Upload
independent
View
0
Download
0
Embed Size (px)
Citation preview
UNIT 303 – PROJECT MANAGEMENT
ELECTRICAL SUBSTATIONS FOR MAFRAQ HOSPITAL
PROJECT DONE BY ABC COMPANY.
LECTURER NAME: NAJMUL HUSSAIN SUBMISSION DATE: 1st April 2014
_____________________________________________________________________________
________________
STUDENT NAME :STUDENT ID: 866187
2 Unit 303 – Project Management
_____________________________________________________________________________
________________
EXECUTIVE SUMMARY
ABC Company was contracted to supply all the equipment required for Mafraq
hospital’s Electrical substations, including the Generators with all their
accessories, Switchgear panels, control panels and all the required power
and control cables.
The First section of the report provides an introduction to the project’s
stakeholders such as the contractors, consultant and end-user
The second section addresses the project definition stage including
project’s scope, customer’s specifications, ABC Company stakeholders’
activates and responsibilities
The third section represents the project’s planning stage including
project’s Schedule, Budgeting, Resources and risks.
The fourth section represents the project’s execution stage including
project’s Status reports, change management and quality management.
The fifth section represents the project’s delivery stage including
project’s Site Acceptance Test (SAT) , customer training and creation of
the As-built drawings & the Operation and Maintenance manuals.
The Sixth section addresses the lessons learnt from the project
3 Unit 303 – Project Management
_____________________________________________________________________________
________________
TABLE OF CONTENTS
1 Introduction ……………………….…………………...……………………………… 4 1.1 Introduction to Project Management……………………………………………. 4
1.2 Mafraq Hospital project overview………………………………………...………..
4
2 Project Definition…………………………… …...........................................................
5
2.1 Scope………………………………………………………………..………. 52.2 Specifications……………………………………………………..……..…. 62.3 Tasks …………………………………………………...……………..……. 72.4 Responsibilities ……………………….….…………...……………..…….. 8
3 Project Planning……………………………………….................................................
10
3.1 Schedule………………………..…………………………………..………. 103.2 Budget……………………………………………………………..……..…. 123.3 Resources ……………………………….……………...……………..……. 133.4 Risks ……………………………….……………...……………..…………. 14
4 Project Excection………………………………………................................................
16
4 Unit 303 – Project Management
_____________________________________________________________________________
________________3.1 Status reports………………………..……………….……………..………. 163.2 Change management……………………………………….……..……..…. 173.3 Quality management ……………………………….….....…………..……. 17
5 Project Delivery.………………………………………................................................
18
3.1 Customer hand-over………………..……………….……………..………. 183.2 Customer training………………………………………….……..……..…. 203.3 As-built drawings & Manuals delivery ………………………….…..…….
20
6 Lessons Learned.………………………………………................................................
21
7 Refrences.………………………………………………................................................
22
8 List of Figures
Fig (1) ABC Company Electrical Substations solution for Mafraq Project ……....….
5
Fig (2) C&E Matrix for the functional operation of ElectricalSubstations -Mafraq Project...
6
Fig (3) RACI Matrix Definition……………………………………………………………… 8Fig (4) RACI Matrix Benefits………………………………………………………………. 8Fig.(5) Mafraq hospital Electrical Substation Project RACI Matrix…………………………
9
Fig.(6) Mafraq hospital Electrical Substation project’s WBS structure……………………...
11
Fig.(7) Mafraq hospital Electrical Substation project’s Milestones………………………….
11
Fig.(8) Mafraq hospital Electrical Substation project’s Budget……………………………...
12
Fig.(9) Resource planning and budgeting for Mafraq Project………………………………..
13
Fig (10) Fish bone diagram for project’s……………………………………………………..
14
5 Unit 303 – Project Management
_____________________________________________________________________________
________________Fig (11): Mafraq hospital project’s status report…………………………………………….
16
Fig (12) Mafraq hospital Handover SAT report……………………………………………..
