Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
Adkins Consulting Engineering, LLP
ii
Table of Contents Table of Figures ............................................................................................................................................. ii List of Appendices ........................................................................................................................................ iii Chapter 1 - Executive Summary ....................................................................................................... 1-1 Chapter 2 - Background Information ................................................................................................ 2-1 The Project ................................................................................................................................................. 2-1 Site Review ................................................................................................................................................. 2-1 Existing Infrastructure ................................................................................................................................ 2-2 Chapter 3 - Existing Constraints ....................................................................................................... 3-1 Adjacent Properties ................................................................................................................................... 3-1 Street/Driveway Crossings ......................................................................................................................... 3-1 Storm Culverts ........................................................................................................................................... 3-2 Storm Drains .............................................................................................................................................. 3-3 Chapter 4 - The Trail System ............................................................................................................ 4-1 Chapter 5 – Canal Seepage .............................................................................................................. 5-2 Methodology .............................................................................................................................................. 5-2 Site Descriptions ........................................................................................................................................ 5-2 Results & Discussion .................................................................................................................................. 5-3 Chapter 6 - Design Criteria ............................................................................................................... 6-1 Introduction ............................................................................................................................................... 6-1 Capacity ...................................................................................................................................................... 6-1 Storm Runoff .............................................................................................................................................. 6-1 Design Flow ................................................................................................................................................ 6-2 Maximum Upstream Water Surface Elevation .......................................................................................... 6-3 Chapter 7 - Alternatives .................................................................................................................. 7-1 Purpose ...................................................................................................................................................... 7-1 Project Alternatives.................................................................................................................................... 7-1 Net Present Value ...................................................................................................................................... 7-4 Preferred Alternative ................................................................................................................................. 7-5 Chapter 8 - Construction Timeline ................................................................................................... 8-1 Constraints ................................................................................................................................................. 8-1 Schedule ..................................................................................................................................................... 8-2
Table of Figures
Figure 2-1 Vicinity Map Figure 3-1 Existing Constraints by Property Figure 3-2 Map of Street Crossings Figure 3-3 Existing Constraints at Road Crossings Figure 3-4 Drainage Crossings Map Figure 4-1 Ashland Canal Trail Easements Figure 5-1 Seepage Test Locations Figure 7-1 Alternative Schematics Figure 7-2 to 7-9 Preliminary Cost Estimates Figure 7-10 Net Present Value Figure 8-1 Preliminary Construction Schedule ‘A’ Figure 8-2 Preliminary Construction Schedule ‘B’
Adkins Consulting Engineering, LLP
iii
List of Appendices
Appendix A - Hydrology Drainage Basins Map Basin Hydrographs
Appendix B – Hydraulics Channel Report – Starlight Monitoring Station Pipeline Summary Report Pipeline Hydraulic Grade Line Computations Culvert Report – Roca Creek Culvert Report – Beach Creek Culvert Report – North Basin Culvert Report – Weller Crossing
Appendix C – Tree Report Appendix D - Site Photos Appendix E - Wetland Determination Appendix F – Works Cited
Adkins Consulting Engineering, LLP
Page 1-1
Chapter 1 - Executive Summary
The Ashland Canal Piping Project (The Project) consists of piping 10,700 feet of the Ashland
Canal within the City’s jurisdiction between Starlite Place and Terrace Street in Ashland, Oregon.
The majority of the canal within the City is located in residential areas and is often paralleled by
recreational trails making it susceptible to contamination requiring treatment for potable water use
and adversely affecting downstream drainages. The City’s 2012 Comprehensive Water Master
Plan identified the project as an opportunity to reduce losses from evaporation and infiltration,
prevent contamination from a variety of sources along the canal, and reduce overflows to Ashland
Creek.
The existing open ditch portion of the canal has concrete that is in fair condition with isolated
sections of cracking mostly caused by tree roots or failing subgrade. The piped sections consist
of several segments totaling approximately 3350 linear feet of canal. The majority of the piped
sections are corrugated metal, but there are also sections of HDPE pipe and concrete pipe. There
are 5 existing monitoring stations that the city uses along the canal; the main monitoring station
located north of Starlite Place is a concrete broad-crested weir. There are seventeen turnouts
throughout the project used for irrigation. The project terminates at the Terrace Street Pump
Station where it can be pumped to the City’s treatment plant, diverted to a TID canal/piping, or
discharged to Ashland Creek.
Because the project primarily lies in a dense residential area, there are numerous constraints to
address in the design of this project. There are 86 properties that the canal crosses or is adjacent
to within the project. Some of the constraints on these properties include trees, fences, bridges,
driveways, and vaults. Trees are by in large the most common constraint for this project with
approximately 284 potentially conflicting trees on the project.
There are seven street crossings throughout this project all of which are paved with concrete curb
and gutter on both sides. The crossings are located at Morton Street, S. Mountain Avenue, Emma
Street, Elkader Street, Leonard Street, Woodland Avenue, and Starlite Place. Morton Street is
the only crossing that has a sidewalk along it. All of the street crossings are piped; Morton Street
is a single 36” x 24” arched corrugated metal pipe (CMP), and the other six crossings are dual
pipes of various sizes.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Executive Summary
Adkins Consulting Engineering, LLP
Page 1-2
Four major drainages intersect with the canal within the project area; they are in order of
occurrence downstream to upstream: Weller Crossing, North Basin, Beach Creek, and Roca
Creek. North Basin is the only intersection that flows into the canal; the other three drainages are
piped under the canal. North Basin during a 50-year storm has a peak flow of 1.21 cfs into the
canal. There are 15 other drain pipes that flow into the canal most of which are footing or roof
drains with minimal impact on flow, except for two 12 inch culverts that flow into the canal from
Pinecrest Street.
Three ponding seepage tests were conducted on the canal by Adkins during November of 2018.
A seepage test was performed at a test site to represent a good, fair and poor condition section
of the canal. After the seepage tests were completed, Adkins visually assessed the condition of
the Canal. From the results of the tests and assessment, it is estimated that the canal is losing
23% of its flow rate to seepage and evaporation.
The primary design criteria for the project are flow capacity and maximum upstream water surface
elevation. TID specified a limit of 6 cfs as the baseline for design flow for the project which is
supported by the historical flow data as well as the hydraulic analysis completed by Adkins. Since
the upstream canal can’t support more flow, there is no need to over design the canal since there
would be no added benefit. A factor of safety was added to account for field adjustments during
construction; therefore, the recommended design flow is 7.2 cfs for the pipeline.
Since the upstream flows are restricted to a maximum of 6 cfs, there is no capacity to develop
pressure head for the pipeline. Open channel flow analysis of the canal section approaching the
Starlite Monitoring Station indicates that the maximum flow produces a flow depth of
approximately 1 ft upstream approaching Starlite Place. Based on this and the topographic survey
completed by Adkins, the maximum upstream water surface elevation is 2327.05 ft.
Four alternatives were evaluated for the design and presented to the City as viable alternatives
for the Project. Each of the alternatives met the design criteria of 7.2 cfs of flow and a maximum
upstream surface water elevation of 2327.05 ft.
Alternative 1: All 24-inch corrugated HDPE pipeline
Alternative 2: 30-inch corrugated HDPE pipeline with 24-inch corrugated HDPE
crossings; retain and rehabilitate the existing pipe from Elkader Street ending near Beach
Street.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Executive Summary
Adkins Consulting Engineering, LLP
Page 1-3
Alternative 3: Replace the canal liner with a concrete liner and urethane underliner; retain
and rehabilitate the existing piped sections.
Alternative 4: Do nothing
Of the four alternatives, The City chose Alternative 1: 24-inch corrugated HDPE pipeline as the
preferred alternative for the project. The inlet structure will be located south of the Starlite Place
crossing and include a traveling bar screen to collect and remove debris traveling down the TID
canal. A non-contact flow meter such as an ultrasonic flow meter will be installed to monitor flows.
The inlet structure will also have an overflow bypass weir to protect the upstream canal from
overtopping in the unlikely event of a blockage of the traveling bar screen. At the Terrace Street
Pump Station, the current trash rack will be removed, and the 24-inch pipeline will be connected
into the existing wet well structure.
The 24-inch corrugated HDPE pipeline is estimated to have a total project cost of $3,095,000
(2018 dollars). This cost estimate includes project soft costs such as final design, construction
administration, public outreach, contingency, as well as all construction costs. The estimated
construction cost is $2,174,000 (2018 dollars).
Construction of the Ashland Canal Piping project is expected to begin at the end of the 2019 water
year and will primarily occur during the non-irrigation season (October 1st to April 15th).
Construction is expected to last 18 calendar months and cover two irrigation seasons.
Adkins Consulting Engineering, LLP
Page 2-1
Chapter 2 - Background Information
The Project
The City of Ashland (City) receives water from Talent Irrigation District (TID) via the Ashland
Canal. The canal was constructed in the early 1900s and operates seasonally from April to
October. Much of the Ashland Canal today consists of concrete lined open ditch though, over the
years portions have been piped due to maintenance issues or development. This water is
primarily used as irrigation for users within the City; however, during drought years the canal is
used as a raw surface water source to supplement the City’s main source (Ashland Creek) for
potable municipal water. When the City is not pumping from the canal, water either siphons under
to continue to an unlined irrigation canal or is spilled at Ashland Creek.
Most of the Ashland Canal within the City is located in residential areas and often times is
paralleled by a recreational trail making the canal and water it carries susceptible to
contamination, requiring excessive treatment for potable use and adversely affecting downstream
drainages such as Ashland Creek. In 2011, the Ashland Creek E. Coli Bacteria Study, completed
by Rogue River Keeper, revealed that E. coli levels in the Ashland Canal increase substantially
as the water travels through the town. Since then, limited sampling of the canal completed by the
City during the summer of 2018 has shown that E. Coli levels increase from the time the canal
enters the city limits to the spill point at Ashland Creek.
The Ashland Canal Piping Project (The Project) consists of piping 10,700 feet of the Ashland
Canal within the City’s jurisdiction between Starlite Place and Terrace Street in Ashland, Oregon
(see Figure 2-1). The City of Ashland’s 2012 Comprehensive Water Master Plan identified the
Project as an opportunity to reduce losses from evaporation and infiltration, prevent contamination
from a variety of sources along the canal, and reduce overflows to Ashland Creek. The
Comprehensive Water Master Plan recommended The Project for short-term implementation and
estimated total costs to be $1.1 Million (September 2011 Dollars).
Site Review
The existing Ashland Canal meanders through residential areas along the westerly hillsides above
the City of Ashland, Oregon. The canal is primarily located within easements on private property
and is wholly located within the limits of the City’s Hillside Lands Overlay as defined by Chapter
18.3.10 of the City’s Land Use Ordinance. This chapter of the City’s Land Use Ordinance imposes
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Background Information
Adkins Consulting Engineering, LLP
Page 2-2
requirements for, but not limited to grading and erosion control, surface and groundwater
drainage, tree conservation, protection, and removal, and building location and design standards.
A preliminary geotechnical review was completed by The Galli Group of Grants Pass, Oregon to
address site geology, site seismicity, geologic hazards, geoscience considerations, and
geotechnical recommendations pertaining to the project.
The Project crosses three drainages identified in the City’s Comprehensive Plan as Riparian
Corridors with each classified as an Ephemeral Stream per Chapter 18.3.11 of the City’s Land
Use Ordinance. During preliminary engineering, a wetland investigation was performed by
Anderson Perry Inc., to delineate the extent of wetland areas at the crossings and identify the
existence of any isolated wetland areas within the project extents. During this investigation, it was
determined that no wetlands were present in the project area. This Determination will need to be
submitted for concurrence prior to completing final design. See Appendix E for a copy of the
Determination.
Existing Infrastructure
The existing open ditch portion of the canal has a concrete lining and bottom widths that vary from
3.5 to 7 feet. The concrete lining is estimated to range from 2 to 4 inches in thickness, and the
lining height on the canal slopes varies from 1.5 to 2.5 feet. The canal lining appears to be in fair
condition with isolated areas of cracking that often is caused by tree roots heaving or penetrating
the lining and in some cases by what appears to be failing subgrade.
The canal has a number of culverts or piped sections the longest of which is a double-barrel, arch
type smooth bore (asphalt lined) corrugated metal pipe constructed in 1977 which is
approximately 1775 feet long stretching north from Elkader Street. The existing pipe/culvert
materials include corrugated metal, high-density polyethylene, and reinforced concrete pipes. The
existing culverts/pipe sections vary in age and account for a total of 3350 linear feet of the canal.
Many of the smaller sections are crossings at public streets or driveways while the larger sections
seem to have been installed to allow or accommodate development of adjacent properties which
the pipe is crossing. Photo 1 shows the crossing at Leonard Street.
The City uses five monitoring stations along the canal to measure flow. Starlite Monitoring Station,
located approximately 500 feet north of Starlite Place, is a formed concrete broad-crested weir
(see Photo 2) and the primary measuring point for tracking water deliveries from TID. The four
other monitoring stations are Cipoletti style sharp-crested weirs that slide into vertical grooves
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Background Information
Adkins Consulting Engineering, LLP
Page 2-3
formed in the canal lining. During irrigation season the City monitors and records flows at each of
these locations.
A number of delivery turnouts are located along the open canal sections. Seventeen turnout
structures are concrete and appear to have been cast-in-place with the canal lining (see Photo
3); of those, three appear to be abandoned or have not seen use in many years. In addition to
the concrete boxes, there are a number of locations where pipes are penetrating through the
canal embankment; it is assumed these are being used to deliver irrigation water as well. There
is at least one service connection along the piped section to the west of South Mountain Ave.
The Project terminates at Terrace Street Pump station. There, water passes through a final weir
before passing the inlet trash rack and flows into a dual chambered wet-well at the pump station
(see Photo 4). One chamber of the wet well feeds the pumps and the other chamber provides
outlets for a TID irrigation line, the canal siphon, and the spill into Ashland Creek. Construction
drawings by Keller and Associates for the 2018 upgrades indicate three new 1,215 gpm vertical
turbine pumps designed to operate in tandem with one of the pumps reserved for backup.
Adkins Consulting Engineering, LLP
Page 3-1
Chapter 3 - Existing Constraints This chapter provides an overview of the existing constraints along the canal between Starlite
Place and Terrace Street. During the Preliminary Phase, the City conducted public outreach which
included meeting on site with individual residents (backyard visits) to discuss concerns while
Adkins performed a field survey and site visits to identify objects or issues that may need to be
considered in the design of the pipeline. Each adjacent property, roadway crossing, and drainage
crossing was evaluated using the City’s and Adkins’ notes and constraints were identified.
Adjacent Properties
There are 86 properties that the canal crosses or is adjacent to within the project boundaries. Of
the 86 properties 73 of them contain one or more potential conflict(s) for the proposed pipeline.
Trees are the most common conflict for the project. There are approximately 284 trees that are
potential conflicts for construction based on whether the tree was within ±10 feet of the alignment.
The 10-foot buffer includes trees with root systems in the path of the canal; the trees would likely
die as a result of construction or cause future conflict with the pipeline. Appendix C shows a report
that highlights conflicting trees larger than 6-inches in diameter that are within 10 feet of the
alignment. Photo 5 shows a tree likely to be impacted by the proposed pipeline. Other conflicts
include; roads, drain/irrigation pipes, driveways, fences, inlet vaults, signs, bridges, utilities, and
balconies. Photo 6 shows a balcony that protrudes over the canal easement at the 954 Elkader
Street property. These constraints are inventoried and listed by property according to project
stationing (downstream to upstream) in Figure 3-1.
Street/Driveway Crossings
There are seven street crossings along the canal all of which are paved with concrete curb and
gutter on both sides. There is only one sidewalk section at the Morton Street crossing. The
crossings are located at Morton Street, S. Mountain Avenue, Emma Street, Elkader Street,
Leonard Street, Woodland Drive and Starlite Place; see Figure 3-2 for a map of these crossings.
These crossings range from 25 – 35’ in width. The crossing at Morton Street is a single 36” x 24”
arched Corrugated Metal Pipe (CMP). The other six crossings are dual pipes of various sizes.
Three of these crossings in particular occur within a single 600-foot long existing piped portion of
the canal (S. Mountain Ave., Emma St., and Elkader St.). This piped portion consists of 40 year
old dual 29”x18” 14 gauge asphalt lined smooth bore CMP’s. Photo 7 shows the end of the
driveway looking across the S. Mountain Ave. crossing
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Existing Constraints
Adkins Consulting Engineering, LLP
Page 3-2
There are multiple potential utility conflicts at each crossing. Horizontal utility locations are shown
on the preliminary drawings based on field survey of utility locates; however these utilities should
be pot-holed and field surveyed prior to construction to verify depths and locations. These
potential utility conflicts as well as the physical constraints are inventoried and listed by crossing
in Figure 3-3.
Storm Culverts
There are four drainages that intersect the canal within the project limits (in order of occurrence
downstream to upstream - Weller crossing, North basin, Beach Creek, and Roca Creek). See
Figure 3-4 for a map of these drainages. The Roca, Beach, and Weller drainages cross the canal
in existing culverts. The North Basin drainage appears to pond on the uphill side of the canal and
overflow into the channel (see Photo 8); however, City records indicate a culvert may exist at this
location. Based on site visits and information from the Preliminary Geotechnical Review we
suspect that this culvert may have been concealed by a debris flow. This location is expected to
be reconstructed as a functioning culvert and so will be included as a constraint and considered
in the hydrologic analysis for the project.
Each basin was analyzed with Hydraflow–Hydragraphs software using TR-55 method for time of
concentration and SCS method to determine peak flows expected at the point of intersection with
the canal. Roca Creek is the largest basin with an area of roughly 145 acres and a peak flow of ±
13.2 cfs during a 50-year storm event. All four drainages are summarized in Table 3-1, further
discussed in Chapter 5 – Design Criteria, and additional information (maps and drainage reports)
are located in Appendix A.
