What we plan to do next
Digital Thinking, Smart Building: Driving Building Lifespan and Resource Efficiencies
The Performance Gap
Reid Cunningham
@CunninghamReid
Strategic Development Director, BAM FM
Traditional Construction Process, Knowledge and Data Transfer
Design
OperationConstruction
Soft Landings, Whole Life Cost Enabled by Collaboration, Knowledge and Transfer – (The Vision)
Design
OperationConstruction
UK FM Context
Project Robin – Operational Phase2REVIT data Preparation via. Toolkits
• Classification Toolkit by Autodesk UK Consulting Team xml Uniclass2 import to Revit toolkit
• Applying Uniclass2 PR codes to Family Types within Revit Data Model to provide a common linking mechanism for Field360 and FM System
• FM System PPM regimes automatically created from Uniclass2 Coding system
• Agree Additional 360Field Data required
Project Robin – Operational Phase2BIM360 Field – Navigation by end users
• Room or Asset listing to model or model to Room or Asset listing
• Navigational Views and hiding of Objects or separated ModelsProvides full facility to get to the equipment data for FM purposes
• ALL information available as required to FM Engineers
Project Robin – Faster First Fix
New Job received by technician via tablet
Report of Heating Issue in room 501
Technician visits room to perform checks.User has the ability to view services within room
Technician has the ability to view plant and interrogate operatingmanuals including elements of commissioning data
Project Robin – Faster First Fix
Project Robin PPM – Know Before You Go
Technician receives job card via FSI GO. This includes Asset ID and Uniclass Code.
The Asset ID enables the technicianto search for asset within BIM 360Field.
Project Robin PPM – Know Before You Go
Technician has the ability to interrogate O&M ‘s including elements of commissioning information, fault codes and supplier maintenance manuals
QR codes have been implemented to provide those without access to BIM 360 Field / FSI GO with access similar information.
‘The ability to interrogate issues whilst off site has been useful’
‘The ability to view issues, visualise the asset and retrieve information such as Model / Serial Number whilst being off site will enable engineers to come to site with the knowledge of what is required to rectify the job’
Dean Dixon
Project Robin - Results