

    6 Joint numbering in Isometries (Big & Small Bore) WC S

    7 Preparation of sketches for job in case of off sites WC S A/G piping and Joint Numbering

    8 Transfer of Heat Nos. & Traceability WC W

    B FABRICATION (SHOP & FIELD)

    1 Material as per piping class (check w.r.t. approved WC S Colour coding procedure)

    1 a Fit-up check WC S b Dimensional checks WC S

    2 Pre-heat (if any) WC S

    3 Check for purity of purging/ shielding gas WC Rw/S

    4 Purging WC S

    5 Shielding rate (if any) WC S

    6 Baking of Electrodes WC S

    7 Interpass cleaning & Temperature check WC S

    8 Visual check of completed welds WC S

    9 Monitoring of PWHT Cycle WC S

    10 Hardness Check

    i) For C.S. Materials WC S ii) For A.S. Materials Piping WC W iii) For A.S. Material Heating Coil WC HP

    SL.

    NO. ACTIVITY CONTRACTOR PMC

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 11

    11 PT/MT WC S 12 Radiography marking (for Random Radiography WC W only)

    13 Radiography Interpretation WC HP

    i.For Carbon Steel Piping WC HP ii.For Alloy Steel/SS Piping WC HP

    14 Spool clearance WC HP

    C ERECTION

    1 Lifting arrangement WC S 2 Test Certificates for lifting tackles WC Rw

    3 Location and orientation of branches WC S

    4 Provision of Instrument Tappings WC S

    5 Provision of vents and drains WC S

    6 Correctness of type of supports, anchors, guides WC S

    7 Correctness of gasket/ fasteners WC S

    8 Correctness of valves (NRV, Gate, Globe, Control WC S Valves), Steam traps and their direction of flow

    9 Provision of cold pull WC HP

    D PROOF TESTING (See enclosed checklist in Annexure-A)

    1 Procedure WC HP

    2 Correctness of testing arrangements WC S

    3 All valves to be kept open and chek if testing done WC S against closed valve position

    4 Isolation of equipments, control valves, instruments, WC S ellows, before testing. Removal of flappers from

    check valves

    5 Scrutiny of test packs for Mechanical and NDT WC HP Clearance

    6 Positive Material Identification as per specification WC HP after completion of installation

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 12

    7 Calibration of pressure gauges WC Rw

    8 Preparation of check list WC S

    9 Liquidation of check list WC S

    10 Air/Water flushing (preliminary) WC W

    11 Pneumatic / Hydrotesting (See Annexure - B) WC HP

    12 Draining & drying WC S

    13 Removal of temporary blinds/ supports WC W

    14 Pickling of system, if required WC W

    15 Boxing up including reinstallation of flappers WC W of check valves

    16 a. Check on fasteners & gaskets and record WC Rw Thereof b. Torque tightening of flange joints WC S

    17 System testing WC W

    18 Setting of spring supports WC W Inspection & Test Documents

    Review Test and Inspection Documents HP Rw

    Abbreviations:

    NDT : Non Destructive Testing

    WPS : Welding Procedure Specifications

    A/G : Above Ground

    PT : Penetrant Testing

    MT : Magnetic Particle Testing

    PWHT : Post Weld Heat Treatment

    For liquidation of Punch list. See Annexure - C.

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 13

    CHECKLIST FOR MECHANICAL CLEARANCE A/G Piping (Sheet 1 of 4)

    Project: ___________________

    Plant/Unit: ___________________

    Contractor: ___________________

    Loop No: ___________________

    Report No: ___________________

    Date : ___________________

    Area : ___________________

    INCH MTR ___________________

    Line No (Isometric No.) Rev. GAD NO. Rev. P&ID No.

    Sr. No.

    Items to be checked Acceptance by Contractor

    Witness by Owner/ PMC as required by

    ITP 1 Installation checked as per Isometric w.r.t.

    CONFIGURATION : Route, plumb, elevation, clearance

    for thermal expansion/ insulation

    BRANCH: Location, angle, orientation, type, R.F. pad etc.

    STEAM TRAP : Direction

    2 Installation checked as per GAD w.r.t. CONFIGURATION : Route clearance for thermal expansion /

    insulation

    3 Installation checked as per P&ID

    4 Isometrics completed for (enclosed) a) Joint numbering (Shop and Field welds)

    b) Spool numbering

    c) As-built routing and dimensions

    Valves (Check Rating, Gaskets, Flow direction, Sheet No.,

    Tag No., Spindle direction. CSO, LO/LC, Damage etc.)