Table 3-1: Drainage Basin Summary
Weller North Beach Roca
Area (acres) 5.3 29.8 32.2 149
Time to Concentration (min)
30.2 40 35 34
Peak Flow (cfs) 0.37 1.21 0.92 13.19
Discharge 24” RCP xing Canal (culvert
possibly buried) 24” CPP xing 24” CMP xing
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Existing Constraints
Adkins Consulting Engineering, LLP
Page 3-3
Storm Drains
There are more than 15 drain pipes that discharge into the canal within the project limits. Many of
these are 4-inch perforated plastic pipe roof or footing drains and contribute minimal flow to the
canal; however, two in particular are storm drain outlets and collect flow at an inlet and on the
uphill side of the canal. One of these is a 12-inch steel pipe (Photo 9) located on the 891 Roca
Street Property; This pipe is not shown in the City’s records. The other is a 12-inch CPP (Photo
10) located at 920 Pinecrest Terrace. In addition to these two storm drains, an 8-inch CPP drain
discharges into the canal on the 615 Taylor Street Property (Photo 11). Site investigations did not
reveal an apparent inlet structure for this drain so it is believe to be a roof or footing drain for the
residence.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
A B C D E F G H I J K L M N O P Q R S T
MAP LOT FEE OWNER SITE ADDRESS
START
STATION
END
STATION
SIDE FROM START TO
FINSIH TOTAL TREES
DRAIN / IRRIGATION
PIPES DRIVEWAYS FENCES
INLET
VAULTS SIGNS BRIDGES UTILITIES STAIRS
RETAINING
WALLS
PUMP
HOUSES OTHER COMMENTS
391E16BA1401HILLENGA MARK
ALANTERRACE ST 1+19.0 2+43.0
BOTH MOSTLY LEFT
(EAST)5 2 1 1 1
TREES (CEDAR: 19, 19"), PEDESTRIAN BRIDGE, FENCE
ALONG TERRACE STREET WITH GATE OVER CANAL
391E16BA1402OLSON CYNTHIA
LEE560 TERRACE ST 2+43.0 4+06.0
BOTH MOSTLY LEFT
(EAST)7 3 1 1 1 1
TREES (DECID: 19, 21" PINE:20"), SINGLE LANE VEHICLE
BRIDGE, METAL SCULPTURE, 2' TALL RETAINING WALL, 2"
DRAIN PIPE
391E16BA1400MARTIN LEONARD
C/ELIZABETH608 TERRACE ST 3+44.0 4+06.0 RIGHT (EAST) 0
OWNER WANTS NEW SERVICE CONNECTION, OWNERS
WANT PRIVACY (NO PATH), POSSIBLE IRRIGATION TO TREES
AND VEGITATION DEPENDANT ON CANAL SEEPAGE
391E16BA1400MARTIN LEONARD
C/ELIZABETH608 TERRACE ST 4+06.0 6+04.0 BOTH 2 1 1 TREE (DECID 21"), 1" DRAIN PIPE,
391E16BA1402OLSON CYNTHIA
LEE560 TERRACE ST 4+06.0 4+39.0 LEFT (EAST) 1 1 FENCE 8' OFF ALIGNMENT
391E16BA1205 ASHLAND CITY OF ASHLAND ST 6+05.0 7+43.0 BOTH 9 6 2 1TREES (DECID: 8", 9", 10", PINE: 11", 7", 15"), PED BRIDGE,
2" & 10" DRAIN PIPES
391E16BA1500 ASHLAND CITY OF 696 TERRACE ST 6+33.0 7+44.0 RIGHT (SOUTH) 0
391E16BA1300 ASHLAND CITY OF ASHLAND ST 7+42.5 10+54.0 LEFT (NORTH) 4 3 1 TREES (PINE: 18", 8" DECID: 19")
391E16BA1200BOSMA P ALLEN
AND VENESSA J400 ASHLAND ST 7+43.0 12+99.0 RIGHT (SOUTH) 36 21 1 1 13
TREES (PINE: 10, 6, 7, 20, 16, 9, 17, 18, 23, 27" DECID: 6, 6,
6, 7, 8, 8, 9, 9, 10, 16" CEDAR 7"), FENCE WITH E-GATE, 12'
WIDE DRIVEWAY, 13 RAISED GARDEN BOXES | GARDEN
IMPORTANT TO OWNER, OWNER WANTS NEW SERVICE
CONNECTION
391E16BA1100COTTLE MORGAN
CURTIS/TARA D390 ASHLAND ST 10+55.0 12+67.0 LEFT (NORTH) 4 3 1
TREES (CEDAR: 16, 16" DECID: 12"), 2" PIPE | OWNER
WOULD LIKE TO MAINTAIN PRIVACY, IRRIGATION
CONNECTION ALWAYS PLUGS, WANTS TO KEEP TRAIL
391E16BA800RATZLAFF JAMES
WILLIAMS JR621 LONG WAY 12+99.0 16+08.0 RIGHT (SOUTH) 18 11 1 1 1 2 1 1
TREES (DECID: 7, 8, 8, 8" PINE: 14, 15, 18, 18, 23, 25"
CEDAR: 6"), 20' WIDE DRIVEWAY W/ CURB, 4" PIPE FROM
PUMP HOUSE, UNDER GOUND POWER & SANITARY SEWER
LINE
391E16BA114HAMMELL TROY
M/SAMANTHA S597 HENLEY WAY 12+99.0 13+95.0 LEFT (NORTH) 0
391E16BA118JOHNSON GAIL K
TRUSTEE ET A611 LONG WAY 13+95.0 15+46.0 LEFT (NORTH) 2 1 1 TREE (PINE 29"), PIPE FROM PUMPHOUSE
391E16BA707PARK ESTATES
ASSOC INCWATERLINE RD 16+14.5 16+36.5 RIGHT (SOUTH) 2 1 1 10" CONC PIPE, SANITARY SEWER LINE
391E16BA301MORAN SHAUN J
TRUSTEE ET AL615 TAYLOR ST 16+44.0 21+59.0 RIGHT (SOUTH) 26 23 1 1 1
TREES (DECID: 9, 7" MADRN: 7, 9" PINE: 8, 8, 9, 9, 10, 11,
11, 12, 13, 14, 15, 15, 16, 17, 18, 24, 28, 30, 42"), 12' WIDE
DRIVEWAY, STONE WALKWAY STAIRS
391E16BA109WESTIGARD PETER
H TRUSTEE610 LONG WAY 17+02.0 18+21.0 LEFT (NORTH) 0
391E16BA400WRIGHT EILEEN
TRUSTEE FBO595 TAYLOR ST 18+21.0 19+24.0 LEFT (NORTH) 0
391E16BA200LARSON PAUL H ET
AL604 TAYLOR ST 19+70.0 21+59.0 LEFT (NORTH-EAST) 3 3 TREES (DECID: 12, 15" PINE: 13")
391E16BA790MORAN SHAUN J
TRUSTEE ET ALLONG WAY 21+59.0 21+66.5 RIGHT (WEST) 4 4
TREES (MADRN: 7, 10" PINE: 7, 9") 10" MADRONE AT
STATION 16+50
391E16AB2115DIENEL NICHOLAS
H TRUSTEE EWELLER LN 21+66.5 22+42.0 MOSTLY LEFT (EAST) 6 4 1 1 TREES (PINE 8, 11, 13, 13")
391E16AB2118DICHIRO ROBERT L
TRUSTEE ET635 WELLER LN 22+41.0 24+59.5 RIGHT (WEST) 8 7 1 TREES (PINE: 8, 12, 13, 18, 19, 22, 23"), SPLIT DRIVEWAY
391E16AB2116SNEIDER-BROWN J
L TRSTE FBO625 WELLER LN 22+42.0 24+15.0 LEFT (EAST) 0
391E16AB2117
WELLER LANE
HOMEOWNERS
ASSN
WELLER LN 24+15.0 25+54.0 LEFT (EAST) 2 1 1 TREES (MADRN: 7"), SPLIT DRIVEWAY
391E16AB2119HENDRICKSON
SARA K645 WELLER LN 24+59.5 26+09.0 RIGHT (WEST) 8 7 1
TREES (DECID 11" MADRN: 12" PINE: 6, 6, 10, 11, 16"), SPLIT
DRIVEWAY
391E16AB2125STUBBS MILTON
O/TRACIE E650 WELLER LN 25+54.0 27+86.0
BOTH MOSTLY LEFT
(NORTH)8 7 1
TREES ( DECID: 6, 7, 7, 7, 12" MADRN: 9, 11"), 24"
DRAINAGE PIPE (STARTS ON CATCH BASIN ON PROP#
391E16AB2124) | OWNER WOULD LIKE FENCE EXTENDED
FOR PRIVACY
391E16AB2124
WELLER LANE
HOMEOWNERS
ASSN
WELLER LN 26+09.0 27+31.0 RIGHT (SOUTH) 6 5 1TREES (MADRN: 11, 11, 12, 12, 14"), 24" DRAINAGE PIPE
GOES UNDER CANAL
391E16AB2001KEEVIL THOMAS
A/JEAN A600 FOREST ST 27+86.0 29+60.5 BOTH 10 9 1 TREES (DECID: 8" PINE: 8, 13, 17, 19, 20, 24, 24, 25")
EXISTING CONSTRAINTS BY PROPERTYASHLAND CANAL PIPING
1/4 Figure 3-1
1
2
3
A B C D E F G H I J K L M N O P Q R S T
MAP LOT FEE OWNER SITE ADDRESS
START
STATION
END
STATION
SIDE FROM START TO
FINSIH TOTAL TREES
DRAIN / IRRIGATION
PIPES DRIVEWAYS FENCES
INLET
VAULTS SIGNS BRIDGES UTILITIES STAIRS
RETAINING
WALLS
PUMP
HOUSES OTHER COMMENTS
EXISTING CONSTRAINTS BY PROPERTYASHLAND CANAL PIPING
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
391E16AB1900WOLFE PATRICIA J
TRUSTEE ET650 FOREST ST 29+60.5 31+46.0 BOTH 5 5 TREES (DECID: 12, 13 PINE: 26, 26, 43")
391E16AB2209 HUMMELL BEN JR 721 MORTON ST 31+46.0 32+59.0BOTH MOSTLY RIGHT
(SOUTH)15 11 3 1
TREES (MADRN: 21" PINE: 8, 8, 8, 8, 9, 11, 12, 12, 13"), 3 - 4"
FOUNDATION DRAIN PIPES, GAS LINE
391E16AB2220INGALLS PETER
D/JAN ELLEN L671 MORTON ST 31+58.0 33+46.0 LEFT (NORTH) 1 1 TREE (PINE: 13")
391E16AB2208LOVE TIMOTHY
P/BELL LAUREL707 MORTON ST 32+59.0 34+10.0
BOTH, ENDS @
MORTON STREET11 3 2 2 1 2 1
TREES (DECID: 12", PINE 10", PINE (BLUE SPRUCE): 12"),
ASPALT AND CONCRETE DRIVEWAY, WOODEN STEPS, 2 - 4"
FOUNDATION DRAIN PIPES, UNDER GORUND POWER
391E16AB2212PARK ESTATES
ASSOC INCMORTON ST 34+69.0 37+14.0 BOTH 8 6 1 1
TREES (DECID: 10" MADRN: 6" PINE: 10, 10, 13, 29"),
UNDER GOUND POWER CROSSING (FOLLOWS ALONG
CANAL), SEWER PARALLELS CANAL (EAST), LARGE BOULDER
391E16AB2213COHEN ANDREA B
TRUSTEE ET A748 LISA LN 35+00.0 37+14.0 LEFT (EAST) 1 1
TREE (PINE: 28") | OWNER DOESN’T WANT ANYTHING ON
HIS PROPERTY, CONCERNED ABOUT PROP VALUE,
CONCERNED ABOUT TREES RELYING ON SEEPEAGE
391E16AC447
FERNANDES
JOAO/BERGAN-
FERNA
762 LISA LN 37+14.0 37+85.0 BOTH 1 1
391E16AC408MOGEL RONALD
TRUSTEE ET AL774 LISA LN 37+85.0 38+57.0 BOTH 9 4 1 3 1
TREES (DECID: 7" MADRN: 7" PINE 28, 29") SEWER, UNDER
GROUND COMM AND POWER, POWER TRANSFORMER |
OWNER WANTS NEW SERVICE CONNECTION
391E16AC406 BUCCINA JUNE 784 LISA LN 38+57.0 39+30.0 BOTH 4 4 TREES (DECID: 12, PINE: 10, 16, 17")
391E16AC405SINGER REUVEN
D/BALDOVINO B800 LISA LN 39+30.0 41+87.0 BOTH 11 11 TREES (MADRN: 9, 12" PINE: 7, 9, 9, 12, 1, 20, 28, 29, 40")
391E16AC404SHERIDAN JAMES
D825 WATERLINE RD 39+73.0 42+00.0 RIGHT (WEST) 4 4 TREES (MADRN: 9, 22, 30" PINE: 18")
391E16AC409PARK ESTATES
ASSOC INCLIBERTY ST 41+87.0 42+42.0 BOTH 0
391E16AC300D & S VENTURES
LLCLIBERTY ST 42+42.0 52+82.5 BOTH 35 31 3 1
TREES (DECID 9, 10, 11, 14, 14, 15, 19" FIR: 6" MADRN: 8,
10, 10, 12, 14, 20, 25" PINE: 6, 7, 8, 9, 9, 11, 12, 13, 15, 15,
16, 17, 22, 24, 25, 26"), 24" PIPE UNDER CURRENT CANAL
PIPING, 2 SDL COMING OFF HILLSIDE, TRAIL CROSSING, LOTS
OF BRUSH
391E16AC200 CITY OF ASHLAND LIBERTY ST 42+42.0 47+50.0 LEFT (NORTH) 4 4
391E16AD5200HARKER JEFFREY
PAUL911 BEACH ST 52+82.5 55+79.0 BOTH 14 9 1 1 1 1 1
TREES (MADRN: 9" PINE: 17, 18, 20, 24, 24, 26, 31. 32"),
FENCE WITH GATE, WOODEN STAIRCASE, PAVED
DRIVEWAY, 4" DRAIN CrOSSES PIPE, SPRINKLER SYSTEM,
LOTS OF BRUSH
391E16AD5201DIMITRE THOMAS
N TRUSTEE901 BEACH ST 54+12.0 55+52.0 LEFT (NORTH) 0
391E16AD5001ARNDT DENIS
LEROY TRUSTEE E930 BEACH ST 55+94.0 56+78.5 BOTH 2 1 1 TREE (PINE: 40"), CONCRETE DRIVEWAY
391E16AD4700 WATT RANDY/EVIE 900 BEACH ST 56+78.5 58+87.0 BOTH 3 3 TREES ( PINE 9, 11, 12, 33")
391E16AD4300 WATT RANDY/EVIE 820 BEACH ST 58+87.0 5+30.0 BOTH 6 6 TREES (DECID 8, 9, 16" PINE: 6, 8, 38")
391E16AD4200 MULLEN MIRIN 1020 WILDWOOD WAY 59+30.0 59+91.0 BOTH 5 2 2 1TREES (10, 13"), OLD WOODEN RETAINING WALL, 2 - 6"
ROOF DRAINS CROSS OVER PIPING
391E16AD4100 KENDALL KAY 1025 WILDWOOD WAY 59+91.0 61+18.0 BOTH 7 5 1 1TREES (DECID: 10, 15, 15, 16" PINE: 31"), 4" FOOTING
DRAIN, IRRIGATION CONNECION AT VAULT STA: 60+80
391E16AD4000
KNECHT
ALEXANDER/KONN
Y
890 BEACH ST 61+18.0 61+50.5 BOTH 1 1
391E16AD3100 GURWELL JULIA K 1047 WILDWOOD WAY 61+50.5 62+71.0 RIGHT (SOUTH) 4 2 1 1TREES (DECID: 9" PINE:24"), IRRIGATION CONNECTION
WITH PUMP
391E16AD3406
ROBERTS
ANTOINETTE M IRA
ET
771 MOUNTAIN AVE 61+55.0 62+47.0 LEFT (NORTH) 1 1 IRRIGATION CONNECTION WITH SPIGOT
391E16AD3200LITTLE JOHN D
TRUSTEE ET AL807 S MOUNTAIN AVE 62+47.0 64+84.0 LEFT (NORTH) 1 1 6 FOOT WOODEN FENCE
391E16AD2900HERING WILLIAM
TRUSTEE ET A1071 WILDWOOD WAY 62+71.0 64+84.5
LEFT (SOUTH), ENDS @
S. MOUNTAIN AVE13 12 1
TREES (DECID: 8, 9, 13, 13, 15" PINE: 10, 12, 18, 23, 24, 24"),
DECORATIVE ROCK RETAINING WALL
2/4 Figure 3-1
1
2
3
A B C D E F G H I J K L M N O P Q R S T
MAP LOT FEE OWNER SITE ADDRESS
START
STATION
END
STATION
SIDE FROM START TO
FINSIH TOTAL TREES
DRAIN / IRRIGATION
PIPES DRIVEWAYS FENCES
INLET
VAULTS SIGNS BRIDGES UTILITIES STAIRS
RETAINING
WALLS
PUMP
HOUSES OTHER COMMENTS
EXISTING CONSTRAINTS BY PROPERTYASHLAND CANAL PIPING
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
391E16AD6800BAILEY LISA G
TRUSTEE ET AL822 S MOUNTAIN AVE 65+43.0 66+30.5
BOTH, BEGINS @ S.
MOUNTAIN7 5 1 1
TREES (DECID: 7, 9" PINE: 9, 12, 21"), PAVED DRIVEWAY,
POWER TRANSFORMER
391E16AD7200QUENELL MARY
VIRGINIA840 S MOUNTAIN AVE 66+30.5 67+05.0 BOTH 4 2 1 1 TREES (PINE: 8, 36"), PAVED DRIVEWAY, CAR PORT
391E16AD7100
KOOPMAN
RONALD P
TRUSTEE ET
1133 EMMA ST 67+05.0 68+12.0BOTH, ENDS @ EMMA
ST7 5 1 1
TREES (OAK: 6, 9" PINE: 14, 18, 30"), DECORATIVE PATH
WITH STAIRCASE @ EMMA STREET
391E16AD300STIERS ROBERT
T/ALETA M1120 EMMA ST 68+55.0 69+69.0 RIGHT (WEST) 0
391E16AD400AMES CAROLYN
TRUSTEE1130 EMMA ST 68+84.5 69+56.0
BOTH, BEGNS@EMMA
ENDS@ELKATR6 4 1 1
TREES (CEDAR: 6, 6, 6, 6"), FENCE, STAIRS, BRUSH | OWNER
CONCERNED ABOUT LOOSING PRIVACY FROM BUSH
REMOVAL
391E15BC2306BENEDETTI LAURA
TRUSTEE FBO938 ELKADER ST 70+35.0 71+17.0 LEFT (EAST) 2 1 1
391E15BC2307KOERBER
BENJAMIN JAMES954 ELKADER ST 70+64.0 73+40.0
BOTH, BEGINS @
ELKATER11 4 4 1 1 1
TREES (OKA: 7" PINE: 18, 20, 23"), OLD PED BRIDGE, 3 - 4"
ROOF DRAINS, IRRIGATION LINE, COMM LINES,
HOUSE/DECK CLOSE TO CANAL | OWNER CONCEREND
ABOUT LARGE TREES NEXT TO CANAL, OWNER HAS
ENCROACHMENT PERMIT FOR DECK OVER CANAL
391E15BC2308 COX THOMAS 950 ELKADER ST 70+65.0 73+40.0 LEFT (EAST) 1 1 3" SDL
391E15BC2304WELCH WILLIAM L
TRUSTEE ET970 ELKADER ST 73+40.0 77+91.0
BOTH, GAP 75+71 TO
76+94 (BLEIWEISS
PROP)
4 1 1 2 TREE (OAK: 24")
391E15301BLEIWEISS PETER
RICHARD TRU1131 HIGHWOOD DR 75+71.0 76+94.0 BOTH 2 1 1 24" CMP UNDER CANAL
391E15BC2403DE ROUCHEY
LOUIS/AMANDA891 ROCA ST 77+91.0 82+37.0 BOTH 7 6 1 TREES (FIR: 6, 9, 10, 11, 13" MADRN:10"), 12" PIPE
391E15BC2400KINARD JOHN G
TRUSTEE ET AL875 ROCA ST 82+37.0 83+00.0 BOTH 1 1
391E15BC2500HESTER FREDERICK
C/CARLENE820 PINECREST TR 83+00.0 84+22.0 BOTH 4 1 1 1 1
TREE (OAK: 9"), SMALL PED BRIDGE, FENCE WITH GATE,
ROCK RETAINING WALL ABOVE CANAL
391E15BC2502ELDRIDGE NATHAN
P/LESLIE M840 PINECREST TR 84+22.0 84+95.0 BOTH 4 1 1 1 1
TREE (FIR: 10"), PED. BRIDGE WITH STAIRS GOING UP TO
THE HOUSE | OWNERS CONCERNED ABOUT LOOSING
ACCESS TO BOTTOM PORTION OF PROPERTY DURING
CONSTRUCTION
391E15BC3101NELSON STEVEN
J/MARY P1286 WOODLAND DR 84+95.0 85+70.5 BOTH 6 2 1 2 1
TREES (FIR: 10" OAK:6"), PEDESTRIAN BRIDGE, IRRIGATION
VAULT DOWN HILL
391E15BC1000SANDLER ALLAN F
TRUSTEE FBO1260 PROSPECT ST 85+70.5 86+18.0 BOTH 4 1 1 1 1
TREES (MADRN: 6"), PED. BRIDGE, INLET VAULT WITH
STAIRS
391E15BC1006
GOLDMAN
BRANDON
L/NANCY G
827 LEONARD ST 86+18.0 87+52.0RIGHT (SOUTH), ENDS
@ LEONARD ST6 4 2 TREES (FIR: 8, 28" OAK: 6" PINE: 24"), 2 - 4" DRAINS
391E15BC1004MCCORMACK
HOLLY825 LEONARD ST 86+18.0 87+52.0
LEFT (NORTH), ENDS 2
LEONARD ST3 2 1 TREES (FIR: 10, 10"), 4" DRAIN PIPE
391E15BC501WHIPPLE GALEN
CHARTER1313 WOODLAND DR 88+02.0 89+07.0
BOTH,
BEGNS@LEONRD
ENDS@WOODLND
5 3 1 1TREES (FIR: 14" PINE: 10, 12"), PEDESTRIAN BRIDGE OVER
CANAL, IRRIGATION VAULT
391E15BC3001
CONNOR
TIMOTHY/DRON
KATHERI
1314 WOODLAND DR 89+57.0 90+88.0BOTH, BEGINS @
WOODLAND DRIVE6 2 1 2 1
TREES (FIR: 10" MADRN: 6"), GATE FOR TRAIL EACH END OF
PROPERTY, INLET VAULT WITH TWO HEADGATES, 2" STEEL
PIPE FROM BOTTOM OF CANAL
391E15BC2900MARTIN PATRICK
M1300 WOODLAND DR 89+57.0 90+70.0 RIGHT (WEST) 1 1
391E15BC2800 DOWNS JENNIFER 880 PINECREST TR 90+88.0 91+95.0 RIGHT (WEST) 1 1 4" DRAIN PIPE
391E15BC3008MARTIN NEIL M
TRUSTEE ET AL925 PENNY DR 90+88.0 91+55.0 LEFT (EAST) 3 1 1 1
SMALL PEDESTRIAN BRIDGE WITH GATE & SMALL FENCE
SECTION, NO TRESPASSING SIGN
391E15BC3009BURNAM
MICHAEL/JESSICA945 PENNY DR 91+55.0 92+76.0 LEFT (EAST) 4 3 1 TREES (OAK 10, 10" PINE: 12")
391E15BC3004 PERINA HELEN A 900 PINECREST TR 91+96.0 93+19.5BOTH, MOSTLY RIGHT
(WEST)3 2 1 TREES (FIR: 10, 14"), 4" DRAIN PIPE
391E15BC3010 BONNEY JULIA A 955 PENNY DR 92+75.5 95+69.0 BOTH 6 4 2TREES (FIR:8" OAK: 6, 8, 16"), INLET VAULTS ON NEIGHBORS
PROP (900 & 920 PINCREST TR)
3/4 Figure 3-1
1
2
3
A B C D E F G H I J K L M N O P Q R S T
MAP LOT FEE OWNER SITE ADDRESS
START
STATION
END
STATION
SIDE FROM START TO
FINSIH TOTAL TREES
DRAIN / IRRIGATION
PIPES DRIVEWAYS FENCES
INLET
VAULTS SIGNS BRIDGES UTILITIES STAIRS
RETAINING
WALLS
PUMP
HOUSES OTHER COMMENTS
EXISTING CONSTRAINTS BY PROPERTYASHLAND CANAL PIPING
83
84
85
86
87
88
89
90
91
391E15BC3003
NORTH
JAMIE/BROWN
ERIK
920 PINECREST TR 93+19.5 94+28.0BOTH, MOSTLY RIGHT
(WEST)2 1 1
TREE (MADRN: 8"), 12" CPP FLOWS INTO CANAL (WAS ON
955 PENNY DRIVE PROP FROM OLD RECORDS BUT NEW PLA
LATHE SHOWS IT ON 920 PINCREST TR)
391E15BC3011WHITE ELIZABETH
A BOWLUS TRPENNY DR 95+69.0 97+52.0 LEFT (NORTH) 2 1 1 TREE (MADRN: 8")
391E15BC3012WHITE ELIZABETH
A BOWLUS TR980 PENNY DR 97+52.0 97+82.0 LEFT (NORTH) 1 1 TREE (FIR: 8")
391E15BD7401BOUTACOFF ALEXIS
JR/LINDAPINECREST TR 97+98.0 102+15.5 LEFT (NORTH) 0
391E15BD7403MATTSON PETER
W TRUSTEE ET940 PINECREST TR 102+15.5 104+26.0 LEFT (NORTH) 0
391E15BD7402
TOKAREFF
RAYMOND L AND
MARS
944 PINECREST TR 104+26.0 105+41.0 LEFT (NORTH) 1 1 12' WIDE PAVED DRIVEWAY
391E15BD7400BIBEE LEONARD
DALE/PATRICIA950 PINECREST TR 105+41.0 106+67.0 LEFT (EAST) 2 1 1 12' WIDE PAVED DRIVEWAY
391E15BD7412VANDERLIND
LARRY R TRUSTEE960 PINECREST TR 106+67.0 107+23.5 LEFT (EAST) 0
TOTALS: 453 297 37 17 15 14 14 12 11 8 4 2 22
4/4 Figure 3-1
!H
!H
!H
!H
!H!H
!H7
65
4
1
23
Legend!H Street Crossing
Street Name1 - Morton Street2 - S. Mountain Avenue3 - Emma Street4 - Elkader Street5 - Leonard Street6 - Woodland Drive7 - Starlite Place
Proposed Pipe24" Corrugated Dual Wall HDPE Pipe
0 1,000500 Feet
NAME
START
STATION
END
STATION TOTAL
CANAL
PIPES
CURB /
GUTTER SIDEWALK
WATER
LINE
SEWER
LINE
STORM
LINES
OVERHEAD
POWER
UNDERGROUND
POWER
COMM
LINES
GAS
LINES
TRASH
RACK OTHER COMMENTS
MORTON ST 34+11.0 34+69.5 12 1 2 1 1 1 2 2 2
SINGLE 36X24" ARCHED CMP, SDMH IN ROADWAY WHERE
PIPE BENDS (STA: 34+38), APPROX 25' PAVED ACROSS,
RETAINING WALL FOR DRIVEWAY ON 707 MORTON ST.
PIPING CONTINES WEST OF CROSSING
S. MOUNTAIN AVE 64+84.0 65+43.5 7 2 2 1 1 1
DUAL 27X20" CMP PIPES, APPROX 31' PAVED ACROSS,
ACCESS VAULT AT STA: 64+78 JUST INSIDE THE 1071
WILLWOOD WAY PROP, MANHOLE AT STA: 65+25 LOCATED
IN DRIVEWAY. PIPING CONTINUES IN BOTH DIRECTIONS
EMMA STREET 68+12.0 68+84.5 11 2 2 2 1 1 3
DUAL 27X20" CMP PIPES, APPROX 33' PAVED ACROSS,
MAILBOX, STAIRCASE, ROCKWALL, PIPING CONTINUES BOTH
DIRECTIONS
ELKADER STREET 69+56.0 70+64.5 11 2 2 2 1 1 2 1
DUAL 27X20" CMP PIPES, APPROX 25' PAVED ACROSS,
WATER METERS CLOSE TO PIPE, PIPING CONTINUES NORTH
WEST, OVERHEAD POWER EAST SIDE AND CROSSING STREET
LEONARD STREET 87+52.0 88+02.0 9 2 2 1 1 2 1DUAL 36X24" CMP, APPROX 32' PAVED ACROSS, OVERHEAD
POWER BOTH SIDES OF STREET
WOODLAND DRIVE 89+07.0 89+57.0 8 2 2 1 1 1 1DUAL 36X24" CMP, APPROX 35' PAVED ACROSS, OVERHEAD
POWER TO WEST
STARLITE PLACE 107+15.0 107+67.0 13 2 2 1 1 1 1 1 1 3
15" & 18" PVC PIPES, APRROX 30' PAVED ACROSS, 18"
STORM PIPE CROSSING, MAIL BOXES, TELEPHONE PEDESTAL,
WATER METER, STORM GRATE, CURB INLET
TOTALS: 71 13 14 1 9 6 4 5 4 3 1 1 10
STREET CROSSING INVENTORIES
ASHLAND CANAL PIPING
1/1 Figure 3-3
WellerBasin
BeachBasin
NorthBasin
RocaBasin
Sources: Esri, HERE, Garmin, Intermap, increment P Corp., GEBCO, USGS, FAO, NPS, NRCAN, GeoBase, IGN, Kadaster NL, Ordnance Survey, Esri Japan,METI, Esri China (Hong Kong), swisstopo, © OpenStreetMap contributors, and the GIS User Community
H:\35
22-01
Ashla
nd C
anal
Piping
\GIS\
Drain
age C
rossin
gs.m
xd
LegendXINGSAshland Canal
Ashland Canal (Pipe)
0 0.1 0.2
Miles
Adkins Consulting Engineering, LLP
Page 4-1
Chapter 4 - The Trail System There is roughly 5420 feet of intermittently accessible trail between Terrace Street and Starlite
Place located primarily within easements on private land (see Figure 4-1). Access to the trail is
intermittent at locations due to no trespassing signs and gates. There are seven gates located
along the trail system, not all of these gates are used to block public access. The path is mostly
composed of gravel, decomposed granite and/or soil sections of varying conditions with a 275-
foot paved section between Starlite Place and Penny Drive. There are 14 bridges over the canal
used for private and/or public access. One of the bridges is used as a driveway to the residence
at 560 Terrace Street. The other 13 bridges are pedestrian bridges of various sizes and used for
trail access or property owner access across the canal. Photo 12 shows a section of trail located
along the 650 Weller Lane Property.
