Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Msukaligwa Local Municipality | CHAPTER 1 – MAYOR’S FOREWORD AND EXECUTIVE SUMMARY 1
2
4.6.1
CONTENTS
Msukaligwa Local Municipality | 2015/2016 Annual Report 2
CONTENTS
CHAPTER 1 – MAYOR’S FOREWORD AND EXECUTIVE SUMMARY .................................................................................. 6
COMPONENT A: MAYOR’S FOREWORD .......................................................................................................................... 6
COMPONENT B: EXECUTIVE SUMMARY ......................................................................................................................... 8
1.1. MUNICIPAL MANAGER’S OVERVIEW ............................................................................................................ 8
1.2. MUNICIPAL FUNCTIONS, POPULATION AND ENVIRONMENTAL OVERVIEW ........................................... 9
1.3. SERVICE DELIVERY OVERVIEW .................................................................................................................. 12
1.4. FINANCIAL HEALTH OVERVIEW .................................................................................................................. 13
1.5. ORGANISATIONAL DEVELOPMENT OVERVIEW ........................................................................................ 15
1.6. AUDITOR GENERAL REPORT ...................................................................................................................... 15
1.7. STATUTORY ANNUAL REPORT PROCESS ................................................................................................. 16 CHAPTER 2 – GOVERNANCE .............................................................................................................................................. 17
2.1. POLITICAL GOVERNANCE ............................................................................................................................ 17
2.2. ADMINISTRATIVE GOVERNANCE ................................................................................................................ 18
COMPONENT B: INTERGOVERNMENTAL RELATIONS ................................................................................................. 19
2.3. INTERGOVERNMENTAL RELATIONS .......................................................................................................... 19
COMPONENT C: PUBLIC ACCOUNTABILITY AND PARTICIPATION ............................................................................ 19
2.4. PUBLIC MEETINGS ........................................................................................................................................ 20
2.5. INTEGRATED DEVELOPMENT PLAN (IDP) PARTICIPATION AND ALIGNMENT ...................................... 21
COMPONENT D: CORPORATE GOVERNANCE.............................................................................................................. 21
2.6. RISK MANAGEMENT ..................................................................................................................................... 21
2.7. BY-LAWS ........................................................................................................................................................ 22
2.8. WEBSITES ...................................................................................................................................................... 22 CHAPTER 3 – SERVICE DELIVERY PERFORMANCE (PERFORMANCE REPORT PART I) ............................................. 24
COMPONENT A: BASIC SERVICES ................................................................................................................................. 24
3.1. WATER PROVISION ....................................................................................................................................... 24
3.2. WASTE WATER (SANITATION) PROVISION ................................................................................................ 27
3.3. ELECTRICITY ................................................................................................................................................. 29
3.4. PROJECTS MANAGEMENT ........................................................................................................................... 31
3.5. WASTE MANAGEMENT (THIS SECTION TO INCLUDE: REFUSE COLLECTIONS, WASTE DISPOSAL, STREET CLEANING AND RECYCLING) ....................................................................................................... 32
3.6. HOUSING ........................................................................................................................................................ 34
3.7. FREE BASIC SERVICES AND INDIGENT SUPPORT ................................................................................... 35
COMPONENT B: ROAD and stormwater ........................................................................................................................... 36
3.8. ROADS AND STORM WATER MANAGEMENT ............................................................................................ 36
Msukaligwa Local Municipality | 2015/2016 Annual Report 3
3.9. STORM WATER DRAINAGE .......................................................................................................................... 39
COMPONENT C: PLANNING AND DEVELOPMENT ........................................................................................................ 39
3.10. PLANNING ...................................................................................................................................................... 39
3.11. LOCAL ECONOMIC DEVELOPMENT (INCLUDING TOURISM AND MARKET PLACES) ........................... 42
COMPONENT D: COMMUNITY & SOCIAL SERVICES .................................................................................................... 45
3.12. LIBRARIES and COMMUNITY FACILITIES ................................................................................................... 45
3.13. CEMETERIES AND CREMATORIUMS .......................................................................................................... 46
3.14. CHILD CARE; AGED CARE; SOCIAL PROGRAMMES ................................................................................. 48
COMPONENT E: ENVIRONMENTAL PROTECTION........................................................................................................ 49
3.15. POLLUTION CONTROL .................................................................................................................................. 49
3.16. BIO-DIVERSITY AND LANDSCAPE (INCL. OPEN SPACES AND SIDEWALKS) ......................................... 49
COMPONENT F: HEALTH ................................................................................................................................................. 50
3.17. HEALTH SERVICES ....................................................................................................................................... 50
3.18. CLINICS .......................................................................................................................................................... 50
3.19. AMBULANCE SERVICES ............................................................................................................................... 50
3.20. HEALTH INSPECTION; FOOD AND ABBATOIR LICENSING AND INSPECTION; ETC .............................. 50
COMPONENT G: SECURITY AND SAFETY ..................................................................................................................... 50
3.21. TRAFFIC SERVICES ...................................................................................................................................... 50
3.22. FIRE AND RESCUE SERVICES ..................................................................................................................... 53
3.23. DISASTER MANAGEMENT ............................................................................................................................ 56
3.24. LICENSING ..................................................................................................................................................... 57
COMPONENT H: SPORT AND RECREATION ................................................................................................................. 59
3.25. SPORT AND RECREATION ........................................................................................................................... 59
COMPONENT I: CORPORATE POLICY OFFICES AND OTHER SERVICES.................................................................. 60
3.26. EXECUTIVE AND COUNCIL .......................................................................................................................... 60
3.27. FINANCIAL SERVICES ................................................................................................................................... 60
3.28. HUMAN RESOURCE SERVICES ................................................................................................................... 61 CHAPTER 4 – ORGANISATIONAL DEVELOPMENT PERFORMANCE (PERFORMANCE REPORT PART II) .................. 62
COMPONENT A: INTRODUCTION TO THE MUNICIPAL PERSONNEL.......................................................................... 62
4.1. EMPLOYEE TOTALS, TURNOVER AND VACANCIES ................................................................................. 62
COMPONENT B: MANAGING THE MUNICIPAL WORKFORCE ...................................................................................... 64
4.2. POLICIES ........................................................................................................................................................ 64
4.3. INJURIES, SICKNESS AND SUSPENSIONS ................................................................................................ 65
COMPONENT C: CAPACITATING THE MUNICIPAL WORKFORCE ............................................................................... 67
4.4. SKILLS DEVELOPMENT AND TRAINING ..................................................................................................... 67
COMPONENT D: MANAGING THE WORKFORCE EXPENDITURE ................................................................................ 69
Msukaligwa Local Municipality | 2015/2016 Annual Report 4
4.5. EMPLOYEE EXPENDITURE .......................................................................................................................... 69 CHAPTER 5 – FINANCIAL PERFORMANCE ........................................................................................................................ 71
COMPONENT A: STATEMENTS OF FINANCIAL PERFORMANCE ................................................................................ 71
5.1. STATEMENTS OF FINANCIAL PERFORMANCE .......................................................................................... 71
5.2. GRANTS.......................................................................................................................................................... 72
5.3. ASSETS MANAGEMENT ................................................................................................................................ 73
5.4. FINANCIAL RATIOS BASED ON KEY PERFORMANCE INDICATORS ....................................................... 74
COMPONENT B: SPENDING AGAINST CAPITAL BUDGET............................................................................................ 78
5.5. CAPITAL EXPENDITURE ............................................................................................................................... 79
5.6. SOURCES OF FINANCE ................................................................................................................................ 79
5.7. CAPITAL SPENDING ON 5 LARGEST PROJECTS IN 2015/16 FY .............................................................. 80
5.8. BASIC SERVICE AND INFRASTRUCTURE BACKLOGS – OVERVIEW ...................................................... 82
COMPONENT C: CASH FLOW MANAGEMENT AND INVESTMENTS............................................................................ 84
5.9. CASH FLOW ................................................................................................................................................... 84
5.10. BORROWING AND INVESTMENTS .............................................................................................................. 85
5.11. PUBLIC PRIVATE PARTNERSHIPS .............................................................................................................. 86
COMPONENT D: OTHER FINANCIAL MATTERS ............................................................................................................ 86
5.12. SUPPLY CHAIN MANAGEMENT ................................................................................................................... 86
5.13. GRAP COMPLIANCE ...................................................................................................................................... 86 CHAPTER 6 – AUDITOR GENERAL AUDIT FINDINGS ........................................................................................................ 87
COMPONENT A: AUDITOR-GENERAL OPINION OF FINANCIAL STATEMENTS 2014/15 ........................................... 87
6.1. AUDITOR GENERAL REPORTS 2015/16 ...................................................................................................... 87 GLOSSARY ............................................................................................................................................................................ 89
APPENDICES ......................................................................................................................................................................... 91
APPENDIX A – COUNCILLORS; COMMITTEE ALLOCATION AND COUNCIL ATTENDANCE ...................................... 91
APPENDIX B – COMMITTEES AND COMMITTEE PURPOSES ...................................................................................... 95
APPENDIX C –THIRD TIER ADMINISTRATIVE STRUCTURE......................................................................................... 96
APPENDIX D – FUNCTIONS OF MUNICIPALITY / ENTITY ............................................................................................. 96
APPENDIX E – WARD REPORTING ................................................................................................................................. 98
APPENDIX F – WARD INFORMATION ........................................................................................................................... 103
APPENDIX G – RECOMMENDATIONS OF THE MUNICIPAL AUDIT COMMITTEE 2015/2016 ................................... 106
APPENDIX H – LONG TERM CONTRACTS AND PUBLIC PRIVATE PARTNERSHIPS ............................................... 108
APPENDIX I – MUNICIPAL ENTITY/ SERVICE PROVIDER PERFORMANCE SCHEDULE ......................................... 109
APPENDIX J – DISCLOSURES OF FINANCIAL INTERESTS ........................................................................................ 110
APPENDIX K: REVENUE COLLECTION PERFORMANCE BY VOTE AND BY SOURCE ............................................ 112
APPENDIX K (i): REVENUE COLLECTION PERFORMANCE BY VOTE ....................................................................... 115
Msukaligwa Local Municipality | 2015/2016 Annual Report 5
APPENDIX K (ii): REVENUE COLLECTION PERFORMANCE BY SOURCE ................................................................. 116
APPENDIX L: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG ....................................................................... 118
APPENDIX M: CAPITAL EXPENDITURE – NEW & UPGRADE/RENEWAL PROGRAMMES ...................................... 119
APPENDIX M (i): CAPITAL EXPENDITURE - NEW ASSETS PROGRAMME ................................................................ 119
APPENDIX M (ii): CAPITAL EXPENDITURE – UPGRADE/RENEWAL OF ASSETS PROGRAMME ............................ 122
APPENDIX N – CAPITAL PROGRAMME BY PROJECT 2015/16................................................................................... 125
APPENDIX O – CAPITAL PROGRAMME BY PROJECT BY WARD 2015/2016............................................................. 127
APPENDIX P – SERVICE CONNECTION BACKLOGS AT SCHOOLS AND CLINICS................................................... 128
APPENDIX Q – SERVICE BACKLOGS EXPERIENCED BY THE COMMUNITY WHERE ANOTHER SPHERE OF
GOVERNMENT IS RESPONSIBLE FOR SERVICE PROVISION .......................................................... 129
APPENDIX R – DECLARATION OF LOANS AND GRANTS MADE BY THE MUNICIPALITY ....................................... 129
APPENDIX S – DECLARATION OF RETURNS NOT MADE IN DUE TIME UNDER MFMA S71 ................................... 129
VOLUME II: ANNUAL FINANCIAL STATEMENTS .......................................................................................................... 130
Msukaligwa Local Municipality | CHAPTER 1 – MAYOR’S FOREWORD AND EXECUTIVE SUMMARY 6
CHAPTER 1 – MAYOR’S FOREWORD AND EXECUTIVE SUMMARY
COMPONENT A: MAYOR’S FOREWORD
In 2011, the democratically elected leadership has received an overwhelming mandate to
continue with its developmental agenda of eliminating poverty, reducing unemployment
and bettering the lives of our communities.
In the past four years and nine months as the municipality we have addressed the
following:-
PROMOTING MORE EFFECTIVE COMMUNITY PARTICIPATION IN MSUKALIGWA
We have strengthened the voice of the communities and ensured that adequate support
is provided for communities’ empowerment on decision making processes of the
municipality and on issues affecting their lives.
We have ensured that all ward committees are fully functional and better resourced; ward
councillors hold at least four ward constituency meetings per annum. Integrated,
developmental communication strategies are in place. Among others we have expanded
the communication platforms through the establishment and use of municipal quarterly
newsletter, the Community Radio Station etc.
We have community complains raised in various platforms i.e. Presidential Hotline, Memorandum etc. We have increased
the response level from 36% in 2011 to average of 89% in 2016.
SERVICE DELIVERY
INFRASTRUCTURE AND INTERGRATED HUMAN SETTLEMENTS
We have created 2009 new residential stands opportunities for the low- income households, through the formalisation of the
informal settlements. 600 stands 12 stands Wesselton Ext 1; 177 stands Wesselton Ext 2; 66 stands Wesselton Ext 4; 99
stands Wesselton Ext 5; and 600 stands Wesselton Ext 6.
We have established new townships and created 5484 residential stands opportunities for low to high income households.
484 stand for Ermelo Ext 43 (Next to new Ermelo-Nyibe); 4000 stands for Ermelo Ext 44 (Rietspruit Farm) and 1000 stand for
Wesselton Ext 7.
Working together with the Mpumalanga Provincial Department of Human Settlements we have restored the dignity of our
people by transferring the ownership of land and houses by issuing 1500 title deeds to the low – income households. 700 title
deeds Ermelo Ext 32, 33 and 34; 500 Ext 4 KwaZanele; 50 Ext 2 KwaDela; 150 Wesselton Ext 3; Lothair; Warburton etc.
WATER AND SANITATION
We have increased access to water from approximately 37000 households in 2011 to approximately 42 000 households in
2016.
Approximately 38000 household have access to flush toilets and provided 76 boreholes and 499 VIP’s toilets in farms areas.
We installed 12 km 350 diameter pipe from the Department of Water Rietspruit Reservoir to the Municipal Northern Water
Treatment Works to alleviate water shortage and also to work as an emergency water supply in times of need.
Approximately 38 000 households received free 6kl and free basic sewer per month per household.
ELECTRIFICATION
We have electrified 2564 new households; 50 household at erf 4105 (ward 1); 74 Wesselton Ext 4; 443 Wesselton Ext 6; 927
Wesselton Ext 11 (Khayelihle); 191 Ermelo Ext 33; 546 Ermelo Ext 34; 18 households opposite Qambekile School; 40
households Breyten- Tambo.
We have upgraded 11Kv Wesselton switching station and 11KV main Sub-station. We built a switch station / substation
88/11Kv Ermelo Ext 33. Installation of 10 high mast lighting across all wards.
Working together with Eskom we have electrified 122 households at Chressiesmeer; 557 household in 15 farms; 342
households in 4 villages and 120 household in 3 CPA.
ROADS
Cllr. J. S. Bongwe
Executive Mayor
Msukaligwa Local Municipality | 2015/2016 Annual Report 7
We have upgraded gravel roads to tar / paving of 8.406 KM. (1.3 km Silindile Road (Lothair); 1 km Amsterdam weg Ext 32
&33; 1.306 km Isidingo / link road Kwachibikhulu; 900 m Manana Street (Ext 1); 200 m Mokoena Street (Ext 1); 550 m in PS
Simelane Street (ward 3); 1.7 km Phosa village ( Breyten) ; 430m KwaZanele ; 620m President Fouche Street Ext 18; and
together with the District Municipality, we have also attended to the potholes on our main roads. Although much more
attention and budget need to be invested in this regard.
CONCLUSION
We hope that the mandate that was given to us was executed with honesty and diligence against a myriad of obstacles and
historical odds. We also believe that we have further consolidated a foundation from where the struggle to emancipate our
people from shackles of poverty, unemployment and inequality can be taken forward with relative ease.
We are also confident that if the community can be actively involved on issues of development, much more can be achieved
in the current second phase of our transition into social economic transformation.
Thank you!
Cllr. J.S. Bongwe Executive Mayor
Msukaligwa Local Municipality | 2015/2016 Annual Report 8
COMPONENT B: EXECUTIVE SUMMARY
1.1. MUNICIPAL MANAGER’S OVERVIEW
The year 2015/2016 was one of those years in which the municipality grabbled with number challenges which amongst others include cash flow challenges that had an impact on service delivery, the high Eskom bill and inability to implement most the key service delivery projects. As a result of the various challenges that the municipality faced, some projects could not be implemented due the downscaling of the Municipal Infrastructure Grant. The positions of the Chief Financial Officer which remained vacant over the year under review, also had a bearing on the overall financial performance of the municipality though Council had in June 2016 approved the appointment of the CFO who therefore resumed duties in the 2016/2017 financial year.
The overall performance of the municipality for the 2015/2016 financial year in respect of
service delivery remained the same as compared to 2014/2015 financial year in which we have
experienced a limited success on implementation of new projects due the downscaling of the
MIG as well as the limited revenue for maintenance and upgrading of the municipality’s ageing
infrastructure. We have seen some sporadic service delivery protests mostly on water and
electricity supply at some wards of the municipality of which the municipality has plans in place to address such issues as
contained in the municipal IDP. The spending on the Municipal Infrastructure Grant had slightly improved from R 33,766,603
to R 35,089,356 in the 2015/2016 financial year but still remains a course for concern considering the MIG allocation for the
year under review. The original MIG allocation for 2015/2016 was R 61,066,000 which was mainly allocated for water and
sanitation projects and due to failure in implementing some of the projects by the appointed service provider, the funds were
downscaled by R 11,000,000 which had a significant impact on the performance of the municipality.
The financial position of the municipality continued to be under severe pressure as it was in the previous financial year which
sees the municipality being dependent on the equitable share allocation. Considering the liquidity of the municipality, it is
evident that the municipality may in future struggle to finance its short-term liabilities should drastic steps not be taken on the
implementation of strategies to increase its revenue streams. The cash position of the municipality in terms of money
available decreased from R 29,958,697 to R 19,264,769 being a decrease of R 10,693,928.
With regard to the audit outcome, there is an improvement as the municipality has received a qualified audit opinion with
findings as opposed to the previous year’s disclaimer audit opinion which is a sign of commitment by the municipality to
improve its performance.
The municipality shall therefore endeavour within its available resources and through implementation of necessary policies
and programmes work towards improving the financial situation and addressing the various challenges as experienced in the
2015/016 financial year.
Mr. Z. T. Shongwe
Municipal Manager
Z.T. Shongwe
Municipal Manager
Msukaligwa Local Municipality | 2015/2016 Annual Report 9
1.2. MUNICIPAL FUNCTIONS, POPULATION AND ENVIRONMENTAL OVERVIEW
INTRODUCTION TO BACKGROUND DATA The municipality performs its functions in terms of Section 152 and 153 of the Constitution of the Republic of South Africa, Act 108 of 1996. In addition to the provisions of Section 152 and 153, Schedule 4, Part B of the Constitution provide for the functional areas of the local municipality of the municipality is rendering such services. It should however be borne in mind that some of the function may not be applicable to this municipality while some are rendered by the District Municipality since the municipality does not have capacity. Those services that are not rendered by this municipality are indicated in this document. Improving the lives of the citizens of the municipality through provision of improved service delivery remains at the centre of the municipal priorities hence the municipality has through the District, Municipal Infrastructure Grant (MIG) and other funding extended its services to rural/farms communities by providing water through boreholes, sanitation and electricity. To this far almost all farm settlements have access to basic water, sanitation through VIP toilets and electricity. It should however be borne in mind that there are some areas that still need services provision at rural/ farm areas which the municipality is working on. Resistance by some of farm/land owners also poses a challenge on provision some services as they have to consent for such. All urban areas within the municipality have access to running water which includes informal settlements areas where water is provided through communal taps. The municipality has further endeavored to meet the millennium target of eradicating the bucket system at all its towns with the exception of informal settlements where pit latrines are still used. In dealing with the informal settlements, the municipality has plans in place to relocate those settlements where in-situ development is not possible and developed those that could be developed. T 1.2.1
Municipal Demographics
Msukaligwa population dynamics is based on statistics derived from Statistics South Africa 2001 to 2011. The 2014 estimated population figures were calculated based on the growth rate between 2001 and 2011. Statistics South Africa data had been used for the demographics and where data could not be derived from Statistics South Africa, other sources had been used. The population of Msukaligwa showed a grown of 19.7% from 2001 to 2011 at an average annual growth of 1.8% and grew with 24,564 persons. There is an estimated growth of 11,167 persons from 2011 to 2015 with total growth 35,731 persons during the period 2001 to 2015
Population Details
Age Groups
2001 2011 2016 (Community Survey)
Male Female Total Male Female Total Male Female Total
0-4 6,882 7,017 13,902 8,301 8,273 16,574 8818 8886 17704
5-9 7,351 7,376 14,753 7,590 7,271 14,861 7433 7109 14542
10-14 7,455 7,479 14,911 7,030 6,944 13,974 6774 6741 13515
15-19 6,972 7,128 14,110 7,532 7,542 15,074 7860 7904 15764
20-24 5,124 5,936 11,058 8,089 7,908 15,997 8853 8933 17786
25-29 4,819 5,607 10,416 7,969 7,520 15,489 9461 9600 19061
30-34 4,309 4,701 9,011 5,829 5,359 11,188 8155 7017 15172
35-39 4,038 4,317 8,381 4,794 4,741 9,535 6117 5843 11960
40-44 3,406 3,661 7,040 4,125 4,191 8,316 4823 4551 9374
45-49 2,745 2,956 5,697 3,427 3,921 7,348 3775 3567 7342
50-54 2,307 2,380 4,660 3,001 3,238 6,239 2942 3151 6093
55-59 1,530 1,510 3,038 2,417 2,673 5,090 2847 2727 5574
60-64 1,198 1,519 2,729 1,656 1,970 3,626 1815 2102 3917
65-69 758 1,046 1,795 969 1,192 2,161 1360 1496 2856
70-74 564 806 1,374 649 1,082 1,731 788 1331 2119
75-79 325 556 876 365 638 1,003 301 589 890
Msukaligwa Local Municipality | 2015/2016 Annual Report 10
80+ 334 701 1035 370 801 1,171 319 620 939
TOTAL 60,119 64,694 124,813 74,113 75,264 149,377 82442 82166 164608
Source: Statistics SA Census 2001 & 2011
T 1.2.2
Socio Economic Status (as a %)
Year Housing Backlog as proportion of
current demand
Unemployment Rate HIV/AIDS
Prevalence
Illiterate people older than
14 years
2011/12 9% 26% 37% 12%
2012/13 9% 26% 36% 9.8%
2013/14 14% 26.8% 37.1% 9.4%
2014/15 15% 26.8% 34.4% 8.8%
2015/16 15% 26.8% 34.4% 8.8%
T1.2.4
–
5
10
15
20
25
30
35
40
45
2011/12 2012/13 2013/14 2014/15 2015/16
Households in Poverty
Number of households in municipal area Number of poor households in municipal area
T1.2.
Msukaligwa Local Municipality | 2015/2016 Annual Report 11
T1.2.5
Natural Resources
Major Natural Resource Relevance to Community
Coal Mining opportunities, transportation, employment opportunities and economic
development.
Arable land Agricultural production, forestry, employment opportunities, economic
development and poverty alleviation.
T1.2.7
0%
5%
10%
15%
20%
25%
30%
35%
40%
Housing Backlog asproportion of current
demand
Unemploy-ment Rate HIV/AIDS Prevalence Illiterate people olderthan 14 years
Socio Economic Status
2011/12 2012/13 2013/14 2014/15 2015/16
Msukaligwa Local Municipality | 2015/2016 Annual Report 12
1.3. SERVICE DELIVERY OVERVIEW
SERVICE DELIVERY INTRODUCTION The municipality is responsible for delivery of basic services to its community in terms of the provisions of Schedule 4 of the Constitution of the Republic of South Africa as well as Section 152 which provides for the object of Local Government which requires the municipality to provide the following:
(a) to provide democratic and accountable government for local communities; (b) to ensure the provision of services to communities in a sustainable manner; (c) to promote social and economic development; (d) to promote a safe and healthy environment; and (e) to encourage the involvement of communities and community organizations in the matters of local government.
Section 152 (2) further provides that a municipality must strive, within its financial and administrative capacity, to achieve the objects set out in subsection (1) The Integrated Development Plan of the municipality is therefore prepared in line with the provisions of the said Act and all other legislative mandates to ensure service delivery to its constituent communities.
T 1.3.1
T1.3.2
0%
20%
40%
60%
80%
100%
2011/12 2012/13 2013/14 2014/15 2015/16
Proportion of households with access to basic services
Electricity service connections Water - available within 200 m from dwelling
Sanitation - Households with at leats VIP service Waste collection - kerbside collection once a week
Msukaligwa Local Municipality | 2015/2016 Annual Report 13
ACCESS TO BASIC SERVICES As depicted in the diagram above, service delivery in respect of electricity, water, sanitation and waste collection has improved over the past five years though a slide drop on water provision may be evident. The drop in water supply was as a result of new settlements that emerged and the water issue is being addressed. Communal water supply within 200m from dwellings has also been reduced as a result of formalization of most of the informal settlements and water is connected to the yards or houses where houses are built. There is quite a significant progress made in electricity connections to households except areas where houses were not yet completed and in the informal settlements that cannot be formalized. There are some areas that need to be electrified and they in the municipal plans to be electrified. Provision of VIP sanitation services to farm areas has covered most the areas in the municipality and since decision has been taken at the provincial level to replace the VIP toilets with convertible water borne toilets system, the municipality will continue providing sanitation services through the new system until all farm dwellers have access to sanitation. About 17% of the households within Msukaligwa do not have hygienic sanitation services and provisions have been made for the future years to provide the service through the convertible water borne toilets. 12% of the households that do not have hygienic sanitation are in the informal settlements within various towns including Nganga Township in Warburton where sewer reticulation was completed but no connections were made due to challenges in related to water supply. With regard to waste collection, household waste is collected twice a week in all townships except Everest Park, Long Homes, Klipbou and Ermelo suburbs which is collected once a week with the exception of Warburton and Sheepmoor due to lack of resources and dumping sites as well as the fact that communities at these areas are not billed for the services.