    Gate valve

    Globe valve

    Check valve

    Control valve Tag Nos.

    Safety Valve Tag Nos.

    5

    Any other valves

    FORMAT NO:_______________________________________ (Sheet 2/4)

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 14

    CHECKLIST FOR MECHANICAL CLEARANCE A/G Piping (Sheet 2 of 4)

    Sr. No.

    Items to be checked Acceptance

    by Contractor

    Witness by Owner/ PMC

    as required by ITP

    6 Strainers: Check for clearance, flow direction, elements

    Flanged joints

    Total Nos.

    Check for type of flange

    Check for Rating

    Check for Alignment, (Proper gap and parallelity)

    Check for correct studs and nuts dia, length, material, uniform protrusion of

    studs, anti seize compound

    Check for correct gasket (type, size, spec., thickness, etc.)

    7

    Torque values used for tightening

    8 Seal welding of Screwed connections (If required)

    9 Vents/ Drains as per Dwg. And provision of additional high point vents and / or low point drains, if reqd.

    10 Reinforcement pads as per piping class

    Orifice flanges 11

    Check for Tag. No. tapping orientation, tap valve, jack screw, straight run

    length of upstream and downstream

    12 Local Gauges: Check for accessibility

    13 Slope (When applicable)

    Supports

    a) Guides, Cross Guides, Trunnion etc.

    i) Check for correct type, material and dimension

    ii) Check welding

    iii) Check for vent hole on pads (if applicable)

    iv) Check offset for thermal expansion

    v) Check clearance of guide

    vi) Check U bolt for slide support

    b) Spring support

    i) Verify tag no. and check details as per data sheet/ spring set

    ii) Check for locking arrangement and any damage during transit, etc.

    iii) Check for completeness of installation as per drg. Including welding of

    mounting cleat/ bracket

    iv) Check for locking during installation and pressure test

    c) Bracket support and inserts with Anchor fasteners:

    i) Check for members dimensions and materiall

    ii) Check for welding

    iii) Check for bolting

    14

    iv) Check for appearance damage

    Vents/ Drains

    As per Drg

    Orientation of valve handles

    Clearance for hose

    15

    Requirement of additional vents/ drains (highest/ lowest pt.)

    FORMAT NO:_______________________________________ (Sheet 2/4)

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 15

    CHECKLIST FOR MECHANICAL CLEARANCE A/G Piping (Sheet 3 of 4)

    Sr. No.

    Items to be checked

    Acceptance by

    Contractor

    Witness by Owner/ PMC as required by

    ITP

    16 Earthings:

    a) Check for location

    b) Check for dimension of lug welding

    17 17 Joints History sheets enclosed for

    17.1 17.1 Material Traceability as per Procedure No: (refer enclosed suggested format)

    17.2 Fit ups checked

    17.3 NDT Complete (Radiography, MT, PT)

    17.4 Stress Relieving & Hardness Check complete

    17.5 Positive Material Identification (PMI)

    Checked for Removal Binding off of:

    a. Control, Safety and Check valves

    b. In-line instruments

    c. Rupture discs

    d. Equipment nozzles

    18

    e. Others

    19 19 Supports and Weld/Flanged/ Screwed connections free from insulation or other coverage

    Checked installation of (Indicate location in Drawings)

    a. Temporary Blinds, Spades

    b. Temporary Strainers

    c. Temporary Dummy-spools

    d. Temporary Gaskets

    20

    e. Others

    Expansion Bellows

    a) Checks prior to installations

    Physical damage

    Transit locks are intact

    Dimensions as per drgs.

    b) Check during installations

    Parallelity of mating flanges

    Face to face dimensions of mating flanges

    Concentricity of mating flanges

    No stress on expansion bellows

    Record

    c) Isolation during pressure tests

    Bellow manufacturers recommendations on isolation of

    bellow during Pr. Test to be followed

    21

    If recommended expn, bellow to be dropped during pr. Test

    22 Cleanliness internally and externally

    23 Rotating equipment final alignment checked with piping

    FORMAT NO:______________________________________ (Sheet 3/4)

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 16

    CHECKLIST FOR MECHANICAL CLEARANCE A/G Piping (Sheet 4 of 4)