Walkers, joggers, and dog-walkers regularly travel the portions of the trail that are granted public
access. The presence of animal feces (mostly dog) was regularly noted during the Ashland Creek
Bacteria Study and is considered a probable factor contributing to the E. Coli levels that are
measured in the canal. Piping the canal within the City limits was recommended in the Ashland
Creek bacteria study because it would likely lead to a reduction in additional bacterial
contamination from a variety of sources.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Canal Seepage
Adkins Consulting Engineering, LLP
Page 5-2
Chapter 5 – Canal Seepage
Methodology
Three ponding tests were conducted at the Ashland Canal between Starlite Place and Elkader
Street in November of 2018. A ponding test measures how fast water seeps from the canal into
the ground, since the Ashland Canal is lined with concrete the seepage was attributed to the
cracks and holes in the liner. Each test was conducted at a preselected 100 feet long section of
canal. The locations were selected based on the condition of the canal liner. Each location was
selected to represent a good, fair, and poor condition section of the canal.
At each test location, dams were constructed out of butyl flexible rope gasket, thick plastic
sheeting and sandbags (see Photos 13 and 14). Staff gauges were installed at each end of the
ponded area to measure water levels (see Photo 15). Rain gauges were also installed to account
for precipitation even though no rainfall occurred during any of the three ponding tests.
Evaporative losses were considered insignificant for these tests due to the time of year,
temperatures and amount of shade at the sites. After the dams were built, water was fed into the
ponding site via a 4,000-gallon water truck. The ponding sites were filled until the water met the
existing high water mark on the canal lining. Each test was conducted for a full 48 hours to account
for the ground saturation period. The water levels were measured every hour during the day. As
the water level dropped, water was added to the ponding site to keep the pressure head
consistent. The testing method was derived from Texas A&M’s AgriLife Extension article on
‘Measuring Seepage Losses from Canals Using the Ponding Test Method” (Fipps, 2009).
Site Descriptions
Ponding Site No. 1 was located near the address of 944 Pinecrest Street (see Photo 16). This
ponding site was chosen as the good condition site, as it had very little sign of cracking. Site No.
1 was possibly one of the best overall sections of the canal. The test was conduction from
November 5th at 10:30 AM to November 7th at 10:30 AM. During the 48-hour test, temperatures
ranged from 30°F to 58°F.
Ponding Site No. 2 was located near the intersection of Woodland Drive and Leonard Street in
the canal south of Woodland Drive (see Photo 17). This ponding site was chosen as the fair
condition test site. The test location had moderate hardened cracks most likely due to long-term
expansion and shrinkage of volume from drying and wetting cycles (see Photo 18). Site No. 2
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Canal Seepage
Adkins Consulting Engineering, LLP
Page 5-3
was an accurate representation of the fair condition sections of the canal. The test was conducted
from November 7th at 1:00 PM to November 9th at 1:00 PM. During the 48-hour test,
temperatures ranged from 27°F to 64°F.
Ponding Site No. 3 was Located east of Elkader Street (see Photo 19). This ponding site was
chosen to represent the poor condition canal lining. The canal lining was severely cracked in this
location; there were lateral cracks along the wall the entire width of the test section and the lining
was pushed up and broken exposing the soil beneath in two places from tree roots (see Photo
20). Although Site No. 3 was in poor condition, it was not the worst condition site in the canal.
Due to accessibility, it was the best representation available for the test. The test was conducted
from November 13th at 10:30 AM to November 15th at 10:30 AM. During the 48-hour test,
temperatures ranged from 29°F to 59°F.
The test locations were chosen to best represent the range of conditions in the canal while still
being accessible with the equipment required for the test. See Figure 5-1 for a map if the test
locations. The Ashland Canal is not uniform, so not only were the sites different in condition but
they also varied in cross-section. Generally, the canal is trapezoidal in shape with varying
dimensional parameters. To estimate the seepage loss at each test site, the parameters
measured onsite shown in table 5-1 were used.
Table 5-1: Seepage Test Site Parameters
Site Top Width
(feet) Bottom Width
(feet) Depth (feet)
Length (feet)
Wetted Perimeter (feet)
Side Slope Volume
(ft3)
1 8.5 5.0 1.09 100 9.12 1.61 : 1 736
2 5.0 3.5 0.74 100 5.60 1.02 : 1 312
3 8.3 6.8 0.94 100 9.24 0.80 : 1 710
Results & Discussion
The results from the tests show that there is a noticeable amount of water lost through seepage
in the Ashland Canal. The seepage losses vary greatly by the condition of the canal liner. The
first test site had the least seepage of all three sites, as expected. The measured seepage losses
at site 1 ranged from 0.07 to 0.27 cfs/mile. The measured seepage was higher than reported due
to leaks in the dam. The losses in the dam were visually estimated and subtracted from the
measured losses. The following two Site’s (No. 2 and No. 3) dams sealed up much better resulting
in nearly zero losses through the dam. The estimated seepage losses range from 0.22 to 0.54
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Canal Seepage
Adkins Consulting Engineering, LLP
Page 5-4
cfs/mile at ponding site two. At ponding Site No. 3 the estimated seepage losses range from 0.75
to 1.15 cfs/mile. The first 24-hours of the test were used as a saturation period; the seepage rates
were still recorded but not used to estimate the average seepage rates. Table 5-2 breaks down
the results after the dam losses were accounted for on test 1.
Table 5-2: Ponding Seepage Loss Results
Site Condition Test Average
Flow (cfs)
Estimated Unit Seepage Losses
(cfs/mile) (ac-ft/mile/day)
1 Good 0.0014 0.07 0.15
2 Fair 0.0061 0.32 0.63
3 Poor 0.0183 0.97 1.92
Although test Site No. 3 was the most degraded test site and showed the highest seepage rate,
test Site No. 2 was the only site that seeped nearly completely dry overnight resulting in dry
sections in the canal. The canal did not go completely dry because the canal bottom is not a
consistent grade and has some low spots resulting in ponding. There are a number of factors that
play a part in this. First, the canal section at Site No. 2 had a considerably smaller volume than
the first two sites, less than half. Secondly, Site No. 2 had cracking on the bottom of the canal
where at Site No. 3 most of the cracks were three to five-tenths of a foot above the canal bottom.
Also, the soil underneath the canal may vary at each given location affecting the seepage rates.
The results from the tests show the seepage rates at a full flow condition. If the canal is flowing
less than full flow, the seepage will vary, and the correlation is may not be linear. See Table 5-3
for a breakdown of how much loss the canal is experiencing at full flow conditions.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Canal Seepage
Adkins Consulting Engineering, LLP
Page 5-5
Table 5-3: Canal Water Loss
Water Loss Type Applicable Distance
(feet)
Average Flow (cfs)
Estimated Losses (ac-ft) for the Irrigation Season
Good Condition Canal Seepage 1,975 0.03 9.36
Fair Condition Canal Seepage 3,713 0.23 75.44
Poor Condition Canal Seepage 1,662 0.30 101.94
Evaporation 7,350 0.01 3.39
Total 0.57 190.13
The total flow rate loss during an irrigation season assuming an 840 acre-feet delivery year (2.5
cfs average flow) is estimated to be as high as 23% based on Adkins findings. The evaporation
was calculated for all of the canal sections (7,350 feet) using the Western Regional Climate
Centers evaporation station records (Western Regional Climate Center, 2018). Assuming a 169
day irrigation season, the canal from Starlite Place to the Terrace Street pump station loses 190
acre-feet of water annually through seepage and evaporation. This estimation is based on the
evaluation that 27% of the canal qualifies as good condition, 50% qualifies as fair, and 23%
qualifies as poor condition. Adkins visually assessed the canal condition on December 11, 2018.
Losses estimated over the canal are based on limited measurements made during the above
described three tests to represent the entire canal.
Another method used to measure the seepage is the inflow-outflow method. The inflow-outflow
method involves measuring the flow into and out of a defined section of the canal, the difference
representing the losses. With the inflow-outflow method, all losses are accounted for, the other
losses (turnouts, evaporation and tree uptake) must be corrected in order to get the seepage loss.
One benefit of this method is that it allows you to measure all of the losses in the canal. The
inflow-outflow method was not an option for the tests conducted by Adkins, due to the tests being
conducted outside of the irrigation season.
Another factor to consider from the canal seepage is the amount of water that trees absorb. A
noticeable percentage of the poor conditions sections of the canal is due to tree roots breaking
up the canal lining. Site 3 was in poor condition mostly from tree root destruction. The irrigation
season aligns with hot and dry temperatures which is when the trees are transporting the most
water. Some of the trees along the canal are particularly large most likely due to the availability
of water. The seepage tests took place during November which is a much cooler and damper
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Canal Seepage
Adkins Consulting Engineering, LLP
Page 5-6
month than the irrigation season (April 15th to October 1st); therefore the analysis assumes water
absorbed by trees was negligible.
With recent years of drought, the need to conserve water is more apparent than ever. The old
water conveyance system that is currently in use loses substantial water from seepage. The 190
acre-feet of lost water, at the TID billing rate of $51.17 per acre-foot equates to $9,722 of
purchased water lost each irrigation season. If that water was billed out at the City of Ashland’s
2018 billing rate for TID non-potable water ($0.0024 / ft3), it is estimated to gross $20,000. Now,
that does not mean that the city would see an additional revenue of $20,000 if the seepage was
eliminated, but it is one way to represent its value. The water has value somewhere; whether it’s
served as irrigation water, treated for drinking water or sent down the line. The alternatives
presented in Chapter 7 will save significant quantities of water compared to the current canal
which will only deteriorate further in the future. This section does not address any losses attributed
to the aged piped sections of the canal.
!H
!H
!H1
2
3
Legend!H Ponding Seepage Test
Canal Test Location1 - 944 Pinecrest Street2 - Woodland & Leonard3 - Elkader Street
Canal PathAshland Canal
0 650325 Feet
Adkins Consulting Engineering, LLP
Page 6-1
Chapter 6 - Design Criteria
Introduction
This chapter defines the design criteria for the Project and describes the information and
methodologies used to determine these criteria. The primary design criteria identified for the
proposed pipeline are; design flow and maximum upstream water surface elevation. These criteria
were determined using information provided by the City of Ashland Public Works Department and
Talent Irrigation District (TID), as well as a topographic survey and hydraulic analysis performed
by Adkins. The design flow was established to be 7.2 cfs, and the maximum upstream water
surface elevation was established at 2327.05 ft. Other design criteria must be determined or
checked for items such as storm crossings or City storm drains that may receive increased flows
due to the canal being piped.
Capacity
Adkins performed a hydraulic analysis of the existing canal with Hydraflow-Express software
using manning’s equation for open channel steady flow. This analysis indicates a maximum
capacity of 6.35 cfs while maintaining 6-inches of freeboard as the canal approaches Starlite
Monitoring Station. A Hydraflow Express channel report can be found in Appendix B.
The Starlite monitoring station flow data provided by the City and TID indicates a max flow while
pumping at Terrace Street Pump Station of 6.1 cfs and a max irrigation flow of 3.6 cfs (no
pumping). The improvement plans for the Terrace Street Pump Station completed by Keller and
Associates indicates a pumping capacity of 5.42 cfs (two pumps operating at 1215 gpm). In
addition, TID has stated in a meeting with Adkins on April 18th, 2018 that they are limited to
delivering about 6 cfs to the City via the Ashland Canal which is supported by the flow data and
open channel flow analysis.
Storm Runoff
It is important to consider the effects of storm runoff on the existing canal for design of the
proposed pipeline. All of the storm runoff that is generated upland of the canal must be allowed
to either discharge into the pipeline or bypass the pipeline in an existing storm culvert, City storm
drain, or via overland flow. Since the City has indicated that preferably no storm runoff enters the
pipeline, the impact to each of the other destinations must be considered to ensure that increased
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Design Criteria
Adkins Consulting Engineering, LLP
Page 6-2
flow will not overwhelm existing infrastructure or if needed, provided criteria for replacing with
adequate solutions.
Three types of drainage basins were delineated for the Project: those crossing the canal via
culverts (4 total), those that are intercepted by City storm drains before reaching the canal (2
total), and those that overland flow into the existing canal (7 total). Peak flows were determined
for basins that cross the canal or flow into the canal with Hydraflow-Hydrographs software using
method TR-55 for time of concentration and SCS method for peak flows of 2, 10, 25, 50, and 100-
year storms. A map of the basins as well as Hydrograph reports are located in Appendix A. A
summary of the 50-yr Hydrographs is shown in Table 6-1.
It is important to note that the peak overland flow is not the algebraic sum of the peak flows for
each of the 7 individual basin. This is because the Time to peak is not necessarily the same for
each basin. In Addition, the overland flow basins include 1 basin that lies outside of the project
limits but still would be collected by the canal. This basin is located between the upstream end of
the project and Paradise Creek.
Design Flow
TID’s specified limit of 6 cfs was chosen as the baseline for design flow for The Project which is
supported by the historical flow data provided by the City/TID as well as hydraulic analysis
completed by Adkins. Theoretically, the maximum use combination (municipal + irrigation) should
be used for design flow; however, this combination (9.7 cfs) exceeds the stated capacity of TID
and the existing canal to deliver. Furthermore, while the existing canal does collect some degree
of storm runoff, it is spread out over a relatively large area of canal frontage across multiple basins,
and the impacts of allowing it to bypass The Project are considered negligible.
Table 6-1: Hydrograph Summary for 50-yr Storm at Culvert Crossings
Weller North Beach Roca Total Overland Flow into Canal
Area (acres) 5.3 29.8 32.2 149 67.7
Time to Peak (min)
498 522 1016 502 1226
Peak Flow (cfs)
0.37 1.21 0.92 13.19 0.86
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Design Criteria
Adkins Consulting Engineering, LLP
Page 6-3
Unless TID upsizes the entire canal upstream of the project any unnecessary over-design for
capacity would increase project cost with no added benefit to the City. However, the pipeline
should be designed with some degree of safety factor to allow for minor alterations during
construction that could adversely affect the hydraulics of the system and have an allowance for
surge capacity. This surge capacity helps ensure that unanticipated flows or blockages are less
likely to produce overtopping of embankments upstream. Therefore, we recommend a design flow
of 7.2 cfs for the pipeline. This flow is based on the capacity of the Ashland Canal within TID
jurisdiction to deliver water to the proposed pipeline of the Ashland Canal with an additional 20-
percent factor of safety. In reality, the capacity of the pipeline will likely be higher because
standard pipe materials are incrementally sized.
Maximum Upstream Water Surface Elevation
In the previously mentioned meeting with TID, TID communicated that during maximum deliveries
in the Ashland Canal (6 cfs), there is no available capacity to use for developing pressure head
for the pipeline. This means that any piping improvements completed by the City must function
hydraulically without exceeding preexisting maximum water surface elevations upstream.
Open channel flow analysis of the existing canal section approaching Starlite Monitoring Station
indicates that maximum flows produces flow depths of approximately 1 ft upstream approaching
Starlite Place. Based on topographic survey data collected by Adkins this establishes a maximum
water surface elevation at 2327.05 ft.
Adkins Consulting Engineering, LLP
Page 7-1
Chapter 7 - Alternatives
Purpose
This chapter describes the four alternatives considered for the Ashland Canal Piping Project and
describes the design differences as well as costs associated with each. All of the proposed
alternatives meet the design criteria of 7.2 cfs minimum for flow and a maximum upstream water
elevation of 2327.05 feet. See Figure 7-1 for schematics of each Alternative. Although all of the
action based alternatives were viable options, after consideration, the City chose Alternative 1 for
the project.
Project Alternatives
Alternative 1
Alternative 1 consists of replacing the entire canal with 24-inch Corrugated Plastic Pipe (CPP).
This alternative calls for the deepest cut of all the options, requiring the most excavation of all
alternatives and less imported fill than Alternative 2. Approximately 5,700 linear feet of existing
pipe sections will need to be removed for the new pipe to be installed (some of the sections are
double-barrel pipes). Approximately 284 trees will require removal.
Alternative 1’s capital improvement costs were estimated to be approximately $3,095,000. The
biggest contributor to cost for this alternative is the pipe (material and installation). The alternative
will keep future maintenance and repair costs down significantly since it will be an entirely new
system from Starlite Place to Terrace Street.
Alternative 2
Alternative 2 consists of 30-inch CPP with 24-inch CPP sections at certain streets and driveway
crossings. This option retains the existing piped section starting at Elkader Street and ending near
Beach Street. The 30-inch pipe allows for a flatter slope than Alternative 1 minimizing excavation.
Alternative 2 requires more fill than Alternative 1 since the pipe maintains a higher elevation. The
older sections of the existing pipe will require rehabilitation; the recommended rehabilitation is a
cured in place pipe (CIPP). Approximately 1,500 linear feet of existing pipe will need to be
removed for the new pipe to be installed. Approximately 284 trees will require removal.
The costs associated with Alternative 2 were estimated to be around $3,950,000. The increase in
cost over Alternative 1 is mostly attributed to the cost of pipe (30” vs. 24”), increased fill material,
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-2
and pipe rehabilitation. Similar to Alternative 1, this alternative will keep future repairs and
maintenance to a minimum. Approximately 284 trees will require removal.
Alternative 3
Alternative 3 considers lining the existing canal to seal the existing cracks. A concrete liner with
a geomembrane under-liner is recommended for this alternative. This style of liner will have the
best longevity and least seepage over the expected lifespan when compared to other types of
liners. A concrete liner alone is susceptible to cracking and seepage but does a great job of
protecting the geomembrane from a variety of sources including animal traffic, weathering, and
vandalism. Lining of the canal does not address the key issues of water quality and losses due to
evaporation. Similarly to Alternative 2, the older sections of existing pipe will require rehabilitation,
the recommended rehabilitation is a cured in place pipe (CIPP). Approximately 284 trees will
require removal as it proper canal maintenance that has been deferred.
The costs associated with Alternative 3 were estimated to be around $2,429,000. Pipe
rehabilitation is the single largest contributor to the costs of this alternative. Since this alternative
still has an open canal, maintenance costs will still be high to keep the canal free a debris and
maintain its condition.
Alternative 4
Alternative 4 is the “do nothing” alternative. This alternative would involve leaving the existing
canal as is. Existing problems with contamination, deteriorating conditions, and seepage will
continue. Although no capital costs have been associated with this alternative, ongoing operations
and maintenance costs will continue. Failure conditions are likely due to further deterioration,
repairs will be required at an unknown but probably high cost.
Alternative Comparison
Either of the first three alternatives presented will help remedy the City’s significant water losses
in the current canal each year. The piping alternatives (Alternatives 1 and 2) will have the least
water loss and have the distinct advantage of reducing the risk of contamination through the
projects heavily traveled sections of the canal. Alternative 4 (do nothing) will cost the least initially
but could lead to unforeseen lengthy and costly repairs in the future. Table 7-1 shows the
alternatives primary costs and rehabilitation costs compared for each alternative.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-3
Table 7-1: Alternative Cost Comparison
ALTERNATIVE ESTIMATED PRIMARY
PROJECT COSTS
1 $ 3,095,000
2 $ 3,950,000
3 $ 2,429,000
4 $0
The cost estimates include project soft costs such as final design, construction administration,
public outreach, contingency, as well as all construction costs. Of the action alternatives
(Alternatives 1, 2 and 3) Alternative 3 appears to have the lowest initial cost.
It is crucial to keep in mind the indirect costs and non-monetary factors. Water quality is an indirect
cost associated with this project. Water quality affects the cost to treat the municipal water as well
as affecting the water quality of Ashland Creek. For Alternatives 1, 2 and 3 it is recommended
that post-construction tree monitoring take place for 3-5 years after the project is completed. The
monitoring will look for potential negative impacts to trees outside of the project limits and
easement. It is also recommended that public outreach/education and tree health support are
implemented after construction is completed. The monetary and non-monetary values of these
effects were not addressed in this report.
For Alternatives 1 and 2 per the City of Ashland’s request, Adkins created costs estimated for
corrugated HDPE pipe, 3034 PVC, and solid wall HDPE pipe for comparison. For Alternative 3
Adkins created a cost estimate for a concrete liner and a urethane liner with a protective concrete
liner on top. See figures 7-2 through 7-9 for details on the project cost estimated for each
alternative. For planning purposes, the costs should be inflated by 3% to 5% (multiply by 1.03 or
1.05) at a minimum for each year if the project is delayed.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-4
Net Present Value
A life cycle cost analysis was performed to evaluate both the present and future costs for a 60-
year timeframe to directly compare each of the technically feasible alternatives.
The life cycle costs or net present value (NPV) is a way to present the value of a project by
summing the capital costs and operations and maintenance (O&M) minus the present worth of
the salvage value.
The NPV equation and variables are defined as (Agriculture, 2013):
NPV = C + USPW (O&M) – SPPW (S)
C = Capital Cost
USPW (O&M) = Uniform Series Present Worth of Annual O&M
SPPW (S) = Single Payment Present Worth of Salvage Value
The criteria used for the project are as follows:
Planning Period: 60 Years
Real Interest Rate: 0.70% (Business, 2016)
Useful Life of Pipe: 100 Years (Pluimer, 2006)
Since the pipe is the only part of the infrastructure that is intended to last past the planning period,
it is the only piece that has a salvage value. In the report conducted by the Bureau of Reclamation
(Reclamation, 2002) completed in Oregon, Montana, Idaho, and Oklahoma shows that a canal
liner has a lifespan of 40-60 years. The tests in Oregon were located in Central Oregon, where
the climate has a harsher freeze-thaw cycle than Ashland, so 60 years was chosen as the lifespan
for the canal liner. Since the liners lifespan matched the planning period, it has a salvage value
of $0. The typical expected lifespan of CIPP is 50-60 years, therefore giving the canal liner
alternative a salvage value of $0. Other components such as the bar screen, meters and turnouts
are considered short-lived assets and will be included in the O&M costs. Figure 7-10 shows the
NPV Analysis.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-5
Preferred Alternative
The alternatives were presented to the City and Alternative 1 was chosen for the design of this
project. Alternative 1 landed in the middle for comparative construction costs but when
considering future maintenance, rehabilitation, and treatment costs associated with Alternatives
2, 3 and 4, it was the least expensive alternative.
Inlet
The inlet structure will be located south of the Starlite Place crossing. Water flowing down the TID
canal will be screened by a traveling bar screen. The traveling bar screen will remove debris such
as leaves, sticks, and trash that may collect in the canal and travel downstream. The traveling bar
screen will unload the debris via a conveyor system into a dumpster that can easily be hauled
away by City maintenance crews or a waste disposal company. An internal spray wash will keep
the screen from clogging, minimizing the risk of the inlet being blocked. This low maintenance
system keeps the pipeline clean allowing the downstream turnouts and pump station to function
correctly and efficiently as well as minimize organic matter in the pipeline which should help to
reduce treatment costs at the water treatment plant.
To replace the Starlite Monitoring Station we recommend a non-contact flow meter such as an
ultrasonic flow meter is installed in the inlet structure. An ultrasonic flow meter will give accurate
readings during all flow circumstances especially low flow conditions. This style flow meter would
reduce the need for site visits as it could be remotely monitored and requires minimal
maintenance.
The inlet structure design will include an overflow bypass. This bypass will be two flash board
style weirs (one on each side of the structure). The overflow bypass weirs will be set at the
maximum upstream water elevation of 2327.05 feet. In the unlikely circumstance that there is a
blockage of the traveling bar screen, the overflow bypass weir would protect the upstream canal
from overtopping the banks by allowing water to bypass the bar screen into the 24-inch pipeline
downstream. The weirs will need to have a minimum crest length of 10 feet combined to pass the
design flow of 7.2 cfs without exceeding the available freeboard in the canal.
