Rajasthan State Road Development & Construction Corporation Ltd. - Development of - Gotan-Pundlu-Borunda-Ransigaon - Khariameethapur-Bilara-Sojat Road. BLG Construction Services (P) Ltd. AN ISO 9001-2000 CERTIFIED COMPANY FOR CIVIL ENGINEERING CONSULTANCY. Project Location. Gotan. - PowerPoint PPT Presentation
Citation preview
GotanGotan
BilaraBilara
BorundaBorunda
SojatSojat
KhejarlaKhejarla
Project LocationProject Location
GotanGotan
BilaraBilara
BorundaBorunda
SojatSojat
KhejarlaKhejarla
Project MapProject Map
This route Carries Heavy Mining and Industrial Traffic. A large number of lime, cement and chemical Industries nearly more than 100 are situated on this road. Besides this a large number lime stone quarries are also situated in the surroundings of this Road.
The road caters for raw and finished lime product transportation. The area is agriculturally rich and improvement of this road will reduce the operation and maintenance cost of vehicles plying over this road.
Necessity of The ProjectNecessity of The Project
Study ObjectiveStudy Objective
Development of the road as two laning with paved shoulder or earthen shoulder.
Determining technical feasibility & financial viability.
Development & Construction of project highway with project facilities, enhanced safety & Level of services.
To ensure minimum adverse impact on local population, road users & environment .
Phased development of project highway for improving its financial viability with minimum inconvenience to traffic if additional work are undertaken within 7 years.
Study ObjectiveStudy Objective
Work Done Till DateWork Done Till Date
Reconnaissance Survey Completed Mobilization of Staff 7 Days Traffic demand assessment and
classified Traffic Volume count work completed, Intersection volume count completed, Pedestrian crossing completed. Axle load Spectrum completed.
Topographic, Alignment and Land use survey completed for 70km of project road. Bridge & road condition survey completed.
Geotech, material, hydrology, drainage survey in progress
Inspection of available records completed. Land Plan survey under preparation. Environment and social impact study in
progress.
Work Done Till DateWork Done Till Date
Key Date No. Description of Deliverables Week No.KD1 Submission of Inception Report 1
KD2 Submission of Draft Detailed Project Report, Bidding Documents and land acquisition report
4
KD3 Approval of Final Detailed Project Report and Bidding Documents
6
KD4 Submission of required project clearances from the concerned agencies
8
KD5 Completion of project 104
Time Schedule for Submission Time Schedule for Submission
Road DetailsRoad Details
• Project Road is Road from Gotan to Sojat Via Pundlu – Borunda
• Project Road is having total length of 93 Kms.• Project Road length is 23 KM in district Nagour.• Project Road length is 58 KM in district Jodhpur &
12 KM in Pali
Existing ROW12 – 15 M 15 – 20 M
13 KM 80 KM
Project DescriptionProject Description
Predominant land use is agriculture. Structures are generally in good condition. Minor bridges and pipe culverts shall have to be reconstructed / widened. Flush Causeways will be replaced by Culverts. Bypass at Ransigaon-Hariadhana and pundlu are proposed. Construction of CC road in Borunda mining area and other water logged
village portions.
KM City / Village Name
0 Gotan
16 Pundlu
28 Borunda
36 Haria Dhana
41 Ransigaon
61 Kharia Meethapur
63 Bilara
Project Road passes through town villages as below :
Project Description contd..Project Description contd..
Features DetailRoad Length (in KM)93Km + 7.0km Extended loop to Khejarla + 6.0km Bypasses + 1.0 Geometrical Improvement of road
107 Km
Intersection 11
Minor Bridge 2
Causeway / Culverts 49
Road Condition
Fair 38 Km
Poor 50 Km
Kuccha / damaged 5 KM
Physical FeaturesPhysical Features
Formation Width Various from 10 M to 12 MCarriageway Width KM 0/0 – 22/0 5.5 M KM 22/0 – 26/0 Kuccha/Damaged KM 26/0 – 45/0 3.75 M KM 45/0 – 53/0 5.5 M KM 53/0 – 62/0 3.75 M KM 62/0 – 63/0 7 M KM 63/0 – 93/0 5.5 MCrust Thickness WBM - 150 MM GSB - 300 MM to 230 MM B.T. - 20mm PMCCBR 10.0%
Physical Features contd..Physical Features contd..
Linear PlanLinear Plan
Linear ChartLinear Chart
PhotosPhotos
The alignment passes through village Gotan-Pundlu-Borunda-Hariadhana-Ransigaon-Murkasni-Jhaak-Khariameethapur-Bilara-Barna and Atpada. Bypass is proposed at Ransigaon.