    Sr. No. Items to be checked

    Acceptance by

    Contractor

    Witness by

    Owner/ PMC

    as required by

    ITP

    24 Removal of unwanted construction supports

    25 Instrument tappings provided as per Drawing

    26 Physical Walk Through The Line Checked for gross

    irregularities including physical damages, unwanted tacks,

    arc strikes, spatters and space for thermal expansion

    Other

    Remarks

    Contractor :

    Sign. :

    Date :

    Name : Designation :

    PMC

    Sign : Review by Area Co-ordinator (PMC)

    Date : Sign :

    Date : Date :

    Name : Designation : Name : Designation :

    FORMAT NO:_______________________________________ (Sheet 4/4)

  • HPCL, Visakh

    INDICATIVE INSPECTION & TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 17

    DAILY MATERIAL TRACEABILITY REPORT

    (FOR ABOVE GROUND PIPING/ HEATER)

    Contract No. : _______________________ Report No.: ______________

    Contractor : ________________________ Date : ___________________

    Verified Remarks Sl.

    No.

    Line / Heater No. Area

    No.

    Dia Joint No. Spool

    No.

    Piping Component Heat / Batch No. Colour Code

    Contractor PMC

    Contractor PMC

    Note : A Sketch of the spool may be enclosed.

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 18

    Piping Hydro Test Release / Acceptance Record A/G Piping (Sheet 1 of 2)

    Project :

    Report No:

    Plant / Unit : Date :

    Contractor : Area :

    Loop No. : REF P & ID No.

    INCH MTR

    From

    ______________

    To _________________

    Line No (s) Isometric No. (s) P & ID No.

    Test Medium : Test Duration Design/ Test pressure

    Test Pressure Gauge No. Range Calibration

    Certificate No. Gauge Calibration Date

    Items to check Accept Witness

    Contractor PMC

    Field installation Checklist prior to Hydrotest

    Signed

    Punch list prepared Yes/ No

    Pre-Hydrotest Punch items cleared

    Accessibility to inspection/ witness locations

    Capacity of pressurising pump checked

    Cordon off area for high pressure testing as

    required

    Pre-hydrotest flushing carried out

    IBR/Others test Witnessing required Yes/ No

    System released for Pressure Testing :

    Contractor PMC Sign Name Sign Name

    Date Date Designation Designation

    FORMAT NO:_______________________________________ (Sheet 1/ 2)

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 19

    Piping Hydro Test Release / Acceptance Record A/G Piping (Sheet 2 of 2)

    Activity

    Date Time

    Water Filling and Venting started at

    Water Filling completed

    Vents closed

    Isolation of Pressurising pump

    Test completed at :

    - Water drained

    - Air

    - Temp Blinds Removed

    - Checked for reinstallation of

    a. Control & Safety valves

    b. On line instruments

    c. Rupture disks

    d. Deblinding

    e. Others

    - Cold setting of spring supports carried out

    Contractor PMC

    Sign Sign

    Date Date

    Name Designation Name Designation

    FORMAT NO:_______________________________________ (Sheet 2 / 2)

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 20

    Punchlist

    Project:

    Report No:

    Plant/Unit:

    Date :

    Contractor:

    Area :

    Loop No:

    REF P&ID No.

    Description :

    Ref. Document :

    Punc h

    Item No

    Priority

    Description of

    Punch Items

    Location Prepared by

    Action by Due Date

    Completion Acceptance

    Priority: 1 Needed for Pressure test 2. Needed for commissioning 3.Needed for plant acceptance Contractor PMC Sign Sign

    Date Date

    Name Designation Name Designation

    FORMAT NO:_______________________________________

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 21

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    III

    STORAGE TANKS

    A PRIOR TO FABRICATION

    1 Acceptance of the tanks foundation WC W 2 Materials WC W 3 Filler materials tests and approval WC HP 4 WPS/ PQR WC HP 5 Welders performance qualification WC HP 6 Radiography procedure WC HP 7 Joint numbering in drawings WC S 8 Welding equipment and accessories WC S 9 Tools and Tackles WC S 10 Baking ovens