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-6
Pipeline
The preliminary design for an all 24-inch pipeline requires a slightly steeper slope than the existing
canal bottom. This helps keep cost down by reducing unnecessary imported fill material other
than that which is required for proper pipe bedding. The 24-inch dual wall low head HDPE pipe is
nearly 70% cheaper per linear foot than the equivalent 30-inch pipe. Since the flows in the pipe
are limited by the upstream canal flow capacity, it is unnecessary to install a larger pipe with more
capacity.
The established design criteria requires the pipeline to accept a minimum 7.20 cfs of flow from
the upstream canal. Through modeling using Hydraflow software, it was determined that the
actual capacity of the pipe shown in the preliminary design drawings is 7.95 cfs. When the pipe
is flowing at its max capacity sections of pipe will be full flow and under pressure. It is very unlikely
that the pipe will ever encounter this flow due to the limited upstream capacities. A Storm Sewers
Pipeline Summary Report and Pipeline Hydraulic Grade Line Computation Report for the
Preferred Alternative at the design flow of 7.2 cfs is included in Appendix B.
The alignment of the new pipeline was carefully chosen to best fit the terrain, minimize tree
removal and accommodate landowners’ concerns. The City has received input from land owners
during backyard visits and as the design process proceeds the City will continue to receive input
from the land owners and the Ashland Canal Advisory Group (ACAG). As the alignment is
finalized in the final design phase, the City will obtain easements as necessary for the pipeline.
Terrace Street Pump Station
At the Terrace Street Pump Station the current trash rack will be removed and the 24-inch pipeline
will be connected through the wall of the existing wet well structure. Water will flow directly into
the dual chambered wet well where it can be pumped to the City water treatment plant, or
discharged through the TID irrigation line, the canal siphon, or the spill into Ashland Creek.
Services
There are two types of service turnouts for the pipeline depending on whether it located on the
down or uphill side of the pipeline. The first type is gravity fed, this style of service turnout will feed
just above the invert of the main pipeline into a two-inch pipe, down to a reduced service tap that
the user can attach a hose to for use. The second type is a sump service; this service will feed
out just above the invert of the pipe into a 12-inch diameter, 24-inch deep sump where users can
lower their pumps into. Since the turnouts will feed near the invert of the pipe if any water is
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-7
present in the pipe the turnout will be submerged and a propeller style meter can be used to
monitor water consumption. See the details on design sheet C34 for further details.
Access
Access ports will be located near road crossings along the pipeline to allow City crews access to
inspect and maintain the pipe. The preliminary design intends for there to be access ports at most
of the road crossings. Other access points may be placed near driveways if necessary, so that a
maintenance or inspection vehicle can access the pipeline without driving down the trail.
Crossings
There are 4 creek and drainage crossings in the project, 3 of which are currently functional and 1
that is believed to have been buried by a debris flow. The preliminary design calls to either
maintain or replace each of these pipes (all are 24 inch) crossing underneath the new 24-inch
pipeline. These 4 crossing were checked for capacity versus the 50-yr storm peak flows
summarized in Chapter 6. Culvert reports for each crossing are located in Appendix B. Each
crossing will remain a 24-inch culvert as the reports indicate sufficient capacity to pass the 50-yr
peak flows.
Storm Drains
The two 12-inch drainage pipes that currently flow into the canal will have to be piped past the
new pipeline. The preliminary design proposes the 12-inch steel pipe on the 891 Roca Street
property be piped under the new pipeline and discharged in Roca Creek with the proper energy
dissipation system. The 12-inch HDPE pipe from Terrace Street on the 920 Pinecrest Terrace
property will be piped to the cul-de-sac on Penny Drive. Adkins will coordinate with the City and
Kennedy Jenks Consultants (currently working on the City’s Storm Water Master Plan) during the
final design to assess drainage capacities and determine the best location for these pipes.
Currently, most of the roof and footing drains uphill of the project flow into the canal. For the
preliminary design these are shown to be connected to the proposed pipeline. During final design,
these could be reconsidered on a case-by-case basis to be treated with Low Impact Development
(LID) measures; however, the Preliminary Geotechnical review reveals that the project area is not
conducive to LID methods, as the soil profile tends to be shallow and underlined with rock (The
Galli Group, 2018).
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Alternatives
Adkins Consulting Engineering, LLP
Page 7-8
Trail
Once the canal lining is removed and the pipe is installed and backfilled, a new trail will be
established over the pipeline. The trail will allow access to the pipe for inspections and
maintenance, as well as give pedestrians access to the trails where authorized. Public access is
dependent on landowner cooperation and there are currently several sections of the trail that the
landowner has chosen to deny public access.
The new trail in a typical section will be close to or slightly lower than the existing trail and
constructed to the standards and requirements of the City of Ashland’s Trail Master Plan. After
the pipe is properly bedded with the primary fill, the trail will be level and create at minimum one
foot of fill over the pipe.
ASHLNAD ST
PONDEROSA DR
ELM ST
OREGON ST
RO
CA
ST
WINDSOR ST
PIN
ECREST T
ER
FIELDER ST
LILAC ST
IVY LN
ELK
AD
ER
ST
S. M
OU
NT
AIN
AV
E
PA
LM
ER
RD
IND
IAN
A S
T
UN
IVE
RS
ITY
WA
Y
S. M
OU
NT
AIN
AV
E
BE
AC
H S
T
LIB
ER
TY
ST
MO
RT
ON
ST
LO
NG
WA
Y
TE
RR
AC
E S
T
TA
YLO
R S
T
GU
TH
RIE
ST
ELK
AD
ER
ST
ASHLNAD LOOP RD
WATER
LINE R
D
TIMBERLINE TER
ST
AR
LIT
E P
L
CO
UR
TN
EY
ST
JE
NN
IFE
R S
TEUCLI
D S
T PRACHT ST
FOREST ST
WEBSTER ST
MADRONE ST
GLE
NW
OO
D D
R
ALTAMONT ST
WOODLAND DREMMA ST
LE
ON
AR
D S
T
SISKIYOU BLVD
ASHLNAD ST
PONDEROSA DR
ELM ST
OREGON ST
RO
CA
ST
WINDSOR ST
PIN
ECREST T
ER
FIELDER ST
LILAC ST
IVY LN
ELK
AD
ER
ST
S. M
OU
NT
AIN
AV
E
PA
LM
ER
RD
IND
IAN
A S
T
UN
IVE
RS
ITY
WA
Y
S. M
OU
NT
AIN
AV
E
BE
AC
H S
T
LIB
ER
TY
ST
MO
RT
ON
ST
LO
NG
WA
Y
TE
RR
AC
E S
T
TA
YLO
R S
T
GU
TH
RIE
ST
ELK
AD
ER
ST
ASHLNAD LOOP RD
WATER
LINE R
D
TIMBERLINE TER
ST
AR
LIT
E P
L
CO
UR
TN
EY
ST
JE
NN
IFE
R S
T
EUCLI
D S
T PRACHT ST
FOREST ST
WEBSTER ST
MADRONE ST
GLE
NW
OO
D D
R
ALTAMONT ST
WOODLAND DREMMA ST
LE
ON
AR
D S
T
SISKIYOU BLVD
ASHLNAD ST
PONDEROSA DR
ELM ST
OREGON ST
RO
CA
ST
WINDSOR ST
PIN
ECREST T
ER
FIELDER ST
LILAC ST
IVY LN
ELK
AD
ER
ST
S. M
OU
NT
AIN
AV
E
PA
LM
ER
RD
IND
IAN
A S
T
UN
IVE
RS
ITY
WA
Y
S. M
OU
NT
AIN
AV
E
BE
AC
H S
T
LIB
ER
TY
ST
MO
RT
ON
ST
LO
NG
WA
Y
TE
RR
AC
E S
T
ELK
AD
ER
ST
ASHLNAD LOOP RD
WATER
LINE R
D
ST
AR
LIT
E P
L
EUCLI
D S
T
FOREST ST
MADRONE ST
GLE
NW
OO
D D
R
WOODLAND DREMMA ST
LE
ON
AR
D S
T
SISKIYOU BLVD
ASHLAND CANAL PIPING ALTERNATIVES
FIGURE
7-1
CITY OF
ASHLAND, OREGON
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $197,700 All Req'd 197,700$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $100,000 All Req'd 100,000$
3 Construction Surveying (2% of Total Bid Price) LS $38,800 All Req'd 38,800$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$
6 Removal of Pipe LF $14 5,355 75,000$
7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$
10 Bar Screen LS $20,000 All Req'd 20,000$
11 Controls & Telemetry LS $25,000 All Req'd 25,000$
12 24-Inch Dual Wall Low Head HDPE Pipe LF $82 10,801 885,700$
13 Service Turnout Gravity Each $2,500 29 72,500$
14 Service Turnout Sump Each $3,500 4 14,000$
15 Drain Connections Each $600 16 9,600$
16 Manhole / Access Vault Each $6,000 5 30,000$
17 Weller Crossing LS $5,000 All Req'd 5,000$
18 Roca Creek LS $38,500 All Req'd 38,500$
19 Beach Creek LS $5,000 All Req'd 5,000$
20 North Basin LS $8,000 All Req'd 8,000$
21 Trail (Decomposed Granite) LF $6 8,900 53,400$
22 Fence LF $15 650 9,800$
23 Driveway Crossings SF $10 3,810 38,100$
24 Road Crossings LS $50,000 All Req'd 50,000$
25 Removal Each $325 284 92,300$
26 Planted Each $750 125 93,800$
2,174,000$
$435,000$218,000
$218,000
$50,000
3,095,000$
NO. ITEM
Inlet Structure
Pipeline
Restoration
CITY OF ASHLAND, OREGON
24-INCH CORRUGATED HDPE PIPELINE (ALTERNATIVE 1A)
COST ESTIMATE(YEAR 2018 COST)
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
Sum of Estimated Construction Cost
Trees
Drainage Crossing
Contingency (20%)
Construction Administration (10%)
Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Public Outreach
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-2
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $202,100 All Req'd 202,100$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $100,000 All Req'd 100,000$
3 Construction Surveying (2% of Total Bid Price) LS $39,700 All Req'd 39,700$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$
6 Removal of Pipe LF $14 5,355 75,000$
7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$
10 Bar Screen LS $20,000 All Req'd 20,000$
11 Controls & Telemetry LS $15,000 All Req'd 15,000$
12 24-Inch 3034 PVC Pipe LF $86 10,801 928,900$
13 Service Turnout Gravity Each $2,750 29 79,800$
14 Service Turnout Sump Each $3,750 4 15,000$
15 Drain Connections Each $700 16 11,200$
16 Manhole / Access Vault Each $6,000 5 30,000$
17 Weller Crossing LS $5,000 All Req'd 5,000$
18 Roca Creek LS $38,500 All Req'd 38,500$
19 Beach Creek LS $5,000 All Req'd 5,000$
20 North Basin LS $8,000 All Req'd 8,000$
21 Trail (Decomposed Granite) LF $6 8,900 53,400$
22 Fence LF $15 650 9,800$
23 Driveway Crossings SF $10 3,810 38,100$
24 Road Crossings LS $50,000 All Req'd 50,000$
25 Removal Each $325 284 92,300$
26 Planted Each $750 125 93,800$
2,222,000$
$445,000$223,000
$223,000
$50,000
3,163,000$
NO. ITEM
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
24-INCH 3034 PVC PIPELINE (ALTERNATIVE 1B)
COST ESTIMATE(YEAR 2018 COST)
Inlet Structure
Pipeline
Drainage Crossing
Restoration
Trees
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-3
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $238,300 All Req'd 238,300$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $100,000 All Req'd 100,000$
3 Construction Surveying (2% of Total Bid Price) LS $46,800 All Req'd 46,800$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$
6 Removal of Pipe LF $14 5,355 75,000$
7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$
10 Bar Screen LS $20,000 All Req'd 20,000$
11 Controls & Telemetry LS $15,000 All Req'd 15,000$
12 24-Inch Solid Wall HDPE LF $118 10,801 1,274,600$
13 Service Turnout Gravity Each $3,000 29 87,000$
14 Service Turnout Sump Each $4,000 4 16,000$
15 Drain Connections Each $750 16 12,000$
16 Manhole / Access Vault Each $6,000 5 30,000$
17 Weller Crossing LS $5,000 All Req'd 5,000$
18 Roca Creek LS $38,500 All Req'd 38,500$
19 Beach Creek LS $5,000 All Req'd 5,000$
20 North Basin LS $8,000 All Req'd 8,000$
21 Trail (Decomposed Granite) LF $6 8,900 53,400$
22 Fence LF $15 650 9,800$
23 Driveway Crossings SF $10 3,810 38,100$
24 Road Crossings LS $50,000 All Req'd 50,000$
25 Removal Each $325 284 92,300$
26 Planted Each $750 125 93,800$
2,620,000$
$524,000$262,000
$262,000
$50,000
3,718,000$
NO. ITEM
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
24-INCH SOLID HDPE PIPELINE (ALTERNATIVE 1C)
COST ESTIMATE(YEAR 2018 COST)
Inlet Structure
Pipeline
Drainage Crossing
Restoration
Trees
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-4
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $253,200 All Req'd 253,200$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $50,000 All Req'd 50,000$
3 Construction Surveying (2% of Total Bid Price) LS $49,700 All Req'd 49,700$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$ 6 Removal of Pipe LF $14 5,355 75,000$ 7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$ 10 Bar Screen LS $20,000 All Req'd 20,000$ 11 Controls & Telemetry LS $15,000 All Req'd 15,000$
12 30-Inch Dual Wall Low Head HDPE Pipe LF $98 8,100 793,800$ 13 24-Inch Dual Wall Low Head HDPE Pipe LF $82 550 45,100$ 14 Rehabilitated Pipe Sections (CIPP Liner) LF $186 3,500 651,000$ 15 Service Turnout Gravity Each $2,500 29 72,500$ 16 Service Turnout Sump Each $3,500 4 14,000$ 17 Drain Connections Each $600 16 9,600$ 18 Manhole / Access Vault Each $6,000 5 30,000$
19 Weller Crossing LS $5,000 All Req'd 5,000$
20 Roca Creek LS $38,500 All Req'd 38,500$ 21 Beach Creek LS $5,000 All Req'd 5,000$ 22 North Basin LS $8,000 All Req'd 8,000$
23 Trail (Decomposed Granite) LF $6 8,900 53,400$ 24 Fence LF $15 650 9,800$ 25 Driveway Crossings SF $10 3,810 38,100$ 26 Road Crossings LS $50,000 All Req'd 50,000$
27 Removal Each $325 284 92,300$ 28 Planted Each $750 125 93,800$
2,785,000$
$557,000$279,000
$279,000
$50,000
3,950,000$
NO. ITEM
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
30" & 24" CORRUGATED HDPE PIPELINE (ALTERNATIVE 2A)
COST ESTIMATE(YEAR 2018 COST)
Inlet Structure
Pipeline
Drainage Crossing
Restoration
Trees
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-5
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $285,000 All Req'd 285,000$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $50,000 All Req'd 50,000$
3 Construction Surveying (2% of Total Bid Price) LS $55,900 All Req'd 55,900$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$ 6 Removal of Pipe LF $14 5,355 75,000$ 7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$ 10 Bar Screen LS $20,000 All Req'd 20,000$ 11 Controls & Telemetry LS $15,000 All Req'd 15,000$
12 30-Inch 3034 PVC Pipe LF $135 8,100 1,093,500$ 13 24-Inch 3034 PVC Pipe LF $86 550 47,300$ 14 Rehabilitated Pipe Sections (CIPP Liner) LF $186 3,500 651,000$ 15 Service Turnout Gravity Each $2,750 29 79,800$ 16 Service Turnout Sump Each $3,750 4 15,000$ 17 Drain Connections Each $700 16 11,200$ 18 Manhole / Access Vault Each $6,000 5 30,000$
19 Weller Crossing LS $5,000 All Req'd 5,000$
20 Roca Creek LS $38,500 All Req'd 38,500$ 21 Beach Creek LS $5,000 All Req'd 5,000$ 22 North Basin LS $8,000 All Req'd 8,000$
23 Trail (Decomposed Granite) LF $6 8,900 53,400$ 24 Fence LF $15 650 9,800$ 25 Driveway Crossings SF $10 3,810 38,100$ 26 Road Crossings LS $50,000 All Req'd 50,000$
27 Removal Each $325 284 92,300$ 28 Planted Each $750 125 93,800$
3,134,000$
$627,000$314,000
$314,000
$50,000
4,439,000$
NO. ITEM
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
30" & 24" 3034 PVC PIPELINE (ALTERNATIVE 2B)
COST ESTIMATE(YEAR 2018 COST)
Inlet Structure
Pipeline
Drainage Crossing
Restoration
Trees
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-6
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $300,100 All Req'd 300,100$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $50,000 All Req'd 50,000$
3 Construction Surveying (2% of Total Bid Price) LS $58,900 All Req'd 58,900$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$ 6 Removal of Pipe LF $14 5,355 75,000$ 7 Removal of Asphalt / Concrete LS $14,000 All Req'd 14,000$
8Removal and Disposal of Structure (Turnouts,
Manhole, Trash Rack, etc.)Each $2,000 11 22,000$
9 Reinforced Concrete LS $20,000 All Req'd 20,000$ 10 Bar Screen LS $20,000 All Req'd 20,000$ 11 Controls & Telemetry LS $15,000 All Req'd 15,000$
12 30-Inch 3034 PVC Pipe LF $150 8,100 1,215,000$ 13 24-Inch 3034 PVC Pipe LF $118 550 64,900$ 14 Rehabilitated Pipe Sections (CIPP Liner) LF $186 3,500 651,000$ 15 Service Turnout Gravity Each $3,000 29 87,000$ 16 Service Turnout Sump Each $4,000 4 16,000$ 17 Drain Connections Each $750 16 12,000$ 18 Manhole / Access Vault Each $6,000 5 30,000$
19 Weller Crossing LS $5,000 All Req'd 5,000$
20 Roca Creek LS $38,500 All Req'd 38,500$ 21 Beach Creek LS $5,000 All Req'd 5,000$ 22 North Basin LS $8,000 All Req'd 8,000$
23 Trail (Decomposed Granite) LF $6 8,900 53,400$ 24 Fence LF $15 650 9,800$ 25 Driveway Crossings SF $10 3,810 38,100$ 26 Road Crossings LS $50,000 All Req'd 50,000$
27 Removal Each $325 284 92,300$ 28 Planted Each $750 125 93,800$
3,301,000$
$661,000$331,000
$331,000
$50,000
4,674,000$
NO. ITEM
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
30" & 24" SOLID HDPE PIPELINE (ALTERNATIVE 2C)
COST ESTIMATE(YEAR 2018 COST)
Inlet Structure
Pipeline
Drainage Crossing
Restoration
Trees
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-7
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $154,500 All Req'd 154,500$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $50,000 All Req'd 50,000$
3 Construction Surveying (2% of Total Bid Price) LS $30,300 All Req'd 30,300$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$
7 Concrete Canal Liner SF $4 75,338 301,400$
8 Urethane Liner SF $1.60 75,338 120,600$
9 Service Turnout Gravity Each $1,500 29 43,500$
10 Rehabilitated Pipe Sections (CIPP Liner) LF $186 3,500 651,000$
11 Removal Each $325 284 92,300$
1,699,000$
$340,000$170,000
$170,000
$50,000
2,429,000$
CITY OF ASHLAND, OREGON
URETHANE & CONCRETE LINER (ALTERNATIVE 3A)
COST ESTIMATE(YEAR 2018 COST)
Canal Liner
Trees
Sum of Estimated Construction Cost
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
NO. ITEM
Pipe Rehabilitation
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-8
UNIT UNIT PRICE AMOUNT TOTAL PRICE
General
1 Mobilization/Demobilization (not to exceed 10%
of Total Bid Price)LS $142,200 All Req'd 142,200$
2 Temporary Protection and Direction of
Traffic/Project SafetyLS $50,000 All Req'd 50,000$
3 Construction Surveying (2% of Total Bid Price) LS $27,900 All Req'd 27,900$
4 Erosion and Sediment Control LS $50,000 All Req'd 50,000$
Demolition of Existing Infrastructure
5 Removal of Canal Lining LF $28 7,350 205,800$
7 Concrete Canal Liner SF $4 75,338 301,400$
8 Service Turnout Gravity Each $1,500 29 43,500$
9 Rehabilitated Pipe Sections (CIPP Liner) LF $186 3500 651,000$
10 Removal Each $325 284 92,300$
1,564,000$
$313,000$157,000
$157,000
$50,000
2,241,000$
NO. ITEM
Pipe Rehabilitation
Canal Liner
Trees
Sum of Estimated Construction Cost
CITY OF ASHLAND, OREGON
CONCRETE LINER (ALTERNATIVE 3B)
COST ESTIMATE(YEAR 2018 COST)
Contingency (20%)Final Design, Engineering, Permitting Easements and Geotechnical (10%)
Construction Administration (10%)
Public Outreach
TOTAL ESTIMATED PROJECT COST (2018 DOLLARS)
CITY OF
ASHLAND, OREGONASHLAND CANAL PIPING
COST ESTIMATE
FIGURE
7-9
Corrugated HDPE 3034 PVC Solid Wall HDPE Corrugated HDPE 3034 PVC Solid Wall HDPE Concrete & Urethane Concrete
Capital Costs 3,095,000$ 3,163,000$ 3,718,000$ 3,950,000$ 4,439,000$ 4,674,000$ 2,429,000$ 2,241,000$ -$
Annual O&M 12,500$ 12,500$ 12,500$ 12,500$ 12,500$ 12,500$ 39,000$ 39,000$ 50,000$
Salvage Value 354,280$ 371,560$ 509,840$ 335,560$ 456,320$ 511,960$ -$ -$ -$
Net Present Value 3,472,579$ 3,529,209$ 3,993,219$ 4,339,897$ 4,749,436$ 4,947,824$ 4,334,379$ 4,146,379$ 2,442,794$
ALTERNATIVE 1 - ALL NEW 24" PIPELINE ALTERNATIVE 2 - 30" & 24" PIPELINE ALTERNATIVE 3 - REPLACE CANAL LINER ALTERNATIVE 4 -
Do Nothing
CITY OF ASHLAND, OREGON
NET PRESENT VALUE ANALYSIS
CANAL IMPROVEMENTS(YEAR 2018 COST)
FIGURECITY OF
ASHLAND, OREGONNPV ANALYSIS (60 Year) 7-10
Adkins Consulting Engineering, LLP
Page 8-1
Chapter 8 - Construction Timeline Construction for the Ashland Canal Piping Project is expected to begin at the end of the 2019
water year and will primarily occur during the non-irrigation season (October 1st to April 15th). The
critical aspect of the project to ensure water deliveries is the construction of the pipeline itself;
other items that do not affect the ability to deliver water such as surface restoration,
planting/seeding, trail building, and final asphalt patching, can or are even better suited to occur
at times that take place during irrigation season.
For the Project, construction is likely to occur in a manner that is typical for canal piping projects
with limited access. An expected work force would consist of two crews: one to set erosion control
measures, demolish the lining, and level the existing canal; and the second to construct the
pipeline, once crew one has moved far enough ahead. The first crew would begin at a downstream
access point working upstream while shuttling debris back down the canal to the access point.
Once the demo crew has reached the next access point and begins work on a second section,
the pipe crew can begin work on the prior section. The piping crew will work in a backwards
fashion, traveling upstream while excavating the trench. Pipe sections will be shuttled in from the
nearest upstream access point and backfill material will be shuttled in from the nearest
downstream access point.
Constraints
There will be several factors that negatively affect the rate at which the crews can complete work
on the Project. The following is not an all-inclusive list but represents what are considered to be
the major factors that will affect the construction schedule.
Weather
Since work will occur during late fall to spring, weather will be a primary concern as Ashland
averages over 2.5-inches of precipitation during the months of November to March. Excessively
wet weather will slow crews as much of the work is expected to be performed with smaller
equipment and manpower.