T1.3.3
1.4. FINANCIAL HEALTH OVERVIEW
FINANCIAL OVERVIEW Municipality has cash flow challenges due to high level of nonpayment, distribution loses and illegal connections. In an endeavor to address the cash flow challenges, a Financial Recovery Plan was developed in which short, medium and long term strategies are contained. The following are therefore the strategies:
(a) Strategy One: Restructure the Budget (b) Strategy Two: Revise Tariff Policies and Tariff Increases (c) Strategy Three: Revenue Enhancement (d) Strategy Four: Financial Administration (e) Strategy Five: Cash Management Strategy (f) Strategy Six: Human Resource Management
T1.4.1
Financial Overview – 2015/16
R' 000
Details Original budget Adjustment Budget Actual
Income
Grants 182 299 213 423 170 498
Taxes, Levies and tariffs 379 802 379 607 273 288
Other 43 137 49 734 137 736
Sub Total 605 238 642 764 581 522
Less Expenditure 652 911 666 706 736 566
Net Total* -47 673 -23 942 -155 034
Msukaligwa Local Municipality | 2015/2016 Annual Report 14
* Note: surplus/(- deficit) T1.4.2
Operating Ratios
Detail %
Employee Cost 20.45%
Repairs & Maintenance 3.39%
Finance Charges & Depreciation 20.47%
T1.4.3
Capital Budget
R'000
Detail 2011/12 2012/13 2013/14 2014/15 2015/16
Original Budget 39 967 44 058 63 981 56 622 61 066
Adjustment Budget 50 959 44 058 57 981 51 572 50 173
Actual 42 447 23 289 50 365 47 778 52 605
T1.4.4
T1.4.5
COMMENT ON CAPITAL EXPENDITURE The projects for 2015/2016 financial year were implemented late and some projects still on the design stage hence the less expenditure and draw down of R 11.1M. The electricity projects undertaken in the 2015/2016 financial year included the upgrading of the 11kv Main Intake point.
T 1.4.5.1
0
20 000
40 000
60 000
80 000
2011/12 2012/13 2013/14 2014/15 2015/16
Capital Expenditure
Original Budget Adjustment Budget Actual
Msukaligwa Local Municipality | 2015/2016 Annual Report 15
1.5. ORGANISATIONAL DEVELOPMENT OVERVIEW
ORGANISATIONAL DEVELOPMENT PERFORMANCE Organizational development matters are to be re-enforced on annual basis following the organizations wide analysis outcome pertaining to attitudes, belief and values of employees in order to adapt the organization to the external environment. Msukaligwa local municipality re-enforced the implementation of the following organizational development interventions for the year under review. WORKPLACE SKILLS PLAN The Municipality developed, adopted and implemented a Workplace Skills Plan with the following targets:
Target Actual Performance
Number of councilors trained 38 24
Number of officials trained 126 28
BATHO PELE SERVICE STANDARDS The Municipality adopted and implemented the Batho Pele Service Charter in all functional areas of the Municipality.
Community Satisfaction Survey
Batho Pele Services Charter
Personnel Name tags
Customer Care Centre
Security / Information Desk in the main building EMPLOYMENT EQUITY PLAN The Municipality has developed the Employment Equity Plan with clear numerical targets for the financial year 2015/2016. Refer to Chapter 4 for detailed numerical targets. EMPLOYEE PERFORMANCE MANAGEMENT SYSTEM The Municipality has since adopted a Performance Management Framework on the 31st March 2015 and it is currently being implemented to establish an effective Performance Management System. Currently it is being done on Section 54A and Section 56 of the Municipal Systems Act. T1.5.1
1.6. AUDITOR GENERAL REPORT
AUDITOR GENERAL REPORT 2014/2015 The municipality has received a Qualified Audit Opinion with the following matters:
Property plant and equipment
Value Added Tax
Irregular expenditure
Receivables from exchange transactions
Msukaligwa Local Municipality | 2015/2016 Annual Report 16
The full report of the Auditor General for 2015/2016 will be attached as Appendix Volume II. T 1.6.1
1.7. STATUTORY ANNUAL REPORT PROCESS
No. Activity Timeframe
1
Consideration of next financial year’s Budget and Integrated Development Plan (IDP) process plan.
Except for the legislative content, the process plan should confirm in-year reporting formats to ensure
that reporting and monitoring feeds seamlessly into the Annual Report process at the end of the
Budget/IDP implementation period. July
2 Implementation and monitoring of approved Budget and Integrated Development Plan (IDP)
commences (In-year financial reporting).
3 Finalise 4th quarter Report for previous financial year
4 Submit draft 11/12 Annual Report to Internal Audit and Auditor-General
5 Municipal entities submit draft annual reports to Municipal Manager
6 Audit/Performance committee considers draft Annual Report of municipality and entities (where
relevant)
August
8 Mayor tables the unaudited Annual Report
9 Municipality submits draft Annual Report including consolidated annual financial statements and
performance report to Auditor General.
10 Annual Performance Report as submitted to Auditor General to be provided as input to the Integrated
Development Plan (IDP) Analysis Phase
11 Auditor General assesses draft Annual Report including consolidated Annual Financial Statements
and Performance data
September -
October
12 Municipalities receive and start to address the Auditor General’s comments
November 13
Mayor tables Annual Report and audited Financial Statements to Council complete with the Auditor-
General’s Report
14 Audited Annual Report is made public and representation is invited
15 Oversight Committee assesses Annual Report
16 Council adopts Oversight report
December 17 Oversight report is made public
18 Oversight report is submitted to relevant provincial councils
19 Commencement of draft Budget and finalization of the draft Integrated Development Plan (IDP) for the
next financial year. Draft Annual Report and Oversight Reports to be used as input. January
T1.7.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 17
CHAPTER 2 – GOVERNANCE
2.
2.1. POLITICAL GOVERNANCE
Cllr. B.M. Vilakazi Speaker
POLITICAL STRUCTURE
Executive Mayor Cllr. J.S. Bongwe
MEMBER OF THE MAYORAL COMMITTEE
Cllr. N.G. Mashinini Chief Whip
Cllr. M.P. Nkosi MMC for Technical, Community and Public Safety Department
Cllr. V.C.N. Madini MMC for Finance and Corporate Services Dept.
COUNCILLORS Refer to Appendix A where a full list of Councilors can be found (including committee allocations and attendance at council meetings). T2.1.2
Msukaligwa Local Municipality | 2015/2016 Annual Report 18
2.2. ADMINISTRATIVE GOVERNANCE
INTRODUCTION TO ADMINISTRATIVE GOVERNANCE Msukaligwa Local Municipality achieved administrative governance by complying to municipal legislation and regulations as follows: 1. The Integrated Development Plan (IDP) for 2015/2016 financial year was adopted in accordance with the provisions of the Municipal Systems Act. 2. The Service Delivery and Budget Implementation Plan (SDBIP) for 2015/2016 was approved by the Executive Mayor in accordance with the provisions of the Municipal Finance Management Act (MFMA). 3. Performance Agreements for 2015/2016 financial year were signed within the 1st month of the financial year and submitted to the Member of the Executive Council (MEC) for Cooperative Governance and Traditional Affairs (Cogta) as per the provisions of the performance regulations. 4. Performance Management is implemented at the strategic level for Section 56 employees as required by the Municipal Systems Act. 5. There were two Audit committee meetings held in the 2015/2016 financial year. 6. Mid- year performance reports for 2015/2016 was submitted to Council as per Section 72 of the Municipal Finance Management Act (MFMA) including the 3rd and the 4th quarter Service Delivery and Budget Implementation Plan (SDBIP) reports. 7. The municipality engaged the services of consultants to assist in dealing with findings identified by the Auditor General pertaining to administrative governance as well as compilation of the AFS. 8. The municipality filled the positions of Chief Financial Officer during the 2015/2016 financial year. T2.2.1
TOP ADMINISTRATIVE STRUCTURE
MUNICIPAL MANAGER Mr. Z.T. Shongwe TIERS 2
DIRECTORS Mr. N.L. Maimela Director: Corporate Service Ms. M.M.P. Matsheka Chief Financial Officer
Msukaligwa Local Municipality | 2015/2016 Annual Report 19
Mr. D.I. Maluleke Director: Public Safety Mr. B.C. Sibeko Director: Community Services Mr. S.R. Magudulela Director: Technical Services
T2.2.2
COMPONENT B: INTERGOVERNMENTAL RELATIONS
2.3. INTERGOVERNMENTAL RELATIONS
INTERGOVERNMENTAL STRUCTURE Intergovernmental structures in which engagements are taking place comprise the Provincial Planners Forum, District IDP Management Committee, District and Local IDP Rep Forum and PCF meetings other plenary meetings in which the municipality participate for plenary and strengthening of IGR. In the Provincial Planners Forum, the planning cycles of the provincial government and the municipal planning cycles are discussed in order to have a common understanding on how these cycles complement each other and how best can municipal planning be timed to assist in contributing to the provincial planning process. These meetings have benefited the municipality to have a better understanding on how our planning cycles influence the proper planning of other spheres of government. The District or Local forums and committees provide a platform for interaction on planning issues, information sharing and learning from best practices between municipalities and other spheres of government. There has been a great improvement on the packaging of our IDP and valuable information was obtained from these meetings or forums. T2.3.2
COMPONENT C: PUBLIC ACCOUNTABILITY AND PARTICIPATION
OVERVIEW OF PUBLIC ACCOUNTABILITY AND PARTICIPATION In terms of Section 152 of the Constitution of the Republic of South Africa, Local Government Municipal Systems Act, Act 32 of 2000 as amended and Local Government Structure Act, Act 117 of 1998, Municipalities are required to:
Encourage the involvement of communities and the community organisations in matters of Local Government.
Develop the culture of participatory development.
Establish ward committees as a vehicle for community participation. Community Participation takes place to involve communities during the following processes:
(i) The preparation, implementation and review of the Integrated Development Plan (IDP). (ii) The establishment implementation and review of its Performance Management System (iii) Preparation of the Budget.
The following are structure established to promote community participation:
Integrated Development Plan (IDP)Representative Forum
Local Economic Development (LED) Forum
Msukaligwa Local Municipality | 2015/2016 Annual Report 20
Ward Committees and Ward Community Meetings
Local Geographic Names Committee
Community Development Workers
News Letter Community Participation Programmes per ward were developed and implemented. Refer to Appendix E which contains further details on ward committee governance and to Appendix F that contains performance data on a ward basis. T 2.4.0
2.4. PUBLIC MEETINGS
COMMUNICATION FORUMS The municipal communication is responsible for overarching communication policy, strategy, information dissemination, Presidential Hotline, media monitoring, media liaison, Communication research, Municipal newsletter, Website content development and management, Event management, corporate advertisement / branding. The unit also contributes to Gert Sibande District Municipality and Mpumalanga South African Local Government Association quarterly newsletter. COMMUNICATION INSTITUTIONAL ARRAGEMENT There is no dedicated Communication Unit within the Municipality. The Official responsible for communication is placed in the Office of the Executive Mayor and administratively accountable to the Office of the Municipal Manager via the Manager in the Office of the Executive Mayor. COMMUNICATION FORUM The municipality attends and participates at the District and Provincial Government Communicators Forum. LEGISLATIVE FRAMEWORK There are various pieces of legislations that give credence to the existence and functioning of local Government Communication which amongst others include the following: Constitution Act 108 of 1996
Section 152 (1)(e): that municipalities must encourage the involvement of communities and community organizations in matters of local government.
Section 160(7): A municipal council must conduct its business in an open manner, and may close its sittings, or those of its committees, only when it’s reasonable to do so.
Local Government: municipal Systems Act, 2000
Section 21: communication with local community must take place through the following. Promotion of Access to information Act , Act No.2 of 2000
This act operationalizes sections 8 and 32 of the constitution, it foster the culture of transparency and accountability and promotes effective access to information to protect an individual’s rights.
Msukaligwa Local Municipality | 2015/2016 Annual Report 21
Promotion of Administrative Justice Act. Act No 3 of 2000
The act requires that all decisions of administrative bodies have to be lawful, procedurally fair and reasonable.
People have the right to be given reasons for decisions that adversely affect them which are taken by the government officials.
Protection of Disclosure Act, Act No 26 of 2000
The act protects people who speak out against government corruption, dishonesty and bad administration. T 2.4. 1
2.5. INTEGRATED DEVELOPMENT PLAN (IDP) PARTICIPATION AND ALIGNMENT
IDP Participation and Alignment Criteria* Yes/No
Does the municipality have impact, outcome, input, output indicators? Yes
Does the IDP have priorities, objectives, KPIs, development strategies? Yes
Does the IDP have multi-year targets? Yes
Are the above aligned and can they calculate into a score? Yes
Does the budget align directly to the KPIs in the strategic plan? Yes
Do the IDP KPIs align to the Section 57 Managers Yes
Do the IDP KPIs lead to functional area KPIs as per the SDBIP? Yes
Do the IDP KPIs align with the provincial KPIs on the 12 Outcomes Yes
Were the indicators communicated to the public? Yes
Were the four quarter aligned reports submitted within stipulated time frames? Yes
* Section 26 Municipal Systems Act 2000
T2.5.1
COMPONENT D: CORPORATE GOVERNANCE
2.6. RISK MANAGEMENT
RISK MANAGEMENT The municipality needs to have systems that are proactively continuously identifying, evaluating, analysing, measuring and managing risks that might directly affect the municipality so that it is able to put in key control measures in addressing those risks. The risk management unit helps in identifying and putting measures in place to contain, avoid or transfer the risk concerned. Currently there are systems in place to monitor the identified risks, a Risk Management Committee was established and a continuous yearly risk management implementation plan was designed together with the risk register to monitor and manage identified risk. As per risk assessment conducted during the financial year, 73 risks were identified with their magnitudes as follows:
Risk Magnitude No of Risk per Risk Magnitude
Maximum Risk 28
High Risk 21
Medium Risk 11
Msukaligwa Local Municipality | 2015/2016 Annual Report 22
Low Risk 12
Minimum Risk 1
Total number of Risk Identified 73
T2.6.1
2.7. BY-LAWS
By-laws Introduced during 2015/16
Newly Developed Date Revised Public Participation Conducted Prior to Adoption of By-Laws (Yes/No)
Dates of Public Participation
Date of Publication
None
T2.9.1
2.8. WEBSITES
Municipal Website : Content and Currency of Material
Documents published on the Municipality's / Entity's Website <Yes / No> Publishing Date
Annual and adjustment budget and budget-related policies Yes 2015-07-24
All current budget-related policies Yes 2015-06-20
The previous annual report (2014/2015) Yes
The annual report (2015/2016) published/to be published Yes To be published after
Council’s approval
All current performance agreements for 2015/16 as required in terms of section
57(1)(b) of the Municipal Systems Act. No None
All service delivery agreements (2014/2015) No None
All long-term borrowing contracts (2014/2015) No None
All supply chain management contracts above a prescribed value ( give value) for
2015/2016 No None
An information statement containing a list of assets over a prescribed value that
have been disposed of in terms of section 14 (2) or (4) during 2015/2016 No None
Contracts agreed in 2015/2016 to which subsection (1) of section 33 apply,
subject to subsection (3) of that section No None
Public-private partnership agreements referred to in section 120 made in
2015/2016 No None
All quarterly reports tabled in the council in terms of section 52 (d) during
2015/2016 No None
T2.10.1
COMMENT ON MUNICIPAL WEBSITE CONTENT AND ACCESS The Municipal Website is functional and accessible to the public. The following documents are available on the website:
Integrated Development Plan (IDP)
Msukaligwa Local Municipality | 2015/2016 Annual Report 23
Service Delivery Budget implementation Plan (SDBIP)
Budget and Budget related policies
Annual Financial Statements
Annual Reports
Vacant positions
Tenders
By-Laws and other related information. The Municipal libraries have internet access for the public to access inforamtion and the Msukaligwa Local Municipality website address is www.msukaligwa.gov.za. T2.10.1.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 24
CHAPTER 3 – SERVICE DELIVERY PERFORMANCE (PERFORMANCE REPORT PART I)
COMPONENT A: BASIC SERVICES
This component includes: water; waste water (sanitation); electricity; waste management; and housing services; and a summary of free basic services. 3.
3.1. WATER PROVISION
INTRODUCTION TO WATER PROVISION Msukaligwa is a water services authority which provides water to all households and businesses within its areas. The raw water sources for Msukaligwa
Brummer
Douglas dam
Department of Water and Sanitation (DWS) (Jericho scheme), and other sources are:
Torbanite dam for Breyten and Chrissiesmeer
Mpuluzi River for Lothair.
Farming and rural areas use boreholes as well as Sheepmoor and Warburton Drought water sources Department of Water and Sanitation (DWS) appointed Rand Water to resolve water shortages in Ermelo/Wesselton and the project included the following:
Upgrading of purification plants
Installation of raw water emergency pipe line.
A service provider was appointed to detect water loss management
Regional bulk water infrastructure projects. Achievements The Municipality has over the past five years (2011/2012 – 2015/2016) in implementing its five year Integrated Development Plan (IDP), managed to provide water to 11156 households which constitute 5% increase in households with access to basic level of water services. As at the end of the 2015/2016 financial year, the backlog on water provision has been at 8% (4243 households) and plans are in place to provide 1411 households over the next two financial years should enough funds be available. The process of providing water to communities will continue in future until all households are provided with water. Municipal Infrastructure Grant (MIG)
Drilling of boreholes in farms and rural areas; and
Extend water reticulation in Sheepmoor. The above projects were implemented in the tune of R 8,800,000 and other projects were still at a design stage by the end of the financial year. The Blue drop status as rated in 2014 for the municipality was at 18.1% worse than the 2012 rating of 21% which depicts a critical performance for the municipality. T3.1.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 25
Total Use of Water by Sector (cubic meters)
Agriculture Forestry Industrial Domestic
Unaccountable water
losses
2011/12 0 0 0 4083861 29%
2012/13 0 0 0 4727943 36%
2013/14 0 0 0 3115578 55%
2014/15 0 0 0 6408650 65%
2015/16 0 0 0
T3.1.2
Water Service Delivery Levels
Households
Description 2011/12 2012/13 2013/14 2014/15 2015/16
Actual Actual Actual Actual Actual
No. No. No. No. No.
Water: (above min level)
Piped water inside dwelling 21,707 21,707 22,552 22,552 22,552
Piped water inside yard (but not in dwelling) 11,370 11,670 11,670 11,670 11,809
Using public tap (stand pipes )
Other water supply (within 200m) 2,614 2,614 2 ,614 2,864 12,486
Minimum Service Level and Above sub-total 35,691 35,991 36,836 37,086 46,847
Minimum Service Level and Above Percentage 87% 88% 90% 91% 92%
Water: (below min level)
Using public tap (more than 200m from dwelling) 2,586 2,044 0 0 0
Other water supply (more than 200m from dwelling 0 0 2,868 3,846 4,243
No water supply 2,655 2,897 1,228 0 0
Below Minimum Service Level sub-total 5,241 4,941 4,096 3,846 4,243
Below Minimum Service Level Percentage 13% 12% 10% 9% 8%
Total number of households* 40,932 40,932 40,932 40,932 51,098
* - To include informal settlements
T3.1.3
The wording “within/more 200m from dwellings” be replaced with “stand pipes” as it challenging to measure.
Msukaligwa Local Municipality | 2015/2016 Annual Report 26
Households - Water Service Delivery Levels below the minimum
Description Households
2011/12 2012/13 2013/14 2014/15 2015/16
Actual
No.
Actual
No.
Actual
No.
Actual
No.
Actual
No.
Formal Settlements
Total households 34,569 34,569 34,567 34,877 46,279
Households below minimum service
level 0 0 0 0 0
Proportion of households below
minimum service level 0 0 0 0 0
Informal Settlements
Total households 6,363 6,363 6,365 6,055 4,819
Households that’s below minimum
service level 6,363 6,363 4,916 2,893 4,243
Proportion of households that’s below
minimum service level 18% 18% 14% 8% 9%
Water Service Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of households with access to basic water
Increase the number of households accessing water supply
35,710 35,991 36,551 36,836 37,122 37,086 38,344 46,855 47,299
Number of boreholes drilled
Increase the number of households accessing water supply
0 0 16 30 18 22 22 19 0
Percentage of damaged water pipes repaired within 24hrs after being reported.
Water pipe bursts repaired or replaced within 24hrs of being reported.
450 (100%)
466 (100%)
100% 98% 100% 95% 100% 99% 100%
T3.1.6
Msukaligwa Local Municipality | 2015/2016 Annual Report 27
Employees: Water Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies (fulltime) Vacancies (as a % of
total posts)
0 - 3 0 1 0 1 100%
4 - 6 1 1 1 0 0%
7 - 9 11 12 11 1 9.09%
10 - 12 7 27 11 16 59.26%
13 - 15 0 4 0 4 100%
16 - 17 17 40 15 25 62.50
Total 36 85 38 47 55.29%
Totals should equate to those included in the Chapter 4 total employee schedule. Employees and Posts numbers are as at 30
June. *Posts must be established and funded in the approved budget or adjustments budget. Full-time equivalents are
calculated by taking the total number of working days lost (excluding weekends and public holidays) while a post remains
vacant and adding together all such days lost by all posts within the same set (e.g. ‘senior management’) then dividing that total
by 250 to give the number of posts equivalent to the accumulated days.
T3.1.7
3.2. WASTE WATER (SANITATION) PROVISION
INTRODUCTION TO SANITATION PROVISION Msukaligwa provides sanitation services to all households and businesses within its jurisdiction in accordance with Schedule 5 part B of the Constitution. Since the municipality comprises of rural urban areas, sanitation services is provided through construction of VIP toilets (convertible water borne toilets) at rural areas and water borne toilets at urban areas. The sanitation service extends to sucking of septic tanks at those areas with septic tanks. Achievements Since 2011/2012 financial year, the households with minimum level of sanitation services have increased from 32,236 to 49,803 or from 79% to 97% leaving us with a backlog 3%. During the year 2015/2016, 36 water borne toilets were constructed at Jericho Farm by the MIG. The provision of sanitation services has been implemented over the past five years form 2011/2012– 2015/2016 through the following projects:
Installation of Convertible Waterborne Toilets in farm areas
Sewer reticulation and construction of water borne toilets at urban/township areas. The total cost of the above projects amounted to R 2,800,378.00. The projects were completed but it was established that more fund are required to complete the outstanding projects. Though water borne sewer is provided in the urban areas, the ageing infrastructure remains a challenge causing regular blockages that cause effluent overflows which is currently under investigation. The Green drop status as rated in 2014 for the municipality was at 98.5% worse than the 2013 rating 96.3% which depicts a critical performance for the municipality. T3.2.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 28
Sanitation Service Delivery Levels
*Households
Description 2011/12 2012/13 2013/14 2014/15 2015/16
Actual Actual Actual Actual Actual
No. No. No. No. No.
Sanitation/sewerage: (above minimum level)
Flush toilet (connected to sewerage) 29, 410 29,410 30,255 30,510 31,710
Flush toilet (with septic tank) 912 912 912 912 912
Chemical toilet 321 321 321 321 321
Pit toilet (ventilated) 1,593 2,061 2,194 2,194 16,860
Other toilet provisions (above min. service level) 0 0
0
Minimum Service Level and Above sub-total 32,236 32,704 33,682 33,937 49,803
Minimum Service Level and Above Percentage 79% 80% 82% 83% 97%
Sanitation/sewerage: (below minimum level)
Bucket toilet 0 0 0 0 0
Other toilet provisions (below min. service level) 6,491 6,023 5,045 4,790 0
No toilet provisions 2,205 2,205 2,205 2,205 1,295
Below Minimum Service Level sub-total 8,696 8,228 7,250 6,995 1,295
Below Minimum Service Level Percentage 21% 20% 18% 17% 3%
Total households 40,932 4,0932 40,932 40,932 51,098
*Total number of households including informal settlements
T3.2.3
Waste Water (Sanitation) Service Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of
households
with access to
basic
sanitation
Increase in
number of
households
having
access to
basic level
of
sanitation.
32,447 32,704 32,847 33,682 33,433 33,937 34,900 49,803 50,149
Number of
rural
households
provided with
convertible
water borne
toilets
0 0 0 0 100 0 100 30 156
Percentage
network
blockages
attended to
Sewer
blockages
attended to
within 24
100% 95% 100% 93% 100% 95% 100% 95% 100%
Msukaligwa Local Municipality | 2015/2016 Annual Report 29
within 24
hours after
being reported
hours of
being
reported.
T3.2.6
Employees: Sanitation Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies
(fulltime)
Vacancies (as a % of
total posts)
0 - 3 0 0 0 0 0%
4 - 6 1 2 1 1 50%
7 - 9 8 12 7 5 41.67%
10 - 12 6 10 6 4 33.33%
13 - 15 0 3 0 3 100%
16 - 17 15 40 15 25 60%
Total 30 67 29 38 56.72%
Totals should equate to those included in the Chapter 4 total employee schedule. Employees and Posts numbers are as at
30 June. *Posts must be established and funded in the approved budget or adjustments budget. Full-time equivalents are
calculated by taking the total number of working days lost (excluding weekends and public holidays) while a post remains
vacant and adding together all such days lost by all posts within the same set (e.g. ‘senior management’) then dividing that
total by 250 to give the number of posts equivalent to the accumulated days.
T3.2.7
3.3. ELECTRICITY
INTRODUCTION TO ELECTRICITY The municipality is licensed to provide electricity in Ermelo, Wesselton, Kwa-Dela, Breyten and Silindile. The rest of the admin units as well rural areas of the municipality get electricity from Eskom. An electricity Master plan has been developed and approved by Council to address the operation and maintanance challenges. This master plan was due for reviewed in the 2014 /2015 financial year but due to financial constraints it could not be reviewed. Achievement Since the 2011 /2012 financial year, the number of households that had received electricity increased from 30,561 to 35,030 (4,469 electrified households) which constitutes 87% of households with access to electricity. The electricity projects and bulk infrastructure has been funded by Department of Energy under the Integrated National Electrfication Programme as well as Eskom at areas licensed to Eskom. This has been achived through electrification projects at various settlements of the municipality and has cost an amount of R 2,638,000 from INEP and R 14,040,719 by Eskom in-kind grant. A futher amonunt of R 10,000,000 was spent for the construction of a main substation at Ermelo extension 34 and the project is being implemented in phases.The projects include the following:
Construction of main substation at Ermelo extension 34 (bulk supply); and
Electrification of households Provision and maintenance of public light also form part of the functions of the muncipality and a number of high mast lights were installed in various areas through MIG funding which funds are included in the total eletrification funding.