Road Geometrics Improvement proposed near village Pundlu and at road from Pundlu to Borunda.
ALIGNMENT THROUGH TOWN/VILLAGES
ALIGNMENT THROUGH TOWN/VILLAGES
Road AlignmentRoad Alignment
N
Gotan
Borunda
Road Geometrics Improvement
Road Geometrics Improvement
PUNDLU
Existing RoadProposed Road
Existing Length = 850m
Proposed Length = 525m
Existing Length = 225m
Proposed Length = 105m
Road Geometrics Improvement
Road Geometrics Improvement
Existing RoadProposed Road
Existing Length = 950m
Proposed Length = 515m
N
RANSIGAON
KHEJARLA
BORUNDA
N
RANSIGAON
NH
112
NH 112
KHARIAMEETHAPUR
RANSIGAON
EXISTING TRAFFIC FLOWPROPOSED TRAFFIC FLOW
Proposed bypass at Ransigaon
Proposed bypass at Ransigaon
Existing RoadProposed Road
Prop. Length = 1800m
Prop. Length = 2500m
Existing Length = 2470m
Existing Length = 3130m
KHARIAMEETHAPUR
NH 11
2
NH 112
Bilara
N
N
NH
14
Bilara
SojatSH58
SH62
Traffic DetailsTraffic Details
S. No. Traffic Count Stations Location
1 KM 1 – TVC – I Just after Gotan Town area
2 KM 20 – TVC II Pundlu
3 KM 45 – TVC III Ransigaon
4 KM 45 – TVC IV Khejrla
5 KM 65 – TVC – V Bilara Town
Traffic Data CollectionTraffic Data Collection
Vehicles ADT
Equiva-lent PCU
Factor
PCU
Two Wheeler 399 0.5 200Auto Rickshaw 7 1 7Car/Jeep/ Taxi 290 1 290Buses 25 3 75Truck < 5 Tonne 20 3 60Truck > 5 Tonne 271 3 813Multi Axle Truck/ Trailer
339 4.5 1526
Tractor Excluding Agriculture Produce
52 4.5 234
Tractor with Agriculture Produce
301 4.5 1355
Cycle 84 0.5 42
Other/ Bullock Cart 16 8 128
4730
Gotan to BorundaGotan to Borunda
Vehicles ADT
Equiva-lent PCU
Factor
PCU
Two Wheeler 1520 0.5 760Auto Rickshaw 100 1 100
Car/Jeep/ Taxi 390 1 390Buses 59 3 177
Truck < 5 Tonne 160 3 480
Truck > 5 Tonne 530 3 1590Multi Axle Truck/ Trailer 211 4.5 950Tractor Excluding Agriculture Produce 280 4.5 1260Tractor with Agriculture Produce 214 4.5 963
Cycle 303 0.5 152
Other/ Bullock Cart 37 8 296
7118
Borunda to KhariameethapurBorunda to Khariameethapur
Vehicles ADT
Equiva-lent PCU
Factor
PCU
Two Wheeler 637 0.5 319Auto Rickshaw 40 1 40Car/Jeep/ Taxi 172 1 172Buses 28 3 84Truck < 5 Tonne 5 3 15Truck > 5 Tonne 43 3 129Multi Axle Truck/ Trailer 123 4.5 554Tractor Excluding Agriculture Produce 120 4.5 540Tractor with Agriculture Produce 160 4.5 720Cycle 202 0.5 101
Other/ Bullock Cart 14 8 112
2786
Khejarla to KhariameethapurKhejarla to Khariameethapur
Vehicles ADT
Equiva-lent PCU
Factor
PCU
Two Wheeler 2011 0.5 1006Auto Rickshaw 167 1 167
Car/Jeep/ Taxi 533 1 533Buses 67 3 201
Truck < 5 Tonne 184 3 552
Truck > 5 Tonne 305 3 915Multi Axle Truck/ Trailer 311 4.5 1400Tractor Excluding Agriculture Produce 118 4.5 531Tractor with Agriculture Produce 152 4.5 684
Cycle 230 0.5 115
Other/ Bullock Cart 20 8 160
6264
Bilara to SojatBilara to Sojat
As per IRC-37:2001 7.5% increase in traffic per AnnumAs per Model Concession Agreement 6% increase in traffic per
AnnumFor pavement design :CBR : 10%VDF :
BUS 1.5Truck 3.5LCV 1.5
Hence for crust design purposes as per IRC-37:2001
S.No. Section MSA Total Pavement Thickness BC DBM WMM GSB
1. CBR 10% 20 565 40 75 250 200
Traffic ProjectionsTraffic Projections
Capacity PCU/Day (Level of Services – B)
PCU/Day (Level of Services – C)
Two Lane with 1.5m earthen shoulder 15000 17500
Two Lane with 1.5m paved shoulder 18000 24000
Lane Capacity StandardsLane Capacity Standards
Laning RequirementLaning Requirement
S. No. SECTION PCU
2010PCU 2012
PCU 2017
PCU 2022
PCU 2027
PCU 2030
1 Gotan to Borunda 4730 5315 7113 9519 12738 15171
2 Borunda to Khariameethapur 7118 7998 10704 14325 19171 22832
3 Khejarla to Khariameethapur 2786 3130 4189 5604 7498 8931
4 Bilara to Sojat 6264 7038 9418 12603 16867 20089
Capacity of 2 lane with earthen shoulder exhausting in year 2023 in respect of Borunda to Khariameethapur, in year 2025 in respect Bilara to Sojat and year 2030 in respect to reach from Gotan to Borunda hence to two lane with paved Shoulder will be required.