    - Portable WC S

    - Heavy WC S 11 Jig & Fixtures WC S 12 Suitability of plate bending machine WC S

    B FABRICATION/ ERECTION BOTTOM

    1 Plate size, marking and cutting WC S 2 Blast cleaning & painting of underneath

    bottom plates

    WC S

    3 Plate layout, overlap and fitup WC S 4 Sequence of welding to follow WC S 5 Size and positioning of backing plate for

    annular plates WC S

    6 Baking of electrodes/ interpass cleaning WC S 7 Visual check WC S 8 LPI/MPI/ Radiography of annular plate butt

    welds and

    bottom plate butt welds (if any)

    WC HP

    9 Vacuum/ MPI/ LPI of shell portion of the bottom plates

    WC HP

    10 Vacuum box test for the bottom plate welding

    WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 22

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    SHELL 1 Plate size, marking and cutting. WC S 2 Plate bending, curvature check, stacking. WC S 3 Shell course alignments and fitup of vertical

    and

    circumferential joints.

    WC S

    4 Shell diameter, circularity, perpendicularity, straightedge before welding.

    WC HP

    5 Visual and Back chip check WC S 6 Second side visual. WC S 7 Location, size and alignment of nozzles and

    other Openings WC

    HP

    8 R.F.Pads fitup / welding. WC W 9 PWHT of RF pad. Nozzles & manhole, etc.

    (As

    applicable)

    WC HP

    10 Radiography marking for Random radiography only

    WC W

    11 Curbangle and Wind girders fitup / welding WC S 12 MPI/LPI nozzles, wind girders fitup/welding WC W 13 RF Pads air test. WC HP 14 Shell to bottom fit-up WC W 15 Sheel to bottom I/S welding root run visual/

    Oil chalk test WC

    HP

    16 Sheel to bottom O/S welding visual and LPI for toecracks

    WC HP

    17 Fabrication and erection of stairways WC S 18 Cleates welding for insulation WC S 19a Radiography interpretation. WC HP 19b Extension marking for repair

    WC HP

    FIXED ROOF

    1 Identification of Roof Structure members in AFC drgs

    WC Rw

    2 Blast cleaning and painting Roof Structure underside of Roof plates

    WC S

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 23

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    3 Location and welding of roof supports. WC S 4 Alignment and welding of Roof Structures. WC W

    5 Plate layout, overlap and fitup WC S

    6 Visual check of roof welds WC W 7 Location, size and alignment of roof man-

    holes and vents WC S

    8 PWHT (As applicable) WC HP 9 RF pads fit-up & Welding WC W 10 RF pad pneumatic testing WC W 11 PT/MT of Nozzles, vents & other

    attachments

    WC W

    12 Welding of Roof plate with shell / curb angle

    WC W

    FLOATING ROOF WC 1 Temporary staging spacing and levels WC S 2 Plate size, straightening and cutting WC S 3 Plate layout, overlap and fitup/ welding WC S 4 Buoys fabrications WC S 5 Vacuum testing of roof-plate welds WC HP 6 Location of sleeve supports WC W 7 Pad plate welding with roof and sleeve

    support WC W

    8 Fixing and welding of Buoys WC S 9 Initial lift WC W 10 Supports fixing through sleeves WC S 11 Seal welding of support sleeves from

    beneath after dewatering WC W

    12 Air test of Buoys WC HP 13 Pontoon welding WC W 14 Location, fixing and welding of man holes,

    drains etc.

    WC S

    15 Shell to pontoon clearance WC W 16 Seal fixing W W

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 24

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    C TESTING

    1 Correctness of testing arrangements especially

    size of blind flanges/ vents/ drains/ temporary

    piping

    WC S

    2 Mechanical / Inspection clearances WC HP

    3 Earthing of ladder and shell WC W

    4 Settlement readings during water filling WC W

    5 Hammer test WC HP

    6 Air pressure test WC HP

    7 Vacuum test WC HP

    8 Roof collapsability test in case of floating roof

    tanks

    WC HP

    9 Calibration of tanks in case of floating roof

    tanks

    WC Rw

    D PAINTING AND INSULATION

    1 Cleaning WC S

    2 Painting WC W

    3 Insulation WC W

    Inspection & Test Documents

    Review Test and Inspection Documents HP Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 25

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    IV

    EQUIPMENT ERECTION (STATIC)

    1 BEFORE ERECTION A Execution scheme WC Rw B Materials supply WC W C Readiness of erection WC S

    I Level of foundation (shims/ packing with marking to be prepared & kept ready)