Msukaligwa Local Municipality | 2015/2016 Annual Report 30
T3.3.1
Electricity Service Delivery Levels
Households
Description 2011/12 2012/13 2013/14 2014/15 2015/16
Actual Actual Actual Actual Actual
No. No. No. No. No.
Energy: (above minimum level)
Electricity (at least min. service level) 19,768 20,493 21,111 21,194 21,194
Electricity - prepaid (min. service level) 11,825 12,259 12,629 13,130 23,489
Minimum Service Level and Above sub-total 31,593 32,752 33,740 34,324 44,683
Minimum Service Level and Above Percentage 77% 80% 82% 84% 87%
Energy: (below minimum level)
Electricity (< min. service level)
Electricity - prepaid (< min. service level)
Other energy sources 9,339 8,180 7,192 6,608 6,415
Below Minimum Service Level sub-total 9,339 8,180 7,192 6,608 6,415
Below Minimum Service Level Percentage 23% 20% 18% 16% 13%
Total number of households 40,932 40,932 40,932 40,932 51,098
T3.3.3
Electricity Service Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of households with access to basic level of electricity
Eradication of electricity backlogs
31,667 32,752 32,669 33,740 33,771 34,324 34,905 44,683 44,889
T3.3.5
Employees: Electricity Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies
(fulltime)
Vacancies (as a % of
total posts)
0 - 3 0 1 0 1 100%
4 - 6 3 3 3 0 .00%
7 - 9 14 23 16 7 30.43%
10 - 12 0 0 0 0 0%
13 - 15 0 0 0 0 0%
16 - 17 12 19 11 8 42.11%
Msukaligwa Local Municipality | 2015/2016 Annual Report 31
Total 29 46 30 16 34.78%
T3.3.6
3.4. PROJECTS MANAGEMENT
INTRODUCTION TO PROJECTS MANAGEMENT The municipality has established a project management unit dealing with overall projects management from projects planning, application for finding, monitoring and reporting of projects progress to confirmation of projects completion and signing off of completed projects. Projects dealt with by the unit are listed on Appendix F and N of this report. T3.3.1
Projects Management Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Number of jobs opportunities created through EPWP
Achieving the EPWP target
0 0 0 0
187 398 97 115
Percentage projects implemented within prescribed specifications by June each year
Ensuring that projects are implemented according to specification and within budget.
100% 100% 100% 100% 100% 100% 100% 100% 100%
Yearly Capital
plan
submitted to
COGTA for
MIG funding
by May each
year.
Funds allocated to the municipality on time
1 1 1 1 1 1 1 1 1
T3.3.6 a
Msukaligwa Local Municipality | 2015/2016 Annual Report 32
Employees: Projects Management
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies
(fulltime)
Vacancies (as a % of
total posts)
0 - 3 1 1 1 0 0%
4 - 6 3 3 3 0 0%
7 - 9 0 0 0 0 0%
10 - 12 1 1 1 0 0%
Total 5 5 5 0 0%
T3.3.6 b
3.5. WASTE MANAGEMENT (THIS SECTION TO INCLUDE: REFUSE COLLECTIONS,
WASTE DISPOSAL, STREET CLEANING AND RECYCLING)
INTRODUCTION TO WASTE MANAGEMENT Core Functions of waste management are to renders the following:
Solid waste removal and prevention illegal dumping
Development and Enforcement of Waste Management BY-Laws
Establishment and Management of landfill sites
Cleaning of public open spaces. The municipality is currently operating two registered landfill sites situated in Ermelo and Breyten while the others are utilized as transfer stations. Medical waste is not disposed at the municipality’s landfill sites. Generators of such waste dispose it privately. T3.4.1
Solid Waste Service Delivery Levels
Households
Description
2011/12 2012/13 2013/14 2014/15 2015/16
Actual No. Actual No.
Actual No.
Actual No. Actual No.
Solid Waste Removal: (Minimum level)
Removed at least once a week 26,810 26,810 30,311 31,801 32,427
Minimum Service Level and Above sub-total 26,810 26,810 30,311 31,801 32,427
Minimum Service Level and Above percentage 65% 65% 74% 78% 63%
Solid Waste Removal: (Below minimum level)
Removed less frequently than once a week 0 585 585 585 804 Using communal refuse dump 1,270 1,270 1,270 1,270 1,768 Using own refuse dump 8,549 8,549 4,789 3,558 7,810 Other rubbish disposal 404 404 404 404 3,470 No rubbish disposal 3,767 3,314 3,314 3,314 4,819
Below Minimum Service Level sub-total 14,122 14,122 10,362 9,131 18,671
Below Minimum Service Level percentage 35% 35% 26% 22% 37%
Total number of households 40,932 40,932 40,932 40,932 51,098
Msukaligwa Local Municipality | 2015/2016 Annual Report 33
T3.4.2
Waste Management Service Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of households with access to waste collection.
Number of households with access to refuse removal
28,910 26,810 26,810 30,311 30,811 31,801 32,501 32,427 33,127
% of households with access to basic to higher level of solid waste removal
Increase in number of households with access to refuse or waste collection.
73% 65% 65% 74% 75% 78% 79% 79% 81%
Number of waste disposal site maintained regularly
Proper waste management
0 0 5 5 5 5 5 4 5
Number of waste educational campaigns conducted quarterly each year.
Education and creating awareness to communities on cleanliness and environmental conservation.
0 0 0 0 0 0 8 15 8
T3.4.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 34
Employees: Waste Disposal and Other Services
Job Level
2014/15 2015/16
Employees No.
Posts No.
Employees No.
Vacancies (fulltime equivalents)
Vacancies (as a % of total posts)
0 - 3 1 1 1 0 0%
4 - 6 0 2 2 0 0%
7 - 9 7 7 7 0 0%
10 - 12 0 0 0 0 0%
13 - 15 7 9 7 2 28.57%
16 - 17 80 104 77 27 35.06%
Total 95 123 94 29 23.58%
T3.4.5
3.6. HOUSING
INTRODUCTION TO HOUSING The mandate of the housing section in the Municipality is to render housing supprot services within the municipality and the department of Human Settlements which include the following:
Identifying of land for human settlement
Support Department of Human Settlements in identifying potential beneficieries for low cost housing.
Management and maintaining of housing waiting list database.
Management of housing rental stock.
Managing and Controling of illegal land invasions.
Facilitation of land transfers.
T3.5.1
Housing Service Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of informal settlements with upgrading plans (in-situ upgrading or relocation)
Formalized informal settlements
0 0 0 0 2 2 1 2 1
T3.5.3
Msukaligwa Local Municipality | 2015/2016 Annual Report 35
Employees: Housing Services
Job Level 2014/15 2015/16
Employees No.
Posts No.
Employees No.
Vacancies (fulltime equivalents)
Vacancies (as a % of total posts)
0 - 3 1 1 1 0 0%
4 - 6 0 0 0 0 0%
7 - 9 4 6 4 2 33.33%
10 - 12 2 3 2 1 33.33%
13 - 15 0 0 0 0 0%
16 - 17 0 0 0 0 0%
Total 7 10 7 3 30.00%
T3.5.4
A narrative providing information on the staff critical to service delivery and shortage hereof to accompany the above table on
all municipal services. Municpalities should report for employees where cost centers are allocated.
3.7. FREE BASIC SERVICES AND INDIGENT SUPPORT
INTRODUCTION TO FREE BASIC SERVICES AND INDIGENT SUPPORT The indigent household subsidy policy was approved as part of budget related policies in 30 June 2015. The municipality supported 10,916 indigents in 2015/16 financial year. The municipality budgeted R 17,277,552 from equitable share to support indigent consumers and free 6kl of water is provided the indigent households only. Indigents were supported as follows:
6kl free water
50kw basic electricity
Free refuse removal
Free sanitation services
Property rates – R15 000 reduction on property value The following table illustrates how the indigent households were supported in 2015/2016: Support to indigent households
Electricity Water Sewer Refuse Rates Total Amount
R 2,791,360 R 4, 870,501 7 533 954 8 052 045 772 398 26 135 750
Free 6kl of water is provided to all registered indigent households.
Msukaligwa Local Municipality | 2015/2016 Annual Report 36
COMPONENT B: ROAD AND STORMWATER
This component includes: roads; transport; and waste water (storm water drainage).
3.8. ROADS AND STORM WATER MANAGEMENT
INTRODUCTION TO ROADS AND STORM WATER MANAGEMENT Road access needs to be provided to all residents in Msukaligwa. Grants received from Municipal Infrastructure Grant (MIG) and Gert Sibande District Municipality (GSDM) enables the Municipality to re-build gravel roads to a tar or paved surface. During the Integrated Development Plan (IDP) process, projects were identified at the community consultative meetings. Council takes final resolution on projects that will be implemented. Achievements Though most projects were not implemented in the 2013/2014 and 2014/2015 financial years due to Municipal Infrastructure Grants being redirected to water and sanitation related projects, there are roads projects that have been implemented over the past years and since the implementation of the 2011/2012 – 2015/2016 Integrated Development Plan (IDP), 14.2km of roads had been upgraded from gravel to paved roads. Roads upgrade projects will be reinstated once the water problems have been addressed. General continuous maintenance is done on asphalt roads on daily basis through potholes repair. The asphalted roads need to be resurfaced in order to maintain their asset value and owing to financial constraint, no resurfacing was done in the past 4 years. Storm water systems are cleaned and broken pipes replaced. Inlet structures are repaired and new inlet structures build. Gravel roads are graded continuously, and new gravel imported to repair roads. Sidewalks are maintained by replacing broken concrete tiles, as well as constructing new sections where and when needed. Roads projects that were upgraded to a length of 14.2km were implemented over the period 2011/2012 to 2015/2016 at an amount of R 41,513,179. 2011/2012
Construction of various roads and storm water in Msukaligwa townships
Construction and repair of roads in Amsterdam weg 2012/2013
Upgrading of Manana street (phase 2)
Upgrading of Kwa-Chibikhulu street
Upgrading of Tayob street
Upgrade of road Phosa village (phase 2)
Upgrade of roads in Silindile
Construction of storm water drainage
Upgrade of PS Simelane
Upgrade of KwaZanele Street 2013/2014
Upgrade of road at Nganga
Construction of storm water drainage
Upgrade of Kwa-Dela road
Upgrading of Amsterdam Weg
Upgrade of roads in Wesselton ext. 5 (GSDM)
Msukaligwa Local Municipality | 2015/2016 Annual Report 37
2013/2014
Upgrade of road at Silindile phase 2
Construction of storm water drainage T3.7.1
Gravel Roads Infrastructure
Kilometers
Total gravel roads New gravel roads
constructed
Gravel roads upgraded to
asphalt or paved
Gravel roads graded
/maintained
2011/12 180 2 7.8 169
2012/13 174.2 182 5.2 251
2013/14 351 0 0.9 244
2014/15 350.1 0 0 245
2015/16 350.1 0 0.3 246
Total 349.8 0 14.2
T3.7.2
Asphalted Roads Infrastructure Kilometers
Total asphalted and paved roads
New asphalt or paved roads
Existing asphalt roads re-asphalted
Existing asphalt roads re-sheeted
Asphalt and paved roads maintained
2011/12 235.5 km 7.8 km 0 km 1,6 km 235 km
2012/13 243.3 km 5.2 km 0 km 0 km 243 km
2013/14 248.5 km 0.9 km 0 km 0 km 248 km
2014/15 249.4 km 0 km 0 km 0 km 248 km
2015/16 249.4 km 0.3 km 0 km 0 km 248 km
Total 249.7 km 14.2 km 0 1.6 km
T3.7.3
Msukaligwa Local Municipality | 2015/2016 Annual Report 38
Roads and Storm Water Management Service Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To Provide Sustainable Basic Services and Sustainable Infrastructure
Km of roads
upgraded
from gravel to
tar or paved
surface with
storm water
measures
Well
maintained
roads
infrastructure
and storm
water
drainage
systems
4.5 km 5.2 km 4 km 0.9 km 2 km 0 0 0.3 km 5.5 km
Km of tar
roads re-
surfaced
Well
maintained
roads
infrastructure
5 km 0 km 5 km 0 km 2.3 km 0 28,000
m2 0 20,000m2
Km of roads
re-gravelled
and graded
Well
maintained
roads
infrastructure
0 0 0 0.8 km 10 km 0 5 km 0 5 km
Reports on
number of
potholes
attended to
Well
maintained
roads
infrastructure
N/A N/A N/A N/A 4 4 4 4 4
T3.7.6
Employees: Roads and Storm Water Management Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies (fulltime
equivalents)
Vacancies (as a % of
total posts)
0 - 3 1 1 1 0 0%
4 - 6 1 1 1 0 0%
7 - 9 10 11 8 3 27.27%
10 - 12 7 7 4 3 42.86%
13 - 15 5 9 3 6 66.67%
16 - 17 23 40 21 19 47.50%
Total 47 69 38 31 44.93%
T3.7.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 39
3.9. STORM WATER DRAINAGE
Storm water drainage forms part of the roads and storm water management reported in section 3.7 of this report.
COMPONENT C: PLANNING AND DEVELOPMENT
This component includes: planning; and local economic development.
3.10. PLANNING
INTRODUCTION TO PLANNING AND DEVELOPMENT The purpose and function of the Town Planning and Building Control Section is to facilitate the effective implementation and enforcement of the Msukaligwa Spatial Development Framework 2010, the Msukaligwa Spatial Planning and Land Use Management By-Law of 2016, the Spatial Planning and Land Use Management Act, 2013 (Act 16 of 2013) and the National Building Regulations. The objectives of the enforcement of the above-mentioned pieces of legislation and policy documents seek to give effect to the following:
indicate where public and private land development and infrastructure investment should take place;
indicate desired or undesired utilization of space in a particular area;
delineate the urban area within a well-defined urban edge;
identify areas where strategic intervention is required; and
Indicate areas where priority spending is required.
ensure compliance with applicable land use and building regulations The Town Planning Section is composed of the following sub-functions:
Spatial Planning
Land Use Management
Building Control Management
Geographic Information System (GIS) Management The major project for the 2015/2016 Financial Year which has rolled-over from preceding years and which is now complete was the Town Planning and Land Surveying (Subdivision) of Various Identified Parcels of Land within Wesselton Township which is informed by the Municipality’s In-fill Development strategy as enshrined in the Msukaligwa Spatial Development Framework 2010. Provision for the review of the Msukaligwa Spatial Development Framework 2010 in the 2015/16 financial year was also made. T3.8.1
Applications for Land Use Development
Detail Formalization of
Townships Rezoning Built Environment
2014/15 2015/16 2014/15 2015/16 2014/15 2015/16
Planning application received 3 0 31 31 171 276
Determination made in year of receipt 0 0 12 4 171 215
Determination made in following year 0 0 0 0 0 61
Applications withdrawn 0 0 0 0 0 0
Applications outstanding at year end 3 0 19 27 0 61
T3.10.2
Msukaligwa Local Municipality | 2015/2016 Annual Report 40
Planning Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure integrated long term planning
Number of the Adopted IDP/ Budget Process Plan tabled to Council.
IDP/budget process plan developed and approved by Council every year
1 1 1 1 1 1 1 1 1
Number of community consultative meetings (IDP/Budget) held
Encourage community participation in the affairs of the municipality.
38 34 38 25 38 34 38 35 38
Number of IDP Rep-Forums held
Strengthened intergovernmental relations
4 1 4 1 4 3 4 2 4
Percentage of building and land-use contraventions received and attended to for enforcement within 35 days
Compliance to land use legislation town planning schemes
N/A N/A N/A N/A N/A N/A 100% 100% 100%
Percentage of building and land-use contraventions received and referred to legal unit for prosecution on expiry of 35 days of the enforcement period.
Compliance to land use legislation town planning schemes
N/A N/A N/A N/A 100% 100% 100% 100% 100%
Number of areas identified and consolidated /
Orderly and SG approved settlements
N/A N/A N/A N/A 2 2 2 0 2
Msukaligwa Local Municipality | 2015/2016 Annual Report 41
subdivided for residential/human settlement.
Percentage building plans applications received and processed within 30 days of receipt as legislated.
Compliance to land use legislation town planning schemes
N/A N/A N/A N/A 100% 92% 100% 96% 100%
T3.10.3
Employees: Planning Services
Job Level
2014/15 2015/16
Employees Posts Employees Vacancies (fulltime equivalents)
Vacancies (as a % of total posts)
No. No. No. No. %
0 - 3 1 1 1 0 0%
4 - 6 3 4 4 1 25%
7 - 9 1 1 1 0 0%
10 - 12 0 0 0 0 0%
13 - 15 0 0 0 0 0%
16 - 17 0 0 0 0 0%
Total 5 6 6 1 12.50%
T3.10.4
COMMENT ON THE PERFORMANCE OF PHYSICAL PLANNING OVERALL The major project in the planning unit which has rolled-over from preceding years was the formalization of informal settlements within the municipality so that the affected communities could have basic services. As part of the Municipality’s In-fill Development strategy as enshrined in the Msukaligwa Spatial Development Framework 2010, various vacant and in some cases informally settled parcels of land has been identified in Wesselton for this purpose and this seeks to maximise on the large tracts of unused parcels of land by subdividing them into residential stands and other complimentary uses in order to try and meet the Human Settlement demand/backlog. With regards to the informal areas that have organically formed over time, the formalization of these areas will also be achieved through this process and this will result in the revival of these areas into a state that will make the provision of needed infrastructure and services attainable. The project is now 100% complete and this process will be followed by the same undertaking at all the other Service Administrative Areas/Units within Msukaligwa. In as far as our mandate to ensure compliance by enforcing applicable municipal land use and building regulations, achieving 100% in how we administer land use and building contraventions means that we are able to effectively respond to public complaints and detected cases of non-compliance within the legislated timeframes. We are further committed to maintaining the above status quo. Since the promulgation of the Spatial Planning and Land Use Management By-Law on the 23rd of April 2016, the Section has been successfully implementing the Spatial Planning and Land Use Management Act, 2013 (Act 16 of 2013) (SPLUMA) in the assessment of new land use and development applications, and there are plans in the 2016/2017 Financial Year to embark on a review process of the Msukaligwa Spatial Development Framework, 2010 to be in line with the SPLUMA.
T3.10.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 42
3.11. LOCAL ECONOMIC DEVELOPMENT (INCLUDING TOURISM AND MARKET PLACES)
INTRODUCTION TO ECONOMIC DEVELOPMENT The purpose of Local Economic Development (LED) is to build up the economic capacity of a local area to improve its economic future and the quality of life for all as well ensuring that plans are in place to improve the socio economic status of the municipality through infrastructure development. Through our engagements and partnership with other stakeholders a number of Local Economic Development (LED) objectives such business opportunities for locals, youth skills development, employment and poverty alleviation were achieved. The development of the Local Economic Development (LED) strategy for Msukaligwa local municipality was viewed as part of the broader Local Economic Development (LED) Planning process and the development of this strategy took into account work previously done as well as the new developments. Furthermore the Gert Sibande District Municipality is in a process of developing the Growth and Development Strategy for Msukaligwa Municipality and its objective is to advise council as well as provide a strategic plan to implementation plan for the strategy. Key stakeholders in Local Economic Development (LED) planning, implementation and evaluation are:
Government
State enterprises
Private sector
Community structures The LED Vision Elements and Objectives: Key Vision Elements:
Creation of job opportunities and the empowerment of local communities.
SMME development and support.
Sustainable growth and development based on sectoral competitiveness of the local space.
Addressing socio-economic challenges faced by local communities, such as poverty, unemployment and skills levels.
Infrastructure development for local economic growth. Job Creation Projects There is also an initiative form the National government to extend the railway line from Lothair to Swaziland in order to improve transportation of goods between South Africa and Swaziland which will in turn alleviate the road transportation burden as well as creating job opportunities. In improving transport system, the government commits to shift the transportation of coal from road to rail in order to protect the provincial roads through a planned construction of Majuba Rail coal line linking to the existing rail line in Msukaligwa to Majuba power station. The Majuba rail coal line has commissioned and the following jobs were created. Since the commissioning of the project, skills transfer for non-contractual targets has resulted in 560 candidates to be trained. The total number of demobilized staff is 404. Through the municipal engagements with Eskom, 11 local companies and SMMEs benefited from the project. In term skills development the following skills were transferred to locals:
Artisan assistants;
Environmental officers;
Laboratory technicians;
Operators; and
Quality
Msukaligwa Local Municipality | 2015/2016 Annual Report 43
Economic Activity by Sector
Sector 2014/15 2015/16
Agric, forestry and fishing 14.5 19.5
Mining and quarrying 10.0 10.0
Manufacturing 0.7 5.7
Wholesale and retail trade 20.2 17.6
Finance, property, etc. 10.2 6.2
Govt, community and social services 21.1 20.7
Construction services 8.9 4.7
Transport 5.5 5.7
Utilities 0.8 0.8
Private Households 8.1 9.1
Total 100 100
T3.11.2
Jobs Created during 2015/16 by Local Economic Development (LED) Initiatives (Excluding Extended Public Works
Programme (EPWP) projects)
Total Jobs created
/ Top 3 initiatives
Jobs
created No.
Jobs lost/displaced
by other initiatives
No.
Net total jobs
created in year
No.
Method of validating jobs created/lost
Initiative A None
Initiative B None
Initiative C None
T3.11.5
Job creation through Extended Public Works Programme (EPWP) * projects
Year
Extended Public Works
Programme (EPWP) Projects
Community Workers
Programme (CWP)
Jobs created through Extended Public
Works Programme (EPWP) projects
No. No. No.
2011/2012 6 Projects 0 80 Jobs created
2012/2013 5 Projects 128 Jobs created
2013/2014 2 Projects 975 Jobs created 170 Jobs created
2014/2015 4 Projects 1036 Jobs created 195 Jobs created
2015/2016 11 Projects 1070 Jobs created 97 Jobs created
* - Extended Public Works Programme
T3.11.6
Msukaligwa Local Municipality | 2015/2016 Annual Report 44
Local Economic Development Policy Objectives Taken From Integrated Development Plan (IDP)
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To encourage shared economic growth and development
Number of LED Forum Meetings held
Functional Local economic development forum
4 1 4 0 4 0 4 0 4
Number of Corporatives supported and registered
Support provided to SMMEs
5 5 5 10 5 5 5 5 5
T3.11.7
Employees: Local Economic Development Services
Job Level
2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
0 - 3 1 1 1 0 0%
4 - 6 0 2 2 0 0%
7 - 9 2 0 0 0 0%
10 - 12 0 0 0 0 0%
13 - 15 0 0 0 0 0%
16 - 17 0 0 0 0 0%
Total 3 3 3 0 0%
Totals should equate to those included in the Chapter 4 total employee schedule. Employees and Posts numbers are as at 30 June. *Posts must be established and funded in the approved budget or adjustments budget. Full-time equivalents are calculated by taking the total number of working days lost (excluding weekends and public holidays) while a post remains vacant and adding together all such days lost by all posts within the same set (e.g. ‘senior management’) then dividing that total by 250 to give the number of posts equivalent to the accumulated days.
T3.11.8
Msukaligwa Local Municipality | 2015/2016 Annual Report 45
COMPONENT D: COMMUNITY & SOCIAL SERVICES
This component includes: libraries and archives; museums arts and galleries; community halls; cemeteries and crematoria; child care; aged care; social programmes, theatres.
3.12. LIBRARIES and COMMUNITY FACILITIES
INTRODUCTION TO LIBRARIES AND COMMUNITY FACILITIES The Public Libraries of Msukaligwa are a local gateway to knowledge. They provide a basic condition for lifelong learning, independent decision making and cultural development of individuals and social groups. The Libraries are established, supported and funded by Msukaligwa Municipality. The Provicial government assists in the provision of some functions such as purchasing of library material by allocating funds to such functions. Msukaligwa Libraries provide access to information, knowledge and works of the imagination through a range of resources and services and all our libraries are equally available to all members of the community regardless of race, nationality, gender, religion, language, disability, economic and employment status and educational attainment. We have eight (8) fully functional Libraries in the following areas:
a. Ermelo b. Wesselton c. Cassim park d. Chrissiesmeer e. Davel f. Breyten g. Kwazanele h. Silindile
The Libraries have been able to provide resources and services in a variety of media to meet the needs of individuals and groups for education, information and personal development including recreation and leisure. They are constantly playing an important role in the development and maintainance of a democratic society by giving the individual access to a wide and varied range of knowledge, ideas and opinions. One of our achievements was being able to create and strengthen the reading habits in children from early age. We have manage to engaged all schools within the vicinity of the libraries to participate in the activites of the libraries which are aimed at enhacing and empowering the learners of these schools. All Libraries are a local centre of information making all kinds of knowledge and information readily available to their users. Another of our achievements as Msukaligwa Libraries is that we have managed to bridge a gap between the information rich and the information poor by providing public access to the Internet as well as providing information in traditional formats. We have the opportunity to be the electronic gateway to the information world. All eight libraries provide electronic corners in their facilties which give free access to internet and personal computing. Msukaligwa Libraries therefore continue to provide services which are aimed at meeting the needs of the local communities and continue to operate within the context of those communities. T3.12.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 46
Libraries Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery
Number of library event and programmes rolled out
Library information reaching wider community
N/A N/A N/A N/A N/A N/A 1 3 0
T3.12.3
Employees: Libraries and Community Facilities
Job Level
2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
0 - 3 1 1 1 0 0%
4 - 6 2 4 3 1 25%
7 - 9 0 1 0 1 100%
10 - 12 8 14 8 6 43%
13 - 15 0 0 0 0 0%
16 - 17 3 7 5 2 29%
Total 14 27 17 10 37%
T3.12.4
3.13. CEMETERIES AND CREMATORIUMS
INTRODUCTION TO CEMETERIES & CREMATORIUMS The top priorities of the municipality in relation to cemeteries are to provide burial space as required by legislation and maintain it to the required standards, securing and fencing of the cemeteries and the enforcement of the by-laws. Msukaligwa municipality has 21 cemeteries of which 6 of them are still in an operational state whereas 15 are closed. It is therefore imperative to provide the community with burial facilities that will be able to meet the burial demand. We envisage that the Municipality will not run short of burial space for the next five to ten years. Plans are in place to extend cemetery services to areas where we don’t provide i.e. Warburton/Nganga. T3.13.1
SERVICE STATISTICS FOR CEMETERIES & CREMATORIUMS
Group 2011/12 2012/13 2013/14 2014/15 2015/16
Adults 2241 2280 887 1010 680
Children 315 360 210 112 155
Paupers 0 21 13 12 2
T3.13.2
Msukaligwa Local Municipality | 2015/2016 Annual Report 47
T 3.13.2a
The burial statistics are only for those cemeteries that are registered. There are areas where the burials are not accounted for due to the cemeteries or graveyards not being registered. Some graveyards are located on private farms which we cannot account for.