Design Standard for 2 Lane with Paved Shoulder
S No. Design Element UnitProposed Design
Standard as per the contract
1 Design Speed Ruling KM/h 100 Minimum KM/h 802 Number of traffic lanes No. 23 Width of each lane
carriagewaym 3.5
4 Shoulder width Hard m 1.5 Earthen m 1.05 Cross fall Carriageway % 2.5 Earthen Shoulder % 4.06 Embankment Slope (H:V) 2:017 Sight Distance Desirable m 250 Absolute Minimum m 180
8 Horizontal Curves
Maximum Super Elevation % 5.0
Ruling minimum radius m 500
Absolute Minimum radius m 360
Radius beyond which super elevation is not required
m 1800
9 Transition Curve Length m 0.0215 V3/ CR where V= design speed, R= radius
of curve10 Vertical Alignment
Ruling Gradient % 2.0
Maximum Gradient % 2.5
Minimum Length of Vertical Curve
m 60
S No. Design Element UnitProposed Design
Standard as per the contract
Toll PlazaToll Plaza
Toll Station No.
Location Tollable Length
1 Km 1 (At Gotan) 28 Km
2 Km 35 (At Borunda) 35 Km
3 Km 60 (At Khariameethapur) 27 Km
4 Km 70 (At Bilara) 30 Km
5 Km 93 (At Sojat)
Location of Proposed Toll Plazas
Location of Proposed Toll Plazas
Cross Section of RoadCross Section of Road
Cross Section of RoadCross Section of Road
Cross Section of RoadCross Section of Road
Project ViabilityProject Viability
Cost Estimate Cost Estimate Particulars Amount (in lacs)A Construction of Road (I) BT Road 8039.89(II) CC Road 736.94 Total of A 8776.83B Cost for CD work 1200.00C Utility Shifting 50.00D Cost for Toll Plazas (5 nos) 100.00E Cost for Truck Lay Byes 25.00F Cost for Bus Shelters L-S 25.00 Base cost of A to F 10176.83 Land Acquisition @ 5% 508.84 Escalation for the 2nd year @ 10% (Without LA) 1017.68 TP @ 10% (Without LA) 1017.68 Contingency @ 5% (Without LA) 508.84 Quality control @ 1% (Without LA) 101.77 Guarantee Commission to State Govt. (Without LA) 101.77 Sub Total 13433.41 A&S Charges 1343.34 Application fee and front end fee 67.17 IDCP 1333.83 Total Cost of Project 16177.75
For Toll Realisation following exemption have been made
Type of Traffic
Percentage assumed excluding
daily passes
Presumed Tollable Traffic in % of Colume 2
Net Tollable Traffic
1 2 3 4
Tractors 30 90 27
Cars % Jeeps 70 85 59.5
Buses 70 95 66.5
Trucks < 5 T 70 95 66.5
Trucks > 5 T 70 97 67.9
Multi Axle Trucks
70 100 70
Toll RealisationToll Realisation
Of the net Tollable Traffic 85% Toll realisation has been assumed in the project viability calculation.
Project Cost 13433.41 Lac
Construction Period 2 Year
Toll Collection Period 18 Years 2 Months
Concession Period 20 Years 2 Months
Project Cost RepaymentProject Cost Repayment