Location
The Project meanders through the southwest hillsides of the City, a residential area where the
road network has low connectivity and lacks through-routes which means multiple staging areas
City of Ashland, Oregon
Ashland Canal Piping Project – Preliminary Engineering Report Construction Timeline
Adkins Consulting Engineering, LLP
Page 8-2
along the length of the project would be ideal for crews to quickly retrieve equipment and
materials. Unfortunately, the Project’s location also provides limited options for staging areas that
could readily and conveniently service the length of the project. This means crews will have to
spend more time transporting equipment and materials or shuttling from section to section along
the project. The project also crosses a number of private drives and streets through which the
contractor will have to allow a reasonable amount of access for residents. This will require traffic
control to be continually adjusted during the project, which takes time away from working on the
pipeline.
Schedule
Considering these factors and the anticipated workflow, two preliminary construction schedules
were modeled for the project. Preliminary Construction Schedule ‘A’ is a conservative estimate
that the demo crew will be able to complete 300 feet/day and the pipe crew will be able to complete
200 feet/day. This estimate essentially assumes a very wet winter/spring. Preliminary
Construction Schedule ‘B’ is more optimistic than ‘A’ and assumes the demo crew will complete
500 feet/day and the pipe crew will complete 400 feet/day. Both schedules are based on a 4-day,
10-hour workweek and assume that the entire week of Thanksgiving, Christmas, and New Year’s
will be taken off. See Figures 8-1 and 8-2 for Preliminary Construction Schedule ‘A’ and ‘B’,
respectively.
Both schedules start construction in fall of 2019 and depict a timeline that will encompass two
irrigation off-seasons. This will require that a temporary inlet structure to be constructed at the
end of the construction first season to screen the canal water during the 2020 water season.
ID Task Name Duration Start Finish
1 End of Water Season 0 days Tue 10/1/19 Tue 10/1/192 Waterdown 8 days Tue 10/1/19 Wed 10/16/193 ESC 1+00 to 13+00 0.5 days Tue 10/1/19 Tue 10/1/194 Construct Temp Access at TSPS 1 day Thu 10/17/19 Mon 10/21/195 Demo 1+00 to 13+00 5 days Mon 10/21/19Wed 10/30/196 Excavate/ Construct 1+00 to 13+006 days Wed 10/30/19Tue 11/12/197 Rebuild DW @ 13+00 2 days Wed 11/13/19Mon 11/18/198 ESC 13+00 to 19+50 0.5 days Wed 10/30/19Thu 10/31/199 Demo 13+00 to 19+50 2.5 days Thu 10/31/19 Wed 11/6/19
10 Excavate/ Construct 13+00 to 19+505 days Mon 11/18/19Wed 12/4/1911 ESC 19+50 to 24+75 0.5 days Wed 11/6/19 Wed 11/6/1912 Demo 19+50 to 24+75 2 days Mon 11/18/19Wed 11/20/1913 Excavate/ Construct 19+50 to 24+753 days Wed 12/4/19 Wed 12/11/1914 Rebuild DW @ 19+50 1 day Thu 11/21/19 Mon 12/2/1915 ESC 24+75 to 34+50 (Morton) 1 day Thu 11/21/19 Mon 12/2/1916 Demo 24+75 to 34+50 (Morton) 3.5 days Wed 12/11/19Wed 12/18/1917 Remove/Reconstruct Culvert @ 27+251 day Wed 12/18/19Mon 1/6/2018 Excavate/Construct 24+75 to 34+505 days Mon 1/6/20 Wed 1/15/2019 Morton St Xing 2 days Wed 1/15/20 Mon 1/20/2020 ESC 34+50 tp 38+00 0.5 days Wed 12/18/19Thu 12/19/1921 Demo 34+50 to 38+00 1 day Thu 12/19/19 Mon 1/6/2022 Excavate/Construct 34+50 to 38+002 days Mon 1/20/20 Thu 1/23/2023 Rebuild DW @ 38+00 1 day Thu 1/23/20 Mon 1/27/2024 ESC 38+00 54+25 2 days Mon 1/6/20 Thu 1/9/2025 Demo 38+00 to 54+25 5.5 days Thu 1/9/20 Wed 1/22/2026 Install Culvert 42+50 1 day Wed 1/22/20 Thu 1/23/2027 Excavate/Construct 38+00 to 54+258 days Mon 1/27/20 Wed 2/12/2028 ESC 54+25 to56+40 0.5 days Wed 1/22/20 Wed 1/22/2029 Demo 54+25 to 56+401 1 day Wed 1/22/20 Thu 1/23/2030 Excavate/Construct 54+25 to 56+401 day Wed 2/12/20 Thu 2/13/2031 Rebuild DW @ 56+40 1 day Thu 2/13/20 Tue 2/18/2032 ESC 56+40 to 64+75 (S Mtn) 1 day Mon 1/27/20 Tue 1/28/2033 Demo 56+40 to 64+75 (S Mtn) 3 days Wed 2/12/20 Wed 2/19/2034 Excavate/Construct 56+40 to 64+754 days Wed 2/19/20 Thu 2/27/2035 Rebuild S Mtn 1 day Thu 2/27/20 Mon 3/2/2036 ESC 64+75 to 68+25 1 day Wed 2/19/20 Thu 2/20/2037 Demo 64+75 to 68+25 (Emma) 1 day Thu 2/20/20 Mon 2/24/2038 Excavate/Construct 64+75 to 68+25 (Emma)2 days Mon 3/2/20 Thu 3/5/20
10/1Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Ashland Canal Preliminary Construction Schedule 'A'
Page 1 Figure 8-1
ID Task Name Duration Start Finish
39 Emma/Elkader Xing 8 days Thu 3/5/20 Tue 3/24/2040 Construct Temporary Inlet at 70+258 days Tue 3/24/20 Thu 4/9/2041 Begin 2020 Water Season 0 days Wed 4/15/20 Wed 4/15/2042 2020 Water Season 78 days Wed 4/15/20 Thu 10/1/2043 Grading/ Surface Restoration 1+00 to 70+2540 days Thu 4/9/20 Tue 7/7/2044 2020 Water Season Ends 0 days Thu 10/1/20 Thu 10/1/2045 Waterdown 8 days Mon 10/5/20 Tue 10/20/2046 ESC 70+25 to 87+50 1 day Wed 10/21/20Thu 10/22/2047 Demo 70+25 to 87+50 5 days Thu 10/22/20 Tue 11/3/2048 Roca Creek Xing 1 day Tue 11/3/20 Wed 11/4/2049 Excavate/Construct 70+25 to 87+508 days Wed 11/4/20 Mon 11/23/2050 Leonard St Xing 1 day Mon 11/23/20Tue 11/24/2051 ESC 87+50 to 104+25 2 days Tue 11/3/20 Thu 11/5/2052 Demo 87+25 to 104+25 5 days Mon 11/9/20 Wed 11/18/2053 Excavate/Construct 87+25 to 104+509 days Mon 11/23/20Thu 12/10/2054 ESC 104+25 to 108+00 0.5 days Wed 11/18/20Wed 11/18/2055 Demo 104+25 to 108+00 1.5 days Wed 11/25/20Thu 11/26/2056 Excavate/Construct 104+25 to 108+002 days Mon 12/14/20Wed 12/16/2057 Rebuild Starlite Xing 1 day Wed 12/16/20Thu 12/17/2058 Construct Inlet 16 days Thu 12/17/20 Thu 1/21/2159 Grading/Surface Restoration 20 days Thu 1/21/21 Mon 3/8/2160 Punch List 25 days Mon 3/8/21 Thu 4/29/2161 Final Seeding/Planting 25 days Mon 3/8/21 Thu 4/29/2162 2021 Water Season Starts 0 days Thu 4/15/21 Thu 4/15/21
4/15
10/1
4/15
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Ashland Canal Preliminary Construction Schedule 'A'
Page 2 Figure 8-1
ID Task Name Duration Start Finish
1 End of Water Season 0 days Tue 10/1/19 Tue 10/1/192 Waterdown 8 days Tue 10/1/19 Wed 10/16/193 ESC 1+00 to 13+00 0.5 days Tue 10/1/19 Tue 10/1/194 Construct Temp Access at TSPS 1 day Thu 10/17/19 Mon 10/21/195 Demo 1+00 to 13+00 2 days Mon 10/21/19Wed 10/23/196 Excavate/ Construct 1+00 to 13+00 3 days Wed 10/23/19Wed 10/30/197 Rebuild DW @ 13+00 2 days Wed 10/30/19Mon 11/4/198 ESC 13+00 to 19+50 0.5 days Wed 10/23/19Thu 10/24/199 Demo 13+00 to 19+50 1.5 days Thu 10/24/19 Tue 10/29/19
10 Excavate/ Construct 13+00 to 19+502 days Tue 11/5/19 Thu 11/7/1911 ESC 19+50 to 24+75 0.5 days Tue 10/29/19 Tue 10/29/1912 Demo 19+50 to 24+75 1 day Tue 11/5/19 Wed 11/6/1913 Excavate/ Construct 19+50 to 24+751.5 days Thu 11/7/19 Tue 11/12/1914 Rebuild DW @ 19+50 1 day Wed 11/6/19 Thu 11/7/1915 ESC 24+75 to 34+50 (Morton) 1 day Wed 11/6/19 Thu 11/7/1916 Demo 24+75 to 34+50 (Morton) 2 days Tue 11/12/19 Thu 11/14/1917 Remove/Reconstruct Culvert @ 27+251 day Thu 11/14/19 Tue 11/19/1918 Excavate/Construct 24+75 to 34+502.5 days Tue 11/19/19 Mon 12/2/1919 Morton St Xing 1 day Mon 12/2/19 Tue 12/3/1920 ESC 34+50 tp 38+00 0.5 days Thu 11/14/19 Mon 11/18/1921 Demo 34+50 to 38+00 1 day Mon 11/18/19Tue 11/19/1922 Excavate/Construct 34+50 to 38+001 day Tue 12/3/19 Wed 12/4/1923 Rebuild DW @ 38+00 1 day Wed 12/4/19 Thu 12/5/1924 ESC 38+00 54+25 2 days Tue 11/19/19 Mon 12/2/1925 Demo 38+00 to 54+25 3.5 days Mon 12/2/19 Mon 12/9/1926 Install Culvert 42+50 1 day Mon 12/9/19 Tue 12/10/1927 Excavate/Construct 38+00 to 54+254 days Mon 12/9/19 Tue 12/17/1928 ESC 54+25 to56+40 0.5 days Mon 12/9/19 Tue 12/10/1929 Demo 54+25 to 56+401 0.5 days Tue 12/10/19 Tue 12/10/1930 Excavate/Construct 54+25 to 56+401 day Tue 12/17/19 Wed 12/18/1931 Rebuild DW @ 56+40 1 day Mon 1/13/20 Tue 1/14/2032 ESC 56+40 to 64+75 (S Mtn) 1 day Tue 12/10/19 Thu 12/12/1933 Demo 56+40 to 64+75 (S Mtn) 2 days Tue 12/17/19 Mon 1/6/2034 Excavate/Construct 56+40 to 64+752 days Tue 1/14/20 Mon 1/20/2035 Rebuild S Mtn 1 day Mon 1/20/20 Tue 1/21/2036 ESC 64+75 to 68+25 1 day Tue 1/14/20 Wed 1/15/2037 Demo 64+75 to 68+25 (Emma) 1 day Thu 1/16/20 Mon 1/20/2038 Excavate/Construct 64+75 to 68+25 (Emma)1 day Tue 1/21/20 Wed 1/22/20
10/1Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Ashland Canal Preliminary Construction Schedule 'B'
Page 1 Figure 8-2
ID Task Name Duration Start Finish
39 Emma/Elkader Xing 8 days Wed 1/22/20 Mon 2/10/2040 Construct Temporary Inlet at 70+2512 days Mon 2/10/20 Thu 3/5/2041 Water Season Begins 0 days Wed 4/15/20 Wed 4/15/2042 2020 Water Season 78.1 daysWed 4/15/20 Thu 10/1/2043 Grading/Surface Restoration 1+00 to 70+2540 days Mon 3/23/20 Wed 6/17/2044 2020 Water Season Ends 0 days Thu 10/1/20 Thu 10/1/2045 Waterdown 8 days Thu 10/1/20 Tue 10/20/2046 ESC 70+25 to 87+50 2 days Thu 10/1/20 Tue 10/6/2047 Demo 70+25 to 87+50 3.5 days Tue 10/20/20 Tue 10/27/2048 Rebuild Culvert at Roca 1 day Tue 10/27/20 Thu 10/29/2049 Excavate/Construct 70+25 to 87+504 days Thu 10/29/20 Mon 11/9/2050 Leonard St Xing 1 day Mon 11/9/20 Tue 11/10/2051 ESC 87+50 to 104+25 2 days Tue 10/27/20 Mon 11/2/2052 Demo 87+50 to 104+25 3.5 days Mon 11/2/20 Mon 11/9/2053 Excavate/Construct 87+50 to 104+254 days Tue 11/10/20 Wed 11/18/2054 ESC 104+25 to 108+00 0.5 days Mon 11/9/20 Tue 11/10/2055 Demo 104+25 to 108+00 1 day Tue 11/10/20 Wed 11/11/2056 Excavate/construct 104+25 to 108+002 days Wed 11/18/20Mon 11/30/2057 Construct Inlet 16 days Mon 11/30/20Tue 1/12/2158 Grading/Surface Restoration 70+25 to 108+0020 days Tue 1/12/21 Wed 2/24/2159 Punch List 24 days Wed 2/24/21 Mon 4/19/2160 Final Seeding/Planting 25 days Mon 4/19/21 Mon 6/14/2161 2021 Water Season Starts 0 days Thu 4/15/21 Thu 4/15/21
4/15
10/1
4/15
Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Ashland Canal Preliminary Construction Schedule 'B'
Page 2 Figure 8-2
WellerBasin
BeachBasin
NorthBasin
RocaBasin
Interceptedby CityStorm
Interceptedby City Storm
1
2
3
4
5
6
7
Sources: Esri, HERE, Garmin, Intermap, increment P Corp., GEBCO, USGS, FAO, NPS, NRCAN, GeoBase, IGN, Kadaster NL, Ordnance Survey, Esri Japan,METI, Esri China (Hong Kong), swisstopo, © OpenStreetMap contributors, and the GIS User Community
H:\35
22-01
Ashla
nd C
anal
Piping
\GIS\
Appe
ndix
C Dr
ainag
e Ove
rview
Map
.mxd
LegendXINGS
Intercepted by City Storm
Runs into Existing Canal
Drains into Existing Culverts
Ashland Canal
Ashland Canal (Pipe)
0 0.1 0.2Miles
Hydraflow Table of Contents Basins (N M S).gpw
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Watershed Model Schematic..................................................................................... 1
Hydrograph Return Period Recap............................................................................. 2
2 - YearSummary Report......................................................................................................................... 3Hydrograph Reports................................................................................................................... 4
Hydrograph No. 1, SCS Runoff, North Basin........................................................................... 4TR-55 Tc Worksheet............................................................................................................ 5
Hydrograph No. 2, SCS Runoff, Beach Basin.......................................................................... 6TR-55 Tc Worksheet............................................................................................................ 7
Hydrograph No. 3, SCS Runoff, Roca Basin............................................................................ 8TR-55 Tc Worksheet............................................................................................................ 9
Hydrograph No. 4, SCS Runoff, Weller Basin........................................................................ 10TR-55 Tc Worksheet.......................................................................................................... 11
10 - YearSummary Report....................................................................................................................... 12Hydrograph Reports................................................................................................................. 13
Hydrograph No. 1, SCS Runoff, North Basin......................................................................... 13Hydrograph No. 2, SCS Runoff, Beach Basin........................................................................ 14Hydrograph No. 3, SCS Runoff, Roca Basin.......................................................................... 15Hydrograph No. 4, SCS Runoff, Weller Basin........................................................................ 16
25 - YearSummary Report....................................................................................................................... 17Hydrograph Reports................................................................................................................. 18
Hydrograph No. 1, SCS Runoff, North Basin......................................................................... 18Hydrograph No. 2, SCS Runoff, Beach Basin........................................................................ 19Hydrograph No. 3, SCS Runoff, Roca Basin.......................................................................... 20Hydrograph No. 4, SCS Runoff, Weller Basin........................................................................ 21
50 - YearSummary Report....................................................................................................................... 22Hydrograph Reports................................................................................................................. 23
Hydrograph No. 1, SCS Runoff, North Basin......................................................................... 23Hydrograph No. 2, SCS Runoff, Beach Basin........................................................................ 24Hydrograph No. 3, SCS Runoff, Roca Basin.......................................................................... 25Hydrograph No. 4, SCS Runoff, Weller Basin........................................................................ 26
100 - YearSummary Report....................................................................................................................... 27Hydrograph Reports................................................................................................................. 28
Hydrograph No. 1, SCS Runoff, North Basin......................................................................... 28Hydrograph No. 2, SCS Runoff, Beach Basin........................................................................ 29Hydrograph No. 3, SCS Runoff, Roca Basin.......................................................................... 30Hydrograph No. 4, SCS Runoff, Weller Basin........................................................................ 31
1 - North Basin 2 - Beach Basin 3 - Roca Basin 4 - Weller Basin
1
Watershed Model SchematicHydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Project: Basins (N M S).gpw Friday, 08 / 31 / 2018
Hyd. Origin Description
Legend
1 SCS Runoff North Basin
2 SCS Runoff Beach Basin
3 SCS Runoff Roca Basin
4 SCS Runoff Weller Basin
Hydrograph Return Period Recap
2
Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph
No. type hyd(s) Description
(origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr
1 SCS Runoff ------ ------- 0.331 ------- ------- 0.508 0.857 1.214 1.958 North Basin
2 SCS Runoff ------ ------- 0.269 ------- ------- 0.435 0.769 0.920 1.314 Beach Basin
3 SCS Runoff ------ ------- 2.409 ------- ------- 3.542 9.875 13.19 18.70 Roca Basin
4 SCS Runoff ------ ------- 0.074 ------- ------- 0.109 0.258 0.366 0.553 Weller Basin
Proj. file: Basins (N M S).gpw Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Summary Report
3
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.331 2 1176 14,528 ------ ------ ------ North Basin
2 SCS Runoff 0.269 2 1248 10,379 ------ ------ ------ Beach Basin
3 SCS Runoff 2.409 2 1058 123,743 ------ ------ ------ Roca Basin
4 SCS Runoff 0.074 2 1104 3,547 ------ ------ ------ Weller Basin
Basins (N M S).gpw Return Period: 2 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 1
North Basin
Hydrograph type = SCS Runoff Peak discharge = 0.331 cfsStorm frequency = 2 yrs Time to peak = 1176 minTime interval = 2 min Hyd. volume = 14,528 cuftDrainage area = 29.800 ac Curve number = 68.1Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 39.90 minTotal precip. = 1.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
4
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
North Basin
Hyd. No. 1 -- 2 Year
Hyd No. 1
TR55 Tc Worksheet5
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hyd. No. 1
North Basin
Description A B C Totals
Sheet FlowManning's n-value = 0.400 0.011 0.011Flow length (ft) = 293.0 0.0 0.0Two-year 24-hr precip. (in) = 1.80 0.00 0.00Land slope (%) = 9.00 0.00 0.00
Travel Time (min) = 37.07 + 0.00 + 0.00 = 37.07
Shallow Concentrated FlowFlow length (ft) = 1638.00 0.00 0.00Watercourse slope (%) = 36.00 0.00 0.00Surface description = Unpaved Paved PavedAverage velocity (ft/s) =9.68 0.00 0.00
Travel Time (min) = 2.82 + 0.00 + 0.00 = 2.82
Channel FlowX sectional flow area (sqft) = 0.00 0.00 0.00Wetted perimeter (ft) = 0.00 0.00 0.00Channel slope (%) = 0.00 0.00 0.00Manning's n-value = 0.015 0.015 0.015Velocity (ft/s) =0.00
0.000.00
Flow length (ft) ({0})0.0 0.0 0.0
Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00
Total Travel Time, Tc .............................................................................. 39.90 min
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 2
Beach Basin
Hydrograph type = SCS Runoff Peak discharge = 0.269 cfsStorm frequency = 2 yrs Time to peak = 1248 minTime interval = 2 min Hyd. volume = 10,379 cuftDrainage area = 32.200 ac Curve number = 65.3Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.50 minTotal precip. = 1.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
6
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
Beach Basin
Hyd. No. 2 -- 2 Year
Hyd No. 2
TR55 Tc Worksheet7
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hyd. No. 2
Beach Basin
Description A B C Totals
Sheet FlowManning's n-value = 0.400 0.011 0.011Flow length (ft) = 287.0 0.0 0.0Two-year 24-hr precip. (in) = 1.80 0.00 0.00Land slope (%) = 13.00 0.00 0.00
Travel Time (min) = 31.48 + 0.00 + 0.00 = 31.48
Shallow Concentrated FlowFlow length (ft) = 1703.00 0.00 0.00Watercourse slope (%) = 35.00 0.00 0.00Surface description = Unpaved Paved PavedAverage velocity (ft/s) =9.55 0.00 0.00
Travel Time (min) = 2.97 + 0.00 + 0.00 = 2.97
Channel FlowX sectional flow area (sqft) = 0.00 0.00 0.00Wetted perimeter (ft) = 0.00 0.00 0.00Channel slope (%) = 0.00 0.00 0.00Manning's n-value = 0.015 0.015 0.015Velocity (ft/s) =0.00
0.000.00
Flow length (ft) ({0})0.0 0.0 0.0
Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00
Total Travel Time, Tc .............................................................................. 34.50 min
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 3
Roca Basin
Hydrograph type = SCS Runoff Peak discharge = 2.409 cfsStorm frequency = 2 yrs Time to peak = 1058 minTime interval = 2 min Hyd. volume = 123,743 cuftDrainage area = 149.000 ac Curve number = 72.8Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.00 minTotal precip. = 1.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
8
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
3.00 3.00
Q (cfs)
Time (min)
Roca Basin
Hyd. No. 3 -- 2 Year
Hyd No. 3
TR55 Tc Worksheet9
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hyd. No. 3
Roca Basin
Description A B C Totals
Sheet FlowManning's n-value = 0.400 0.011 0.011Flow length (ft) = 300.0 0.0 0.0Two-year 24-hr precip. (in) = 1.80 0.00 0.00Land slope (%) = 23.00 0.00 0.00
Travel Time (min) = 25.96 + 0.00 + 0.00 = 25.96
Shallow Concentrated FlowFlow length (ft) = 3478.00 0.00 0.00Watercourse slope (%) = 20.00 0.00 0.00Surface description = Unpaved Paved PavedAverage velocity (ft/s) =7.22 0.00 0.00
Travel Time (min) = 8.03 + 0.00 + 0.00 = 8.03
Channel FlowX sectional flow area (sqft) = 0.00 0.00 0.00Wetted perimeter (ft) = 0.00 0.00 0.00Channel slope (%) = 0.00 0.00 0.00Manning's n-value = 0.015 0.015 0.015Velocity (ft/s) =0.00
0.000.00
Flow length (ft) ({0})0.0 0.0 0.0
Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00
Total Travel Time, Tc .............................................................................. 34.00 min
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 4
Weller Basin
Hydrograph type = SCS Runoff Peak discharge = 0.074 cfsStorm frequency = 2 yrs Time to peak = 1104 minTime interval = 2 min Hyd. volume = 3,547 cuftDrainage area = 5.300 ac Curve number = 70.7Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 30.20 minTotal precip. = 1.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
10
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.01 0.01
0.02 0.02
0.03 0.03
0.04 0.04
0.05 0.05
0.06 0.06
0.07 0.07
0.08 0.08
0.09 0.09
0.10 0.10
Q (cfs)
Time (min)
Weller Basin
Hyd. No. 4 -- 2 Year
Hyd No. 4
TR55 Tc Worksheet11
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hyd. No. 4
Weller Basin
Description A B C Totals
Sheet FlowManning's n-value = 0.400 0.011 0.011Flow length (ft) = 300.0 0.0 0.0Two-year 24-hr precip. (in) = 1.80 0.00 0.00Land slope (%) = 16.70 0.00 0.00
Travel Time (min) = 29.50 + 0.00 + 0.00 = 29.50
Shallow Concentrated FlowFlow length (ft) = 473.00 0.00 0.00Watercourse slope (%) = 53.10 0.00 0.00Surface description = Unpaved Paved PavedAverage velocity (ft/s) =11.76 0.00 0.00
Travel Time (min) = 0.67 + 0.00 + 0.00 = 0.67