Cemeteries Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To provide sustainable basic services and sustainable infrastructure
Number of
cemeteries
maintained
annually
Well
maintained
and
aesthetic
cemeteries
14 14 14 9 14 14 14 14 14
T3.13.3
0
500
1000
1500
2000
2500
2011/12 2012/13 2013/14 2014/15 2015/16
Burial Statistics
Adults
Children
Paupers
Msukaligwa Local Municipality | 2015/2016 Annual Report 48
Employees: Cemeteries
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees No. Vacancies (fulltime
equivalents) No.
% Vacancies (as a % of total
posts)
0 - 3 1 1 0 1 100%
4 - 6 1 2 2 0 0%
7 - 9 4 3 3 0 0%
10 - 12 1 1 1 0 0%
13 - 15 7 7 6 1 14%
16 - 17 50 65 46 19 29%
Total 64 79 58 21 27%
T3.13.4
There are two main challenges in rendering proper services which are:
1. The staff component at the municipal units outside of Ermelo is not assigned to specific tasks and they are doing rotational work from one division to the other. Only the Ermelo unit staff is assigned to specific tasks.
2. The other challenge in rendering proper services is obsolete equipment which the municipality is unable to replace
due to financial constraints.
COMMENT ON THE PERFORMANCE OF CEMETERIES OVERALL The priority projects were to fence all the existing and new cemeteries and to establish new cemeteries in those areas where there are no cemeteries. Most of the cemeteries have been fenced, and only seven (7) out of 21 of the existing cemeteries have not been fenced and are in the Municipality’s plans to be fenced. The only area without a registered cemetery is Warburton/Nganga and the municipality is a process of establishing a cemetery at that area or unit.
T3.13.7
3.14. CHILD CARE; AGED CARE; SOCIAL PROGRAMMES
COMMENT ON THE PERFORMANCE OF CHILD CARE; AGED CARE; SOCIAL PROGRAMMES OVERALL: Child care, aged care and social programmes are not the competency of the Local municipality but the District.
T3.14.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 49
COMPONENT E: ENVIRONMENTAL PROTECTION
This component includes: pollution control; biodiversity and landscape; and costal protection.
3.15. POLLUTION CONTROL
This function does not fall within the municipality’s competency and is being dealt with by the district municipality.
3.16. BIO-DIVERSITY AND LANDSCAPE (INCL. OPEN SPACES AND SIDEWALKS)
INTRODUCTION BIO-DIVERSITY AND LANDSCAPE These services include the administration, development and upgrading of parks, maintenance of open spaces, parks, sidewalks, street trees and general cleanness of the towns and its grounds. The main priorities in the parks division is to repair and replace all dilapidated playing ground facilities and to maintain parks, sidewalks and municipal terrains. Support is given to communities during the cleaning campaigns through provision of equipment and cleaning material. T3.16.1
SERVICE STATISTICS FOR BIO-DIVERSITY AND LANDSCAPE The towns are divided into sections for the cleaning and cutting of grass as well as the general maintenance of parks and open spaces. Therefore the cutting of grass in parks, open spaces and sidewalks is done on a monthly basis. Inadequate staff and equipment remains a challenge leading to some areas not being attended to on time as per the maintenance plan.
T3.16.2
Parks (Open Spaces) Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To provide sustainable basic services and sustainable infrastructure
Number of parks and public open spaces maintained annually
Well maintained parks and sidewalks
N/A N/A N/A N/A 55 28 55 54 55
T3.16.3
Employees: Parks (Open Spaces)
Job Level
2013/14 2014/15
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
Forms part of the cemeteries and crematoriums in section 3.13
T3.16.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 50
COMPONENT F: HEALTH
This component includes: clinics; ambulance services; and health inspections.
3.17. HEALTH SERVICES
This is the function of the Provincial Department of Health.
3.18. CLINICS
This is the function of the Provincial Department of Health. The municipality only renders support services where applicable.
3.19. AMBULANCE SERVICES
This is the Function of the Department of Health and private ambulance services. The municipality only renders support services where applicable.
3.20. HEALTH INSPECTION; FOOD AND ABBATOIR LICENSING AND INSPECTION; ETC
This is the function of the District Municipality.
COMPONENT G: SECURITY AND SAFETY
This component includes: Police; fire; disaster management, licensing, control of animals and control of public nuisances.
3.21. TRAFFIC SERVICES
INTRODUCTION TO TRAFFIC SERVICES The Traffic Department is responsible for tarffic law enforcement and the administration thereof. This function also ensures the technical sustainability of road traffic signs, signals and markings throughout the municipal area. The main focus is to ensure a reduction in the road accidents death rate, compliance to road rules and regulations and free flow of traffic. The following activities are performed to ensure improvement in the municipal trafic services:
High visibility patrols;
Effective law enforcement;
Effective law speed enforcement;
Attend to accident scenes;
Escort duties for funerals, abnormal loads and dignitaries;
Traffic education in schools;
Road blocks;
Point duties;
Msukaligwa Local Municipality | 2015/2016 Annual Report 51
Scholar patrols; and
Other related traffic duties. T3.21.1
Municipal Traffic Service Data
Details
2013/14 2014/15 2015/16 2016/17
Actual No. Actual No. Estimate No. Actual No. Estimate No.
1 Number of traffic accidents
during the year 1632 1648 Not applicable 1551 Not applicable
2 Number of by-law infringements
attended 1 10 10 10 Not applicable
3 Number of traffic officers in the
field on an average day 7 6 10 9 9
4 Number of traffic officers on duty
on any average day 7 6 10 9 9
T3.21.2
Traffic Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To provide sustainable basic services and sustainable infrastructure
Percentage compliance to road marking schedule
80% 56% 80% 51% 70% 69% 60% 70% 70%
Percentage of road signs replaced /repaired within three weeks
95% 100% 95% 100% 95% 100% 100% 100% 100%
Number of roadblocks held
12 24 12 21 12 22 12 20 12
Number of road safety education projects at school
12 23 12 15 12 26 12 20 12
T3.21.3
Msukaligwa Local Municipality | 2015/2016 Annual Report 52
Employees: Traffic Services
Job Level 2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
Chief Traffic Officer
1 1 1 0 0%
Other Traffic Officers
4 - 6 1 3 2 1 33%
7 - 9 5 10 8 2 20%
10 - 12 0 1 1 0 0%
Other none traffic officers
7 0 1 0 1 100%
8 - 9 4 4 3 1 25%
10 - 17 3 6 2 4 67%
TOTAL 14 26 17 9 35%
T3.21.4
COMMENT ON THE PERFORMANCE OF TRAFFIC SERVICES OVERALL In relation to Traffic control and safety under the Directorate of Public Safety Department as responsibility for issuing traffic fines amongst other related strategic functions, the section is facing a number of challenges amounting to capacity constraints with limited resources in which budget prioritization through proper allocation of financial resources will turn the section around in the acceleration of quality service delivery.
T3.21.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 53
3.22. FIRE AND RESCUE SERVICES
INTRODUCTION TO FIRE SERVICES Msukaligwa fire and rescue services is a public organization that provides predominantly emergency, firefighting and rescue services for in the jurisdiction area of Msukaligwa Municipality. The fire service have two fire stations within its boundaries, and are staffed by full-time firefighters. The fire servcie also provide "fire protection" or fire prevention services, whereby firefighters visit homes and give fire safety advice to members of the public. We see fire protection or prevention as an important role for the fire service, as preventing a fire from occurring in the first place can obviously save lives. The fire service also carry out an enforcement role, to ensure that commercial dwellings (hotels, offices, factories, and so on) are equipped with adequate fire precautions to ensure that in the event of fire, people can safely evacuate the premises unharmed. This is also part of the protection or prevention role. The Fire Service are organized in a system of administration, services, training, and operations: For example: Emergency fire & rescue vehicles administration is responsible for supervision, budgets, policy, and human resources. Service offers protection, safety, and education to the public. Training creates skilled people with the knowledge to perform their duties. Operations performs the tasks to successfully save the public from harm. The fire servcie got a set up where fire stations and sophisticated fire apparatus are strategically deployed throughout the area under its control so that dispatchers can send fire engines, fire trucks from the fire stations closest to the incident. The Fire Service annually survey its jurisdiction areas and use the data for redeploying proper coverage. This data comes from travel time, range from stations, and population survey. This brings equal service to the entire community and gives the department efficient places to launch operations.
T3.22.1
Municipal Fire Service Data
Details
2013/14 2014/15 2015/16 2016/17
Actual No. Actual No. Estimate No. Actual No. Estimate No.
1 Total fires attended in the year 169 357 364 236 236
2 Total of other incidents attended
in the year 212 233 233 193 193
3 Average turnout time - urban
areas 12 11 13 35 13
4 Average turnout time - rural areas 25 25 23 70 23
5 Fire fighters in post at year end 21 20 26 20 26
6 Total emergency vehicles at year
end 10 10 12 10 12
7 Average number of appliance off
the road during the year 4 3 2 4 0
T3.22.2
Msukaligwa Local Municipality | 2015/2016 Annual Report 54
Fire Services Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Percentage of
fire and
emergency
incidents
responded to
within
predetermined
time frame
Turnaround
time
compared to
National
guidelines
85% 88% 85% 86% 85% 86% 85% 79% 85%
Number of
fire safety
inspections/pr
e-fire planning
visits
conducted
Fire Safety
inspections
and risk
visits
conducted
in terms of
National
guidelines
300 551 300 541 500 677 500 637 540
T3.22.3
Employees: Fire Services
Job Level 2014/15 2015/2016
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
Chief Fire Officer 1 1 1 0 0
Other Fire Officers 0
4 - 6 0 0 0 0 0%
7 - 9 3 3 3 0 0%
10 - 12 7 10 7 3 43%
Other none fire officers
9 12 9 3 30%
7 0 0 0 0 0%
8 - 9 0 0 0 0 0%
10 - 17
TOTAL 20 26 20 6 23%
T3.21.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 55
COMMENT ON THE PERFORMANCE OF FIRE SERVICES OVERALL Summary of difficulties experience
1. Member – Qualifications Driver/Operator training is inconsistent and not in compliance with NFPA 1002. Fire service members are not consistently provided with operations-level hazardous materials response training that meets NFPA 472. No comprehensive training exists for fire fighters, officers, or command officers.
2. Fire Service Fleet and Apparatus Condition of the front line and reserve fleet is not in a good condition. Inadequate initial and on-going training for apparatus drivers
3. Fire Stations The shortages of additional fire stations in areas are still a concern, due to the time frame emergency vehicles had to travel from the current two fire stations to those areas which do not have within 23 minutes access to a fire service.
4. Emergency vehicles The current fleet is not sufficient and due to wear and tear the older fire trucks are getting more expensive to maintain due to the availability of parts.
5. General Staffing levels, equipment, and emergency water supplies (fire hydrants) have decreased dramatically over the past year. Summary of accomplishments Fire prevention was limited to land development and inspection programs prior to 2002. The service started to conduct Fire Prevention in the whole of Msukaligwa. The service is a leader in Hazardous Material response. Hazardous materials regulation and response is a prime example of sharing scarce resources between multiple jurisdictions. The service advocates local fire services. Community education programs provide the opportunity to educate adults and children about fire safety and injury prevention. Community preparedness programs provide citizens the required training and education to become self-sufficient following natural or human-made disasters. The municipality is situated on the highveld and is annually facing the risk of losing millions in damages caused by run-away veld fires. In conjunction with NDMC aerial firefighting resources (Spotter, fix wing and helicopter) are made available to the municipality to assist with the combating of major run-away fires. Smart Goals Summary The service will continue to update their legal agreements and by-laws to ensure they are at the most appropriate stage of readiness. Additionally improve upon existing capital funding to ensure a consistent long term stable level of funding has not been achieved. The Fire Services will strive to improve upon their training to enhance the Health and Safety of the Fire Fighters. Additionally, live fire training along with specialty skills training will be started. During 2015/16 the Fire and Rescue Services will be petitioning for funding of additional fire engines and the opening of 4 additional fire stations in Msukaligwa. The enhancing of the emergency management capabilities is an on-going responsibility.
T3.22.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 56
3.23. DISASTER MANAGEMENT
INTRODUCTION TO DISASTER MANAGEMENT The Disaster Management Function manages and controls the key performance areas associated with the disaster management and security functionality through inputs into the design, development of approved policies, alignment of procedures, systems and controls guiding critical interventions and processes with respect to loss control, risk reduction and elimination and, providing advice, information and guidelines on critical initiatives related to legislative imperatives with a view to sustaining interventions and supporting an integrated approach to protecting Council property and the building of resilient individuals, households and communities within the context of the Integrated Development Plan (IDP). The unit is also responsible for rendering an effective and efficient customer care management service and the allocation of adequate resources to address identified security threats and risks. The function of the Disaster Management Section services is administered as follows and includes:
To prevent or reduce the severity of hazards
To ensure the preparedness of the community itself
To provide an effective response should disaster occur
To provide recovery after disaster T3.23.1
SERVICE STATISTICS FOR DISASTER MANAGEMENT Summary of achievements
The Unit has managed to conduct a number of disaster management awareness campaigns around the municipal area of jurisdiction.
Impact assessments were conducted on time to all incidents reported to the function and those families or individuals were provided with necessary assistance from the Disaster Management Centre.
T3.23.2
Disaster Management Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To provide sustainable basic services and sustainable infrastructure
Percentage of incidents attended to timeously
100% 100% 100% 100% 100% 100% 100% 100% 100
Number of disaster awareness campaigns Conducted
Educating community on possible disasters and mitigation thereof.
12 13 12 13 12 20 12 16 12
T3.23.3
Msukaligwa Local Municipality | 2015/2016 Annual Report 57
Employees: Disaster Services
Job Level 2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
Chief Disaster Officer 1 1 1 0 0%
Other Disaster Officers 0%
4 - 6 1 1 1 0 0%
7 - 9 2 2 2 0 0%
10 - 12 6 10 6 4 40%
13 – 15 0 0 0 0 0%
16 - 18 2 2 2 0 0%
TOTAL 12 16 12 4 25%
T3.21.4
3.24. LICENSING
INTRODUCTION TO LICENSING SERVICES The licencing function of the municipality deals with services including registration and licensing of vehicles, testing of roadworthiness of vehicles and issiung of road worthiness certficates, conducting learners and driving licences tests, issuing of learners and drivers licences, issuing of professional driving permits, administering instructors’ certificates and issuing of temporary and special permits. The top 3 priorities of the licensing division is to encrease the number of people tested for learners and driving licences, limit the number of unroadworthy vehicle on municipal and provincial/national roads and maintain and ensure compliance of the National Road Traffic Act 93/1996 and other related legislations. T3.24.1a
Municipal Licensing Service Data
Details
2013/14 2014/15 2015/16 2016/17
Actual No. Actual No. Estimate No. Actual No. Estimate No.
1 Total number applications for
learners licenses received 4,301 4,235 5,032 3,546 3600
2 Total number of applications for
driving licenses received 5,408 1,941 4,000 8256 7600
3 Total number vehicles tested for
roadworthiness 1,689 2,484 1,220 2677 2380
T3.24.2a
Msukaligwa Local Municipality | 2015/2016 Annual Report 58
Licensing Policy Objectives Taken From IDP
Service Objectives Outline
Service Targets
2012/13 2013/14 2014/15 2015/16 2016/17
Target Actual Target Actual Target Actual Target Actual Target
Service Indicators
Service Objective: To ensure long term planning and provision of sustainable services delivery and maintenance of infrastructure
Number of applications for learners licenses
Competent drivers
4,032 4,458 4,532 4,301 5,032 4,235 5,032 3,546 4,200
Number of applications for driving licenses
Competent drivers
3,360 5,523 3,600 5,408 4,000 1,941 4,000 8256 4,000
Number of application for road worthiness certificates received.
Safe and roadworthy vehicles
1,020 1,191 1,220 1,689 1,220 2,484 1,220 2677 1200
T3.24.3a
Employees: Licensing Services
Job Level 2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
Chief Licensing Officer 1 1 1 0 .00%
Other Licensing Officers
4 - 6 2 2 2 0 .00%
7 - 9 19 20 18 2 10%
10 - 12 1 0 0 0 .00%
13 – 15 0 0 0 0 .00%
16 - 18 1 2 1 1 50%
TOTAL 24 25 22 3 12%
T3.21.4
COMMENT ON THE PERFORMANCE OF LICENSING SERVICES OVERALL The plan was to establish service centers at Cassim Park, Lothair and Davel as well as the fencing of the Breyten driving license testing center as key projects for the year but due to lack financial resources the projects could not be financed. The only project that has been rolled over to the next financial year is the fencing of Breyten driving license testing center –fencing has been completed. The Department of Public Safety is busy with planning for the fencing of the whole Department in the next financial year 2015/16.The Department of Community Safety,Security and Liason has deployed Computerised Learners License Mobile Class at Ermelo Driving License Testing Centre for a period of eleven months starting from 2 February 2015 to 31 January 2016 which will assist to prevent fraud and corruption
T3.24.7a
Msukaligwa Local Municipality | 2015/2016 Annual Report 59
COMPONENT H: SPORT AND RECREATION
This component includes sports fields; sports halls; stadiums; swimming pools; and sport promotion.
INTRODUCTION TO SPORT AND RECREATION The mandate of the section is to provide, mantain and manage sports and recreational facilities. Promotion of sports and assisting athletes who participate at regional, provincial and national level with transport and other logistical arrangements also form part of the municipality’s mandate. The municipality is currently managing and mantaining 19 sports facilities that cuts across all sporting codes. Only Ermelo has facilities of reasonable standards while the other six units within the municipality are still having challenges sub-standard sports facilities. Achievements The Municipality gave support to the following sporting activities:
Women in Sports
Soccer and Netball
Mayoral cup
Mayoral golf day
Establishment of sports Councils/Associations
Support Municipal sports teams/individuals
Athletic competitions
Bowling green T3.25.0
3.25. SPORT AND RECREATION
SERVICE STATISTICS FOR SPORT AND RECREATION The municipality facilitates and supports the following sporting codes: Soccer; Rugby; Netball; Tennis; Korfball; Wrestling; Gymnastics; Basketball; Volleyball; Swimming; Karate; Table tennis; Indigenous games, bowling, golf, athletics, pool, squash, pigeon racing club, hockey and Cricket. T3.25.1
Employees: Sports and Recreation Services
Job Level 2014/15 2015/16
Employees No.
Posts No.
Employees No. Vacancies (fulltime equivalents) No.
% Vacancies (as a % of total posts)
0 - 3 1 0 0 0 0%
4 - 7 2 1 1 0 0%
8 - 9 1 1 1 0 0%
12 - 14 3 4 2 2 50%
15 – 17 8 13 9 4 31%
TOTAL 15 19 13 6 32%
T3.21.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 60
COMMENT ON THE PERFORMANCE OF SPORT AND RECREATION OVERALL: None.
T3.25.6
COMPONENT I: CORPORATE POLICY OFFICES AND OTHER SERVICES
This component includes: corporate policy offices, financial services, human resource services, ICT services, property services.
3.26. EXECUTIVE AND COUNCIL
This component includes: Executive office (mayor; councilors; and municipal manager).
Employees: The Executive and Council
Job Level
2014/15 2015/16
Employees No.
Posts No.
Employees No.
Vacancies (fulltime) Vacancies (as a % of total posts)
0 - 3 2 3 3 0 0%
4 - 5 3 8 8 0 0%
6 - 7 1 2 2 0 0%
8 - 9 1 1 1 0 0%
10 - 11 2 2 2 0 0%
12 -14 0 0 0 0 0%
15 -17 0 0 0 0 0%
TOTAL 9 16 16 0 0%
T3.26.4
3.27. FINANCIAL SERVICES
Employees: Financial Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No. Vacancies (fulltime)
Vacancies (as a % of total
posts)
0 - 3 8 8 4 4 50%
4 - 6 13 13 6 7 54%
7 - 9 44 75 55 20 27%
10 - 12 15 4 2 2 50%
13 - 15 0 0 0 0 0%
16 - 17 5 5 5 0 0%
Total 85 105 72 33 31%
T3.27.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 61
3.28. HUMAN RESOURCE SERVICES
INTRODUCTION TO HUMAN RESOURCE SERVICES The functions of the human resource unit includes:
Recruitment, selection, appointment and orientation of staff
Implementation of capacity building programme for Councilors and Officials
Formulation of Human Resource Strategies
T3.28.1
Employees: Human Resource Services
Job Level
2014/15 2015/16
Employees
No.
Posts
No.
Employees
No.
Vacancies (fulltime)
No.
Vacancies (as a % of total
posts)
0 - 3 1 2 2 0 0%
4 - 6 3 4 3 1 25%
7 - 9 1 2 1 1 50%
10 - 12 0 0 0 0 0%
13 - 15 0 0 0 0 0%
16 - 17 0 0 0 0 0%
Total 5 8 6 2 25%
T3.28.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 62
CHAPTER 4 – ORGANISATIONAL DEVELOPMENT PERFORMANCE (PERFORMANCE
REPORT PART II)
COMPONENT A: INTRODUCTION TO THE MUNICIPAL PERSONNEL
INTRODUCTION Council Resolution LM 405/06/2013 approved a functional organogram for the Municipality with a staff compliment 854 positions and 579 positions were filled in the year under review.
T4.0.1
4.
4.1. EMPLOYEE TOTALS, TURNOVER AND VACANCIES
Employees
Description
2014/2015 2015/2016
Employees Approved Posts No.
Employees Vacant Variance %
Filled Variance % No. No.
Water 36 85 38 47 55%
Waste Water (Sanitation) 30 67 29 38 57%
Electricity 29 46 30 16 35%
Waste Management 94 123 94 29 23%
Housing 7 10 7 3 30%
Roads and Storm Water Management 39 69 38 31 45%
Planning 5 8 7 1 13%
Local Economic Development 3 3 3 0 0%
Libraries and Community Facilities 15 27 17 10 37%
Cemeteries and Crematoriums & Parks 42 79 58 21 27%
Traffic Services 8 26 17 9 35%
Fire and Rescue Services 20 28 20 8 28%
Disaster Management 13 16 12 4 25%
Licensing 22 27 22 5 11%
Sport and Recreation 15 19 13 6 32%
Executive and Council 5 16 16 0 0%
Financial Services 75 105 72 33 31%
Human Resource Services 4 8 6 2 25%
Totals 462 737 499 263
Other
- Corporate Services 11 7 6 1 14%
Manager - Office of the Municipal 16 4 3 1 25%
- Public Safety 18 4 4 0 0%
- Technical Services 20 5 2 3 60%
- Finance 31 8 4 4 0%
- Community Services 20 3 3 0 0%
Totals 579 854 568 286 33%
T4.1.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 63
Vacancy Rate 2015/2016
Designations
Total Approved Post Filled Posts Percentage Days
No. No. Vacant Filled
Municipal Manager 1 1 0% 100% 0
Chief Finance Officer 1 0 100% 0% 0
Director Public Safety 1 1 0% 100% 0
Director Corporate Services 1 1 0% 100% 0
Director Community Services 1 1 0% 100% 0
Director Technical Services 1 1 0% 100% 0
Municipal Traffic Officer 10 8 20% 80% 0
Fire Fighter 26 20 23% 77% 0
Managers (Excluding Finance) 31 23 26% 74% 0
Finance Managers 8 4 50% 50% 0
Supervisors (Excluding Finance) 47 47 0% 100% 0
Finance Supervisors 13 13 0% 100% 0
Total 141 120 14.89% 85.15% Note: *For posts which are established and funded in the approved budget or adjustments budget (where changes in employee
provision have been made). Full-time equivalents are calculated by taking the total number of working days lost (excluding weekends and public holidays) while a post remains vacant and adding together all such days lost by all posts within the same set (e.g. ‘senior management’) then dividing that total by 250 to give the number of posts equivalent to the accumulated days.
T4.1.2
Turn-over Rate
Details
Total number of employees as of beginning of Financial Year
Total Appointments as of beginning of Financial Year
Terminations during the Financial Year
Turn-over Rate*
2011/12 595 -19 3%
2012/13 585 86 -35 5.9%
2013/14 531 79 56 0.11%
2014/15 610 25 66 6%
2015/16 610 610 569 6.72%
*Divide the number of employees who have left the organization within a year, by total number of employees who occupied posts at the beginning of the year T4.1.3
COMMENT ON VACANCIES AND TURNOVER In the beginning of the 2015/2016 financial year, the following senior management positions were filled as follows:
Municipal Manager - filled
Chief Finance Officer vacant since 30 September 2013
Deputy Chief Financial Officer and vacant since 24 April 2015
Director Corporate Service -filled
Director Public Safety- filled
Director Technical Service - filled
Director Community Services - filled T4.1.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 64
COMPONENT B: MANAGING THE MUNICIPAL WORKFORCE
INTRODUCTION TO MUNICIPAL WORKFORCE MANAGEMENT Msukaligwa Local Municipality has a Human Resources Section whose function is to develop and implement policies, provide guidance to employees on issues of personnel administration, skills development and industrial relations.
T4.2.0
4.2. POLICIES
HR Policies and Plans
Name of Policy Completed Reviewed Date adopted by council or comment on failure
to adopt % %
1 Attraction and Retention 100%
Adopted by Council in June 2012
2 Code of Conduct for employees 100%
Council implements the Code of Conduct which was agreed at between the parties in the Bargaining Council
3 Delegations, Authorisation & Responsibility
100%
Council approved delegation system is being implemented.