18
Fig. (13) Mafraq hospital Handover Punch list MOM………………………………………
19
Fig (14): Mafraq hospital training acceptance report 20
1- INTRODUCTION1.1-Introduction to Project Management
A project is temporary in that it has a defined beginning and end in time,
and therefore defined scope and resources. And a project is unique in that
it is not a routine operation, but a specific set of operations designed
to accomplish a singular goal. So a project team often includes people who
don’t usually work together – sometimes from different organizations and
across multiple geographies. (http://www.pmi.org/About-Us/About-Us-What-is-Project-
Management.aspx)
Project management life cycle has got four main stages:
Defining
Planning
Executing
Delivering and Closing
1.2-Mafraq Hospital Project overview
Mafraq Hospital is a 500-bed tertiary hospital situated on a prominent
site in Abu Dhabi within 35 kilometers from the future Abu Dhabi Central
Business District. Mafraq Hospital is part of the SEHA Health System and
is owned and operated by Abu Dhabi Health Services Company PJSC (SEHA)
6 Unit 303 – Project Management
_____________________________________________________________________________
________________which is responsible for the curative activities of the
public hospitals and clinics of the Emirate of Abu Dhabi.
(http://www.ae-7.com/mafraq.html)
Project size: XXX
Estimated construction cost: XXXX
End user: XXX
Consultant: XXX
Main contractor: XXX
Electrical substations sub-contractor: ABC Company (CME)
Project commencement year: 2011
Project completion year: 2014
2- PROJECT DEFINITION 2.1-Scope
The consultancy group has taken all these project requirements into
consideration during the design stage of the Electrical substations of the
hospital and has defined the project deliverables as below:
1- The hospital has got five Electrical Substations
2- Each substation has got a certain number of backup generators withspecific requirements
3- The subcontractor is responsible for delivering , installing ,
commissioning and testing the whole Electrical system
7 Unit 303 – Project Management
_____________________________________________________________________________
________________4- The substations are turnkey project were the subcontractor is
responsible for handing over all the electrical substations
requirements including the Generators , Electrical Switchgear ,
Control Panels and cables after being commissioned and tested in the
presence of the consultant and the end user.
ABC Company has won the bid of Mafraq hospital Electrical substations,
providing a complete package turnkey project
Fig. (1): ABC Company Electrical Substations solution for Mafraq Project
2.2-Specifications
8 Unit 303 – Project Management
_____________________________________________________________________________
________________The consultant has provided not only specifications for the project
deliverables (Diesel Generators, Switchgear panels, control panels, power
and control cables, etc…), but has also provided a detailed functional
specification that describes how the Electrical substations will operate
in various operation scenarios so as to ensure the availability of
electric power to the hospital during Utility power failure.
One of the functional specification sections was the Cause and Effect (C&E
Matrix). This method is used to narrow a long list of suspected X’s
(inputs) against Y’s (outputs).Accordingly the long list of probabilities
is reduced down to a more manageable list.
ABC Company has provided the technical proposal that complies with the
technical and detailed functional specifications provided by the
consultant, based on that technical proposal in addition to the commercial
terms and conditions CME has won the bid against the competitors.
Fig. (2): C&E Matrix for the functional operation of Electrical
Substations -Mafraq Project-
9 Unit 303 – Project Management
_____________________________________________________________________________
________________
2.3-Tasks
Engineering design
team
Prepare the Generators and Switchgear designs
based consultant's specifications and site
requirements.
Engineering ManagerReview & approve the designs and support the
Engineering team when required.
Production Team
Manufacture the Generators and Switchgears
based on the designs received from the
Engineering design team.
Inspection team
After the manufacturing process completed ,
the inspection team start testing the
Generators and Switchgears to ensure that they
comply with the International standards and
the customer's specifications
Planning team
Follow up the Generators and switchgears
manufacturing progress in the factory in order
to meet the target delivery dates. Planning
manager has to take necessary actions in case
the manufacturing process is behind schedule.Purchasing team Purchasing the products from the market that
10 Unit 303 – Project Management
_____________________________________________________________________________
________________are not manufactured by ABC Company e.g.
cables.
Finance department
Follow up the payment received from the
customer and Release the payments to market
suppliers.
Contracts & Legal
Director
Ensure that the contracts' terms and
conditions with the customer and the suppliers
are followed and take necessary actions in
case these terms are breached.
Freight forwarding
team
Freight forwarding team arranges the best
means of transport for the Generators and the
Switchgear from the factory to site. They use
the services of shipping lines, airlines and
road and rail freight operators.
Project Manager
The Project Manager then ensures that the
project is delivered on time, to budget and to
the required quality standard (within agreed
specifications). He ensures the project is
effectively resourced and manages
relationships with a wide range of groups
(including all project contributors).