Channel FlowX sectional flow area (sqft) = 0.00 0.00 0.00Wetted perimeter (ft) = 0.00 0.00 0.00Channel slope (%) = 0.00 0.00 0.00Manning's n-value = 0.015 0.015 0.015Velocity (ft/s) =0.00
0.000.00
Flow length (ft) ({0})0.0 0.0 0.0
Travel Time (min) = 0.00 + 0.00 + 0.00 = 0.00
Total Travel Time, Tc .............................................................................. 30.20 min
Hydrograph Summary Report
12
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.508 2 1094 25,028 ------ ------ ------ North Basin
2 SCS Runoff 0.435 2 1158 19,574 ------ ------ ------ Beach Basin
3 SCS Runoff 3.542 2 542 192,277 ------ ------ ------ Roca Basin
4 SCS Runoff 0.109 2 1030 5,740 ------ ------ ------ Weller Basin
Basins (N M S).gpw Return Period: 10 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 1
North Basin
Hydrograph type = SCS Runoff Peak discharge = 0.508 cfsStorm frequency = 10 yrs Time to peak = 1094 minTime interval = 2 min Hyd. volume = 25,028 cuftDrainage area = 29.800 ac Curve number = 68.1Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 39.90 minTotal precip. = 2.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
13
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (min)
North Basin
Hyd. No. 1 -- 10 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 2
Beach Basin
Hydrograph type = SCS Runoff Peak discharge = 0.435 cfsStorm frequency = 10 yrs Time to peak = 1158 minTime interval = 2 min Hyd. volume = 19,574 cuftDrainage area = 32.200 ac Curve number = 65.3Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.50 minTotal precip. = 2.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
14
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
Beach Basin
Hyd. No. 2 -- 10 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 3
Roca Basin
Hydrograph type = SCS Runoff Peak discharge = 3.542 cfsStorm frequency = 10 yrs Time to peak = 542 minTime interval = 2 min Hyd. volume = 192,277 cuftDrainage area = 149.000 ac Curve number = 72.8Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.00 minTotal precip. = 2.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
15
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
3.00 3.00
4.00 4.00
Q (cfs)
Time (min)
Roca Basin
Hyd. No. 3 -- 10 Year
Hyd No. 3
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 4
Weller Basin
Hydrograph type = SCS Runoff Peak discharge = 0.109 cfsStorm frequency = 10 yrs Time to peak = 1030 minTime interval = 2 min Hyd. volume = 5,740 cuftDrainage area = 5.300 ac Curve number = 70.7Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 30.20 minTotal precip. = 2.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
16
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
Weller Basin
Hyd. No. 4 -- 10 Year
Hyd No. 4
Hydrograph Summary Report
17
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.857 2 996 47,139 ------ ------ ------ North Basin
2 SCS Runoff 0.769 2 1050 39,857 ------ ------ ------ Beach Basin
3 SCS Runoff 9.875 2 504 328,417 ------ ------ ------ Roca Basin
4 SCS Runoff 0.258 2 502 10,202 ------ ------ ------ Weller Basin
Basins (N M S).gpw Return Period: 25 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 1
North Basin
Hydrograph type = SCS Runoff Peak discharge = 0.857 cfsStorm frequency = 25 yrs Time to peak = 996 minTime interval = 2 min Hyd. volume = 47,139 cuftDrainage area = 29.800 ac Curve number = 68.1Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 39.90 minTotal precip. = 2.60 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
18
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (min)
North Basin
Hyd. No. 1 -- 25 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 2
Beach Basin
Hydrograph type = SCS Runoff Peak discharge = 0.769 cfsStorm frequency = 25 yrs Time to peak = 1050 minTime interval = 2 min Hyd. volume = 39,857 cuftDrainage area = 32.200 ac Curve number = 65.3Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.50 minTotal precip. = 2.60 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
19
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (min)
Beach Basin
Hyd. No. 2 -- 25 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 3
Roca Basin
Hydrograph type = SCS Runoff Peak discharge = 9.875 cfsStorm frequency = 25 yrs Time to peak = 504 minTime interval = 2 min Hyd. volume = 328,417 cuftDrainage area = 149.000 ac Curve number = 72.8Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.00 minTotal precip. = 2.60 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
20
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
2.00 2.00
4.00 4.00
6.00 6.00
8.00 8.00
10.00 10.00
Q (cfs)
Time (min)
Roca Basin
Hyd. No. 3 -- 25 Year
Hyd No. 3
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 4
Weller Basin
Hydrograph type = SCS Runoff Peak discharge = 0.258 cfsStorm frequency = 25 yrs Time to peak = 502 minTime interval = 2 min Hyd. volume = 10,202 cuftDrainage area = 5.300 ac Curve number = 70.7Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 30.20 minTotal precip. = 2.60 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
21
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
Weller Basin
Hyd. No. 4 -- 25 Year
Hyd No. 4
Hydrograph Summary Report
22
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 1.214 2 522 57,350 ------ ------ ------ North Basin
2 SCS Runoff 0.920 2 1016 49,459 ------ ------ ------ Beach Basin
3 SCS Runoff 13.19 2 502 389,219 ------ ------ ------ Roca Basin
4 SCS Runoff 0.366 2 498 12,223 ------ ------ ------ Weller Basin
Basins (N M S).gpw Return Period: 50 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 1
North Basin
Hydrograph type = SCS Runoff Peak discharge = 1.214 cfsStorm frequency = 50 yrs Time to peak = 522 minTime interval = 2 min Hyd. volume = 57,350 cuftDrainage area = 29.800 ac Curve number = 68.1Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 39.90 minTotal precip. = 2.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
23
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
Q (cfs)
Time (min)
North Basin
Hyd. No. 1 -- 50 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 2
Beach Basin
Hydrograph type = SCS Runoff Peak discharge = 0.920 cfsStorm frequency = 50 yrs Time to peak = 1016 minTime interval = 2 min Hyd. volume = 49,459 cuftDrainage area = 32.200 ac Curve number = 65.3Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.50 minTotal precip. = 2.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
24
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (min)
Beach Basin
Hyd. No. 2 -- 50 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 3
Roca Basin
Hydrograph type = SCS Runoff Peak discharge = 13.19 cfsStorm frequency = 50 yrs Time to peak = 502 minTime interval = 2 min Hyd. volume = 389,219 cuftDrainage area = 149.000 ac Curve number = 72.8Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.00 minTotal precip. = 2.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
25
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
2.00 2.00
4.00 4.00
6.00 6.00
8.00 8.00
10.00 10.00
12.00 12.00
14.00 14.00
Q (cfs)
Time (min)
Roca Basin
Hyd. No. 3 -- 50 Year
Hyd No. 3
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 4
Weller Basin
Hydrograph type = SCS Runoff Peak discharge = 0.366 cfsStorm frequency = 50 yrs Time to peak = 498 minTime interval = 2 min Hyd. volume = 12,223 cuftDrainage area = 5.300 ac Curve number = 70.7Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 30.20 minTotal precip. = 2.80 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
26
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.05 0.05
0.10 0.10
0.15 0.15
0.20 0.20
0.25 0.25
0.30 0.30
0.35 0.35
0.40 0.40
0.45 0.45
0.50 0.50
Q (cfs)
Time (min)
Weller Basin
Hyd. No. 4 -- 50 Year
Hyd No. 4
Hydrograph Summary Report
27
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 1.958 2 512 73,920 ------ ------ ------ North Basin
2 SCS Runoff 1.314 2 518 65,237 ------ ------ ------ Beach Basin
3 SCS Runoff 18.70 2 500 486,109 ------ ------ ------ Roca Basin
4 SCS Runoff 0.553 2 496 15,468 ------ ------ ------ Weller Basin
Basins (N M S).gpw Return Period: 100 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 1
North Basin
Hydrograph type = SCS Runoff Peak discharge = 1.958 cfsStorm frequency = 100 yrs Time to peak = 512 minTime interval = 2 min Hyd. volume = 73,920 cuftDrainage area = 29.800 ac Curve number = 68.1Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 39.90 minTotal precip. = 3.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
28
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
Q (cfs)
Time (min)
North Basin
Hyd. No. 1 -- 100 Year
Hyd No. 1
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 2
Beach Basin
Hydrograph type = SCS Runoff Peak discharge = 1.314 cfsStorm frequency = 100 yrs Time to peak = 518 minTime interval = 2 min Hyd. volume = 65,237 cuftDrainage area = 32.200 ac Curve number = 65.3Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.50 minTotal precip. = 3.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
29
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
1.00 1.00
2.00 2.00
Q (cfs)
Time (min)
Beach Basin
Hyd. No. 2 -- 100 Year
Hyd No. 2
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 3
Roca Basin
Hydrograph type = SCS Runoff Peak discharge = 18.70 cfsStorm frequency = 100 yrs Time to peak = 500 minTime interval = 2 min Hyd. volume = 486,109 cuftDrainage area = 149.000 ac Curve number = 72.8Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 34.00 minTotal precip. = 3.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
30
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
3.00 3.00
6.00 6.00
9.00 9.00
12.00 12.00
15.00 15.00
18.00 18.00
21.00 21.00
Q (cfs)
Time (min)
Roca Basin
Hyd. No. 3 -- 100 Year
Hyd No. 3
Hydrograph Report
Hydraflow Hydrographs Extension for AutoCAD® Civil 3D® 2018 by Autodesk, Inc. v12 Friday, 08 / 31 / 2018
Hyd. No. 4
Weller Basin
Hydrograph type = SCS Runoff Peak discharge = 0.553 cfsStorm frequency = 100 yrs Time to peak = 496 minTime interval = 2 min Hyd. volume = 15,468 cuftDrainage area = 5.300 ac Curve number = 70.7Basin Slope = 0.0 % Hydraulic length = 0 ftTc method = TR55 Time of conc. (Tc) = 30.20 minTotal precip. = 3.10 in Distribution = Type IAStorm duration = 24 hrs Shape factor = 484
31
0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560
Q (cfs)
0.00 0.00
0.10 0.10
0.20 0.20
0.30 0.30
0.40 0.40
0.50 0.50
0.60 0.60
0.70 0.70
0.80 0.80
0.90 0.90
1.00 1.00
Q (cfs)
Time (min)
Weller Basin
Hyd. No. 4 -- 100 Year
Hyd No. 4
1 2 3 4 5 6 7
1
Watershed Model SchematicHydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Project: Storm Flow Into Canal.gpw Friday, 08 / 31 / 2018
Hydrograph Return Period Recap2
Hyd. Hydrograph Inflow Peak Outflow (cfs) Hydrograph
No. type hyd(s) Description
(origin) 1-yr 2-yr 3-yr 5-yr 10-yr 25-yr 50-yr 100-yr
1 SCS Runoff ------ ------- 0.068 ------- ------- 0.156 0.352 0.445 0.600 Basin 1
2 SCS Runoff ------ ------- 0.007 ------- ------- 0.015 0.033 0.042 0.057 Basin 2
3 SCS Runoff ------ ------- 0.027 ------- ------- 0.061 0.137 0.174 0.234 Basin 3
4 SCS Runoff ------ ------- 0.009 ------- ------- 0.021 0.047 0.059 0.079 Basin 4
5 SCS Runoff ------ ------- 0.009 ------- ------- 0.021 0.048 0.060 0.081 Basin 5
6 SCS Runoff ------ ------- 0.000 ------- ------- 0.000 0.020 0.031 0.049 Basin 6
7 SCS Runoff ------ ------- 0.000 ------- ------- 0.000 0.046 0.071 0.114 Basin 7
Proj. file: Storm Flow Into Canal.gpw Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydrograph Summary Report3
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.068 2 1440 1,086 ------ ------ ------ Basin 1
2 SCS Runoff 0.007 2 1440 103 ------ ------ ------ Basin 2
3 SCS Runoff 0.027 2 1440 424 ------ ------ ------ Basin 3
4 SCS Runoff 0.009 2 1440 144 ------ ------ ------ Basin 4
5 SCS Runoff 0.009 2 1440 147 ------ ------ ------ Basin 5
6 SCS Runoff 0.000 2 n/a 0 ------ ------ ------ Basin 6
7 SCS Runoff 0.000 2 n/a 0 ------ ------ ------ Basin 7
Storm Flow Into Canal.gpw Return Period: 2 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydrograph Summary Report4
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.156 2 1372 4,311 ------ ------ ------ Basin 1
2 SCS Runoff 0.015 2 1366 409 ------ ------ ------ Basin 2
3 SCS Runoff 0.061 2 1366 1,682 ------ ------ ------ Basin 3
4 SCS Runoff 0.021 2 1366 570 ------ ------ ------ Basin 4
5 SCS Runoff 0.021 2 1366 585 ------ ------ ------ Basin 5
6 SCS Runoff 0.000 2 n/a 0 ------ ------ ------ Basin 6
7 SCS Runoff 0.000 2 n/a 0 ------ ------ ------ Basin 7
Storm Flow Into Canal.gpw Return Period: 10 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydrograph Summary Report5
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.352 2 1220 13,835 ------ ------ ------ Basin 1
2 SCS Runoff 0.033 2 1214 1,314 ------ ------ ------ Basin 2
3 SCS Runoff 0.137 2 1214 5,397 ------ ------ ------ Basin 3
4 SCS Runoff 0.047 2 1214 1,830 ------ ------ ------ Basin 4
5 SCS Runoff 0.048 2 1214 1,877 ------ ------ ------ Basin 5
6 SCS Runoff 0.020 2 1440 327 ------ ------ ------ Basin 6
7 SCS Runoff 0.046 2 1440 754 ------ ------ ------ Basin 7
Storm Flow Into Canal.gpw Return Period: 25 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydrograph Summary Report6
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.445 2 1174 18,932 ------ ------ ------ Basin 1
2 SCS Runoff 0.042 2 1170 1,798 ------ ------ ------ Basin 2
3 SCS Runoff 0.174 2 1170 7,385 ------ ------ ------ Basin 3
4 SCS Runoff 0.059 2 1170 2,505 ------ ------ ------ Basin 4
5 SCS Runoff 0.060 2 1170 2,569 ------ ------ ------ Basin 5
6 SCS Runoff 0.031 2 1432 686 ------ ------ ------ Basin 6
7 SCS Runoff 0.071 2 1426 1,583 ------ ------ ------ Basin 7
Storm Flow Into Canal.gpw Return Period: 50 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydrograph Summary Report7
Hyd. Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph
No. type flow interval Peak volume hyd(s) elevation strge used Description
(origin) (cfs) (min) (min) (cuft) (ft) (cuft)
1 SCS Runoff 0.600 2 1120 27,807 ------ ------ ------ Basin 1
2 SCS Runoff 0.057 2 1112 2,641 ------ ------ ------ Basin 2
3 SCS Runoff 0.234 2 1112 10,847 ------ ------ ------ Basin 3
4 SCS Runoff 0.079 2 1112 3,679 ------ ------ ------ Basin 4
5 SCS Runoff 0.081 2 1112 3,773 ------ ------ ------ Basin 5
6 SCS Runoff 0.049 2 1344 1,451 ------ ------ ------ Basin 6
7 SCS Runoff 0.114 2 1342 3,351 ------ ------ ------ Basin 7
Storm Flow Into Canal.gpw Return Period: 100 Year Friday, 08 / 31 / 2018
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020
Hydraflow Table of Contents Storm Flow Into Canal.gpw
Hydraflow Hydrographs Extension for Autodesk® Civil 3D® 2019 by Autodesk, Inc. v2020 Friday, 08 / 31 / 2018
Watershed Model Schematic...................................................................................... 1
Hydrograph Return Period Recap............................................................................. 2
2 - YearSummary Report......................................................................................................................... 3
10 - YearSummary Report......................................................................................................................... 4
25 - YearSummary Report......................................................................................................................... 5
50 - YearSummary Report......................................................................................................................... 6
100 - YearSummary Report......................................................................................................................... 7
Channel ReportHydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Aug 31 2018
Starlight Monitoring Station
TrapezoidalBottom Width (ft) = 4.59Side Slopes (z:1) = 0.50, 0.50Total Depth (ft) = 1.50Invert Elev (ft) = 2325.64Slope (%) = 0.06N-Value = 0.024
CalculationsCompute by: Q vs DepthNo. Increments = 15
HighlightedDepth (ft) = 1.00Q (cfs) = 6.347Area (sqft) = 5.09Velocity (ft/s) = 1.25Wetted Perim (ft) = 6.83Crit Depth, Yc (ft) = 0.39Top Width (ft) = 5.59EGL (ft) = 1.02
0 1 2 3 4 5 6 7 8 9
Elev (ft) Depth (ft)Section
2325.00 -0.64
2325.50 -0.14
2326.00 0.36
2326.50 0.86
2327.00 1.36
2327.50 1.86
2328.00 2.36
Reach (ft)
Culvert ReportHydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Aug 31 2018
Weller Crossing 24 Inch Culvert
Invert Elev Dn (ft) = 2305.60Pipe Length (ft) = 50.22Slope (%) = 10.00Invert Elev Up (ft) = 2310.62Rise (in) = 24.0Shape = CircularSpan (in) = 24.0No. Barrels = 1n-Value = 0.013Culvert Type = Circular ConcreteCulvert Entrance = Groove end w/headwall (C)Coeff. K,M,c,Y,k = 0.0018, 2, 0.0292, 0.74, 0.2
EmbankmentTop Elevation (ft) = 2316.25Top Width (ft) = 20.00Crest Width (ft) = 0.00
CalculationsQmin (cfs) = 0.01Qmax (cfs) = 0.37Tailwater Elev (ft) = (dc+D)/2
HighlightedQtotal (cfs) = 0.37Qpipe (cfs) = 0.37Qovertop (cfs) = 0.00Veloc Dn (ft/s) = 0.21Veloc Up (ft/s) = 2.14HGL Dn (ft) = 2306.70HGL Up (ft) = 2310.83Hw Elev (ft) = 2310.91Hw/D (ft) = 0.15Flow Regime = Outlet Control
Culvert ReportHydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Aug 31 2018
North Basin 24 Inch (Future) Culvert
Invert Elev Dn (ft) = 2312.61Pipe Length (ft) = 58.00Slope (%) = 0.67Invert Elev Up (ft) = 2313.00Rise (in) = 24.0Shape = CircularSpan (in) = 24.0No. Barrels = 1n-Value = 0.016Culvert Type = Circular Corrugate Metal PipeCulvert Entrance = ProjectingCoeff. K,M,c,Y,k = 0.034, 1.5, 0.0553, 0.54, 0.9
EmbankmentTop Elevation (ft) = 2316.00Top Width (ft) = 30.00Crest Width (ft) = 0.00
CalculationsQmin (cfs) = 0.00Qmax (cfs) = 1.21Tailwater Elev (ft) = (dc+D)/2
HighlightedQtotal (cfs) = 1.20Qpipe (cfs) = 1.20Qovertop (cfs) = 0.00Veloc Dn (ft/s) = 0.62Veloc Up (ft/s) = 0.99HGL Dn (ft) = 2313.80HGL Up (ft) = 2313.82Hw Elev (ft) = 2313.85Hw/D (ft) = 0.42Flow Regime = Outlet Control
Culvert ReportHydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Aug 31 2018
Beach Creek 24 Inch Culvert
Invert Elev Dn (ft) = 2314.22Pipe Length (ft) = 43.32Slope (%) = 3.99Invert Elev Up (ft) = 2315.95Rise (in) = 24.0Shape = CircularSpan (in) = 24.0No. Barrels = 1n-Value = 0.015Culvert Type = Circular Corrugate Metal PipeCulvert Entrance = ProjectingCoeff. K,M,c,Y,k = 0.034, 1.5, 0.0553, 0.54, 0.9
EmbankmentTop Elevation (ft) = 2322.00Top Width (ft) = 20.00Crest Width (ft) = 0.00
CalculationsQmin (cfs) = 0.00Qmax (cfs) = 0.92Tailwater Elev (ft) = (dc+D)/2
HighlightedQtotal (cfs) = 0.90Qpipe (cfs) = 0.90Qovertop (cfs) = 0.00Veloc Dn (ft/s) = 0.47Veloc Up (ft/s) = 2.70HGL Dn (ft) = 2315.38HGL Up (ft) = 2316.28Hw Elev (ft) = 2316.49Hw/D (ft) = 0.27Flow Regime = Outlet Control
Culvert ReportHydraflow Express Extension for Autodesk® AutoCAD® Civil 3D® by Autodesk, Inc. Friday, Aug 31 2018
Roca Creek 24 Inch Culvert
Invert Elev Dn (ft) = 2315.81Pipe Length (ft) = 30.83Slope (%) = 19.40Invert Elev Up (ft) = 2321.79Rise (in) = 24.0Shape = CircularSpan (in) = 24.0No. Barrels = 1n-Value = 0.016Culvert Type = Circular Corrugate Metal PipeCulvert Entrance = HeadwallCoeff. K,M,c,Y,k = 0.0078, 2, 0.0379, 0.69, 0.5
EmbankmentTop Elevation (ft) = 2325.00Top Width (ft) = 20.00Crest Width (ft) = 0.00
CalculationsQmin (cfs) = 0.00Qmax (cfs) = 13.00Tailwater Elev (ft) = (dc+D)/2
HighlightedQtotal (cfs) = 13.00Qpipe (cfs) = 13.00Qovertop (cfs) = 0.00Veloc Dn (ft/s) = 4.69Veloc Up (ft/s) = 6.03HGL Dn (ft) = 2317.46HGL Up (ft) = 2323.09Hw Elev (ft) = 2323.59Hw/D (ft) = 0.90Flow Regime = Inlet Control
Prepared by: Adkins Engineering & Survey
Client: City of Ashland
Project: Ashland Canal Piping
Date:
Alignment Name: Proposed Alignment
Station Range: Start: 1+00.0, End: 108+09.4
Point Station Offset Elevation Description (Species, Trunk Dia.(in.), Drip Line Dia.(ft)) Trunk Dia.
8375 01+71.7 -18.43 2316.07 (CEDAR 19 20)CEDAR 19 20 19
8374 02+18.1 -16.13 2313.82 (CEDAR 19 20)CEDAR 19 20 19
8373 02+59.6 -18.36 2317.01 (PINE 20 20)PINE 20 20 20
8294 03+45.7 -9.24 2319.40 (DECID 18 35)DECID 18 35 18
8293 04+03.1 -13.45 2319.17 (DECID 21 35)DECID 21 35 21
8318 06+17.5 9.94 2335.94 (DECID 21 40)DECID 21 40 21
8155 06+64.7 4.47 2320.04 (DECID 8 20)DECID 8 20 8
8153 06+64.7 -13.62 2320.87 (PINE 18 25)PINE 18 25 18
8157 06+68.2 0.29 2315.78 (PINE 11 20)PINE 11 20 11
8156 06+69.7 5.37 2320.31 (DECID 9 25)DECID 9 25 9
8152 06+81.6 -19.77 2315.00 (DECID 12 20)DECID 12 20 12
8154 06+81.9 -21.31 2320.78 (PINE 8 25)PINE 8 25 8
8158 06+85.0 5.63 2316.46 (DECID 10 20)DECID 10 20 10
8159 06+88.7 13.68 2322.53 (DECID 10 20)DECID 10 20 10
8160 06+96.4 16.47 2322.70 (DECID 8 15)DECID 8 15 8
8161 07+00.5 15.31 2322.73 (DECID 6 15)DECID 6 15 6
8162 07+09.9 2.76 2328.39 (PINE 7 20)PINE 7 20 7
8163 07+19.3 -0.86 2325.14 (PINE 15 25)PINE 15 25 15
8151 07+46.3 -15.80 2318.31 (DECID 19 30)DECID 19 30 19
8164 07+47.5 -9.85 2318.42 (PINE 8 25)PINE 8 25 8
8165 07+66.2 1.75 2320.36 (PINE 10 20)PINE 10 20 10
8149 07+72.2 -20.59 2318.84 (PINE 18 20)PINE 18 20 18
8150 07+74.9 -24.98 2316.44 (PINE 11 20)PINE 11 20 11
8166 07+96.8 12.77 2319.38 (DECID 7 20)DECID 7 20 7
8168 07+99.6 7.01 2319.65 (PINE 6 15)PINE 6 15 6
8015 08+02.5 16.06 2326.02 (PINE 20 25)PINE 20 25 20
8167 08+06.1 6.88 2319.18 (PINE 7 20)PINE 7 20 7
8016 08+17.6 17.83 2326.48 (DECID 6 15)DECID 6 15 6
8017 08+23.3 17.54 2332.22 (DECID 9 25)DECID 9 25 9
8018 08+35.3 16.73 2334.23 (PINE 16 25)PINE 16 25 16
Tree Station & Offset Report
Description: Station and offset of trees in reference to the proposed alignment. Highlighted cells are within
10' of the proposed alignment. There are 284 trees within 10' of the proposed alignment. Of the trees within
10' of the alignment 195 have a trunk that is 6"-12" in diameter, 75 are 12"-24" and 14 are over 24".