4 Disciplinary Code and Procedures 95%
Council implements the Disciplinary Code and Procedures which was negotiated in the Bargaining Council
5 Essential Services 60%
Council has adopted the Service Charter to provide guidance on Essential Services
6 Employee Assistance / Wellness 100%
Council adopted Employee Assistance / Wellness Policy in June 2012 and is being implemented
7 Grievance Procedures 95%
Council has adopted the Bargaining Council Grievance Procedures and it is being implemented
8 Workplace HIV/Aids 100%
Council has adopted the HIV/Aids Policy and it is being implemented
9 Recruitment Policy 80%
Council has adopted the Employment Practice Policy and the Capacity Building Policy and it is being implemented
10 Occupational Health and Safety 100%
Council adopted the Occupational Health and Safety Policy and it is being implemented
11 Sexual Harassment 100%
Council adopted the Sexual Harassment Policy and it is being implemented
12 Skills Development 75% 50% Council adopted the Capacity Building Policy and it is being implemented
T4.2.1
COMMENT ON WORKFORCE POLICY DEVELOPMENT Corporate Services department has developed Human Resources policies and have reviewed the critical policies. Other policies are being reviewed when there are changes in the legislation and regulations.
T4.2.1.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 65
4.3. INJURIES, SICKNESS AND SUSPENSIONS
Number and Cost of Injuries on Duty
Type of injury Injury Leave
Taken
Employees
using injury
leave
Average injury
leave taken per
employee
Average Injury
Leave per
employee
Total
Estimated Cost
Days No. % Days R'000
Required basic medical attention only
Temporary total disablement
Permanent disablement
Fatal
Total
T4.3.1
Number of days and Cost of Sick Leave (excluding injuries on duty)
Occupational Levels
Total sick leave
Proportion of sick leave without medical certification
Employees using sick leave
Total employees in occupational level*
*Average sick leave per Employees
Estimated cost
Days % No. No. Days R' 000
Top Management 17 N/A 3 5 3.4 R62 129.63
Senior Management 135 N/A 12 20 6.75 R547 644.19
Mid-Management/Proff. 287 N/A 31 52 5.52 R327 263.15
Skilled Tech/ Junior Management 1182 N/A 123 241 4.90 R837 139.82
Semi-Skilled 95 N/A 6 20 4.75 R39 881.49
Unskilled 773 N/A 105 235 3.29 R268 873.85
Total 2 489 N/A 280 573 3.22 R2 082 932.13
* - Number of employees in post at the beginning of the year
T4.3.2
*Average calculated by taking sick leave in column 2 divided by total employees in column 5
Msukaligwa Local Municipality | 2015/2016 Annual Report 66
T4.3.3
COMMENT ON INJURY AND SICK LEAVE Sick leave taken by employees did not have a significant impact on the total budget of the Municipality in the year 2015/2016.
T4.3.4
Number and Period of Suspensions
Position Nature of Alleged
Misconduct
Date of
Suspension
Details of Disciplinary Action
taken or Status of Case and
Reasons why not Finalised
Date Finalised
Traffic Officer Negligence 2015/04/13 Disciplinary hearing was conducted 2015/08/03
General Worker Abscondment 2015/06/26 Case withdrawn 2015/10/02
Squatter Control Officer
Intimidation 2015/07/15 Disciplinary hearing was conducted 2016/03/29
General Worker Assault 2015/08/23 Case withdrawn 2016/03/07
Building Inspector Negligence 2015/10/16 Resigned
Building Inspector Negligence 2015/10/16 Resigned
T4.3.5
Disciplinary Action Taken on Cases of Financial Misconduct
Position Nature of Alleged Misconduct and Rand
value of any loss to the municipality
Disciplinary action taken Date Finalised
None
T4.3.6
3,40
6,75
5,52
4,90
4,75
3,29
0,00 1,00 2,00 3,00 4,00 5,00 6,00 7,00 8,00
TOP MANAGEMENT
SENIOR MANAGEMENT
MID-MANAGEMENT/PROFF.
SKILLED TECH/ JUNIOR MANAGEMENT
SEMI-SKILLED
UNSKILLED
Average Number of Days Sick Leave (Excl IOD)
Msukaligwa Local Municipality | 2015/2016 Annual Report 67
COMPONENT C: CAPACITATING THE MUNICIPAL WORKFORCE
4.4. SKILLS DEVELOPMENT AND TRAINING
Skills Matrix
Management
level Gender
Employee
s in post
as at 30
June
2016
Number of skilled employees required and actual as at 30 June 2016
Learnerships
Skills programmes
& other short
courses
Other forms of
training Total
No.
Planned
30 June
2016
Actual
30 June
2016
Planned
30 June
2016
Actual
30 June
2016
Planned
30 June
2016
Actual
30 June
2016
Planned
30 June
2016
Actual
30 June
2016
MM and S57 Female
Male
1 1
Councilors,
senior officials
and managers
Female
8
Male
4
Technicians
and associate
professionals
Female
1
7
Male
8
2
Professionals Female
10
Male
Sub total Female
1
8 7 10
Male
8
4 1 3
Total
9
12 8 13
T4.5.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 68
Financial Competency Development: Progress Report*
Management level Original Budget and Actual Expenditure on Skills Development 2015/2016
Learnerships Skills programmes & other short courses
Other forms of training
Total
Original Budget
Actual Original Budget
Actual Original Budget
Actual Original Budget
Actual
MM and S57
Legislators, senior officials and managers
Professionals
Technicians and associate professionals
Clerks
Service and sales workers
Plant and machine operators and assemblers
Elementary occupations
Sub total
Total
%* *R
Financial Competency Development: Progress Report*
Description
A. Total number of officials employed by municipality (Regulation 14(4)(a) and (c))
Consolidated: Total of A
Consolidated: Competency assessments completed for A and B (Regulation 14(4)(b) and (d))
Consolidated: Total number of officials whose performance agreements comply with Regulation 16 (Regulation 14(4)(f))
Consolidated: Total number of officials that meet prescribed competency levels (Regulation 14(4)(e))
Financial Officials
Accounting officer
Chief financial officer
Senior managers
Any other financial officials
12
Supply Chain Management Officials
Heads of supply chain management units
Supply chain management senior managers
TOTAL
12
Msukaligwa Local Municipality | 2015/2016 Annual Report 69
*This is a statutory report under the National Treasury: Local Government: MFMA Competency Regulations 29967, June 2007 T4.5.2
COMMENT ON SKILLS DEVELOPMENT AND RELATED EXPENDITURE AND ON THE FINANCIAL COMPETENCY REGULATIONS The Directorate of Corporate Services Department under Skills Development Unit conducted some meticulous investigation through internal skills audit and information gathering sessions after having consulted with the Sectional Heads of various Departments which saw the Msukaligwa Works Skills Plan (WSP) and Annual Training Programme (ATP) being implemented in line with the organizational needs in pursuit of accelerating quality service delivery for sustainable community development. It is extremely imperative to note that officials who were placed on the programme exclude the interns approved and deployed by the Provincial Treasury for work exposure training programme and similar report was sent to the office of the Provincial Treasury detailing the list of the nominated officials to undergo a Minimum Competency Training Programme. The actual expenditure on financial competency training is R 866, 400 as per the signed Agreement, other training initiatives could not be implemented in accordance to the WSP due to financial constraints. Msukaligwa Local Municipality could not implement learnerships for the unemployed because the D.o.I (Declaration of intent) was not approved by the LGSETA.
T4.5.4
COMPONENT D: MANAGING THE WORKFORCE EXPENDITURE
4.5. EMPLOYEE EXPENDITURE
Source: MBRR SA22
T4.6.1
-
20 000
40 000
60 000
80 000
100 000
120 000
140 000
160 000
2011/12 2012/13 2013/14 2014/15 2015/16
Workforce Expenditure Trends
Management & Staff Councillors
Msukaligwa Local Municipality | 2015/2016 Annual Report 70
Number Of Employees Whose Salaries Were Increased Due To Their Positions Being Upgraded
Beneficiaries Gender Total
Top Management Female 0
Male 0
Senior Management Female 0
Male 0
Professional Qualified Female 0
Male 1
Skilled Technical Female 0
Male 0
Semi-Skilled Female 0
Male 0
Unskilled & Defined Female 0
Male 0
Total 1
Those with disability are shown in brackets '(x)' in the 'Number of beneficiaries' column as well as in the numbers at the right hand side of the column (as illustrated above).
T4.6.2
Employees Whose Salary Levels Exceed The Grade Determined By Job Evaluation
Occupation Number of employees Job evaluation level Remuneration
level
Reason for
deviation
None 0 0 0 0
T4.6.3
Employees appointed to posts not approved
Department Level Date of
appointment No. appointed
Reason for appointment when no
established post exist
None
T4.6.4
DISCLOSURES OF FINANCIAL INTERESTS Disclosure forms were issued to all employees and Councillors.
T4.6.6
Msukaligwa Local Municipality | 2015/2016 Annual Report 71
CHAPTER 5 – FINANCIAL PERFORMANCE
INTRODUCTION Chapter 5 contains information regarding financial performance and highlights specific accomplishments. The chapter comprises of three components:
Component A: Statement of Financial Performance
Component B: Spending Against Capital Budget
Component C: Financial Position T5.0.1
COMPONENT A: STATEMENTS OF FINANCIAL PERFORMANCE
5.
5.1. STATEMENTS OF FINANCIAL PERFORMANCE
Description Ref 2014/15 Budget Year 2015/16
Audited Outcome
Original Budget
Adjusted Budget
Monthly actual
YearTD actual
R thousands
Revenue By Source Property rates 67 259 73 742 81 067 6 809 81 295 Property rates - penalties & collection charges Service charges - electricity revenue 164 910 192 159 193 000 14 804 179 693 Service charges - water revenue 41 492 61 768 52 422 3 742 51 154 Service charges - sanitation revenue 18 944 20 409 20 582 1 768 21 109 Service charges - refuse revenue 15 822 17 871 18 305 1 539 18 338 Service charges - other 10 459 13 853 14 230 504 13 750 Rental of facilities and equipment 2 101 2 392 2 180 158 2 073 Interest earned - external investments 881 200 900 334 221 Interest earned - outstanding debtors 20 440 21 307 21 858 2 037 22 693 Dividends received Fines 5 890 1 546 5 611 0 3 057 Licences and permits 3 422 4 000 3 600 291 3 462 Agency services 6 774 6 000 6 700 658 6 377 Transfers recognised - operational 121 005 121 233 152 357 – 127 340 Other revenue 34 445 7 192 7 385 452 49 435 Gains on disposal of PPE 1 287 500 1 500 – 1 524
Total Revenue (excluding capital transfers and contributions)
515 132 544 172 581 698 33 097 581 521
Expenditure By Type
Employee related costs 148 246 156 871 153 167 13 104 150 635 Remuneration of councillors 11 628 12 394 12 349 1 018 12 290 Debt impairment 41 112 80 002 56 280 – – Depreciation & asset impairment 86 534 60 344 80 659 – – Finance charges 17 463 270 135 – 102 Bulk purchases 219 067 193 004 212 240 (3 250) 162 111 Other materials Contracted services 51 702 59 671 63 166 6 486 58 904 Transfers and grants Other expenditure 114 393 90 356 88 710 9 339 415 576 Loss on disposal of PPE – – – – –
Total Expenditure 690 145 652 911 666 707 26 697 799 619
Surplus/(Deficit) (175 014) (108 739) (85 009) 6 400 (218 097)
Transfers recognised - capital 45 590 61 066 61 066 – 61 066
Msukaligwa Local Municipality | 2015/2016 Annual Report 72
Contributions recognised - capital – – – – – Contributed assets – – – – –
Surplus/(Deficit) after capital transfers & contributions (129 423) (47 673) (23 942) 6 400 (157 031) Taxation – – – – –
Surplus/(Deficit) after taxation (129 423) (47 673) (23 942) 6 400 (157 031) Attributable to minorities – – – – –
Surplus/(Deficit) attributable to municipality (129 423) (47 673) (23 942) 6 400 (157 031) Share of surplus/ (deficit) of associate – – – – –
Surplus/ (Deficit) for the year (129 423) (47 673) (23 942) 6 400 (157 031)
COMMENT ON FINANCIAL PERFORMANCE The procurement of goods and services is done in accordance with the Supply Chain Management regulations, PPPFA of 2011 and in line with the approved budget and Integrated Development Plan (IDP) which makes the procurement process to be fair, equitable, cost effective and competitive.
T5.1.3
5.2. GRANTS
COMMENT ON CONDITIONAL GRANTS AND GRANT RECEIVED FROM OTHER SOURCES The municipality received the following grants: Operational Grants
Equitable Share - R 114 641 000
Municipal Finance Management Grant – R 1 675 000
Municipal System Improvement Grant – R 930 000
SETA Grant – R 0
EPWP Grant - R 1 238 000
MIG operational grant -R 2 548 850 Capital Grants
Integrated National Electrification Grant – R 12 638 000
Municipal Infrastructure Grant – R 37 540 477
T5.2.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 73
5.3. ASSETS MANAGEMENT
FINANCIAL POSITION 2015/2016
Audited
Outcome Original Budget
Adjusted Budget YearTD actual
R thousands
ASSETS Current assets
Cash 33 33 500 33 Call investment deposits 29 959 15 000 15 267 19 230 Consumer debtors 42 687 247 730 71 586 50 176 Other debtors 34 703 – 48 670 34 287 Current portion of long-term receivables – – – – Inventory 7 934 3 644 7 934 10 382
Total current assets 115 316 266 407 143 956 114 109
Non current assets
Long-term receivables Investments Investment property 30 273 – 56 098 28 957 Investments in Associate Property, plant and equipment 1 849 651 1 498 438 1 814 369 1 803 289 Agricultural Biological assets Intangible assets – 25 – – Other non-current assets 1 069 1 130 1 069 1 069
Total non current assets 1 880 994 1 499 593 1 871 536 1 833 315
TOTAL ASSETS 1 996 309 1 766 000 2 015 492 1 947 424
LIABILITIES Current liabilities
Bank overdraft – 6 000 – – Borrowing 1 220 – 1 220 338 Consumer deposits 10 688 9 374 10 688 12 262 Trade and other payables 405 735 164 399 332 217 502 761 Provisions 558 – 558
Total current liabilities 418 201 179 774 344 683 515 362
Non current liabilities
Borrowing 569 – 569 234 Provisions 70 542 73 394 71 100 81 863
Total non current liabilities 71 111 73 394 71 669 82 097
TOTAL LIABILITIES 489 312 253 168 416 352 597 459
NET ASSETS 1 506 997 1 512 832 1 599 141 1 349 965
COMMUNITY WEALTH/EQUITY
Accumulated Surplus/(Deficit) 1 506 997 1 560 505 1 515 960 1 349 965 Reserves
TOTAL COMMUNITY WEALTH/EQUITY 1 506 997 1 560 505 1 515 960 1 349 965
Repair and Maintenance Expenditure 2015/16
R' 000
Original
Budget
Adjustment
Budget Actual Budget variance
Repairs and Maintenance Expenditure 34 102 33 421 25 331 76%
T5.3.4
Msukaligwa Local Municipality | 2015/2016 Annual Report 74
COMMENT ON ASSET MANAGEMENT
The Municipality has acquired 3 large assets during the 2015/2016 financial year which were accounted for as per GRAP 17 (Property, Plant and Equipment)
The overall fixed assets register for movable as well as immovable asset of the municipality has also been prepared in accordance to GRAP 17 standards.
The municipality has established an asset management unit in the 2013/2014 financial year and staff appointed to ensure proper Asset Management in the municipality..
5.4. FINANCIAL RATIOS BASED ON KEY PERFORMANCE INDICATORS
0,3
0,2 0,3
0,6
–
0,1
0,2
0,3
0,4
0,5
0,6
0,7
2012/13 2013/14 2014/15 Current Year 2015/16
Liquidity Ration
Liquidity Ratio – Measures the municipality’s ability to pay its bills and is calculated by dividing the monetary assets (due within one year ) by the municipality’s current liabilities. A higher ratio is better.Data used from MBRR SA8 T5.4.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 75
0,5 0,0
0,7
-3,5 (4,0) (3,5) (3,0) (2,5) (2,0) (1,5) (1,0) (0,5)
– 0,5 1,0
2012/13 2013/14 2014/15 Current Year 2015/16
Cost Coverage
Cost Coverage– It explains how many months expenditure can be covered by the cash and other liquid assets available to the Municipality excluding utilisation of grants and is calculatedData used from MBRR SA8 T5.4.2
27,1%
20,3%
27,5% 28,7%
0,0%
5,0%
10,0%
15,0%
20,0%
25,0%
30,0%
35,0%
2012/13 2013/14 2014/15 Current Year 2015/16
Outstanding Service Debtors
Outstanding Service Debtors – Measures how much money is still owed by the community for water, electricity, waste removal and sanitation compared to how much money has been paid for these services. It is calculated by dividing the total outstanding debtors by the total annual revenue. A lower score is better.Data used from MBRR SA8 T5.4.3
Msukaligwa Local Municipality | 2015/2016 Annual Report 76
21,7 14,7
43,5
87
– 10,0 20,0 30,0 40,0 50,0 60,0 70,0 80,0 90,0
100,0
2012/13 2013/14 2014/15 Current Year 2015/16
Debt Coverage
Debt Coverage– The number of times debt payments can be accomodatedwithin Operating revenue (excluding grants) . This in turn represents the ease with which debt payments can be accomodated by the municipalityData used from MBRR SA8 T5.4.4
0,0% 0,0% 0,0% 0,0%0,0%10,0%20,0%30,0%40,0%50,0%60,0%70,0%80,0%90,0%
100,0%
2012/13 2013/14 2014/15 Current Year 2015/16
Creditors System Efficiency
Creditor System Efficiency – The proportion of creditors paid within terms (i.e. 30 days). This ratio is calculated by outstanding trade creditors divided by credit purchases. Data used from MBRR SA8.
T5.4.5
Msukaligwa Local Municipality | 2015/2016 Annual Report 77
2,3%
1,8%
3,0%
0,0%0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
2012/13 2013/14 2014/15 Current Year 2015/16
Capital Charges to Operating Expenditure
Capital Charges to Operating Expenditure ratio is calculated by dividing the sum of capital interest and principle paid by the total operating expenditure.Data used from MBRR SA8.
T5.4.6
30,4% 29,5% 30,5%
20,5%
0,0%
5,0%
10,0%
15,0%
20,0%
25,0%
30,0%
35,0%
2012/13 2013/14 2014/15 Current Year 2015/16
Employee Costs
Employee cost – Measures what portion of the revenue was spent on paying employee costs. It is calculated by dividing the total employee cost by the difference between total revenue and capital revenue. Data used from MBRR SA8.
T5.4.7
Msukaligwa Local Municipality | 2015/2016 Annual Report 78
COMPONENT B: SPENDING AGAINST CAPITAL BUDGET
INTRODUCTION TO SPENDING AGAINST CAPITAL BUDGET The capital spending in the municipality is mainly from grants received from National Treasury. The municipality have improved in terms of capital expenditure as compared to the previous financial year with 72% expenditure. Some of the 2015/2016 projects were implemented late which the reason for underperformance. The late implementation was due to the directive of the province to appoint Rand Water as an implementing Agent which stalled the procurement processes T5.5.0
3,7% 3,4%
6,3%
3,4%
0,0%
1,0%
2,0%
3,0%
4,0%
5,0%
6,0%
7,0%
2012/13 2013/14 2014/15 Current Year 2015/16
Repairs & Maintenance
Repairs and Maintenance – This represents the propotion of operating expenditure spent and is calculated by dividing the total repairs and maintenace. Data used from MBRR SA8.
T5.4.9
Msukaligwa Local Municipality | 2015/2016 Annual Report 79
5.5. CAPITAL EXPENDITURE
T 5.5.1
5.6. SOURCES OF FINANCE
Capital Expenditure - Funding Sources
R' 000
Details
2014/15 2015/16
Actual Original
Budget
(OB)
Adjustment
Budget
Actual Adjustmen
t to OB
Variance
(%)
Actual to
OB
Variance
(%)
Source of finance
External loans 0 0 0 0 0% 0%
Public contributions and
donations 0 28,834 37,811 0 31% 0%
Grants and subsidies 33,767 61,066 73,404 30,711 20% 50%
Other 0 0 0 4,378 0% 0%
Total 33,767 89,900 111,215 35,089 24% 39%
Percentage of finance
External loans 0 0 0 0
Public contributions and 0 32% 31% -100%
-
20 000 000
40 000 000
60 000 000
80 000 000
100 000 000
120 000 000
140 000 000
2013/2014 2014/2015 2015/2016
114 168 740 125 988 000
89 900 150
53 869 548
33 766 603 35 089 356
Capital Budget Capital Expenditure
Capital Expenditure
Msukaligwa Local Municipality | 2015/2016 Annual Report 80
donations
Grants and subsidies 100% 68% 20% 42%
Other 0 0 0 0
Total 100% 100% 24% 39%
Capital
expenditure
Water and sanitation 21 988 48,428 34,975 16,832 -28% -65%
Electricity 11,175 12,638 28, 427 13,878 125% 10%
Housing 202 0 6,302 2,425 0% 0%
Roads and storm water 402 0 3,700 1,954 0% 0%
Other 0 28,834 37,811 0 31% 0%
Total 33,767 89,900 111,215 35,089 24% -61%
Percentage of expenditure
Water and sanitation 65% 54% 31% 48%
Electricity 33% 14% 26% 40%
Housing 0.6% 0% 5.6% 7%
Roads and storm water 1.2% 0% 3.4% 5%
Other 0% 32% 34% 0%
5.7. CAPITAL SPENDING ON 5 LARGEST PROJECTS IN 2015/16 FY
Capital Expenditure of 5 largest projects*
R' 000
Name of Project
Current Year Variance Current Year
Original Budget Adjustment
Budget
Actual
Expenditure
Original
Variance
(%)
Adjustment
variance
(%)
Extend water reticulation in Sheepmoor R 5,112,172.53 R 5,112,172.53 R 5,112,172.53 0 0
Drilling of boreholes in Msukaligwa farm Areas
Phase 2 R 3,608,678.05 R 3,608,678.05 R 3,608,678.05 0 0
Installation of High Mast Lights R 3,141,457.66 R 3,141,457.66 R 3,141,457.66 0 0
Upgrade of roads in Msukaligwa (Upgrade of
roads in Silindile ) R 3,742,120.13 R 3,653,675.93 R 3,653,675.93 0 0
Upgrade of sports facility in Msukaligwa R 4,878,576.51 R 4,878,576.51 R 4,878,576.51 0 0
* Projects with the highest capital expenditure in 2015/16 Variances are calculated by dividing the difference between
actual and original/adjustments budget by the actual.