    WC S

    II No. & Size of bolts WC S

    III Hole dia and no. of hole in base/ structure of equipment and columns

    WC S

    IV Equipment base with actual foundation WC S V Checking the threads of bolts & nuts WC S VI Chipping & roughening of foundation WC S VII C/L marking on equipment WC S

    2 ERECTION SCHEMES FOR CRITICAL EQUIPMENTS

    A Approval of Rigging procedure (As per Annexure 1)

    WC HP

    3

    SAFETY TEST

    A Load test of cranes, lifting beams, slings and shackles, length and dia. of sling &

    condition of wire rope (Broken/ damaged

    strands should not be there)

    WC W

    4

    Cross checking if Data-sheet w.r.t.

    orientation, base plate Deatails

    WC S

    5 DURING ERECTION A Orientation to be checked

    WC S

    B Placement of packing as per marking

    WC S

    C Outside cleaning, coating/ wrapping, painting for underground equipment

    WC W

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 26

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    6 AFTER ERECTION

    A Tightening of Bolts and providing washers WC S

    B Levelling and alignment of equipments WC HP

    C Corresponding requirement elevation and distance

    between nozzles in special cases

    WC S

    D Cleaning of sleeves before grouting WC S

    E Grouting WC S

    F Final tightening of bolts WC S

    G Internals installation after PMI as required

    i. Critical equipments WC HP

    ii. Other equipments WC W

    7 TESTS

    As per specification WC W

    8 Packing of column (As per Annexure 2) WC W

    9 Final Boxing up WC W

    Inspection & Test Documents

    Review Test and Inspection Documents HP Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 27

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    ERECTION SCHEME FOR CRITICAL EQUIPMENT (Rigging Procedure)

    1 BEFORE ERECTION A Checking proper sequence for lifting of the

    equipment WC Rw

    B To check weight of equipment WC Rw C To check the centre of gravity WC Rw D To check suspension points WC Rw E To check the maximum/ minimum radius at which

    the lifting tackle will operate WC Rw

    F To check the maximum load to be lifted including wt. Of slings, hook-block, lifting beams and

    equipment etc.

    WC Rw

    G To identify the safe crane with requisite capacity WC Rw

    2 DURING ERECTION

    A To check counter weight of crane and Boomlength

    WC Rw

    B To check slew limitations of crane WC Rw C To check ground conditions are adequate for

    supporting fully rigged crane and load WC Rw

    D To check the crane can be travelled in loaded condition

    WC Rw

    E To check clearances from overhead electric power cables

    WC Rw

    F To check maintenance certificates WC Rw G To check whether operators, riggers have received

    proper instructions WC Rw

    H To verify safe load indicator been supplied to rig the crane

    WC Rw

    I To check the adequacy of bracing of equipment by guys

    WC Rw

    J To check the guys, shoring, bracing, interference with other works

    WC Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 28

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    PACKING COLUMN

    1 BEFORE INSTALLATION

    A Identify the material, check thickness,

    dimensions, no. and angle of fingers of packing

    rings

    WC S

    2 DURING INSTALLATION

    A Degreasing and cleaning of packing material

    WC S

    B Check packing su

    pport plate

    WC S

    C Check for stacked or dumped packing as per

    Specifications

    WC S

    D Check for nesting WC S

    E Check for packings are touching bed limiter

    (when issued and top level)

    WC S

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 29

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    V

    EQUIPMENT ERECTION (ROTARY)

    1 BEFORE ERECTION A Execution scheme WC Rw B Foundation check I Level / centreline of foundation WC S II No / Dia / Length of anchor bolts, Depth of

    pockets, verticality of pockets WC S

    III Chipping, roughing and cleaning of pockets WC W 2 LIFTING TACKLES Crane/beams/ slings/ shackles etc. to be checked for weight of equipments

    WC S

    3

    VISUAL INSPECTION OF EQPTS. TAG/ IDENTIFICATION NO.