Installation and
Commissioning team
Install and commission all the equipment in
the Electrical substations as per customer's
specifications. Then perform commissioning and
testing for all the equipment and then hand
over the project to the customer.
2.4-Responsibilities
11 Unit 303 – Project Management
_____________________________________________________________________________
________________The RACI matrix is a type of responsibility assignment matrix which is
used to delegate tasks, activities, milestones, or decisions to project
team members in order to clarify expectations on their level of
participation. Each team member is designated a role in the RACI hierarchy
which is an acronym that stands for Responsible, Accountable, Consulted &
Informed. (http://www.brighthubpm.com/templates-forms/53552-constructing-a-raci-matrix/)
Fig. (3):
RACI
Matrix Definition
Source:( http://www.dennis-yu.com/help-how-to-succeed-as-a-first-time-project-manager/)
Fig. (4): RACI Matrix Benefits
12 Unit 303 – Project Management
_____________________________________________________________________________
________________
Source:(http://www.slideshare.net/anandsubramaniam/raci-matrix)
Fig. (5): Mafraq hospital Electrical Substation project RACI Matrix
13 Unit 303 – Project Management
_____________________________________________________________________________
________________
3- PROJECT PLANNING3.3.1-Project Schedule
Developing a project schedule requires the combination of activities,
resources, and performance sequences that gives the project manager the
greatest chance of meeting the customer’s requirements with the least
amount of risk.
Project’s Schedule Importance
They provide a basis for the project manager to monitor and
control project activities.
They help the project manager to determine how best to allocate
resources to achieve the project’s goal.
They help the project manager to assess how time delays will
impact the project.
The project manager can figure out where excess resources are
available to allocate to other projects.
They provide a basis to help the project manager to track project
progress. (http://www.mindtools.com/pages/article/newPPM_71.htm)
3.1.1- Work Breakdown Structure (WBS)
14 Unit 303 – Project Management
_____________________________________________________________________________
________________A work breakdown structure (WBS) is a chart in which the critical work
elements of a project are called tasks, generally the WBS is shown a
graphical representation of the relationships between the stakeholders
working in the project. The graphical nature of the WBS helps the project
manager predict outcomes based on various scenarios, which can ensure that
optimum decisions are made about whether or not to adopt suggested
procedures or changes. (http://searchsoftwarequality.techtarget.com/definition/work-
breakdown-structure)
Fig. (6): Mafraq hospital Electrical Substation project’s WBS
structure
15 Unit 303 – Project Management
_____________________________________________________________________________
________________
3.1.2- Mafraq Hospital project’s Milestones
A milestone is an event during the life cycle of a project that signifies
the end date of one stage. The milestones are considered to be reached
when the required tasks are completed on the required dates.
Fig. (7): Mafraq hospital Electrical Substation project’s Milestones
2.3.
16 Unit 303 – Project Management
_____________________________________________________________________________
________________3.1-3.2-Project Budget
Preparing a project budget involves collecting data, consolidating
information and generating the results. Using organized steps generates
not only the total cost of the project but also defines how much money is
needed at which phase of the project. Inputs for human resources are labor
rates and hours committed. For equipment and supplies, the inputs are cost
per unit and number of units. (http://www.ehow.com/info_7759972_project-budget.html)
The figure below represents the budget arranged by the Project manager for
all project’s activities, the budget also includes safety risk factors
used to cover project delay, failure to meet some customer’s
requirements , etc..
Fig. (8): Mafraq hospital Electrical Substation project’s Budget
17 Unit 303 – Project Management
_____________________________________________________________________________
________________
3.3-Project Resources
The project manager has to get the estimated hours required to complete
each activity from all the teams involved in the project, these hours are
converted into cost ($) by multiplying the number of hours by the cost per
hour.
18 Unit 303 – Project Management
_____________________________________________________________________________
________________From the resources cost allocation table below , the project design stage
consumes 746 hours, these hours are multiplied by the labor cost of
50$/hours, the Project manager calculates the resources cost for the
project design stage to be $37,300
The same method is used to calculate the resources cost for all the other
stages of the project by multiplying the estimated working hours by the
corresponding labor cost/hour.