Name of Project - A Extend water reticulation in Sheepmoor
Objective of Project Provision of water to communities
Delays None
Future Challenges Increase in the demand
Msukaligwa Local Municipality | 2015/2016 Annual Report 81
Anticipated citizen benefits 351 households
Name of Project - B Drilling of boreholes in Msukaligwa farm Areas Phase 2
Objective of Project Provision of water to communities
Delays None
Future Challenges Maintenance cost
Anticipated citizen benefits 110 households
Name of Project - C Installation of High Mast Lights
Objective of Project Provision of community lighting
Delays None
Future Challenges Maintenance cost
Anticipated citizen benefits 5500 households
Name of Project - D Upgrade of roads in Msukaligwa (Upgrade of roads in Silindile )
Objective of Project Upgrading the road infrastructure
Delays None
Future Challenges Maintenance cost
Anticipated citizen benefits 0.3km
Name of Project - E Upgrade of sports facility in Msukaligwa
Objective of Project Provision of community facility
Delays None
Future Challenges Maintenance cost
Anticipated citizen benefits 10000 households
T5.7.1
TREATMENT OF THE THREE LARGEST ASSETS ACQUIRED 2015/16
Asset 1
Name Extend water reticulation in Sheepmoor
Description Water supply to households
Asset Type Infrastructure-Water Bulk
Key Staff Involved PMU personnel, Water and Sanitation section
Staff Responsibilities Monitoring and evaluation of project
Capital Implications
Future Purpose of Asset Water supply to households
Describe Key Issues
Policies in Place to Manage Asset Asset Management Policy
Msukaligwa Local Municipality | 2015/2016 Annual Report 82
Asset 2
Name Upgrade of sports facility in Msukaligwa
Description Provide community facility for the different sporting codes
Asset Type Sport infrastructure
Key Staff Involved PMU personnel, Sports and Recreation section
Staff Responsibilities
Capital Implications
Future Purpose of Asset Provide community facility for the different sporting codes
Describe Key Issues
Policies in Place to Manage Asset Asset Management Policy
Asset 3
Name Upgrade of roads in Msukaligwa (Upgrade of roads in Silindile )
Description Reliable and safe access points
Asset Type Roads and storm water
Key Staff Involved PMU personnel, Roads Section
Staff Responsibilities Monitoring and evaluation of project
Capital Implications
Future Purpose of Asset Access to the community
Describe Key Issues
Policies in Place to Manage Asset Asset Management Policy
T5.3.2
5.8. BASIC SERVICE AND INFRASTRUCTURE BACKLOGS – OVERVIEW
Service Backlogs as at 30 June 2016
Households (HHs)
*Service level above minimum standard **Service level below minimum standard
No. HHs % HHs No. HHs % HHs
Water 46,855 92% 4,243 8%
Sanitation 49,803 97% 1,295 3%
Electricity 44,683 87% 6,415 13%
Waste management 31,801 62% 19,279 38%
Housing 46,279 91% 4,819 9%
% HHs are the service above/below minimum standard as a proportion of total HHs. 'Housing' refers to * formal
and ** informal settlements. T5.8.2
Msukaligwa Local Municipality | 2015/2016 Annual Report 83
Vote Description Ref
2015/16 Budget Year 2016/17
Audited Outcome
Original Budget
Adjusted Budget
Monthly actual
YearTD actual
YearTD budget
YTD variance
YTD variance
Full Year
Forecast R thousands 1 %
Multi-Year expenditure appropriation 2 Vote 01 - Summary Department Technical
Services 19 841 57 564 32 385 3 840 13 480 28 132 (14 652) -52% 32 385 Vote 02 - Summary Electricity 5 323 12 000 9 000 201 6 370 7 673 (1 303) -17% 9 000 Vote 03 - Summary Department Public
Safety – – – – – – – – Vote 04 - Summary Department Community
And Health – – 12 558 3 155 5 198 9 502 (4 304) -45% 12 558 Vote 05 - Summary Department Corporate
Services – – – – – – – –
Vote 06 - Summary Council General (3 490) – – – – – – –
Vote 07 - Summary Department Finance – – – – – – – –
Total Capital Multi-year expenditure 4,7 21 674 69 564 53 943 7 196 25 048 45 306 (20 258) -45% 53 943 Single Year expenditure appropriation 2
Vote 01 - Summary Department Technical Services 8 412 100 6 755 (1 064) 4 591 5 485 (894) -16% 6 755
Vote 02 - Summary Electricity 10 000 – 7 000 – 6 193 5 600 593 11% 7 000 Vote 03 - Summary Department Public
Safety – – – – – – – – Vote 04 - Summary Department Community
And Health 4 333 – 2 466
– 1 672 1 912 (240) -13% 2 466
Vote 05 - Summary Department Corporate Services
– 6 900 6 900
– 220 5 750 (5 530) -96% 6 900
Vote 06 - Summary Council General – – – – – – – – Vote 07 - Summary Department Finance – – – – – – – –
Total Capital single-year expenditure 4 22 745 7 000 23 121 (1 064) 12 676 18 747 (6 071) -32% 23 121
Total Capital Expenditure 44 419 76 564 77 064 6 132 37 724 64 053 (26 329) -41% 77 064
Capital Expenditure - Standard Classification
Governance and administration (3 490) 6 900 6 900 – 220 5 750 (5 530) -96% 6 900
Executive and council (3 490) – – – – – – – Budget and treasury office – – – – – – – – Corporate services – 6 900 6 900 – 220 5 750 (5 530) -96% 6 900
Community and public safety 4 333 – 14 974 3 155 6 870 11 397 (4 527) -40% 14 974
Community and social services –
– 2 430
– 805 1 215 (410) -34% 2 430
Sport and recreation 4 333 12 544 3 155 6 066 10 182 (4 116) -40% 12 544 Public safety – – – – – – – – Housing – – – – – – – – Health – – – – – – – –
Economic and environmental services 4 128 100 22 296 1 400 10 849 17 746 (6 896) -39% 22 296 Planning and development – – – – – – – – Road transport 4 128 100 22 296 1 400 10 849 17 746 (6 896) -39% 22 296 Environmental protection –
Trading services 39 448 69 564 32 894 1 577 19 784 29 160 (9 376) -32% 32 894 Electricity 15 323 12 000 16 000 201 12 563 13 273 (710) -5% 16 000 Water 19 611 57 564 8 779 537 3 814 9 238 (5 423) -59% 8 779 Waste water management 4 514 – 8 065 839 3 407 6 633 (3 226) -49% 8 065 Waste management – – 50 – – 17 (17) -100% 50
Other – – – – – – – –
Total Capital Expenditure - Standard Classification 3 44 419 76 564 77 064 6 132 37 724 64 053 (26 329) -41% 77 064
Funded by:
National Government 46 288 69 564 70 064 6 132 37 504 58 220 (20 -36% 70 064
Msukaligwa Local Municipality | 2015/2016 Annual Report 84
716) Provincial Government – – – – – – – – District Municipality – – – – – – – – Other transfers and grants – – – – – – – –
Transfers recognised - capital 46 288 69 564 70 064 6 132 37 504 58 220 (20 716) -36% 70 064 Public contributions & donations 5 (3 490) – – – – – – – Borrowing 6 – – – – – – – – Internally generated funds – 7 000 7 000 – 220 5 833 (5 613) -96% 7 000
Total Capital Funding 42 798 76 564 77 064 6 132 37 724 64 053 (26 329) -41% 77 064
COMPONENT C: CASH FLOW MANAGEMENT AND INVESTMENTS
5.9. CASH FLOW
Description
2014/15 Budget Year 2015/16
Audited Outcome
Original Budget Adjusted Budget
YearTD actual
R thousands
CASH FLOW FROM OPERATING ACTIVITIES Receipts
Property rates, penalties & collection charges 54 832 54 393 71 975 70 368 Service charges 244 929 237 854 265 318 219 330 Other revenue 11 253 30 485 26 509 17 216 Government - operating 107 677 121 233 121 233 121 233 Government - capital 33 761 61 066 61 066 69 188 Interest 21 321 6 592 1 993 23 884 Dividends
Payments Suppliers and employees (403 561) (496 463) (569 719) (429 897) Finance charges (17 226) (10 597) (135) (58 036) Transfers and Grants – – – –
NET CASH FROM/(USED) OPERATING ACTIVITIES 52 985 4 563 (21 760) 33 287
CASH FLOWS FROM INVESTING ACTIVITIES Receipts
Proceeds on disposal of PPE – 500 1 335 38 Decrease (Increase) in non-current debtors Decrease (increase) other non-current receivables Decrease (increase) in non-current investments – – – –
Payments Capital assets (21 031) (61 066) (45 800) (42 695)
NET CASH FROM/(USED) INVESTING ACTIVITIES (21 031) (60 566) (44 465) (42 657)
CASH FLOWS FROM FINANCING ACTIVITIES Receipts
Short term loans – – – – Borrowing long term/refinancing – – – – Increase (decrease) in consumer deposits – – – –
Payments Repayment of borrowing (2 484) (1 789) (1 220) (1 323)
NET CASH FROM/(USED) FINANCING ACTIVITIES (2 484) (1 789) (1 220) (1 323)
NET INCREASE/ (DECREASE) IN CASH HELD 29 469 (57 792) (67 444) (10 694)
Cash/cash equivalents at beginning: 490 11 135 29 959 29 959 Cash/cash equivalents at month/year end: 29 959 (46 657) (37 486) 19 265
COMMENT ON CASH FLOW OUTCOMES The average payment rate for the year is 77% - this was achieved as a result of strict Credit Control as well as sub project of focusing on the top 600 debtors.
Msukaligwa Local Municipality | 2015/2016 Annual Report 85
. T 5.9.1
5.10. BORROWING AND INVESTMENTS
Actual Borrowings 2011/12 – 2015/16
R' 000
Instrument 2011/12 2012/13 2013/14 2014/15 2015/16
Municipality
Long-Term Loans (annuity/reducing balance) 58,875 22 259
Long-Term Loans (non-annuity)
Local registered stock
Instalment Credit
Financial Leases 6,170,101 5 443 566 1 789 038 1 219 802 337 942
PPP liabilities
Finance Granted By Cap Equipment Supplier
Marketable Bonds
Non-Marketable Bonds
Bankers Acceptances
Financial derivatives
Other Securities
Municipality Total 6,228,976 5 465 825 1 789 038 1 219 802 337 942
T5.10.2
COMMENT ON BORROWINGS The financial leases were for 3 vechiles. T 5.10.3
-
2 000 000
4 000 000
6 000 000
8 000 000
2011/12 2012/13 2013/14 2014/15 2015/16
6 228 976 5 465 825
1 789 038 1 219 802
337 942
T5.10.3a
Msukaligwa Local Municipality | 2015/2016 Annual Report 86
Municipal Investments R' 000
Investment* type 2011/12 2012/13 2013/14 2014/15 2015/16
Actual Actual Actual Actual Actual
Municipality
Securities - National Government
Listed Corporate Bonds
Deposits - Bank 9,999,965 17,006,822 0 29 925 286 19 263 551
Deposits - Public Investment Commissioners
Deposits - Corporation for Public Deposits
Bankers Acceptance Certificates
Negotiable Certificates of Deposit - Banks
Guaranteed Endowment Policies (sinking)
Repurchase Agreements - Banks
Municipal Bonds
Other
Municipality Total 9,999,965 17,006,822 0 29 925 286 19 263 551
T5.10.4
5.11. PUBLIC PRIVATE PARTNERSHIPS
None.
COMPONENT D: OTHER FINANCIAL MATTERS
5.12. SUPPLY CHAIN MANAGEMENT
SUPPLY CHAIN MANAGEMENT The Municipality implemented a supply chain management policy in line with the provisions of Supply Chain Management Regulation. T5.12.1
5.13. GRAP COMPLIANCE
GRAP COMPLIANCE The annual financial statements are prepared on an accrual basis of accounting and are in accordance with historical cost convention. The annual financial statements have been prepared in accordance with the Standards of Generally Recognized Accounting Practice (GRAP) as prescribed by the Minister of Finance in terms of General Notice 991 and 992 of 2005. As far as it has been practicable, applicable standards have been adopted retrospectively and prior year figures have been restated to achieve comparability requirements. T5.13.1
Msukaligwa Local Municipality | 2015/2016 Annual Report 87
CHAPTER 6 – AUDITOR GENERAL AUDIT FINDINGS
COMPONENT A: AUDITOR-GENERAL OPINION OF FINANCIAL STATEMENTS 2014/15
6.
6.1. AUDITOR GENERAL REPORTS 2015/16
The Auditor General report for 2015/2016 has been attached as annexure to this report.
Msukaligwa Local Municipality | 2015/2016 Annual Report 88
MFMA COMPLIANCE
All MFMA and DORA returns are submitted by the municipality as required monthly, quarterly and annually.
Name of return Submitted to
MONTHLY
Financial Management Grant PT and NT
Age Analysis Debtors (AD) and Creditors (AC), Cash Flow, Operating Statement Actual
(OSB)
PT and NT
Section 71 Budget Statements PT and NT
Supply Chain Management NT/PT
MIG returns PT and NT
Equitable Share COGTA
QUARTERLY
MFMA Implementation and monitoring checklist NT
Municipal entities N/A
Public Private Partnerships N/A
Long-term contracts NT
Borrowing NT
ANNUALLY
Appendix A NT
Operating Statement Budget (OSB) PT and NT
New Budget Regulations 1 April 2009 NT/PT
SIGNED (CFO): …………………………………………..... DATED: …………………………..
Msukaligwa Local Municipality | 2015/2016 Annual Report 89
GLOSSARY
Accessibility indicators Explore whether the intended beneficiaries are able to access services or outputs.
Accountability documents Documents used by executive authorities to give “full and regular” reports on the matters under their control to Parliament and provincial legislatures as prescribed by the Constitution. This includes plans, budgets, in-year and Annual Reports.
Activities The processes or actions that use a range of inputs to produce the desired outputs and ultimately outcomes. In essence, activities describe "what we do".
Adequacy indicators The quantity of input or output relative to the need or demand.
Annual Report A report to be prepared and submitted annually based on the regulations set out in Section 121 of the Municipal Finance Management Act. Such a report must include annual financial statements as submitted to and approved by the Auditor-General.
Approved Budget The annual financial statements of a municipality as audited by the Auditor General and approved by council or a provincial or national executive.
Baseline Current level of performance that a municipality aims to improve when setting performance targets. The baseline relates to the level of performance recorded in a year prior to the planning period.
Basic municipal service A municipal service that is necessary to ensure an acceptable and reasonable quality of life to citizens within that particular area. If not provided it may endanger the public health and safety or the environment.
Budget year The financial year for which an annual budget is to be approved – means a year ending on 30 June.
Cost indicators The overall cost or expenditure of producing a specified quantity of outputs.
Distribution indicators The distribution of capacity to deliver services.
Financial Statements Includes at least a statement of financial position, statement of financial performance, cash-flow statement, notes to these statements and any other statements that may be prescribed.
General Key performance indicators
After consultation with MECs for local government, the Minister may prescribe general key performance indicators that are appropriate and applicable to local government generally.
Impact The results of achieving specific outcomes, such as reducing poverty and creating jobs.
Inputs All the resources that contribute to the production and delivery of outputs. Inputs are "what we use to do the work". They include finances, personnel, equipment and buildings.
Integrated Development Plan (IDP)
Set out municipal goals and development plans.
National Key performance areas
Service delivery & infrastructure Economic development Municipal transformation and institutional development Financial viability and management Good governance and community participation
Outcomes The medium-term results for specific beneficiaries that are the consequence of achieving specific outputs. Outcomes should relate clearly to an institution's strategic goals and objectives set out in its plans. Outcomes are "what we wish to achieve".
Outputs The final products, or goods and services produced for delivery. Outputs may be defined as "what we produce or deliver". An output is a concrete achievement (i.e. a product such as a passport, an action such as a presentation or immunization, or a service such as processing an application) that contributes to the achievement of a Key Result Area.
Msukaligwa Local Municipality | 2015/2016 Annual Report 90
Performance Indicator Indicators should be specified to measure performance in relation to input, activities, outputs, outcomes and impacts. An indicator is a type of information used to gauge the extent to which an output has been achieved (policy developed, presentation delivered, service rendered)
Performance Information Generic term for non-financial information about municipal services and activities. Can also be used interchangeably with performance measure.
Performance Standards: The minimum acceptable level of performance or the level of performance that is generally accepted. Standards are informed by legislative requirements and service-level agreements. Performance standards are mutually agreed criteria to describe how well work must be done in terms of quantity and/or quality and timeliness, to clarify the outputs and related activities of a job by describing what the required result should be. In this EPMDS performance standards are divided into indicators and the time factor.
Performance Targets: The level of performance that municipalities and its employees strive to achieve. Performance Targets relate to current baselines and express a specific level of performance that a municipality aims to achieve within a given time period.
Service Delivery Budget Implementation Plan
Detailed plan approved by the mayor for implementing the municipality’s delivery of services; including projections of the revenue collected and operational and capital expenditure by vote for each month. Service delivery targets and performance indicators must also be included.
Vote: One of the main segments into which a budget of a municipality is divided for appropriation of money for the different departments or functional areas of the municipality. The Vote specifies the total amount that is appropriated for the purpose of a specific department or functional area. Section 1 of the MFMA defines a “vote” as: a) one of the main segments into which a budget of a municipality is divided for the appropriation of money for the different departments or functional areas of the municipality; and b) which specifies the total amount that is appropriated for the purposes of the department or functional area concerned
Municipality | APPENDICES 91
APPENDICES
APPENDIX A – COUNCILLORS; COMMITTEE ALLOCATION AND COUNCIL ATTENDANCE
Councillors, Committees Allocated and Council Attendance
Council Members
Full Time /
Part Time Committees Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies for
non-
attendance
FT/PT % %
Cllr. J.S. Bongwe FT Council
Mayoral Committee
Executive
Mayor 67% 8%
Cllr. B.M. Vilakazi FT
Council
Rules and Ethics
By-Laws and Policies
Speaker 100% 0
Cllr. N.G. Mashinini FT
Council
Rules and Ethics
LED and Tourism
Local Labour Forum
Chief Whip 92% 8%
Cllr. V.C.N. Madini FT Council
Mayoral Committee PR ANC 92% 8%
Cllr. M.P. Nkosi FT Council
Mayoral Committee Ward 1 92% 8%
Cllr. E.C. Msezane PT
Council
Community Services
Committee
Ward 2 83% 8%
Cllr. E.C. Lukhele PT
Council
Technical Services
Committee
Local Geographical
Names Committee
Ward 3 92% 0%
Cllr. B. N.N. Ndlovu PT
Council
Corporate Services
Community Services
Municipal Public
Accounts
Ward 4 67% 17%
Cllr. F.J. Mabasa PT
Council
Technical Services
Committee
Ward 5 92% 8%
Cllr. T.T. Malaza PT
Council
Corporate Services
Committee
Rules and Ethics
Local Geographical
Ward 6 92% 8%
Municipality | APPENDICES 92
Councillors, Committees Allocated and Council Attendance
Council Members
Full Time /
Part Time Committees Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies for
non-
attendance
FT/PT % %
Names Committee
Cllr. Z. Breydenbach PT
Council
Corporate Services
Committee
Rules and Ethics
Municipal Public
Account Committee
Ward 7 92% 0%
Cllr. H.F. Swart PT
Council
Finance Committee
Local Labour Forum
Ward 8 83% 0%
Cllr. M.J. Mhlanga PT Council
Local Labour Forum Ward 9 100% 0
Cllr. D.S. Nkosi PT
Council
Finance Committee
LED and Tourism
Ward 10 75% 8%
Cllr. L.P. Mnisi PT
Council
Technical Services
Committee
Finance Committee
Ward 11 100% 0%
Cllr. K.H. Dladla PT
Council
Public Safety
Committee
Rules and Ethics
Ward 12 83% 8%
Cllr. Z.C. Dhludhlu PT
Council
Community Services
Committee
Ward 13 100% 0%
Cllr. S.J. Msibi PT
Council
Technical Services
Committee
Local Geographical
Names Committee
Ward 14 92% 0%
Cllr. S.L. Jele PT
Council
Corporate Services
Committee
Ward 15 58% 8%
Cllr. Z.J. Nkosi PT
Council
Community Services
Committee
Ward 16 75% 8%
Cllr. B.I. Sibiya PT
Council
Municipal Public
Account Committee
Ward 17 92% 8%
Municipality | APPENDICES 93
Councillors, Committees Allocated and Council Attendance
Council Members
Full Time /
Part Time Committees Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies for
non-
attendance
FT/PT % %
Cllr. S.E. Vilakazi PT
Council
Community Services
Committee
Ward 18 100% 0%
Cllr. P.T. Sibeko PT
Council
Public Safety
Committee
Technical Services
Committee
Ward 19 92% 8%
Cllr. D. Mabunda PT
Council
Community Services
Committee
Local Labour Forum
PR ANC 100% 0
Cllr. P.E. Mashiane PT
Council
Public Safety
Committee
By-Laws and Policies
Local Labour Forum
PR ANC 100% 0%
Cllr. T.C. Ngwenya PT
Council
Finance Committee
LED and Tourism
Local Labour Forum
Municipal Public
Account Committee
PR ANC 100% 0%
Cllr. G.T. Msimango PT Council PR ANC 83% 8%
Cllr. P.B. Nkosi PT
Council
Public Safety
Committee
Local Geographical
Names Committee
PR ANC 100% 0%
Cllr. P.B. Maseko PT
Council
Finance Committee
Rules and Ethic
LED and Tourism
Municipal Public
Account Committee
PR ANC 83% 17%
Cllr. S.J. Nkosi PT
Council
By-Laws and Policies
LED and Tourism
PR ANC 92% 8%
Cllr. B.R. Ngwenya PT Council
Corporate Services PR ANC 67% 17%
Municipality | APPENDICES 94
Councillors, Committees Allocated and Council Attendance
Council Members
Full Time /
Part Time Committees Allocated
*Ward and/ or
Party
Represented
Percentage
Council
Meetings
Attendance
Percentage
Apologies for
non-
attendance
FT/PT % %
Committee
Local Geographical
Names Committee
LED and Tourism
Cllr. B.S. Puwani PT
Council
By-Laws and Policies
Municipal Public
Account Committee
PR ANC 75% 17%
Cllr. D.J. Litau PT Council PR ANC 100% 0%
Cllr. S.C. Mathebula PT
Council
Public Safety
Committee By-Laws
and Policies
PR DA 92% 0%
Cllr. J.H. Sibanyoni PT
Council
Finance Committee
By-Laws and Policies
Municipal Public
Account Committee
PR COPE 83% 0%
Cllr. B.I. Mabuza PT
Council
Corporate Services
Committee
PR DA 83% 0%
Cllr. G.S. Greyling PT
Council
Technical Services
Committee
Local Geographical
Names Committee
Municipal Public
Account Committee
PR DA 67% 8%
Cllr. J.D.A. Blignaut PT
Council
Public Safety
Committee
Municipal Public
Account Committee
PR FF+ 92% 8%
Cllr. D.T. Masina PT Council PR ANC 86% 0%
Cllr. V.J. Mokoena PT
Council
By-Laws and Policies
Municipal Public
Account Committee
PR ANC 100% 0%
Note: * Councillors appointed on a proportional basis do not have wards allocated to them T A
Municipality | APPENDICES 95
APPENDIX B – COMMITTEES AND COMMITTEE PURPOSES
Committees (other than Mayoral / Executive Committee) and Purposes of Committees
Municipal Committees Purpose of Committee
Corporate Services Committee To exercise oversight on corporate services matters.
Public Safety Committee To exercise oversight on Public Safety matters.
Technical Services Committee To exercise oversight on Technical Services matters.
Community Services Committee To exercise oversight on Community Services matters.
Finance Committee To exercise oversight on Financial matters.
Rules and Ethics Committee Oversight role on the code of conduct of Councillors.
By- Law and Policies Committee Policy formulation, development and implementation.
Local Geographical Names
Committee Standardization and renaming of identified features and public facilities.
Led and Tourism Committee Promotion of viable economic environment for sustainable growth.
Budget Evaluation committee
Evaluate the income and expenditure activities of the municipality and make
recommendations to section 80 committees for oversight.
Local Aids Forum Council
Creating awareness on the scourge of HIV and AIDS pandemic including coordination HIV
awareness programmes in various workplaces
Local labour Forum Committee Advice on issues of mutual interest involving management and the workforce.
Moral Regeneration Movement
Committee
Promotion of moral values within the society.
Municipal Public Account Committee
To promote good governance, transparency and accountability on the use of public funds and perform any tasks delegated by Council in terms of relevant applicable legislations,
To conduct investigation in the recovery of unauthorized, irregular and fruitless expenditure in terms of section 32 of the Municipal Finance Management Act (MFMA),
To review the Municipality and its entities Annual Report and to develop an oversight report on the Annual Report.
Gender Youth and People with
disabilities Committee
Playing an advocacy role in the protection of the rights and interests of the vulnerable
groups comprising women, youth and people with disability.
T B
Municipality | APPENDICES 96
APPENDIX C –THIRD TIER ADMINISTRATIVE STRUCTURE
Third Tier Structure
Directorate Director/Manager (State title and name)
Corporate Services Mr. N.L. Maimela – Director Corporate Services
Finance Chief Financial Officer - Vacant (Resigned in September 2013)
Deputy CFO – Vacant (Resigned end April 2014)
Technical Services Mr S.R Magudulela – Director Technical Services
Public Safety Mr. D.I Maluleke - Director Public Safety
Community Services Mr B.C. Sibeko – Director Community Services
Office of the Municipal Manager Mr. Z.T. Shongwe - Municipal Manager
Use as a spill-over schedule if top 3 tiers cannot be accommodated in chapter 2 (T2.2.2).