    A For any damage WC S B Free shaft rotation WC S 4

    Drilling and Tapping (if reqd.) hole in the base

    plate of eqpt.

    a. Size/ Taps WC S DURING ERECTION

    A Level/ elevation of base frame WC W B All foundation bolts to be checked WC S C Grouting of base frame / pocket grouting WC W D Orientation of eqpts. WC W E Elevation/ Level of eqpts. WC HP F Shimsize/ material/ thickness WC W G Distance between couplings WC W H No-load run of motors WC W

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 30

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    I Alignment readings WC

    - Without piping (Loose bolts) WC HP

    - With piping (After tightening the flange bolt) WC HP

    J Type of grout and grouting WC S

    K All protection and safety guards installation WC S

    AFTER ERECTION

    A Curing of grout WC S

    B Auxiliary connections to be mounted on eqpts.

    as per drawing

    WC S

    C Final tighting of bolts WC S

    D Tests as per spec. WC W

    E Chemical Cleaning of equipments parts /

    connected piping

    WC S

    F Boxing up of equipment 7 connection piping WC S

    G Log book maintenance (For rotating of shaft,

    lubrication Oil reservoir full, all plugs in

    positions)

    WC S

    H No load run of Motor WC W

    I Recoupling of motor & reconfirmation of

    alighnment

    WC W

    INSPECTION & TEST DOCUMENTS

    Review test and Inspection documents HP Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 31

    SL. NO.

    ACTIVITY CONTRACTOR PMC

    VI CRANE (EOT/ HOT) 1 BEFORE ERECTION A Execution scheme WC Rw B Materials supply (contractor) WC W C Readiness for erection I Structural steel girder span centre to centre and

    elevation Difference WC S

    II Check centre to centre distance of rails, gaps, elevations, crab wheels distances

    WC S

    III Check buffer stops WC S 2 A Erection and assembly of components like LT,

    Crane Girders, Crab, Platforms, etc. WC S

    B Review of hoist ropes and assembly of hook blocks

    WC S

    3 A Electrical installation, testing and no load test of motor

    WC S

    B Coupling of motors to drives WC S

    4 NO LOAD TEST A. Winding & unwinding test WC W B. Traversing test WC W C. Travelling test WC W

    5 LOAD TEST A. Winding & unwinding test WC W B. Traversing test WC W C. Travelling test WC W D. Load & Over load testing WC W E. Deflection of girder WC W

    INSPECTION & TEST DOCUMENTS Review test and Inspection Documents HP Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 32

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    VII INSTALLATION OF COLOUMS INTERNALS

    A Before Installation

    1 Avalable of Venders representatives at site WC HP

    2 Material Inspection

    a) Manufactures Test Certificate WC Rw

    b) Testing, If any WC S*

    c) Positive Material Identification WC* Rw

    3 Fabricated materials receipt WC Rw

    4 Level check on TSRs WC S

    5 Check for down corner clearance and Tray

    clearance

    WC S

    6 Distance between TSRs WC S

    B After Installation

    Check for

    1 Exit weir height WC S

    2 UDFC WC S

    3 Tightness of bolts WC S

    4 Orientation and tightness of clamps WC S

    5 Provision of lock nuts / seal pates WC S

    6 Correctness of installation of shimming / bolting

    for top down corner

    WC S

    7 Correctness of gasketing (if any) WC S

    8 Tray to tray distance and level of tray WC S

    9 Leak testing of seal pans as applicable WC HP

    10 Damaged, missing valves and valve movement

    for valve trays

    WC S

    11

    Fitting of proper valve combination

    WC

    S

    12 Damage to deck components WC S

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 33

    13 Level and alignment of inlet weir and exit weir WC S

    14 Check for slots on tray components to be fully

    covered

    WC S

    15 Gaps at down corner ends WC S

    16 Removal of temporary plugs after testing WC S

    17 Cleaning of all trays & inside of equipment WC S

    18 Certification of installation by Vendors

    representative and operation groups of PMC /

    Owner

    WC HP

    19 Final boxing up and intertisation, if any WC Rw

    INSPECTION & TEST DOCUMENTS

    Review test and Inspection documents HP Rw

    NOTE:- All activities pertaining to material receipt, identification. Pre installation checks

    checks and installation to be carried out in the presence of Vendors

    representative and duly certified and documented for submission as final

    document.