11/28/2018
PAGE 1 OF 20
8019 08+44.0 11.99 2330.98 (PINE 18 20)PINE 18 20 18
8020 08+46.0 15.46 2330.01 (PINE 27 25)PINE 27 25 27
8021 08+52.4 10.90 2330.83 (PINE 9 15)PINE 9 15 9
8022 08+52.9 14.95 2331.14 (PINE 17 30)PINE 17 30 17
8023 08+55.7 17.50 2329.34 (PINE 23 30)PINE 23 30 23
8088 08+72.7 -14.78 2317.28 (DECID 19 30)DECID 19 30 19
8033 09+06.7 6.75 2322.11 (DECID 9 20)DECID 9 20 9
8089 09+12.1 -18.39 2317.56 (PINE 23 30)PINE 23 30 23
8090 09+21.8 -13.82 2317.45 (DECID 6 10)DECID 6 10 6
8091 09+36.4 -19.23 2319.82 (PINE 24 30)PINE 24 30 24
8092 09+41.4 -15.33 2317.91 (MAD 9 20)MAD 9 20 9
8093 09+44.8 -15.16 2316.84 (MAD 7 20)MAD 7 20 7
8031 09+50.9 16.03 2326.83 (DECID 8 25)DECID 8 25 8
8029 09+62.8 15.94 2334.98 (DECID 8 20)DECID 8 20 8
8026 09+73.7 6.93 2318.41 (DECID 10 10)DECID 10 10 10
8027 09+74.2 17.66 2326.24 (DECID 15 25)DECID 15 25 15
8028 09+75.2 3.74 2317.78 (CEDAR 7 20)CEDAR 7 20 7
7986 09+85.6 -11.97 2317.45 (DECID 17 35)DECID 17 35 17
7985 10+17.2 -15.57 2316.39 (DECID 19 35)DECID 19 35 19
7984 10+23.3 -16.79 2315.95 (DECID 11 25)DECID 11 25 11
7940 10+31.6 18.05 2334.11 (PINE 28 35)PINE 28 35 28
7941 10+70.5 15.11 2324.56 (DECID 6 15)DECID 6 15 6
7980 10+73.9 5.76 2316.61 (DECID 6 10)DECID 6 10 6
7983 10+81.4 -13.77 2315.71 (DECID 14 20)DECID 14 20 14
7981 10+81.7 7.94 2322.18 (DECID 6 10)DECID 6 10 6
7979 10+83.4 8.91 2318.82 (DECID 6 10)DECID 6 10 6
7942 10+90.8 17.26 2322.18 (DECID 10 15)DECID 10 15 10
7982 11+02.0 -14.96 2314.87 (DECID 13 15)DECID 13 15 13
7886 11+73.8 -9.94 2318.71 (CEDAR 16 25)CEDAR 16 25 16
7887 12+66.3 -11.87 2320.46 (DECID 12 25)DECID 12 25 12
7888 12+69.9 -15.36 2318.61 (CEDAR 16 20)CEDAR 16 20 16
7890 12+84.7 12.96 2324.30 (DECID 16 25)DECID 16 25 16
7889 13+06.2 -17.80 2317.21 (PINE 15 30)PINE 15 30 15
7706 13+11.7 -19.66 2328.34 (PINE 14 25)PINE 14 25 14
7707 13+17.0 -20.20 2328.16 (PINE 7 20)PINE 7 20 7
7708 13+21.0 -22.93 2323.58 (PINE 8 20)PINE 8 20 8
7709 13+23.6 -21.61 2324.02 (PINE 15 25)PINE 15 25 15
7892 13+24.9 14.76 2327.70 (CEDAR 8 20)CEDAR 8 20 8
7891 13+25.5 18.74 2325.16 (DECID 6 25)DECID 6 25 6
7710 13+27.3 -23.58 2323.97 (PINE 8 20)PINE 8 20 8
7893 13+27.9 18.74 2327.66 (DECID 12 25)DECID 12 25 12
7711 13+31.9 -24.41 2313.46 (PINE 8 20)PINE 8 20 8
7802 13+32.0 13.66 2328.27 (DECID 10 20)DECID 10 20 10
7801 13+39.5 9.66 2327.82 (DECID 7 20)DECID 7 20 7
PAGE 2 OF 20
7800 13+47.7 12.89 2327.53 (DECID 6 20)DECID 6 20 6
7798 13+48.4 7.22 2322.61 (DECID 8 20)DECID 8 20 8
7712 13+55.0 -24.19 2322.06 (PINE 21 35)PINE 21 35 21
7799 13+58.0 5.12 2322.48 (DECID 8 20)DECID 8 20 8
7713 13+67.5 -16.70 2333.68 (DECID 11 20)DECID 11 20 11
7797 13+67.8 6.26 2322.34 (DECID 8 20)DECID 8 20 8
7714 13+81.0 -21.91 2322.55 (PINE 10 15)PINE 10 15 10
7796 13+86.6 15.44 2330.31 (DECID 6 20)DECID 6 20 6
7795 13+91.3 5.12 2331.28 (PINE 14 25)PINE 14 25 14
7695 14+00.0 -26.42 2319.17 (PINE 20 25)PINE 20 25 20
7696 14+08.3 -22.05 2321.89 (PINE 29 40)PINE 29 40 29
7794 14+21.3 4.33 2332.78 (PINE 15 25)PINE 15 25 15
7697 14+32.3 -22.76 2320.07 (PINE 6 10)PINE 6 10 6
7793 14+37.6 5.86 2323.30 (PINE 25 25)PINE 25 25 25
7698 14+47.3 -17.53 2317.01 (DECID 13 20)DECID 13 20 13
7699 14+52.4 -25.56 2319.83 (PINE 13 20)PINE 13 20 13
7700 14+65.9 -23.92 2319.82 (CEDAR 16 20)CEDAR 16 20 16
7792 14+72.0 6.05 2335.10 (PINE 18 25)PINE 18 25 18
7659 14+85.0 -21.64 2320.47 (PINE 27 30)PINE 27 30 27
7660 14+93.2 -21.83 2320.32 (PINE 22 30)PINE 22 30 22
7664 15+27.1 -29.60 2332.85 (PINE 23 40)PINE 23 40 23
7686 15+32.2 3.05 2320.84 (PINE 23 25)PINE 23 25 23
7666 15+37.6 -27.98 2319.59 (PINE 31 40)PINE 31 40 31
7665 15+38.0 -27.89 2319.59 (PINE 24 40)PINE 24 40 24
7663 15+43.6 -23.02 2317.37 (PINE 12 25)PINE 12 25 12
7667 15+49.3 -29.93 2334.37 (PINE 11 25)PINE 11 25 11
7668 15+54.8 -31.70 2313.62 (PINE 7 25)PINE 7 25 7
7685 15+55.0 13.31 2321.43 (PINE 18 20)PINE 18 20 18
7669 15+62.9 -25.93 2311.65 (DECID 7 20)DECID 7 20 7
7670 15+76.2 -16.23 2313.91 (DECID 8 20)DECID 8 20 8
7671 15+98.5 -21.50 2315.03 (PINE 18 30)PINE 18 30 18
7672 16+00.9 -19.62 2315.16 (PINE 14 20)PINE 14 20 14
7673 16+04.6 -25.30 2313.83 (PINE 18 30)PINE 18 30 18
7684 16+20.7 -3.19 2320.49 (CEDAR 6 10)CEDAR 6 10 6
7683 16+36.2 -12.09 2320.87 (MAD 7 15)MAD 7 15 7
7682 16+37.0 -13.13 2321.46 (MAD 10 20)MAD 10 20 10
7681 16+47.2 11.51 2323.78 (PINE 27 25)PINE 27 25 27
7680 16+53.5 15.12 2324.26 (PINE 22 15)PINE 22 15 22
7679 16+60.3 18.87 2323.74 (MAD 10 40)MAD 10 40 10
7674 16+85.6 -24.33 2316.27 (PINE 24 30)PINE 24 30 24
7678 16+87.6 12.92 2325.30 (MAD 11 15)MAD 11 15 11
7677 17+14.4 7.71 2320.82 (PINE 10 20)PINE 10 20 10
7676 17+17.9 10.87 2324.17 (PINE 11 20)PINE 11 20 11
7675 17+19.5 9.14 2339.53 (PINE 11 20)PINE 11 20 11
PAGE 3 OF 20
7560 17+29.0 9.62 2322.87 (MAD 7 20)MAD 7 20 7
7559 17+31.1 18.86 2329.08 (PINE 10 15)PINE 10 15 10
7556 17+32.6 -23.11 2319.09 (PINE 12 15)PINE 12 15 12
7562 17+43.1 8.10 2323.46 (PINE 9 15)PINE 9 15 9
7561 17+44.0 10.18 2323.46 (PINE 13 25)PINE 13 25 13
7563 17+44.4 6.81 2323.44 (PINE 9 15)PINE 9 15 9
7564 17+44.5 3.69 2318.45 (PINE 9 20)PINE 9 20 9
7555 17+46.8 -21.65 2316.91 (PINE 19 30)PINE 19 30 19
7567 17+49.7 22.65 2330.46 (MAD 18 35)MAD 18 35 18
7566 17+58.2 15.78 2327.16 (PINE 17 25)PINE 17 25 17
7565 17+60.2 8.78 2324.13 (PINE 8 20)PINE 8 20 8
7554 17+63.5 -23.72 2314.64 (PINE 21 30)PINE 21 30 21
7568 17+64.9 13.90 2326.60 (PINE 17 30)PINE 17 30 17
7569 17+66.3 15.64 2327.54 (PINE 8 20)PINE 8 20 8
7570 17+69.0 17.19 2327.28 (MAD 13 30)MAD 13 30 13
7553 17+75.0 -27.19 2315.38 (PINE 28 30)PINE 28 30 28
7571 17+79.1 2.77 2320.26 (PINE 12 15)PINE 12 15 12
7572 18+03.0 13.63 2327.67 (PINE 28 35)PINE 28 35 28
7573 18+11.2 5.97 2323.43 (PINE 16 20)PINE 16 20 16
7552 18+13.1 -22.24 2317.22 (PINE 26 30)PINE 26 30 26
7551 18+22.3 -23.29 2317.37 (PINE 23 20)PINE 23 20 23
7574 18+29.1 10.22 2325.86 (PINE 30 35)PINE 30 35 30
7519 18+52.0 -13.24 2318.02 (DECID 6 20)DECID 6 20 6
7518 18+63.9 -14.50 2318.47 (DECID 8 20)DECID 8 20 8
7509 18+66.4 11.03 2325.54 (PINE 18 30)PINE 18 30 18
7517 18+82.1 -14.82 2316.14 (DECID 8 20)DECID 8 20 8
7516 18+87.9 -17.25 2316.67 (DECID 11 20)DECID 11 20 11
7510 19+02.2 6.82 2323.48 (PINE 42 60)PINE 42 60 42
7511 19+02.7 2.82 2321.37 (PINE 8 20)PINE 8 20 8
7512 19+21.7 5.68 2317.48 (DECID 7 15)DECID 7 15 7
7515 19+38.0 -15.01 2314.97 (DECID 6 15)DECID 6 15 6
7513 19+89.3 -24.21 2318.45 (PINE 39 35)PINE 39 35 39
7397 19+92.8 0.59 2323.71 (PINE 24 30)PINE 24 30 24
7514 20+17.8 -14.37 2322.96 (DECID 15 30)DECID 15 30 15
7396 20+18.3 -0.75 2319.22 (PINE 14 20)PINE 14 20 14
7395 20+28.2 6.75 2324.13 (PINE 15 30)PINE 15 30 15
7398 20+57.8 -12.45 2322.53 (DECID 12 30)DECID 12 30 12
7393 20+65.3 9.60 2322.15 (MAD 9 20)MAD 9 20 9
7399 20+81.0 -21.09 2334.34 (CEDAR 10 15)CEDAR 10 15 10
7400 20+85.8 -19.57 2323.56 (CEDAR 13 15)CEDAR 13 15 13
7401 20+90.7 -22.59 2321.81 (CEDAR 14 15)CEDAR 14 15 14
7394 21+03.3 -5.10 2322.19 (PINE 13 30)PINE 13 30 13
7392 21+07.8 3.31 2321.38 (PINE 14 25)PINE 14 25 14
7391 21+21.3 2.72 2320.43 (PINE 15 30)PINE 15 30 15
PAGE 4 OF 20
7390 21+49.4 11.28 2322.09 (DECID 9 35)DECID 9 35 9
7388 21+70.5 3.09 2321.07 (PINE 9 25)PINE 9 25 9
7387 21+73.9 1.51 2320.64 (PINE 7 15)PINE 7 15 7
7389 21+74.0 15.09 2322.97 (MAD 7 25)MAD 7 25 7
7386 21+87.8 4.50 2320.97 (PINE 9 25)PINE 9 25 9
7385 21+97.8 11.28 2322.13 (MAD 19 35)MAD 19 35 19
7384 22+11.8 3.27 2321.57 (PINE 13 30)PINE 13 30 13
7403 22+31.8 -20.17 2316.39 (DECID 9 15)DECID 9 15 9
7383 22+34.1 7.48 2322.49 (PINE 13 30)PINE 13 30 13
7382 22+37.9 5.16 2322.59 (PINE 8 20)PINE 8 20 8
7381 22+40.5 6.93 2322.59 (PINE 11 25)PINE 11 25 11
7402 22+46.5 -19.53 2317.10 (PINE 12 35)PINE 12 35 12
7261 22+58.3 11.41 2328.36 (PINE 8 15)PINE 8 15 8
7252 22+58.7 -21.16 2324.02 (PINE 16 25)PINE 16 25 16
7262 22+61.0 5.99 2323.90 (PINE 12 25)PINE 12 25 12
7249 22+65.1 -18.34 2324.50 (PINE 12 25)PINE 12 25 12
7248 22+78.2 -22.83 2336.83 (PINE 22 30)PINE 22 30 22
7263 22+99.7 3.19 2322.75 (PINE 8 25)PINE 8 25 8
7264 23+01.4 3.91 2321.42 (PINE 13 25)PINE 13 25 13
7245 23+05.9 -18.99 2323.51 (PINE 11 25)PINE 11 25 11
7265 23+27.1 3.52 2320.12 (PINE 23 30)PINE 23 30 23
7266 23+54.6 9.53 2324.42 (PINE 22 30)PINE 22 30 22
7267 23+74.5 2.61 2322.11 (PINE 18 25)PINE 18 25 18
7232 24+00.0 -20.42 2324.72 (PINE 26 35)PINE 26 35 26
7268 24+15.5 2.11 2322.03 (PINE 19 30)PINE 19 30 19
7150 24+25.4 -20.23 2317.86 (PINE 26 35)PINE 26 35 26
7149 24+39.7 -24.63 2317.21 (MADRONE 14 30)MADRONE 14 30 14
7272 24+90.3 -3.10 2321.21 (MADRONE 7 15)MADRONE 7 15 7
7144 25+19.4 6.87 2323.23 (PINE 10 25)PINE 10 25 10
7143 25+23.3 6.42 2323.04 (PINE 16 25)PINE 16 25 16
7145 25+27.6 -26.25 2320.76 (PINE 12 35)PINE 12 35 12
7146 25+32.3 -25.05 2320.46 (PINE 14 35)PINE 14 35 14
7147 25+32.9 -23.64 2320.31 (DECID 12 30)DECID 12 30 12
7142 25+44.0 3.09 2321.41 (PINE 11 20)PINE 11 20 11
7141 25+47.0 5.64 2321.54 (PINE 6 20)PINE 6 20 6
7148 25+49.2 -27.34 2319.29 (PINE 16 30)PINE 16 30 16
7139 25+52.3 7.91 2322.36 (DECID 11 25)DECID 11 25 11
7138 25+61.7 2.96 2320.17 (PINE 7 20)PINE 7 20 7
7092 25+65.4 10.30 2324.40 (PINE 12 20)PINE 12 20 12
7140 25+66.0 7.45 2328.13 (PINE 6 20)PINE 6 20 6
7091 25+86.7 12.77 2324.18 (PINE 6 20)PINE 6 20 6
7087 26+19.4 12.72 2328.64 (MADRONE 12 35)MADRONE 12 35 12
7088 26+25.2 6.65 2325.95 (MADRONE 12 25)MADRONE 12 25 12
7089 26+28.8 9.52 2328.80 (MADRONE 11 30)MADRONE 11 30 11
PAGE 5 OF 20
7090 26+31.5 3.83 2324.73 (MADRONE 9 25)MADRONE 9 25 9
6997 26+50.9 0.20 2327.96 (MADRONE 12 35)MADRONE 12 35 12
7031 26+52.9 -23.37 2319.87 (PINE 26 35)PINE 26 35 26
6998 26+54.1 5.91 2328.08 (DECID 7 25)DECID 7 25 7
6999 26+62.1 5.11 2328.87 (MADRONE 11 30)MADRONE 11 30 11
7029 26+62.5 -26.90 2321.35 (PINE 24 20)PINE 24 20 24
7000 26+71.0 8.08 2330.80 (MADRONE 11 30)MADRONE 11 30 11
7001 26+73.0 9.89 2331.80 (MADRONE 14 30)MADRONE 14 30 14
7002 26+96.2 3.83 2327.22 (MADRONE 12 30)MADRONE 12 30 12
7020 27+61.3 7.43 2326.29 (DECID 12 20)DECID 12 20 12
7035 27+62.7 -24.02 2316.95 (PINE 12 20)PINE 12 20 12
7019 27+67.8 16.55 2333.57 (DECID 7 20)DECID 7 20 7
7018 27+69.6 9.03 2329.97 (DECID 7 20)DECID 7 20 7
7042 27+71.8 -14.17 2321.01 (DECID 14 25)DECID 14 25 14
7041 27+75.0 -14.78 2321.05 (DECID 15 25)DECID 15 25 15
7017 27+81.6 0.40 2327.31 (DECID 6 20)DECID 6 20 6
7040 27+87.9 -19.80 2320.57 (MADRONE 13 30)MADRONE 13 30 13
7039 27+94.2 -22.88 2317.48 (PINE 34 45)PINE 34 45 34
7038 28+25.9 -18.19 2316.35 (PINE 7 15)PINE 7 15 7
7037 28+29.1 -20.25 2315.86 (PINE 12 20)PINE 12 20 12
7016 28+31.5 0.45 2322.84 (PINE 20 30)PINE 20 30 20
7015 28+35.4 3.91 2327.83 (PINE 8 10)PINE 8 10 8
7036 28+36.9 -19.39 2314.91 (DECID 8 20)DECID 8 20 8
7014 28+40.4 2.30 2326.12 (PINE 19 25)PINE 19 25 19
7013 28+44.1 0.08 2324.47 (PINE 17 25)PINE 17 25 17
6925 28+59.8 0.99 2321.78 (PINE 25 35)PINE 25 35 25
6924 28+62.1 -20.25 2316.82 (DECID 12 25)DECID 12 25 12
6923 28+65.3 -22.03 2315.87 (DECID 8 20)DECID 8 20 8
6921 28+68.7 -20.25 2317.10 (DECID 10 25)DECID 10 25 10
6922 29+00.0 -23.54 2319.38 (PINE 23 30)PINE 23 30 23
6930 29+08.0 10.60 2332.48 (DECID 10 20)DECID 10 20 10
6919 29+08.5 -20.45 2318.87 (PINE 22 40)PINE 22 40 22
6928 29+16.1 5.90 2323.92 (DECID 8 30)DECID 8 30 8
6929 29+19.9 12.18 2328.97 (PINE 24 35)PINE 24 35 24
6918 29+26.8 -23.61 2318.33 (DECID 14 30)DECID 14 30 14
6927 29+27.2 2.30 2326.00 (PINE 24 40)PINE 24 40 24
6926 29+54.2 5.07 2324.15 (PINE 13 30)PINE 13 30 13
6917 29+60.2 -22.87 2315.79 (DECID 21 55)DECID 21 55 21
6873 29+82.9 -25.06 2315.13 (DECID 8 25)DECID 8 25 8
6874 30+01.2 2.06 2322.80 (DECID 13 20)DECID 13 20 13
6872 30+14.9 -21.68 2318.44 (DECID 8 25)DECID 8 25 8
6875 30+21.8 3.36 2322.93 (DECID 12 25)DECID 12 25 12
6870 30+31.0 -17.41 2317.13 (DECID 7 30)DECID 7 30 7
6871 30+33.6 -19.39 2321.08 (DECID 7 25)DECID 7 25 7
PAGE 6 OF 20
6869 30+42.6 -16.75 2316.94 (DECID 10 30)DECID 10 30 10
6868 30+43.9 -19.55 2317.14 (DECID 11 25)DECID 11 25 11
6876 30+54.9 4.52 2321.88 (PINE 43 50)PINE 43 50 43
6877 30+79.5 13.96 2325.52 (PINE 12 25)PINE 12 25 12
6867 30+96.4 -15.30 2320.08 (DECID 7 30)DECID 7 30 7
6866 31+03.9 -18.29 2318.63 (PINE 8 20)PINE 8 20 8
6879 31+06.0 -0.21 2326.13 (PINE 26 35)PINE 26 35 26
6880 31+24.4 12.74 2331.41 (PINE 26 35)PINE 26 35 26
6878 31+24.6 11.58 2326.40 (PINE 8 20)PINE 8 20 8
6827 31+58.8 -18.09 2317.44 (DECID 19 30)DECID 19 30 19
6828 31+64.8 13.85 2326.79 (MADRONE 21 35)MADRONE 21 35 21
6829 31+67.3 7.05 2323.26 (PINE 8 25)PINE 8 25 8
6830 31+69.4 3.46 2320.99 (PINE 11 30)PINE 11 30 11
6826 31+76.0 -18.00 2315.88 (MADRONE 17 35)MADRONE 17 35 17
6831 31+86.1 5.17 2321.47 (PINE 9 20)PINE 9 20 9
6825 31+91.0 -18.90 2313.43 (DECID 6 20)DECID 6 20 6
6832 31+96.1 3.85 2320.86 (PINE 8 15)PINE 8 15 8
6824 32+07.4 -20.28 2311.86 (DECID 7 30)DECID 7 30 7
6833 32+13.2 7.00 2322.06 (PINE 13 20)PINE 13 20 13
6823 32+17.0 -21.56 2315.83 (PINE 14 30)PINE 14 30 14
6822 32+23.0 -17.33 2319.25 (DECID 7 20)DECID 7 20 7
6820 32+23.1 -16.63 2317.76 (DECID 15 20)DECID 15 20 15
6821 32+24.2 -20.55 2319.92 (DECID 7 20)DECID 7 20 7
6834 32+32.3 2.96 2321.01 (PINE 12 20)PINE 12 20 12
6835 32+42.5 3.47 2321.41 (PINE 8 20)PINE 8 20 8
6836 32+43.3 2.91 2321.38 (PINE 9 20)PINE 9 20 9
6837 32+47.6 2.41 2321.19 (PINE 8 20)PINE 8 20 8
6819 32+51.6 -19.61 2316.53 (DECID 9 25)DECID 9 25 9
6838 32+53.6 2.64 2320.89 (PINE 12 25)PINE 12 25 12
6817 32+57.1 -21.97 2317.56 (ASPEN 7 20)ASPEN 7 20 7
6816 32+58.2 -16.82 2317.35 (PINE 13 30)PINE 13 30 13
6818 32+59.3 -23.22 2314.49 (ASPEN 8 20)ASPEN 8 20 8
6815 32+64.8 -12.90 2319.37 (PINE 13 30)PINE 13 30 13
6739 33+17.3 -17.15 2317.48 (DECID 20 25)DECID 20 25 20
6738 33+31.1 0.72 2321.20 (PINE 10 20)PINE 10 20 10
6736 33+41.3 -36.97 2314.96 (PINE 27 40)PINE 27 40 27
6737 33+41.4 -36.52 2314.97 (PINE 27 40)PINE 27 40 27