T C
APPENDIX D – FUNCTIONS OF MUNICIPALITY / ENTITY
Municipal / Entity Functions
MUNICIPAL FUNCTIONS Function Applicable to
Municipality (Yes / No)*
Function Applicable to
Entity (Yes /
No)
Constitution Schedule 4, Part B functions:
Air pollution No No
Building regulations Yes No
Child care facilities No Yes
Electricity and gas reticulation Yes Yes
Fire fighting services Yes No
Local tourism No Yes
Municipal airports Yes No
Municipal planning Yes No
Municipal health services No Yes
Municipal public transport No Yes
Municipal public works only in respect of the needs of municipalities in the
discharge of their responsibilities to administer functions specifically assigned
to them under this Constitution or any other law
Yes No
Pontoons, ferries, jetties, piers and harbours, excluding the regulation of
international and national shipping and matters related thereto N/A N/A
Storm water management systems in built-up areas Yes No
Trading regulations Yes No
Water and sanitation services limited to potable water supply systems and
domestic waste-water and sewage disposal systems Yes No
Beaches and amusement facilities N/A N/A
Billboards and the display of advertisements in public places Yes No
Cemeteries, funeral parlours and crematoria Yes No
Cleansing Yes No
Municipality | APPENDICES 97
Municipal / Entity Functions
MUNICIPAL FUNCTIONS Function Applicable to
Municipality (Yes / No)*
Function Applicable to
Entity (Yes /
No)
Constitution Schedule 4, Part B functions:
Control of public nuisances Yes No
Control of undertakings that sell liquor to the public No Yes
Facilities for the accommodation, care and burial of animals No Yes
Fencing and fences Yes No
Licensing of dogs N/A N/A
Licensing and control of undertakings that sell food to the public No Yes
Local amenities Yes No
Local sport facilities Yes No
Markets No Yes
Municipal abattoirs No Yes
Municipal parks and recreation Yes No
Municipal roads Yes No
Noise pollution No Yes
Pounds No Yes
Public places Yes No
Refuse removal, refuse dumps and solid waste disposal Yes No
Street trading Yes No
Street lighting Yes No
Traffic and parking Yes No
* If municipality: indicate (yes or No); * If entity: Provide name of entity T D
Municipality | APPENDICES 98
APPENDIX E – WARD REPORTING
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
One
Cllr MP Nkosi Yes 3 4 2
Mhlambi Sonto
Lukhele Sdudla L
Lubisi Sambulo E
Nyoni Nomsa
Skosana Sonto Rainy
Mthethwa Bongani
Khumalo Dorcas
Zwane Thembi
Mkhonza Smangele M
Nkosi Phindile
Two
Cllr EC Msezane Yes 9 1 2
Vilakazi Esther Fikile
Mkhatshwa Mthunzi J
Nkosi Nokusa S
Thabethe Girly
Magagula Sindisiwe P
Simelane Sizakele M
Mkhwanazi Lucky
Trust Stanley
Ntuli Queen
Shongwe Baby C
Three
Cllr MC Lukhele Yes 3 0 2
Hlengwa Maria N
Nkosi Jonathan
Motau Dolly Elizabeth
Sewpersad Lal Jeeth
Nkosi Lindiwe B D
Nxumalo Nhlanhla G
Hlophe Zenzele Z
Nhlapo Alfred
Mweli John
Four
Cllr BNN Ndlovu Yes 6 0 2
Masina Dumisani
Khumalo Zwelithini G
Municipality | APPENDICES 99
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
Ngema Thembelihle PG
Malinga Banele D
Khanye Valentine
Ngwenya Prudence
Ntshangase Simphiwe
Madonsela Sanele
Mabuza Jabulile
Sibeko Eric
Five
Cllr FJ Mabasa Yes 9 0 6
Dludlu Bethusile
Mdluli Mandlenkosi
Thabethe Ntombimpela
Mavimbela Emanuel
Magagula Zanele
Mthethwa Nelisile
Lukhele Mshiseni A
Mokoena Doctor
Thenjekwayo Mbalenhle
Mnisi Pretty
Six
Cllr TT Malaza Yes 12 2 2
Fakude Bongani E
Tlema Jabulile SS
Lukhele Maria
Mtshali Mandla
Nkosi Nonhlanhla
Simelane Elsie B
Malinga Nondumisa
Sibiya Nkosana
Lukhele Nqobile
Seven
Cllr Z Breydenbach Yes 11 6 1
Monareng Mosela
Reis Micheal Dos
Breydenbach Gerrit
Vilakazi Fikile Linah
Nyawo Luyanda S
Mtshali Precious N
Mahlobo Wiseman M
Municipality | APPENDICES 100
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
Zwane Thembi G
Zimela Nokwanda
Eight
Cllr HF Swart Yes 4 0 1
Badenhorst Jacobus
Cremer Cynthia
Nkosi Themba Joseph
Makhubu P Noncayi
Hlabane Critic Jabu
Mkhwanazi Zandle Ivy
Mahlangu Vangile
Nine
Cllr MJ Mhlanga Yes 7 0 3
Ngwenyama Gift Elton
Maluleka Johannes
Zulu Tafayile P
Madonsela Phindile I
Mlangeni Sindisiwe E
Sithole Sbongile N
Ngwenya Happy
Dludlu Sonto
Dladla John
Ten
Cllr DS Nkosi Yes 5 0 3
Vilakazi Zanele Haizel
Shongwe Joseph
Mngomezulu Zakhele
Thela Siphiwe Anna
Mthethwa Duduzile P
Mahlangu Precious
Sibeko Zodwa Preety
Mabuza Thoko Y
Nhlapho Absalon
Eleven
Cllr LP Mnisi Yes 7 1 5
Nkosi Lina Nyanyekile
Zulu Khulekani
Kunene Sabelo P
Nkosi Gugu P
Khalishwayo Msidi N
Dlangamandla Dizile
Fakude Emmah
Municipality | APPENDICES 101
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
Nkosi Linah Babazile
Dlamini B
Simelane Nonhlanhla
Twelve
Cllr KH Dladla Yes 10 0 3
Ngema Sbongile E
Dladla Majohoda
Dladla JV
Nkosi Sebenzile J
Mkhwanazi Fana S
Slabbert Nonhlanhla
Zwane Nkosinathi I
Nkabinde James K
Nkonde Ntombikayise
Mdluli Mkhipheni Enoch
Thirteen
Cllr ZC Dhludhlu Yes 8 4 4
Thomo Mandiya
Nkosi Jabulile
Msibi Zodwa Phyllis
Nazo Ntombi
Zulu Kholi Nellie
Ngwenya Fakazile L
Dlamini Busi
Fakude Thoko
Shongwe Thembi
Fourteen
Cllr SJ Msibi Yes 5 4 1
Nkonde Xoliswa
Hadebe Nomadlozi
Mkhonza Thalitha
Nkosi Gladwell Thulani
Nkosi Nomgqibelo
Nkonde Sthembile E
Nkambule Delisile E
Sibande Doris
Nkambule Edward S
Mahlangu Sophie S
Fifteen
Cllr SL Jele Yes 4 6 3
Soko M Conception
Maseko Jomo
Municipality | APPENDICES 102
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
Dladla Muzi E
Manana Richard K
Madonsela Nontokozo
Magagula Delisile
Banda PS
Dhludhlu Thulisile
Shabangu Abraham
Thela Mthokozisi
Sixteen
Cllr ZJ Nkosi Yes 11 2 3
Dlhangamandla Msolwa E
Simelane Nonhlanhla
Masuku Joe Zephania
Nkosi Ndundu M
Vilakazi Lizzie N
Masango Sibusiso M
Shongwe Delisile
Madonsela Anna M
Nkosi Dumisani P
Mkhwanazi Bonginkosi
Seventeen
Cllr BI Sibiya Yes 12 4 3
Thwala X George
Nkosi Thulani Monday
Mashinini Petros
Basson Kulph
Ndlovu Gcibelo B
Ngwenya Nokusa
Sibeko Elijah Gideon
Ngubeni Busisiwe
Letaba Khabonina
Mashinini Jacob V
Eighteen
Cllr SE Vilakazi Yes 8 0 2
Monareng Mandla T
Masina Delisile J
Nkambule Themba
Mnisi Siyabonga
Motha Nhlanhla
Nkosi Aslina
Nzimande John
Municipality | APPENDICES 103
Functionality of Ward Committees
Ward Name
(Number)
Name of Ward Councillor and
elected Ward committee
members
Committee
established
(Yes / No)
Number of
monthly
Committee
meetings held
during the
year
Number of
monthly
reports
submitted to
Speakers
Office on time
Number of
quarterly public
ward meetings
held during year
Khumalo M Nelisiwe
Zwane Bongani David
Mlotshwa Smangele
Nineteen
Cllr PT Sibeko Yes 8 0 3
Vilakazi Winnie
Diphofa Nomthandazo
Dhlamini Patience T
Maphanga Khesiah N
Simelane Lopi Norah
Mwali Lindiwe H
Shabangu Lukile G
Hlophe Phamela N
Maseko Maria Zodwa
Zandamela Themba T
APPENDIX F – WARD INFORMATION
Ward Title: Ward 8,9,10,12,13,15,16,18,19
Capital Projects: Seven Largest in 2015/16(Full List at Appendix N)
R' 000
No. Project Name and detail Start Date End Date Total Value
Drilling of Boreholes in farms 19/05/2016 30/06/2016 R 3,608,678.05
T F.1
Ward Title: Ward 11
Capital Projects: Seven Largest in 2015/16 (Full List at Appendix N)
R' 000
No. Project Name and detail Start Date End Date Total Value
Extend water reticulation in Sheepmoor 19/05/2015 15/12/2015 R 5,112,172.53
T F.1
Ward Title: Ward 1,2,3,9,11,12,15,16,17
Capital Projects: Seven Largest in 2015/16 (Full List at Appendix N)
R' 000
No. Project Name and detail Start Date End Date Total Value
Installation of High Mast Lights 01/02/2016 31/05/2016 R 3,141,457.66
Municipality | APPENDICES 104
T F.1
Ward Title: Ward 15
Capital Projects: Seven Largest in 2015/16 (Full List at Appendix N)
R' 000
No. Project Name and detail Start Date End Date Total Value
Upgrade of roads in Msukaligwa (Upgrade of roads in
Silindile )
30/11/2015 29/06/2016 R 3,653,675.93
T F.1
Ward Title: Ward 12,14,19
Capital Projects: Seven Largest in 2015/16 (Full List at Appendix N)
R' 000
No. Project Name and detail Start Date End Date Total Value
Upgrade of sports facility in Msukaligwa 30/11/2015 29/04/2016 R 4,878,576.51
T F.1
Basic Service Provision
Detail Water Sanitation Electricity Refuse Housing
Households with minimum service
delivery 46,846 49,794 44,652 33,231
Households without minimum
service delivery 4,243 1,295 6,437 17,858
Total Households* 51,089 51,089 51,089 51,089
Houses completed in year
Shortfall in Housing units
*Including informal settlements T F.2
Top Four Service Delivery Priorities for the Municipality (Highest Priority First)
No. Priority Name and Detail Progress During 2015/16
1 Provision of adequate water supply.
Extend water reticulation in Sheepmoor
Drilling of boreholes in Msukaligwa farm Areas Phase 2
2 Provision of hygienic sanitation services. Installation of Convertible Waterborne Toilets
in farm areas
3 Provision roads and storm water management Upgrade of roads in Msukaligwa (Upgrade of roads in
Silindile )
4 Electricity Installation of high-mast lights
T F.3
Municipality | APPENDICES 105
ELECTED WARD MEMBERS (STATING NUMBER OF MEETING ATTENDED – MAXIMUM 12 MEETINGS) Elected Councilors and members of ward committees as well as meetings attended are contained in Appendix A and E T F.3
Municipality | APPENDICES 106
APPENDIX G – RECOMMENDATIONS OF THE MUNICIPAL AUDIT COMMITTEE 2015/2016
Municipal Audit Committee Recommendations
Date of Committee Audit Committee recommendations during 2015/2016 Recommendations adopted (enter Yes); not adopted (provide explanation)
2015/2016
Audit Committee recommended that a follow-up should be
conducted to check if the Evacuation plan and Hazards register
have been developed.
Audit Committee recommended that Management should ensure
to develop Evacuation plan and Hazards register.
Audit Committee recommended that a follow-up should be
conducted to check how many lease agreements have been
signed to date and reasons be provided for the once which are
not yet signed
Audit Committee wanted to know what did the Municipality do
after receiving the Audit Report and Management Letter
Audit Committee recommended that the Audit Action Plan should
indicate the progress made to date, since the due date was 31
March 2016,
Audit Committee indicated that the Council has already approved
the budget, and recommended that in future should be submitted
to Audit Committee for quality assurance before tabling the
budget to Council.
Audit Committee recommended that the Officials from Finance
Department needs to be available for Audit Committee meeting
to account for their own reports.
Audit Committee recommended that the litigation report to be re-
submitted to the Audit Committee since the Manager: Legal
Services is part of the meeting
Audit Committee recommended that Internal Audit unit after
receiving management comments should make conclusion
based on the management comments provided against the
finding raised.
Audit Committee recommended that management should
strengthen the security (access to the Municipality not properly
controlled).
Audit Committee recommended that Internal Audit unit should
conduct a follow-up audit to verify whether all the findings have
been corrected or not.
Audit Committee recommended that data cleansing might assist
the Municipality.
Audit Committee recommended that arrangement should be
made with all employees who owe Council, and money should
be deducted directly from their salaries.
Yes adopted
Municipality | APPENDICES 107
Audit Committee recommended that the Municipality should
negotiate with people who are claiming less than R50 000 and if
their cases are found to be legit, we should pay to avoid
unnecessary interest.
Performance Audit Committee advised management to ensure
that if the set target was not achieved; reasons for under
performance should be provided to ensure corrective measures.
Performance Audit Committee recommended that Performance
should be cascaded to all employees within the Municipality. The
Committee also recommended that the Municipality should
benchmark with other Municipalities that are performing
performance correctly.
Municipality | APPENDICES 108 108
APPENDIX H – LONG TERM CONTRACTS AND PUBLIC PRIVATE PARTNERSHIPS
Long Term Contracts (20 Largest Contracts Entered into 2015/16)
R' 000
Name of Service Provider
(Entity or Municipal
Department)
Description of Services
Rendered by the Service
Provider
Start Date of
Contract
Expiry date of
Contract
Project
manager
Contract Value
Mafahleni Engineers
Professional services
and construction for the
sports facilities
30/11/2015 30/06/2017 PMU R 4,878,576.51
Mafahleni Engineers
Professional services
and construction of the
Silindile Road
30/11/2015 30/06/2017 PMU R 3,653,675.93
Gemini Garden Trading
400
Construction services for
the high-mast installation 01/02/2015 30/05/2017 PMU R 3,141,457.66
Thulatsepo General
Trading & Re tla Fihle
Trading and Project
Construction services for
the drilling of the
boreholes
19/05/2016 30/06/2017 PMU R 3,608,678.05
Rand Water
Professional services
and construction of the
Extend of the water
reticulation in Sheepmoor
15/05/2015 15/12/2016 PMU R 5,112,172.53
T H.1
Public Private Partnerships Entered into
2014/15 R' 000
Name and Description of
Project
Name of Partner(s) Initiation
Date
Expiry date Project
manager
Value
2008/09
No PPPs entered into with the
municipality
T H.2
Municipality | APPENDICES 109
APPENDIX I – MUNICIPAL ENTITY/ SERVICE PROVIDER PERFORMANCE SCHEDULE
Municipal Entity/Service Provider Performance Schedule
Service Objectives Outline Service
Targets
2011/12 2012/13 2014/15 2015/16
Target Actual Target Actual Target Actual Future
Service Indicators
Service Objective: To provide sustainable basic services and sustainable infrastructure
None – Contained in
Appendix N
T I
Municipality | APPENDICES 110 110
APPENDIX J – DISCLOSURES OF FINANCIAL INTERESTS
Disclosures of Financial Interests
Period 1 July 2015 to 30 June 2016
Position Name Description of Financial interests*
(Nil / Or details)
(Executive) Mayor Cllr. J.S. Bongwe Residential property
Polo Classic
Speaker Cllr. B.M. Vilakazi None
Council Whip Cllr. N.G. Mashinini None
Member of the Mayco Cllr. M.P. Nkosi None
Member of the Mayco Cllr. V.C.N. Madini None
Councillor Cllr. E.C. Msezane None
Cllr. E.C. Lukhele None
Cllr. B. N.N. Ndlovu Mining Contract – Desertkite Trading – R 20,000.00
Bongintuthuko Trading – Mining Supplies
Cllr. F.J. Mabasa
Financial interest – R 30 000
Close Corporation – R 25,000 per year
Property – R ± 70 00
Cllr. T.T. Malaza None
Cllr. Z. Breydenbach
Estate Agent – Commission
Flat – R 300 000.00
Cllr. H.F. Swart None
Cllr. M.J. Mhlanga House – R 90 000.00
Cllr. D.S. Nkosi None
Cllr. L.P. Mnisi None
Cllr. K.H. Dladla Technical Recorder – R 5000.00
Cllr. Z.C. Dhludhlu
Chairperson – R 3 000.00
Selling Fire Wood – R 9 000.00
Cllr. S.J. Msibi None
Cllr. S.L. Jele None
Cllr. Z.J. Nkosi Tavern & Tuck Shop
Cllr. B.I. Sibiya
Pension – R 8774.90 pm
Retirement Policy – R 519.00 pm
Title Holder – R 1 000 000
Title Holder – R 35 000.00
Cllr. S.E. Vilakazi None
Cllr. P.T. Sibeko None
Cllr. D. Mabunda None
Cllr. P.E. Mashiane None
Cllr. T.C. Motha Three (Close Cooperation)
Cllr. P.B. Nkosi None
Municipality | APPENDICES 111
Disclosures of Financial Interests
Period 1 July 2015 to 30 June 2016
Position Name Description of Financial interests*
(Nil / Or details)
Cllr. G.T. Msimango None
Cllr. P.B. Maseko House – R 120 000.00
VW Golf 5 – R 189 000.00
Cllr. S.J. Nkosi None
Cllr. B.R. Ngwenya None
Cllr. B.S. Puwani None
Cllr. D.J. Litau Close Corporation – R 2 000 00
Cllr. S.C. Mathebula Van Assistant
Cllr. J.H. Sibanyoni None
Cllr. B.I. Mabuza None
Cllr. G.S. Greyling
Property – R 400,000
Law – R 2,750,000
Property 60m2 - R 300,000
Property - 500m2 - R 2,000,000
Property - +- 300m2 – R 1,000,000
Law - R 20,000.00
Law - R 20,000.00
House 500m2 – R 1,500 000
House 340 m2 – R 580,000
Flat 85m2 – R 220,000
Cllr. J.D.A. Blignaut None
Municipal Manager Mr. Z. T. Shongwe Sabatha Shongwe & Daughters Trust – Trustee
Property – 8 Penelope Street, Vanderbijlpark – R 1,000,000
Deputy Chief Financial Officer
Ms. A. D. Twala
(Resigned 30 April
2015)
None
Directors Mr. N.L. Maimela None
Mr. D.I. Maluleke None
Mr. B.C. Sibeko None
Mr. S.R. Magudulela None
Other S57 Officials None
* Financial interests to be disclosed even if they incurred for only part of the year. See MBRR SA34A
T J
Municipality | APPENDICES 112
APPENDIX K: REVENUE COLLECTION PERFORMANCE BY VOTE AND BY SOURCE
MP302 Msukaligwa - Table A3 Budgeted Financial Performance (revenue and expenditure by municipal vote)A
Vote Description Ref
2012/13 2013/14 2014/15 Current Year 2015/16 2016/17 Medium Term Revenue & Expenditure Framework
R thousand Audited Outcome
Audited Outcome
Audited Outcome
Original Budget
Adjusted Budget
Full Year Forecast
Budget Year 2016/17
Budget Year +1 2017/18
Budget Year +2 2018/19
Revenue by Vote 1 Vote 01 - Summary Department Technical Services 91,837 84,460 93,897 82,402 72,947 72,947 73,704 77,785 82,593 01.1 - Director Town Engineer – – – – – – – – – 01.2 - Public Works 34,745 33,912 34,049 0 0 0 0 0 0 01.3 - Public Works Employees From Province – – – – – – – – – 01.4 - Technical Department – – – – – – – – – 01.5 - Pmu 1,653 2,000 2,188 2,549 2,549 2,549 2,878 2,569 2,713 01.6 - Airport 40 57 86 93 89 89 97 103 109 01.7 - Sewerage Income 21,015 17,124 18,984 20,452 20,626 20,626 23,699 25,168 26,728 01.8 - Sewerage Network – – – – – – – – – 01.9 - Sewerage Purification – – – – – – – – – 01.10 - Water Income 34,384 31,366 38,590 59,309 49,683 49,683 47,030 49,946 53,042 01.11 - Water Network – – – – – – – – – 01.12 - Water Purification – – – – – – – – – Vote 02 - Summary Electricity 151,294 189,016 192,735 212,847 214,386 214,386 228,293 242,447 257,479 02.1 - Street Lights – – – – – – – – – 02.2 - Electricity 151,294 189,016 192,735 212,847 214,386 214,386 228,293 242,447 257,479 02.3 - Street Lights – – – – – – – – – Vote 03 - Summary Department Public Safety 8,710 12,563 17,151 13,421 16,786 16,786 17,773 18,875 20,045 03.1 - Director Public Safety – – – 0 0 0 – – – 03.2 - Fire Brigade Services 119 365 1,022 1,829 829 829 1,037 1,102 1,170 03.3 - Disaster Management – – – – – – – – – 03.4 - Safety And Security – – – – – – – – – 03.5 - Licensing 8,135 9,640 10,199 10,004 10,304 10,304 10,873 11,548 12,264 03.6 - Traffic 456 2,557 5,930 1,588 5,654 5,654 5,862 6,226 6,612 03.7 - Parking Meters – – – – – – – – – Vote 04 - Summary Department Community And Health
29,411 17,564 17,893 20,221 21,759 21,759 23,540 24,999 26,549
04.1 - Director Community And Health – – – – – – – – – 04.2 - Cemetary 282 353 364 418 400 400 385 409 434 04.3 - Caravan Park 132 143 179 197 180 180 195 207 220 04.4 - Parks And Grounds – – – – – – – – – 04.5 - Libraries 41 33 44 54 47 47 49 52 55 04.6 - Swimming Pool – – – 0 0 0 – – – 04.7 - Sport & Recreation 4,785 11 16 15 45 45 45 48 51 04.8 - Sport Fields General 29 37 57 51 75 75 120 127 35 04.9 - Golf Course 0 0 0 0 0 0 0 0 0 04.10 - Health – – – – – – – – – 04.11 - Clinics – – – – – – – – – 04.12 - Tuberculosis Hospital 93 – – – – – – – – 04.13 - Welfare – – – – – – – – – 04.14 - Refuse / Sanitary 19,018 14,451 15,822 17,906 18,325 18,325 19,859 21,090 22,398 04.15 - Housing 4,204 1,645 511 571 1,812 1,812 1,940 2,060 2,188 04.16 - Sub-economical Housing 89 102 110 120 118 118 129 137 145 04.17 - Staff Flats 738 788 791 888 757 757 818 869 923 04.18 - Libraries – – – – – – – – – 04.19 - Swimming Pool – – – – – – – – – 04.20 - Sport Fields General – – – – – – – – – 04.21 - Golf Course – – – – – – – – – 04.22 - Sport And Recreation – – – – – – – – – Vote 05 - Summary Department Corporate Services 944 805 616 694 533 533 554 589 625 05.1 - Director Corporate Services 0 0 0 0 0 0 0 0 0 05.2 - Marketing & Communication – – – – – – – – – 05.3 - Grants & Donations – – – – – – – – –
Municipality | APPENDICES 113
05.4 - Mecanical Workshop – – – 0 0 0 – – – 05.5 - Civic Centre 215 550 394 493 332 332 354 376 399 05.6 - Administration 0 1 0 1 0 0 0 0 0 05.7 - Human Resources 728 255 222 200 200 200 200 212 226 05.8 - Occupational Health & Safety And Youth – – – – – – – – – Vote 06 - Summary Council General 107,380 136,278 117,133 177,873 209,021 209,021 193,567 194,973 209,610 06.1 - Town Planning And Building Control 14 0 0 – – – – – – 06.2 - Town Planning – 0 – – – – – – – 06.3 - Integrated Management Information System – – – – – – – – – 06.4 - Local Economic Development 8 1 5 1 1 1 5 5 6 06.5 - Tourism – – – – – – – – – 06.6 - Summary Council General – – – – – – – – – 06.7 - Municipal Manager 0 – 0 0 0 0 0 0 0 06.8 - Integrated Management Information System 1,134 757 816 925 949 949 977 1,037 1,102 06.9 - Local Economic Development – – – – – – – – – 06.10 - Tourism – – – – – – – – – 06.11 - Idp & Internal Audit – – – – – – – – – 06.12 - Council General 106,224 135,519 116,311 176,947 208,071 208,071 192,585 193,931 208,503 06.13 - Exco Councillors – – – – – – – – – 06.14 - Mayor – – – – – – – – – 06.15 - Speaker – – – – – – – – – 06.16 - Councillors – – – – – – – – – 06.17 - Director Marketing And Communication – – – – – – – – – 06.18 - Marketing And Communication – – – – – – – – – 06.19 - Local Economic Development – – – – – – – – – 06.20 - Grants In Aid And Donations – – – – – – – – – 06.21 - Tourism – – – – – – – – – Vote 07 - Summary Department Finance 74,526 76,780 91,854 97,780 107,333 107,333 118,201 125,737 133,638 07.1 - Director Finance – – – – – – – – –
07.2 - Assessment Rates 57,159
61,842
66,149
72,525
80,871
80,871
90,963
96,602
102,592
07.3 - Municipal Store – –
1,287
500
500
500
100
106
113
07.4 - Finance 17,367
14,938
24,419
24,756
25,961
25,961
27,139
29,028
30,933
Total Revenue by Vote 2 464,103
517,467
531,278
605,238
642,764
642,764
655,632
685,406
730,540
Expenditure by Vote 1
Vote 01 - Summary Department Technical Services 108,378
129,557
161,405
143,984
146,542
146,542
183,342
194,221
206,248
01.1 - Director Town Engineer 935
5,876
1,698
1,977
2,080
2,080
2,297
2,439
2,591
01.2 - Public Works 8,128
9,866
55,527
46,433
58,013
58,013
59,856
63,567
67,508
01.3 - Public Works Employees From Province – – – – – – – – –
01.4 - Technical Department 3,108
3,632
3,461
3,903
3,651
3,651
3,790
4,025
4,274
01.5 - Pmu 1,653
1,999
2,140
2,551
2,549
2,549
2,878
2,569
2,713
01.6 - Airport 30
26
41
201
157
157
174
185
196
01.7 - Sewerage Income – – – – – – – – –
01.8 - Sewerage Network 12,584
7,457
22,053
24,757
25,773
25,773
26,262
27,890
29,620
01.9 - Sewerage Purification 5,441
6,151
4,762
6,244
5,392
5,392
6,249
6,637
7,048
01.10 - Water Income – – – – – – – – –
01.11 - Water Network 24,669
17,650
15,715
35,605
27,914
27,914
26,605
28,255
30,007
01.12 - Water Purification 51,830
76,900
56,007
22,313
21,014
21,014
55,229
58,654
62,290
Vote 02 - Summary Electricity 235,129
219,207
212,725
254,388
263,347
263,347
279,187
296,497
314,880
02.1 - Street Lights 42,720
55,403
1,493
1,625
1,330
1,330
1,470
1,561
1,658
02.2 - Electricity 192,142
163,513
211,005
252,363
261,367
261,367
276,717
293,874
312,094
02.3 - Street Lights
Municipality | APPENDICES 114
267 290 227 400 650 650 1,000 1,062 1,128
Vote 03 - Summary Department Public Safety 36,503
37,328
43,603
51,320
54,565
54,565
53,661
56,988
60,522
03.1 - Director Public Safety 14,042
14,985
17,807
22,808
22,231
22,231
19,796
21,024
22,327
03.2 - Fire Brigade Services 8,003
8,604
9,275
10,571
10,288
10,288
11,162
11,854
12,589
03.3 - Disaster Management 4,273
3,371
3,486
3,688
3,518
3,518
3,809
4,045
4,296
03.4 - Safety And Security 9 – – – – – – – –
03.5 - Licensing 5,180
5,534
6,516
6,864
7,472
7,472
7,798
