10
Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration of the activity. Budgeted cost of the activity is earned value. When activity is complete it is assumed to earn value for project equivalent to its budgeted cost. Project progresses track is kept of actual value earned and also actual cost.

Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration

Embed Size (px)

Citation preview

Page 1: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration

Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly

over the duration of the activity. Budgeted cost of the activity is earned value. When activity is complete it is assumed to earn

value for project equivalent to its budgeted cost. Project progresses track is kept of actual value

earned and also actual cost.

Page 2: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration

It is the % of the total cost budgeted against the total cost incurred

Page 3: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration

In case Actual Expenditure incurred for completion of an activity exceeds its budgeted cost, the project does not earn any additional benefit since activity parameters are well specified. The variance indicated cost over-run

Page 4: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration
Page 5: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration
Page 6: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration
Page 7: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration
Page 8: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration
Page 9: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration

CV= ACWP – BCWP Cost Variance CPI = BCWP / ACWP Cost

Performance Index SV = BCWP – BCWS Schedule

Variance SPI = BCWP / BCWS Schedule

Performance Index TV = (Date of Review) – (Date on

which BCWP = BCWS) Time Variance ECP Index = BCTW /(ACWP + ACC)

Estimated cost of performance index

Page 10: Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration

Cost over – run ->When the cost incurred is more than the value of work done.

Cost under – run -> When the cost incurred is less than the value of work done.

CV <1 = cost over run Time over-run -> project is behind schedule Time under-run -> project is ahead of

scheduleSV <1 = time over run