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 34

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    I FIRED HEATERS (FABRICATION & ERECTION

    A PRIOR TO FABRICATION

    1 Material Inspection

    a) Manufacturing Test Certificate WC Rw

    b) Testing, if any WC S

    c) Positive Material Identification for Alloy

    Steel & Stainless Steel material by alloy

    analyzer

    WC S*/RW

    2 WPS / PQR WC HP

    3 Welders Performance WC HP

    4 Welding Consumable WC HP

    5 a) NDT Procedure Qualification WC HP

    b) PWHT Procedure Qualification WC HP

    6 Availability of AFC drawing (Reviewed by

    PMC) WC S

    7 Joint Numbering for coils / pressure parts WC S/Rw

    8 Structural members identification WC S/Rw

    9 Layout Checking WC S/Rw

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 35

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    B FABRICATION

    STEEL WORKS

    1 Materials as per AFC drawing WC S

    2 Dimensional check WC S

    3 Fit-up check WC S

    4 Weld Visual Inspection WC S

    5 Radiography as Applicable

    a) RT Marking (for random radiography only) WC HP

    b) RT Interpretation WC HP

    6 Completion of structures as per AFC

    drawings WC HP

    7 Surface cleaning for primer painting WC S

    8 Primer Coating as applicable

    COIL WORK

    1 Edge Preparation WC S

    2 Fit-up of joints WC S

    3 Weld Visual Inspection WC S

    4 PT/MT Check as required WC S/Rw

    5 PWHT & Hardness check as applicable WC S/Rw

    6 a) RT Marking (for random radiography only) WC HP

    b) RT Inspection WC HP

    7 Check Short for Radiography WC HP

    8 Clearance for Hydro testing WC HP

    9 Hydro testing

    WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 36

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    C ERECTION

    1 Foundation check as per AFC drawing WC Rw

    2 Lifting arrangements WC Rw

    3 Test certificates for lifting tools and tackles WC Rw

    4 Lifting of radiant section columns WC S

    5 Bottom plate fit-up & welding WC S

    6 Radiant shell course fit-up and welding WC S

    7 Weld visual inspection WC S

    8 Radiography as required WC HP

    9 Cutout for burners in bottom / shell plate

    a) Marking WC HP

    b) Cutting WC S

    10 Coil erection in Radiant section WC S

    11 Erection of convection box & APH with all

    sheet work & tube Supports

    a) Erection Procedure WC HP

    b) Erection WC S

    12 Check Shot for radiography for coil field joints WC W

    13 Clearance for Hydro test WC HP

    14 Hydro test field joints WC HP

    15 Erection fit-up & welding of stack

    a) Erection Procedure WC HP

    b) Erection WC S

    16 Erection fit-up & Welding of ducts WC S

    17 Radiography as required

    a) RT Marking WC HP

    b) RT Interpretation WC HP

    18

    FD & ID

    19 Installation of soot blowers

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 37

    a) Marking WC HP

    b) Erection WC S

    20 Erection of all Platforms, ladders, Hand rails &

    miscellaneous structures WC S

    21 Final Painting

    INSPECTION & TEST DOCUMENTS

    Review Test And Inspection Document WC Rw

    Abbreviations:

    NDT : Non Destructive Testing

    WPS : Welding Procedure Specifications

    RT : Radiography Testing

    PT : Penetrant Testing

    MT : Magnetic Particle Testing

    PWHT : Post Weld Heat Treatment

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 38

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    II REFRACTORY & INSULATION WORKS (HEATERS)

    A RADIANT SECTION

    1 Radiant shell

    Fixing of Ceramic fiber blanket /

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC* HP

    III. Marking of studs WC S

    IV. Welding of studs with approved PS&PQR WC S

    V. Surface Cleaning WC S

    VI. Check for individual layers of ceramic fiber

    blankets and SS foils WC W

    VII. Check for overlap of ceramic blanket WC S

    VIII. Fixing of speed fix washer and cup lock WC S

    IX. Cleaning and final inspection WC HP

    2 Arch Plate

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC* HP

    III. Marking of studs / anchors WC S

    IV. Welding of studs / anchors with approved

    PS&PQR WC S

    V. Surface Cleaning WC S

    VI. Check for individual layers of ceramic fiber

    Blankets (CFB) modules and SS foils

    WC

    S

    VII. Check for overlap of CFB and modules WC S

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 39

    VIII. Cleaning and final inspection WC HP

    3 Floor Plate

    Laying of castable / fire bricks

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC HP

    III. Surface Cleaning WC S

    IV. Check Shelf life prior to application WC HP

    V. Check for undulations on floor WC S

    VI. Check for castable mix WC W

    VII. Check for proper compaction WC S

    VIII. Check for thickness of castable WC S

    IX. Curing WC S

    X. Cleaning after laying of castable WC S

    XI. Check for cracks and repair WC W

    XII. Fixing of tar paper, If applicable WC S

    XIII. Cleaning and final inspection WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 40

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    II REFRACTORY & INSULATION WORKS