8,281
8,795
03.6 - Traffic 4,995
4,834
6,518
7,389
11,056
11,056
11,096
11,784
12,515
03.7 - Parking Meters – – – – – – – – – Vote 04 - Summary Department Community And Health
45,963
38,863
122,127
53,282
57,777
57,777
59,931
63,646
67,592
04.1 - Director Community And Health 278
717
10,857
1,903
1,434
1,434
1,485
1,577
1,675
04.2 - Cemetary 1,629
1,939
2,353
2,632
2,628
2,628
2,769
2,940
3,123
04.3 - Caravan Park 131
103
42,074
137
108
108
112
119
126
04.4 - Parks And Grounds 6,209
7,191
17,849
7,182
7,552
7,552
8,114
8,617
9,152
04.5 - Libraries 2,927
3,187
3,497
3,764
3,679
3,679
3,919
4,162
4,420
04.6 - Swimming Pool 15 12 7,006 0 0 0 – – – 04.7 - Sport & Recreation 1,723 1,724 1,900 2,138 4,312 4,312 4,599 4,884 5,187 04.8 - Sport Fields General 1,607 1,574 1,647 3,115 2,232 2,232 2,259 2,399 2,548 04.9 - Golf Course 617 369 2,760 424 304 304 310 330 350 04.10 - Health 15 8 3,326 19 4 4 5 5 6 04.11 - Clinics 15 (727) 2,734 0 0 0 – – – 04.12 - Tuberculosis Hospital – – – – – – – – – 04.13 - Welfare – – – – – – – – – 04.14 - Refuse / Sanitary 27,770 20,361 23,790 29,172 33,096 33,096 33,712 35,802 38,022 04.15 - Housing 3,024 2,406 2,335 2,795 2,426 2,426 2,647 2,811 2,985 04.16 - Sub-economical Housing – – – – – – – – –
04.17 - Staff Flats 3
– – – – – – – –
04.18 - Libraries – – – – – – – – – 04.19 - Swimming Pool – – – – – – – – – 04.20 - Sport Fields General – – – – – – – – – 04.21 - Golf Course – – – – – – – – – 04.22 - Sport And Recreation – – – – – – – – – Vote 05 - Summary Department Corporate Services 37,949 34,114 34,357 46,830 42,799 42,799 45,883 48,728 51,749 05.1 - Director Corporate Services 10,535 7,851 11,296 18,881 15,742 15,742 18,063 19,183 20,372 05.2 - Marketing & Communication 1,192 – – – – – – – – 05.3 - Grants & Donations 12 1 – 0 0 0 – – –
05.4 - Mecanical Workshop 127
120
101
126
224
224
182
193
205
05.5 - Civic Centre 5,936
6,287
6,836
8,206
8,254
8,254
8,279
8,792
9,337
05.6 - Administration 4,973
8,217
9,107
9,171
10,325
10,325
10,636
11,295
11,996
05.7 - Human Resources 15,072
11,624
6,987
10,349
8,188
8,188
8,637
9,172
9,741
05.8 - Occupational Health & Safety And Youth 102
14
31
98
68
68
87
92
98
Vote 06 - Summary Council General 30,916
31,245
31,800
40,657
37,146
37,146
46,404
47,820
50,785
06.1 - Town Planning And Building Control – – 681 – – – – – – 06.2 - Town Planning – – – – – – – – – 06.3 - Integrated Management Information System – – – – – – – – – 06.4 - Local Economic Development – – – – – – – – –
06.5 - Tourism 5,520
1,621
593
–
–
–
–
–
–
06.6 - Summary Council General – – – – – – – – – 06.7 - Municipal Manager
Municipality | APPENDICES 115
4,275 6,066 6,514 8,066 8,469 8,469 15,325 16,275 17,284
06.8 - Integrated Management Information System 1,984
3,148
2,523
4,128
2,314
2,314
2,567
2,726
2,895
06.9 - Local Economic Development 1,180
1,254
1,288
1,323
1,455
1,455
1,529
1,624
1,724
06.10 - Tourism – – – 0 0 0 – – –
06.11 - Idp & Internal Audit 2,645
1,803
2,196
2,400
2,437
2,437
2,489
2,644
2,807
06.12 - Council General 3,392
3,443
3,544
9,196
6,922
6,922
8,144
7,188
7,634
06.13 - Exco Councillors 1,566
1,646
1,752
3,720
3,695
3,695
3,917
4,160
4,418
06.14 - Mayor 690
725
770
819
812
812
860
914
970
06.15 - Speaker 556
584
621
660
654
654
693
736
782
06.16 - Councillors 9,107
10,955
11,318
10,345
10,389
10,389
10,880
11,554
12,270
06.17 - Director Marketing And Communication - - - - - - - - - 06.18 - Marketing And Communication - - - - - - - - - 06.19 - Local Economic Development - - - - - - - - - 06.20 - Grants In Aid And Donations - - - - - - - - - 06.21 - Tourism - - - - - - - - - Vote 07 - Summary Department Finance 73,655 42,745 52,957 62,450 64,496 64,496 69,816 74,352 79,067 07.1 - Director Finance 694 305 24 1,283 2,635 2,635 3,784 4,018 4,267 07.2 - Assessment Rates 44,846 (487) – 19,174 15,200 15,200 19,195 20,385 21,648 07.3 - Municipal Store 2,742 2,621 234 542 611 611 648 689 731 07.4 - Finance 25,373 40,306 52,699 41,450 46,050 46,050 46,189 49,260 52,420
Total Expenditure by Vote 2 568,494 533,060 658,973 652,911 666,672 666,672 738,224 782,252 830,842
Surplus/(Deficit) for the year 2 (104,391) (15,593) (127,695) (47,673) (23,907) (23,907) (82,592) (96,846) 100,303)
References 1. Insert 'Vote'; e.g. Department, if different to standard structure
2. Must reconcile to Financial Performance ('Revenue and Expenditure by Standard Classification' and 'Revenue and Expenditure') 3. Assign share in 'associate' to relevant Vote
APPENDIX K (I): REVENUE COLLECTION PERFORMANCE BY VOTE
MP302 Msukaligwa - Table A3 Budgeted Financial Performance (revenue and expenditure by municipal vote)
Vote Description R
ef 2012/13 2013/14 2014/15 Current Year 2015/16
2016/17 Medium Term Revenue
& Expenditure Framework
R thousand Audited
Outcome
Audited
Outcome
Audited
Outcome
Original
Budget
Adjusted
Budget
Full Year
Forecast
Budget
Year
2016/17
Budget
Year +1
2017/18
Budget
Year +2
2018/19
Revenue by Vote 1
Vote 01 - Summary Department Technical Services
91,837
84,460
93,897
82,402
72,947
72,947
73,704
77,785
82,593
Vote 02 - Summary Electricity
151,294
189,016
192,735
212,847
214,386
214,386
228,293
242,447
257,479
Vote 03 - Summary Department Public Safety
8,710
12,563
17,151
13,421
16,786
16,786
17,773
18,875
20,045
Vote 04 - Summary Department Community And
Health
29,411
17,564
17,893
20,221
21,759
21,759
23,540
24,999
26,549
Vote 05 - Summary Department Corporate Services
944
805
616
694
533
533
554
589
625
Vote 06 - Summary Council General
107,380
136,278
117,133
177,873
209,021
209,021
193,567
194,973
209,610
Vote 07 - Summary Department Finance
74,526
76,780
91,854
97,780
107,333
107,333
118,201
125,737
133,638
Total Revenue by Vote 2
464,103
517,467
531,278
605,238
642,764
642,764
655,632
685,406
730,540
Municipality | APPENDICES 116
Expenditure by Vote to be appropriated 1
Vote 01 - Summary Department Technical Services
108,378
129,557
161,405
143,984
146,542
146,542
183,342
194,221
206,248
Vote 02 - Summary Electricity
235,129
219,207
212,725
254,388
263,347
263,347
279,187
296,497
314,880
Vote 03 - Summary Department Public Safety
36,503
37,328
43,603
51,320
54,565
54,565
53,661
56,988
60,522
Vote 04 - Summary Department Community And
Health
45,963
38,863
122,127
53,282
57,777
57,777
59,931
63,646
67,592
Vote 05 - Summary Department Corporate Services
37,949
34,114
34,357
46,830
42,799
42,799
45,883
48,728
51,749
Vote 06 - Summary Council General
30,916
31,245
31,800
40,657
37,146
37,146
46,404
47,820
50,785
Vote 07 - Summary Department Finance
73,655
42,745
52,957
62,450
64,496
64,496
69,816
74,352
79,067
Total Expenditure by Vote 2
568,494
533,060
658,973
652,911
666,672
666,672
738,224
782,252
830,842
Surplus/(Deficit) for the year 2
(104,391)
(15,593)
(127,695)
(47,673)
(23,907)
(23,907)
(82,592)
(96,846)
(100,30
3)
References
1. Insert 'Vote'; e.g. department, if different to standard classification structure
2. Must reconcile to Budgeted Financial Performance (revenue and expenditure)
3. Assign share in 'associate' to relevant Vote
APPENDIX K (II): REVENUE COLLECTION PERFORMANCE BY SOURCE
MP302 Msukaligwa - Table A2 Budgeted Financial Performance (revenue and expenditure by standard classification)
Standard Classification Description Ref 2012/13 2013/14 2014/15 Current Year 2015/16 2016/17 Medium Term Revenue
& Expenditure Framework
R thousand 1 Audited
Outcome
Audited
Outcome
Audited
Outcome
Original
Budget
Adjusted
Budget
Full Year
Forecast
Budget
Year
2016/17
Budget
Year +1
2017/18
Budget
Year +2
2018/19
Revenue - Standard
Governance and administration
182,433
213,893
209,572
276,310
316,693
316,693
312,158
321,125
343,689
Executive and council
106,224
135,519
116,311
176,947
208,071
208,071
192,585
193,931
208,503
Budget and treasury office
74,526
76,780
91,854
97,780
107,333
107,333
118,201
125,737
133,638
Corporate services
1,682
1,593
1,406
1,582
1,289
1,289
1,372
1,458
1,548
Community and public safety
18,364
14,889
18,431
14,848
19,464
19,464
20,636
21,915
23,274
Community and social services
416
387
408
472
447
447
434
461
489
Sport and recreation
4,945
192
251
264
300
300
360
383
406
Public safety
8,710
12,563
17,151
13,421
16,786
16,786
17,773
18,875
20,045
Housing
4,293
1,747
621
692
1,930
1,930
2,069
2,197
2,333
Health
–
–
–
–
–
–
–
–
–
Economic and environmental services
37,554
36,671
37,059
3,475
3,498
3,498
3,860
3,612
3,821
Planning and development
Municipality | APPENDICES 117
1,156 759 822 926 949 949 982 1,043 1,107
Road transport
36,398
35,912
36,238
2,549
2,549
2,549
2,878
2,569
2,713
Environmental protection
–
–
–
–
–
–
–
–
–
Trading services
225,711
251,958
266,131
310,514
303,020
303,020
318,880
338,651
359,647
Electricity
151,294
189,016
192,735
212,847
214,386
214,386
228,293
242,447
257,479
Water
34,384
31,366
38,590
59,309
49,683
49,683
47,030
49,946
53,042
Waste water management
21,015
17,124
18,984
20,452
20,626
20,626
23,699
25,168
26,728
Waste management
19,018
14,451
15,822
17,906
18,325
18,325
19,859
21,090
22,398
Other 4
40
57
86
93
89
89
97
103
109
Total Revenue - Standard 2
464,103
517,467
531,278
605,238
642,764
642,764
655,632
685,406
730,540
Expenditure - Standard
Governance and administration
132,417
101,947
113,897
144,262
140,382
140,382
157,739
166,265
176,678
Executive and council
19,599
23,419
24,520
32,806
30,941
30,941
39,820
40,827
43,358
Budget and treasury office
76,300
44,549
55,152
64,849
66,933
66,933
72,305
76,995
81,874
Corporate services
36,519
33,979
34,225
46,607
42,508
42,508
45,614
48,442
51,446
Community and public safety
54,796
55,845
141,970
75,528
79,314
79,314
79,967
84,925
90,190
Community and social services
4,864
5,124
22,766
8,318
7,746
7,746
8,177
8,684
9,223
Sport and recreation
10,303
10,972
73,235
12,997
14,509
14,509
15,395
16,349
17,363
Public safety
36,503
37,328
43,603
51,320
54,565
54,565
53,661
56,988
60,522
Housing
3,024
2,406
2,335
2,795
2,426
2,426
2,647
2,811
2,985
Health
102
14
31
98
68
68
87
92
98
Economic and environmental services
18,307
25,896
67,419
60,440
70,284
70,284
73,099
77,143
81,911
Planning and development
4,357
4,403
4,492
5,451
3,768
3,768
4,095
4,349
4,619
Road transport
13,950
21,493
62,927
54,989
66,516
66,516
69,003
72,794
77,292
Environmental protection
–
–
–
–
–
–
–
–
–
Trading services
357,423
347,726
335,053
372,479
376,535
376,535
427,246
453,735
481,866
Electricity
235,129
219,207
212,725
254,388
263,347
263,347
279,187
296,497
314,880
Water
76,500
94,550
71,722
57,918
48,928
48,928
81,835
86,909
92,297
Waste water management
18,025
13,608
26,816
31,001
31,165
31,165
32,512
34,527
36,668
Waste management
27,770
20,361
23,790
29,172
33,096
33,096
33,712
35,802
38,022
Other 4
Municipality | APPENDICES 118
5,550 1,647 634 201 157 157 174 185 196
Total Expenditure - Standard 3
568,494
533,060
658,973
652,911
666,672
666,672
738,224
782,252
830,842
Surplus/(Deficit) for the year
(104,391)
(15,593)
(127,695)
(47,673)
(23,907)
(23,907)
(82,592)
(96,846)
(100,30
3)
References
1. Government Finance Statistics Functions and Sub-functions are standardised to assist the compilation of national and international accounts for comparison
purposes
2. Total Revenue by standard classification must reconcile to Total Operating Revenue shown in Budgeted Financial Performance (revenue and
expenditure)
3. Total Expenditure by Standard Classification must reconcile to Total Operating Expenditure shown in Budgeted Financial Performance (revenue and
expenditure)
4. All amounts must be classified under a standard classification (modified GFS). The GFS function 'Other' is only for Abbatoirs, Air Transport, Markets and Tourism - and if used
must be supported by footnotes. Nothing else may be placed under 'Other'. Assign associate share to relevant classification
APPENDIX L: CONDITIONAL GRANTS RECEIVED: EXCLUDING MIG
Conditional Grants: excluding MIG
R' 000
Details
Budget Adjustment
Budget
Actual Variance Major conditions
applied by donor
(continue below if
necessary)
Budget Adjustment
Budget
Municipal Systems
Improvement Grant 934 000 0 934,000 0% 0%
Finance Management
Grant 1,600,000 0 1,600,000 0% 0%
EPWP 1,144 000 1,144,000 0% 0%
Total 3,678,000 0 3,678,000 0% 0%
* This includes Neighbourhood Development Partnership Grant, Public Transport Infrastructure and Systems Grant and any
other grant excluding Municipal Infrastructure Grant (MIG) which is dealt with in the main report, see T5.8.3. Variances are
calculated by dividing the difference between actual and original/adjustments budget by the actual.
T L
COMMENT ON CONDITIONAL GRANTS EXCLUDING MIG The grants were spent according to the support plan. Funds were utilized to employ interns, assist with the compiling of the Annual Financial Statements and the payment of contract workers. TL.1
Municipality | APPENDICES 119 119
APPENDIX M: CAPITAL EXPENDITURE – NEW & UPGRADE/RENEWAL PROGRAMMES
To be provided in due course
APPENDIX M (I): CAPITAL EXPENDITURE - NEW ASSETS PROGRAMME
MP302 Msukaligwa - Supporting Table SA34a Capital expenditure on new assets by asset class
Description Ref 2012/13 2013/14 2014/15 Current Year 2015/16 2016/17 Medium Term Revenue & Expenditure
Framework
R thousand 1 Audited
Outcome
Audited
Outcome
Audited
Outcome
Original
Budget
Adjusted
Budget
Full Year
Forecast
Budget Year
2016/17
Budget Year
+1 2017/18
Budget Year
+2 2018/19
Capital expenditure on new assets by Asset Class/Sub-class
Infrastructure – 52,773 21,843 89,900 88,028 88,028 69,564 61,375 63,264
Infrastructure - Road transport – 6,821 395 – – – – – –
Roads, Pavements & Bridges – 6,821 395 – – – – – –
Storm water – – – – – – – – –
Infrastructure - Electricity – 17,450 11,175 29,122 41,760 41,760 12,000 10,000 9,000
Generation – – – 29,122 29,122 29,122 12,000 10,000 9,000
Transmission & Reticulation – 15,248 11,149
– 12,638 12,638 – – –
Street Lighting – 2,202 26 – – – – – –
Infrastructure - Water – 26,556 10,272 60,778 39,525 39,525 57,564 51,375 54,264
Dams & Reservoirs – 65 877 – 3,497 3,497 – – –
Water purification – – – – – – – – –
Reticulation – 26,491 9,395 60,778 36,028 36,028 57,564 51,375 54,264
Infrastructure - Sanitation – 164 – – 6,743 6,743 – – –
Reticulation – 164 – – 6,743 6,743 – – –
Sewerage purification – – – – – – – – –
Infrastructure - Other – 1,782 – – – – – – –
Waste Management
Transportation 2
Municipality | APPENDICES 120
Gas
Other 3 – 1,782 – – – – – – –
Community – – – – – – – – –
Parks & gardens
Sportsfields & stadia – – – – – – – – –
Swimming pools
Community halls – – – – – – – – –
Libraries – – – – – – – – –
Recreational facilities
Fire, safety & emergency – – – – – – – – –
Security and policing – – – – – – – – –
Buses 7
Clinics
Museums & Art Galleries
Cemeteries – – – – – – – – –
Social rental housing 8
Other – – – – – – – – –
Heritage assets – – – – – – – – –
Buildings
Other 9
Investment properties – – – – – – – – –
Housing development
Other
Other assets 832 1,498 – – – – 7,000 7,000 7,000
General vehicles – 1,266 – – – – 6,000 6,000 6,000
Specialised vehicles 10 – – – – – – – – –
Plant & equipment – – – – – – – – –
Computers - hardware/equipment 316 232 – – – – 300 200 200
Furniture and other office equipment 129 – – – – – 600 400 400
Abattoirs
Markets
Civic Land and Buildings
Other Buildings
Municipality | APPENDICES 121
Other Land 242 – – – – – – – –
Surplus Assets - (Investment or Inventory)
Other 145 – – – – – 100 400 400
Agricultural assets – – – – – – – – –
Biological assets – – – – – – – – –
Intangibles – – – – – – – – –
Computers - software & programming
Total Capital Expenditure on new assets 1 832 54,271 21,843 89,900 88,028 88,028 76,564 68,375 70,264
Specialised vehicles – – – – – – – – –
Refuse
Fire
Conservancy
Ambulances
Municipality | APPENDICES 122
APPENDIX M (II): CAPITAL EXPENDITURE – UPGRADE/RENEWAL OF ASSETS PROGRAMME
MP302 Msukaligwa - Supporting Table SA34b Capital expenditure on the renewal of existing assets by asset class
Description Ref 2012/13 2013/14 2014/15 Current Year 2015/16 2016/17 Medium Term Revenue & Expenditure
Framework
R thousand 1 Audited
Outcome
Audited
Outcome
Audited
Outcome
Original
Budget
Adjusted
Budget
Full Year
Forecast
Budget Year
2016/17
Budget Year
+1 2017/18
Budget Year
+2 2018/19
Capital expenditure on renewal of existing assets by Asset Class/Sub-class
Infrastructure (3,488) 1,329 11,721 – 23,187 23,187 – – –
Infrastructure - Road transport – – – – 3,700 3,700 – – –
Roads, Pavements & Bridges – – – – 3,700 3,700 – – –
Storm water
Infrastructure - Electricity – – – – 3,151 3,151 – – –
Generation
Transmission & Reticulation – – – – – – – – –
Street Lighting – – – – 3,151 3,151 – – –
Infrastructure - Water – – 11,721 – 9,114 9,114 – – –
Dams & Reservoirs
Water purification – – – – 300 300 – – –
Reticulation – – 11,721 – ,814 8,814 – – –
Infrastructure - Sanitation (3,488) 1,329 – – 920 920 – – –
Reticulation – – – – 920 920 – – –
Sewerage purification (3,488) 1,329 – – – – – – –
Infrastructure - Other – – – – 6,302 6,302 – – –
Waste Management
Transportation 2
Gas
Other 3 – – – – 6,302 6,302 – – –
Community – – – – – – – – –
Parks & gardens
Sportsfields & stadia
Swimming pools
Municipality | APPENDICES 123
Community halls – – – – – – – – –
Libraries
Recreational facilities
Fire, safety & emergency
Security and policing
Buses 7
Clinics – – – – – – – – –
Museums & Art Galleries
Cemeteries
Social rental housing 8
Other
Heritage assets – – – – – – – – –
Buildings
Other 9
Investment properties – – – – – – – – –
Housing development
Other
Other assets – – – – – – – – –
General vehicles
Specialised vehicles 10 – – – – – – – – –
Plant & equipment
Computers - hardware/equipment
Furniture and other office equipment
Abattoirs
Markets
Civic Land and Buildings
Other Buildings
Other Land
Surplus Assets - (Investment or Inventory)
Other – – – – – – – – –
Agricultural assets – – – – – – – – –
Biological assets – – – – – – – – –
Municipality | APPENDICES 124
Intangibles – – – – – – – – –
Computers - software & programming
Total Capital Expenditure on renewal of existing assets 1 (3,488) 1,329 11,721 – 23,187 23,187 – – –
Specialised vehicles – – – – – – – – –
Refuse
Fire
Conservancy
Ambulances
Renewal of Existing Assets as % of total capex 131.3% 2.4% 34.9% 0.0% 20.8% 20.8% 0.0% 0.0% 0.0%
Renewal of Existing Assets as % of deprecn" -7.1% 2.2% 13.5% 0.0% 28.7% 28.7% 0.0% 0.0% 0.0%
Municipality | APPENDICES 125 125
APPENDIX N – CAPITAL PROGRAMME BY PROJECT 2015/16
Capital Programme by Project 2015/16
R' 000
Capital Project Original
Budget
Adjustment
Budget Actual
% Variance (Act
- Adj)
%Variance
(Act - OB)
Water
Drilling of Boreholes in Msukaligwa Farm
phase 2
R
3,608,678.65
R
3,608,678.65
R
3,608,678.65
Extend water reticulation in Sheepmoor
R
5,112,172.53
R
5,112,172.53
R
5,112,172.53
Replacement of AC pipes in
Ermelo/Wesselton
R
3,285,912.95
R
3,285,912.95
R
3,285,912.95
Internal Water Reticulation Breyten Ext 5,
Ward 14
R
2,293,600.89
R
2,293,600.89
R
2,293,600.89
Construction of a 10ML concrete
reservior
R
3,284,857.78
R
3,284,857.78
R
3,284,857.78
Installation of Boreholes and bulk line at
Warburton
R
1,069,237.84
R
1,069,237.84
R
1,069,237.84
Sanitation/Sewerage
Installation of Convertible Waterborne
Toilets in farm areas
R
2,110,609.55
R
2,110,609.55
R
2,110,609.55
Construction of oxidation ponds WWTW
system at Sheepmoor
R
1,721,822.16
R
1,721,822.16
R
1,721,822.16
Internal Sewer network in Breyten Ext 5
R
2,324,754.92
R
2,324,754.92
R
2,324,754.92
Electricity
Installation of High Mast Lights R
3,141,457.66
R
3,141,457.66
R
3,141,457.66
Roads & Storm water
Upgrade of roads in Msukaligwa
(Upgrade of roads in Silindile )
R
3,742,120.13
R
3,742,120.13
R
3,653,675.93 2.4
Construction of storm water drainage R 964,121.16 R 964,121.16 R 964,121.16
Housing
None
Sports, Arts & Culture
Upgrade of sports facility in Msukaligwa R
4,878,576.51
R
4,878,576.51
R
4,878,576.51
Environment
None
Refuse removal
None (Operational programmes only) 0 0 0 0 0
Economic development
None (Operational programmes only) 0 0 0 0 0
Municipality | APPENDICES 126
Health
None 0 0 0 0 0
Safety and Security
None (Operational programmes at Public
Safety department only) 0 0 0 0 0
ICT and Other
None (Operational programmes only) 0 0 0 0 0
T N
Municipality | APPENDICES 127 127
APPENDIX O – CAPITAL PROGRAMME BY PROJECT BY WARD 2015/2016
Capital Programme by Project by Ward 2015/16
R' 000
Capital Project Ward(s) affected Works completed
(Yes/No)
Water
Drilling of Boreholes in Msukaligwa Farm phase 2 8,9,10,12,13,15,16,18,19 Yes
Extend water reticulation in Sheepmoor 11 Yes
Replacement of AC pipes in Ermelo/Wesselton
No
Internal Water Reticulation Breyten Ext 5, Ward 14 14 No
Construction of a 10ML concrete reservior No
Installation of Boreholes and bulk line at Warburton 19 No
Sanitation/Sewerage
Installation of Convertible Waterborne Toilets in farm areas 18 Yes
Construction of oxidation ponds WWTW system at
Sheepmoor 11 No
Internal Sewer network in Breyten Ext 5 14 No
Electricity
Installation of High mast lights 1,2,3,9,11,12,15,16,17 Yes
Roads and storm water
Upgrade of roads in Msukaligwa (Upgrade of
roads in Silindile ) 15 Yes
Construction of storm water drainage 2 No
Housing
None
Sports, Arts & Culture
Upgrade of sports facility in Msukaligwa 12,14,19 Yes
Municipality | APPENDICES 128
APPENDIX P – SERVICE CONNECTION BACKLOGS AT SCHOOLS AND CLINICS
Service Backlogs: Schools and Clinics
Establishments lacking basic services Water Sanitation Electricity Solid Waste
Collection
Schools (NAMES, LOCATIONS)
Schools are provided with all municipal services
except solid waste collections at farm schools.
Clinics (NAMES, LOCATIONS)
Clinics are provided with all municipal services.
Names and locations of schools and clinics lacking one or more services. Use 'x' to mark lack of service at
appropriate level for the number of people attending the school/clinic, allowing for the proper functioning of
the establishment concerned. T P
Municipality | APPENDICES 129 129
APPENDIX Q – SERVICE BACKLOGS EXPERIENCED BY THE COMMUNITY WHERE ANOTHER
SPHERE OF GOVERNMENT IS RESPONSIBLE FOR SERVICE PROVISION
Service Backlogs Experienced by the Community where another Sphere of Government is the Service Provider (where the
municipality whether or not act on agency basis)
Services and Locations Scale of backlogs Impact of backlogs
Clinics:
Farm areas Mobile clinics not doing regular visits.
Communities have to travel to towns to
access health services and some do not
afford transport fares.
Housing:
Ermelo extension 32, 34, Nganga,
Wesselton ext.3 and other areas.
Incomplete houses and houses that
are not built at all.
There is complaining about the houses
that have taken too long to be built or
completed.
Licensing and Testing Centre:
Documentation that must be sent to
the Provincial Department of
Community Safety, Security and
Liaison help desk takes long for
verifications, approval and
capturing.
High
Affects the community at large due
documents that are not processed on
time including our own personnel.
Schools (Primary and High):
Khayelisha settlement at Ward 9
The settlement has grown and due to
the population growth there is a need
for a school.
The current Wesselton Primary school is
too far for small kids and often parents
struggle to pay transport fees for the kids.
APPENDIX R – DECLARATION OF LOANS AND GRANTS MADE BY THE MUNICIPALITY
No grants were made by the municipality.
APPENDIX S – DECLARATION OF RETURNS NOT MADE IN DUE TIME UNDER MFMA S71
There were no returns made in accordance with Section 71 of the MFMA.
Municipality | APPENDICES 130 130
VOLUME II: ANNUAL FINANCIAL STATEMENTS
Attached.