The total cost of resources in addition to safety risk factor calculated
by the project manager was $913,160; the risk calculation was performed
based on the project’s complexity and the previous experience with similar
projects
Fig. (9): Resource
planning and
budgeting for Mafraq
project
19 Unit 303 – Project Management
_____________________________________________________________________________
________________
3.4-Project Risks
3.2.
3.3.
3.4.
Project Risk Management is the process associated with identifying,
monitoring, developing appropriate responses to risks and risk triggers.
It is the responsibility of the project manager to ensure that risk
management is done and that risk triggers are being monitored.
3.4.1- Risk Register
The Risk Register is a spreadsheet that tracks the management of risks,
both threats and opportunities, through the project lifecycle. The
register not only aids the project manager in the process of risk
management, it creates a document for archiving with the project files
that can be used for Lessons Learned and a historical record.
The Risk Register is structured so that each row is a risk and the columns
track information associated with the various risk management processes.
(http://www.projectmanagementguru.com/risk.html)
20 Unit 303 – Project Management
_____________________________________________________________________________
________________Fig. (10):
Sample Project’s risks register spreadsheet
Source: (http://www.projectmanagementguru.com/risk.html)
3.4.2- Risk Identification
There are many methods to identify risks, one of the methods used to
identify risks in Mafraq hospital project was Fishbone diagram.
The Project manager started with major project’s impacts such as, "major
schedule delay" or "test failure." Then identified the possible risks
that might face the project during the implementation phase, these risks
are placed on the diagram as fish bones.
(http://www.projectmanagementguru.com/risk.html)
Fig. (10): Fish bone diagram for project’s risk
Source: (http://www.projectmanagementguru.com/risk.html)
3.4.3- Risk Response Techniques
21 Unit 303 – Project Management
_____________________________________________________________________________
________________Based upon the analysis, some risks will require a response in the project
plan, some will only require a response in the project monitoring, and
some will not require any response at all. If a risk is deemed to be high,
it needs a response. Responses to negative risks – threats are one or a
combination of these five responses:
Avoid - the project plan is changed so that it is impossible for the risk
to occur because the project is never susceptible to that type of risk.
Some risks cannot be avoided.
Mitigate - the project plan is changed so that when or if the risk occurs
it will only have minor effect because the threat has been anticipated and
provisions for addressing it are in place.
Transfer - the project plan is changed so that an outside agency assumes
responsibility for addressing a portion of the risk impact.
Accept - the project plan is not changed because the risk is so
insignificant or the risk is so improbable that no change is needed.
Contingency Plan - the project plan is not significantly changed, although
a risk trigger is established that can be used to indicate whether the
risk will occur and if so in what fashion will it impact the project. If
possible a "Plan B" is developed, or at least has been considered. If the
trigger occurs, the "Plan B" is put into effect and the project is changed
at that time. (http://www.projectmanagementguru.com/risk.html)
22 Unit 303 – Project Management
_____________________________________________________________________________
________________
4- PROJECT EXECUTION4.1-Project change management
Managing Change is vital for project’s success. Because if the project
manager allows for too many changes to be implemented without asking the
customer for cost impact. This will lead to decreasing the overall
project’s profitability.
4.
4.1.
4.2.
The purpose of the Scope Change Management Plan
1. Manage and control scope change during the Implementation Project.
2. Ensure that the project is implemented on time and within the approved
budget and scope.
3. Evaluate and prioritize all changes to the project implementation plan
at the institutional level.
23 Unit 303 – Project Management
_____________________________________________________________________________
________________4. Provide a process for implementing change required by the system.
(http://www.collegiateproject.com/articles/Preliminary%20Change%20Management%20Plan.pdf.)
4.2-Project Quality management
Mafraq project’s deliverables were subjected to quality inspection on two
stages, the first quality inspection stage was performed in the factory by
the inspection team who have inspected the generators and switchgears in
the factory and ensured that they were manufactured as per the IEC
standard as well as Mafraq Project’s specifications.
The second quality inspection stage was done at site by the commissioning
team who has ensured that the generators and switchgear are installed and
operating as per detailed specifications.
5- PROJECT DELIVERY5.
24 Unit 303 – Project Management
_____________________________________________________________________________
________________5.1-Customer handing-over
After having all the Electrical substations’ equipment installed and
commissioned by the commissioning team, the project manager arranged
handing over demonstration meeting in order to test the Electrical
substations’ operation in the presence of the end user, consultant and
ADDC’s representative (Abu Dhabi Distribution Company).