    (HEATERS)

    B CONECTION SECTION

    1 Convection Walls

    Laying of castable

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC* HP

    III. Marking of studs / anchors WC S

    IV. Welding of studs / anchors with approved

    PS&PQR WC S

    V. Surface Cleaning WC W

    VI. Check for undulations on wall WC S

    VII. Check for castable mixing WC W

    VIII. Check for proper compaction WC S

    IX. Check for thickness of castable WC S

    X. curing WC S

    XI. Cleaning after laying of castable WC S

    XII. Check for cracks and repair WC W

    XIII. Cleaning and final inspection WC HP

    2 End tubesheets

    Laying of Castable

    i. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    ii. Clearance for hot work WC HP

    iii. Marking of studs / anchors WC S

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 41

    iv. Welding of studs / anchors with approved

    PS&PQR WC S

    v. Surface Cleaning WC S

    vi. Check for castable mixing WC W

    vii. Check for proper compaction WC S

    viii. Check for thickness of castable WC S

    ix. curing WC S

    x. Cleaning after laying of castable WC S

    xi. Check for cracks and repair WC W

    xii. Cleaning and final inspection WC HP

    3 Breeching Plate

    Laying of castable

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC* HP

    III. Marking of studs / anchors WC S

    IV. Welding of studs / anchors with approved

    PS&PQR WC S

    V. Surface Cleaning WC S

    VI. Check for undulations on plate WC S

    VII. Check for castable mixing WC W

    VIII. Check for proper compaction WC S

    IX. Check for thickness of castable WC S

    X. curing WC S

    XI. Cleaning after laying of castable

    WC

    S XII. Check for cracks and repair WC W

    XIII. Cleaning and final inspection WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 42

    4 Header box

    Laying of castable

    i. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    ii. Clearance for hot work WC* HP

    iii. Marking of studs / anchors WC S

    iv. Welding of studs / anchors with approved

    PS&PQR WC S

    v. Surface Cleaning WC S

    vi. Check for undulations on box WC S

    vii. Check for castable mixing WC W

    viii. Check for proper compaction WC S

    ix. Check for thickness of castable WC S

    x. curing WC S

    xi. Cleaning after laying of castable WC S

    xii. Check for cracks and repair WC W

    xiii. Cleaning and final inspection WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 43

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    II

    REFRACTORY & INSULATION WORKS (HEATERS)

    C STACK

    Laying of castable

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for hot work WC* HP

    III. Marking of studs / anchors WC S

    IV. Welding of studs / anchors with approved

    PS&PQR WC S

    V. Surface Cleaning WC S

    VI. Check for undulations on stack shell WC S

    VII. Check for castable mixing WC W

    VIII. Check for proper compaction WC S

    IX. Check for thickness of castable WC S

    X. curing WC S

    XI. Cleaning after laying of castable WC S

    XII. Check for cracks and repair WC W

    XIII. Cleaning and final inspection WC HP

  • HPCL, Visakh

    INDICATIVE INSPECTION &

    TEST PLAN

    ISSUED :01.06.2009 JOB NO. : 6261 TOYO ENGINEERING INDIA LTD.

    DOC.No. 6261-CD-303 DHT PROJECT Sheet 44

    SL.

    NO. ACTIVITY CONTRACTOR PMC

    II

    REFRACTORY & INSULATION WORKS (HEATERS)

    D HOT AIR DUCT

    I. Material Inspection

    Manufacturing Test Certificate WC Rw

    Testing, if any WC S

    II. Clearance for insulation WC HP

    III. External Surface cleaning WC S

    IV. Provide spacer ring / anchors WC S

    V. Check for thickness of the mineral wool

    insulation WC S

    VI. Check for staggering of joints in insulation WC S

    VII. Check for providing expansion joints WC W

    VIII. Overlapping of metal sheet as per

    specification WC S

    IX. Overlap on joints for aluminium sheets

    as per specifications WC S

    X. Sealing alluminium sheets WC S

    E Final Inspection & Acceptance WC HP

    INSPECTION & TEST DOCUMENTS

    Review Test and Inspection Documents WC Rw