The commissioning team has prepared handing over test procedure document
that represents all the testing procedures steps, each test step is having
check boxes (PASS / FAIL), the SAT (Site Acceptance Test) report is
represented in figure (12)
Fig. (12): Mafraq hospital Handover SAT report
25 Unit 303 – Project Management
_____________________________________________________________________________
________________
During the SAT, the end user has indicated some comments; these comments
were captured in the Minutes of meeting of the SAT in a document tagged as
“Punch list”
The following action done by the project manager is working with the
responsible teams in order to get the comments resolved at the due dates
Fig. (13): Mafraq hospital Handover Punch list MOM
Having all the comments resolved, the project manager invited all the
parties again to inspect the modifications done as per the comments
mentioned in the punch list MOM; having all the comments resolved, the
project manager ensures that all parties signed the SAT report.
26 Unit 303 – Project Management
_____________________________________________________________________________
________________
5.2-Customer Training
ABC Company commissioning team has provided technical hands-on training
for the Electrical substations’ operation team for two weeks as per the
contract, the Project manager has followed the training progress to ensure
that the training was successfully done and the trainees have signed the
training acceptance report which enabled ABC Company to invoice the last
10% of the project’s value after conducting the site training as per the
contractual payment terms.
Fig. (14): Mafraq hospital training acceptance report
27 Unit 303 – Project Management
_____________________________________________________________________________
________________
5.3-Handing over the Project As-built drawings and manuals
During the commissioning stage, there were some modifications required by
the customer in the generators installation due to the site conditions,
all the As-built updates were captured during the installation and
commissioning stage by the Commissioning team and then handed over to the
project manager.
The Project managers worked with the Engineering team in order to create
the As-built drawings and operation manuals as per the current status of
the project and ensured the soft and hardcopies are handed over to the
operations team on the hospital and they’ve signed on the receipt form of
these documents.
6- LESSONS LEARNED
28 Unit 303 – Project Management
_____________________________________________________________________________
________________There are some important lessons learnt from Mafraq hospital Electrical
substations project, some lessons are:
1- All communication between stakeholders have to be documented without
depending on any verbal communication, because verbal communications
are always missed during the project execution phase.
2- The project manager has to work to all the stakeholders to set the
priority of each activity based on the customer requirements, in
order to avoid missing the project’s milestones.
3- The handover between the sales, Engineering and project management
teams have to capture all the project details in order not to lose
any important detail.
4- The customer modifications have to be managed by the Project
manager , the major modifications have to be done against OCR (Order
Change Request) , where the customer has to pay additional cost for
the modifications
29 Unit 303 – Project Management
_____________________________________________________________________________
________________
7- REFERENCES
- Project Management Institute, Inc. www.pmi.org , 20th March. 2014
<http://www.pmi.org/About-Us/About-Us-What-is-Project-Management.aspx
>
- AE7 Inc. www.ae-7.com, 20th March. 2014
<http://www.ae-7.com/mafraq.html >
-Bright Hub Inc. www.brighthubpm.com , 21st March 2014
<http://www.brighthubpm.com/templates-forms/53552-constructing-a-
raci-matrix/>
- Dennis-yu Inc. www.dennis-yu.com , 22nd March 2014
< http://www.dennis-yu.com/help-how-to-succeed-as-a-first-time-
project-manager >
-Slideshare Inc. www.slideshare.net , 22nd March. 2014
< http://www.slideshare.net/anandsubramaniam/raci-matrix>
-Mindtools Inc. www.mindtools.com , 23rd March 2014
30 Unit 303 – Project Management
_____________________________________________________________________________
________________<http://www.mindtools.com/pages/article/newPPM_71.htm>
-Ehow Inc. www.ehow.com , 28th March. 2014
< http://www.ehow.com/info_7759972_project-budget.html>
-Product & Process Innovation, Inc., www.projectmanagementguru.com , 29th March. 2014
< http://www.projectmanagementguru.com/risk.html >
-Collegiate Project Services. www.collegiateproject.com , 30th March 2014
<http://www.collegiateproject.com/articles/Preliminary%20Change%20Management%20Plan.pdf.>
31 Unit 303 – Project Management