6735 33+44.0 -7.76 2320.05 (PINE 7 10)PINE 7 10 7
6734 33+46.7 0.40 2322.72 (DECID 12 20)DECID 12 20 12
9006734 33+61.2 0.26 (PINE 12 17 BLUE SPRUCE)PINE 12 17 12
6657 34+00.3 -13.79 2323.37 (MADRONE 6 10)MADRONE 6 10 6
6474 35+08.3 -22.49 2318.92 (DECID 12 25)DECID 12 25 12
6459 35+17.4 -16.81 2320.56 (PINE 6 20)PINE 6 20 6
PAGE 7 OF 20
6458 35+37.3 -16.80 2319.15 (FIR 12 20)FIR 12 20 12
6473 35+53.6 13.22 2324.05 (PINE 29 35)PINE 29 35 29
6471 35+58.1 11.43 2323.39 (PINE 10 20)PINE 10 20 10
6472 35+58.3 8.36 2322.89 (PINE 13 25)PINE 13 25 13
6470 35+61.2 16.34 2324.00 (PINE 19 30)PINE 19 30 19
6457 35+75.9 -19.55 2319.74 (PINE 8 20)PINE 8 20 8
6469 35+80.3 11.37 2322.89 (MADRONE 20 35)MADRONE 20 35 20
6468 35+83.0 18.94 2325.00 (PINE 23 35)PINE 23 35 23
6456 36+05.2 -21.39 2330.07 (PINE 27 30)PINE 27 30 27
6378 36+58.4 -17.50 2317.80 (CEDAR 8 20)CEDAR 8 20 8
6377 36+70.7 -17.91 2320.38 (PINE 25 30)PINE 25 30 25
6382 36+78.7 4.52 2320.93 (MADRONE 6 15)MADRONE 6 15 6
6376 36+80.9 -18.06 2322.96 (PINE 28 40)PINE 28 40 28
6381 36+86.0 3.21 2321.32 (PINE 10 20)PINE 10 20 10
6380 37+04.4 7.58 2322.87 (DECID 10 20)DECID 10 20 10
6379 37+33.1 7.26 2322.34 (PINE 19 25)PINE 19 25 19
6375 37+38.6 -15.49 2321.06 (PINE 9 20)PINE 9 20 9
6277 37+61.3 12.72 2324.75 (PINE 21 35)PINE 21 35 21
6278 37+69.1 -21.01 2319.83 (PINE 32 40)PINE 32 40 32
6276 37+75.0 14.72 2328.64 (PINE 15 30)PINE 15 30 15
6275 37+80.3 19.15 2330.36 (PINE 17 25)PINE 17 25 17
6274 37+97.7 0.20 2328.73 (MADRONE 7 15)MADRONE 7 15 7
6273 38+07.8 -17.62 2324.72 (MADRONE 7 15)MADRONE 7 15 7
6144 38+46.4 7.45 2323.93 (DECID 7 20)DECID 7 20 7
6143 38+51.7 11.36 2325.08 (PINE 29 40)PINE 29 40 29
6142 38+63.8 16.41 2325.35 (DECID 9 20)DECID 9 20 9
6141 38+75.3 15.65 2325.97 (DECID 10 25)DECID 10 25 10
6140 38+80.8 9.47 2323.41 (PINE 11 20)PINE 11 20 11
6139 38+83.5 9.36 2323.41 (DECID 6 15)DECID 6 15 6
6138 38+83.7 14.91 2328.42 (DECID 30 30)DECID 30 30 30
6137 39+03.5 7.09 2322.02 (PINE 16 30)PINE 16 30 16
6136 39+07.2 4.75 2322.04 (PINE 10 25)PINE 10 25 10
6135 39+21.0 6.23 2322.69 (PINE 10 10)PINE 10 10 10
6134 39+21.1 7.55 2323.32 (DECID 12 25)DECID 12 25 12
6133 39+33.1 6.34 2323.15 (PINE 17 25)PINE 17 25 17
6132 39+45.7 6.81 2323.04 (PINE 12 25)PINE 12 25 12
6130 39+61.1 5.58 2321.81 (PINE 9 25)PINE 9 25 9
6131 39+61.9 4.32 2321.79 (PINE 9 25)PINE 9 25 9
6129 39+76.0 16.53 2326.02 (MADRONE 12 25)MADRONE 12 25 12
6128 39+76.5 3.96 2327.97 (PINE 20 30)PINE 20 30 20
6127 40+10.9 10.47 2326.25 (PINE 29 30)PINE 29 30 29
6126 40+28.3 8.26 2325.95 (PINE 7 20)PINE 7 20 7
6008 40+49.9 7.99 2326.70 (MADRONE 12 25)MADRONE 12 25 12
6009 40+61.3 -6.29 2323.12 (PINE 11 15)PINE 11 15 11
PAGE 8 OF 20
6007 40+70.7 16.59 2328.34 (PINE 18 30)PINE 18 30 18
6006 40+73.8 12.72 2328.09 (PINE 7 15)PINE 7 15 7
6005 40+74.7 12.63 2327.86 (PINE 7 15)PINE 7 15 7
6003 40+78.3 20.56 2329.76 (MADRONE 22 40)MADRONE 22 40 22
6004 40+79.0 14.66 2327.62 (MADRONE 9 25)MADRONE 9 25 9
6002 40+83.0 21.43 2329.75 (MADRONE 30 50)MADRONE 30 50 30
6001 40+95.0 12.92 2327.44 (PINE 12 20)PINE 12 20 12
5999 41+34.3 16.98 2328.97 (PINE 14 20)PINE 14 20 14
6000 41+37.4 10.20 2325.44 (PINE 7 20)PINE 7 20 7
6010 41+40.9 -10.21 2323.69 (PINE 28 35)PINE 28 35 28
5998 41+49.3 19.66 2330.95 (PINE 25 30)PINE 25 30 25
5997 41+53.7 20.35 2331.44 (PINE 12 30)PINE 12 30 12
5996 41+73.7 20.14 2331.53 (PINE 11 25)PINE 11 25 11
6011 41+73.7 -7.38 2321.53 (PINE 40 40)PINE 40 40 40
5995 41+80.0 19.59 2331.91 (MADRONE 11 25)MADRONE 11 25 11
6012 41+81.6 -12.53 2324.93 (MADRONE 10 20)MADRONE 10 20 10
5991 41+84.5 -13.59 2326.09 (PINE 9 20)PINE 9 20 9
5994 42+31.0 12.01 2328.82 (PINE 6 15)PINE 6 15 6
5993 42+31.4 15.72 2325.40 (PINE 7 20)PINE 7 20 7
9005988 42+45.8 -12.18 (FIR 12 20)FIR 12 20 12
5990 42+49.3 -14.33 2320.99 (DECID 12 30)DECID 12 30 12
5989 42+50.5 -23.77 2317.51 (DECID 10 20)DECID 10 20 10
9005992 42+55.1 24.43 (MADRONE 20 26)MADRONE 20 26 20
5992 42+57.4 19.11 2335.16 (MADRONE 25 35)MADRONE 25 35 25
9005993 42+60.1 23.29 (MADRONE 14 20)MADRONE 14 20 14
5987 42+86.6 -27.03 2323.65 (MADRONE 15 35)MADRONE 15 35 15
5896 42+87.3 6.78 2333.08 (PINE 15 20)PINE 15 20 15
5988 42+89.0 -27.90 2322.57 (PINE 22 30)PINE 22 30 22
5897 43+01.2 16.06 2334.74 (MADRONE 12 25)MADRONE 12 25 12
5910 43+21.9 -25.30 2319.85 (MADRONE 13 35)MADRONE 13 35 13
5898 43+27.5 13.18 2333.18 (MADRONE 6 20)MADRONE 6 20 6
5899 43+41.0 6.28 2327.27 (MADRONE 8 20)MADRONE 8 20 8
5911 43+49.8 -22.79 2325.80 (MADRONE 8 30)MADRONE 8 30 8
5900 43+62.9 3.57 2327.47 (PINE 9 25)PINE 9 25 9
5909 43+66.2 -19.46 2321.39 (DECID 9 30)DECID 9 30 9
5908 43+68.7 -19.91 2320.16 (DECID 8 30)DECID 8 30 8
5901 43+76.3 2.40 2327.82 (PINE 24 40)PINE 24 40 24
5907 43+89.4 -23.29 2320.22 (PINE 26 30)PINE 26 30 26
5906 43+94.1 -26.49 2319.15 (PINE 18 20)PINE 18 20 18
5902 43+94.5 8.12 2326.61 (MADRONE 10 20)MADRONE 10 20 10
5903 44+03.7 2.32 2324.46 (MADRONE 10 20)MADRONE 10 20 10
18005850 44+17.4 5.26 (FIR 6 12)FIR 6 12 6
5905 44+17.4 -21.35 2321.67 (PINE 9 15)PINE 9 15 9
5904 44+84.2 -22.45 2319.34 (PINE 30 45)PINE 30 45 30
PAGE 9 OF 20
9005848 44+96.5 6.37 (PINE 8 20)PINE 8 20 8
9005849 45+12.6 9.29 (PINE 12 25)PINE 12 25 12
5848 45+74.4 2.89 2324.76 (" & Drip)" & Drip 10
5850 45+83.7 -24.42 2318.25 (DECID 11 20)DECID 11 20 11
5849 46+07.4 -25.83 2317.92 (MADRONE 8 20)MADRONE 8 20 8
5847 46+16.2 13.17 2328.10 (PINE 21 25)PINE 21 25 21
5843 46+19.0 29.97 2321.30 (PINE 28 30)PINE 28 30 28
5846 46+28.0 2.11 2324.12 (" & Drip)" & Drip 12
5845 46+44.0 3.77 2327.59 (" & Drip)" & Drip 12
5844 46+58.1 -21.45 2327.56 (MADRONE 6 15)MADRONE 6 15 6
5792 46+97.9 8.83 2324.61 (" & Drip)" & Drip 12
5791 47+31.1 -19.54 2319.40 (DECID 7 20)DECID 7 20 7
5790 47+31.9 -18.80 2319.56 (DECID 6 20)DECID 6 20 6
5789 47+58.2 8.48 2323.68 (PINE 15 30)PINE 15 30 15
5788 47+64.4 3.79 2323.22 (PINE 11 20)PINE 11 20 11
5787 47+66.3 7.10 2324.23 (PINE 7 10)PINE 7 10 7
5786 47+84.8 -21.71 2320.47 (PINE 27 25)PINE 27 25 27
5785 47+97.3 -15.19 2321.44 (DECID 19 35)DECID 19 35 19
5783 47+98.4 7.55 2325.16 (PINE 13 20)PINE 13 20 13
5784 47+99.7 -19.51 2319.81 (DECID 13 20)DECID 13 20 13
5728 48+33.3 4.57 2323.23 (PINE 7 15)PINE 7 15 7
5727 48+38.3 9.87 2329.13 (DECID 15 25)DECID 15 25 15
5729 48+39.5 4.45 2323.99 (PINE 6 15)PINE 6 15 6
5726 48+72.1 -15.51 2322.90 (PINE 17 35)PINE 17 35 17
5725 48+81.0 -12.61 2322.72 (PINE 12 20)PINE 12 20 12
5724 48+92.5 -18.84 2319.24 (DECID 14 30)DECID 14 30 14
5722 49+20.1 -33.10 2311.01 (DECID 24 40)DECID 24 40 24
5721 49+54.3 -13.37 2318.66 (DECID 16 20)DECID 16 20 16
5720 49+76.7 -18.61 2322.76 (DECID 11 20)DECID 11 20 11
5719 49+83.2 -7.06 2321.31 (PINE 25 30)PINE 25 30 25
5664 49+91.5 -8.05 2322.86 (DECID 10 30)DECID 10 30 10
5663 49+94.5 -7.63 2319.51 (DECID 11 30)DECID 11 30 11
5662 49+97.8 -9.13 2322.29 (DECID 9 25)DECID 9 25 9
5661 49+99.7 -10.25 2321.37 (DECID 14 30)DECID 14 30 14
5660 50+12.8 13.94 2325.80 (MADRONE 6 15)MADRONE 6 15 6
5659 50+15.4 22.71 2330.00 (MADRONE 8 15)MADRONE 8 15 8
5657 50+20.2 30.28 2327.08 (PINE 29 25)PINE 29 25 29
5658 50+22.0 23.52 2325.32 (PINE 9 20)PINE 9 20 9
5656 50+45.2 21.02 2331.41 (MADRONE 10 20)MADRONE 10 20 10
5723 51+66.1 -25.79 2314.92 (DECID 20 30)DECID 20 30 20
5631 52+36.4 -29.19 2317.37 (PINE 35 30)PINE 35 30 35
5632 52+39.4 -18.84 2322.04 (DECID 15 25)DECID 15 25 15
5633 52+43.4 -13.96 2322.42 (DECID 14 30)DECID 14 30 14
5630 52+52.8 -23.03 2319.71 (PINE 22 20)PINE 22 20 22
PAGE 10 OF 20
5595 52+88.5 0.04 2324.34 (PINE 18 25)PINE 18 25 18
5596 52+93.2 10.09 2327.35 (PINE 26 35)PINE 26 35 26
5594 53+05.1 -13.91 2321.86 (PINE 31 35)PINE 31 35 31
5593 53+27.8 -0.70 2325.56 (MADRONE 9 20)MADRONE 9 20 9
5592 54+04.0 -12.87 2324.10 (PINE 24 30)PINE 24 30 24
5557 54+76.5 1.22 2324.61 (PINE 32 35)PINE 32 35 32
5556 54+99.1 1.68 2324.19 (PINE 20 25)PINE 20 25 20
5555 55+06.2 2.22 2324.09 (PINE 17 25)PINE 17 25 17
5554 55+15.7 3.35 2325.30 (PINE 24 25)PINE 24 25 24
5553 55+18.6 11.14 2328.97 (PINE 10 15)PINE 10 15 10
5552 55+31.9 -20.68 2318.49 (PINE 19 20)PINE 19 20 19
5551 55+57.8 9.02 2325.30 (PINE 14 20)PINE 14 20 14
5507 56+08.4 -17.39 2320.71 (PINE 40 40)PINE 40 40 40
5490 56+90.9 -18.80 2319.00 (DECID 12 20)DECID 12 20 12
5489 57+16.9 -11.41 2321.54 (PINE 10 20)PINE 10 20 10
5488 57+36.6 -16.75 2318.44 (DECID 9 15)DECID 9 15 9
5486 57+44.2 2.60 2324.14 (PINE 33 40)PINE 33 40 33
5487 57+48.6 -19.37 2316.06 (PINE 11 15)PINE 11 15 11
5485 57+73.1 12.15 2328.45 (DECID 8 15)DECID 8 15 8
5484 57+85.2 -21.81 2318.57 (DECID 26 30)DECID 26 30 26
5483 57+88.7 -23.96 2317.90 (DECID 28 25)DECID 28 25 28
5491 58+03.7 -5.83 2322.25 (PINE 11 20)PINE 11 20 11
5482 58+16.9 -14.33 2321.98 (PINE 9 10)PINE 9 10 9
5481 58+20.5 -15.30 2321.90 (PINE 6 10)PINE 6 10 6
5478 58+25.6 4.41 2325.47 (PINE 12 15)PINE 12 15 12
5480 58+27.8 -16.45 2320.86 (DECID 10 15)DECID 10 15 10
5477 58+40.4 11.47 2329.14 (DECID 7 15)DECID 7 15 7
5479 58+41.6 -14.47 2321.80 (DECID 10 15)DECID 10 15 10
5432 58+46.6 -13.85 2321.42 (MADRONE 10 15)MADRONE 10 15 10
5433 58+52.9 5.69 2326.11 (PINE 9 15)PINE 9 15 9
5429 58+66.7 6.33 2326.13 (DECID 9 20)DECID 9 20 9
5431 58+68.1 -12.12 2321.75 (PINE 6 10)PINE 6 10 6
5430 58+77.0 -6.10 2322.69 (PINE 6 10)PINE 6 10 6
5428 58+78.6 7.58 2325.31 (DECID 8 20)DECID 8 20 8
5427 58+84.1 7.75 2325.34 (DECID 16 20)DECID 16 20 16
5426 58+93.1 -1.56 2323.07 (PINE 8 15)PINE 8 15 8
5425 59+11.6 -18.31 2317.84 (PINE 38 40)PINE 38 40 38
5424 59+22.7 11.24 2328.40 (DECID 10 15)DECID 10 15 10
5423 59+55.5 10.55 2327.32 (DECID 13 25)DECID 13 25 13
5407 59+67.9 -10.00 2321.64 (PINE 13 20)PINE 13 20 13
5422 59+68.9 10.75 2328.42 (DECID 10 25)DECID 10 25 10
5408 59+84.6 -13.87 2320.80 (DECID 10 25)DECID 10 25 10
5409 59+92.4 -9.76 2321.51 (PINE 10 15)PINE 10 15 10
5406 60+17.7 3.97 2323.93 (PINE 31 25)PINE 31 25 31
PAGE 11 OF 20
5405 60+34.8 4.36 2325.33 (DECID 15 20)DECID 15 20 15
5404 60+59.9 -24.42 2319.49 (PINE 23 30)PINE 23 30 23
5403 60+72.9 -19.11 2320.56 (DECID 12 20)DECID 12 20 12
5411 60+77.0 3.15 2324.66 (DECID 16 26)DECID 16 26 16
5402 60+86.0 4.42 2325.18 (DECID 15 30)DECID 15 30 15
5410 61+00.5 13.91 2333.04 (DECID 16 15)DECID 16 15 16
5400 61+20.2 -15.49 2321.46 (DECID 9 15)DECID 9 15 9
5295 61+48.9 1.34 2324.43 (DECID 9 20)DECID 9 20 9
5294 61+73.1 -23.77 2322.93 (DECID 21 30)DECID 21 30 21
5292 61+93.6 10.26 2327.61 (PINE 24 30)PINE 24 30 24
5293 61+93.9 -19.41 2322.37 (DECID 19 30)DECID 19 30 19
5290 62+62.5 -15.17 2326.14 (DECID 21 25)DECID 21 25 21
5291 62+65.9 3.31 2325.51 (DECID 15 25)DECID 15 25 15
5288 62+84.7 3.80 2326.53 (DECID 13 20)DECID 13 20 13
5289 62+94.2 -15.88 2322.18 (DECID 13 20)DECID 13 20 13
5215 63+02.8 4.73 2325.90 (PINE 24 30)PINE 24 30 24
5213 63+15.2 1.05 2326.23 (PINE 24 30)PINE 24 30 24
5214 63+17.0 2.58 2325.40 (DECID 9 15)DECID 9 15 9
5216 63+25.0 4.23 2325.39 (DECID 13 20)DECID 13 20 13
5208 63+39.5 -20.22 2320.36 (MADRONE 11 15)MADRONE 11 15 11
5217 63+50.1 16.73 2328.69 (PINE 16 25)PINE 16 25 16
5218 63+57.1 10.45 2324.92 (DECID 8 20)DECID 8 20 8
5207 63+61.1 -10.75 2324.93 (DECID 11 15)DECID 11 15 11
5219 63+68.2 13.80 2327.13 (DECID 10 20)DECID 10 20 10
5220 63+88.6 5.90 2326.79 (PINE 18 20)PINE 18 20 18
5221 63+90.7 9.37 2328.11 (PINE 12 15)PINE 12 15 12
5222 64+16.0 4.87 2326.45 (PINE 12 15)PINE 12 15 12
5206 64+16.1 -21.19 2320.93 (DECID 9 15)DECID 9 15 9
5223 64+34.4 6.49 2327.13 (PINE 16 25)PINE 16 25 16
5224 64+40.9 7.63 2326.84 (PINE 10 15)PINE 10 15 10
5225 64+49.3 6.86 2327.24 (PINE 23 25)PINE 23 25 23
5205 64+94.8 -14.91 2322.83 (MADRONE 7 20)MADRONE 7 20 7
5204 65+05.0 -19.22 2321.48 (DECID 9 30)DECID 9 30 9
5203 65+10.6 14.90 2327.98 (PINE 21 30)PINE 21 30 21
5202 65+50.3 -1.77 2326.56 (DECID 7 15)DECID 7 15 7
5201 65+56.0 -2.66 2327.88 (PINE 21 25)PINE 21 25 21
5200 65+58.8 2.02 2328.65 (PINE 12 20)PINE 12 20 12
5075 65+65.3 -23.40 2323.29 (DECID 6 10)DECID 6 10 6
5199 65+66.8 1.78 2328.75 (DECID 9 15)DECID 9 15 9
5198 65+78.8 -2.01 2329.16 (PINE 9 10)PINE 9 10 10
5074 65+89.4 -19.41 2323.80 (DECID 8 10)DECID 8 10 8
5077 66+02.4 15.09 2334.36 (PINE 36 20)PINE 36 20 36
5073 66+07.0 -23.63 2320.78 (PINE 17 15)PINE 17 15 17
5076 66+11.8 -2.61 2327.27 (PINE 8 20)PINE 8 20 8
PAGE 12 OF 20
5072 66+23.3 -22.33 2321.56 (PINE 9 15)PINE 9 15 9
5071 66+46.7 -16.06 2323.97 (DECID 7 10)DECID 7 10 7
5070 66+60.5 -8.33 2323.69 (PINE 35 20)PINE 35 20 35
3603 66+62.7 -7.69 2324.21 (PINE 36 28)PINE 36 28 36
3602 66+93.8 5.23 2322.58 (OAK 9 11.1)OAK 9 11.1 9
3604 67+01.7 -15.97 2322.81 (PINE 27 15)PINE 27 15 27
3601 67+03.7 5.27 2323.35 (PINE 18 6.3)PINE 18 6.3 18
3600 67+17.3 6.68 2322.80 (PINE 14 10)PINE 14 10 14
3599 67+21.4 16.48 2325.04 (PINE 17 6.8)PINE 17 6.8 17
3598 67+48.2 4.60 2322.62 (PINE 30 26)PINE 30 26 30
3605 67+50.9 -11.32 2322.40 (OAK 8 10)OAK 8 10 8
3597 67+58.3 14.91 2325.06 (PINE 17 13)PINE 17 13 17
3606 67+69.5 -36.54 2317.58 (PINE 48 24.6)PINE 48 24.6 48
3596 67+75.2 4.44 2322.72 (OAK 6 6)OAK 6 6 6
3540 68+12.3 -20.11 2316.16 (PINE 35 19.2)PINE 35 19.2 35
3542 68+54.7 3.94 2323.52 (CEDARX4 6 10)CEDARX4 6 10 6
3541 68+65.3 -7.02 2321.96 (OAKX2 6 14.4)OAKX2 6 14.4 6
3431 68+88.0 -10.83 2318.33 (OAK 7 8)OAK 7 8 7
3430 68+88.2 -16.85 2318.33 (OAK 6 8.3)OAK 6 8.3 6
3429 68+89.5 -8.91 2318.75 (PINE 16 17)PINE 16 17 16
3171 70+46.8 5.09 2323.49 (OAK 7 15)OAK 7 15 7
3172 70+58.8 13.39 2324.03 (OAK 12 18)OAK 12 18 12
3186 70+99.6 -20.69 2321.41 (OAK 8 17.5)OAK 8 17.5 8
3173 71+26.1 5.85 2321.46 (MAD 8 6.9)MAD 8 6.9 8
3174 71+35.3 10.03 2321.51 (OAK 6 10)OAK 6 10 6
3175 71+43.1 6.25 2321.47 (PINE 23 18)PINE 23 18 23
3176 71+81.0 6.58 2321.47 (PINE 18 12)PINE 18 12 18
3185 71+94.7 -17.84 2321.53 (PINE 12 12)PINE 12 12 12
3184 72+10.7 -14.92 2321.52 (PINE 14 12)PINE 14 12 14
3183 72+15.4 -14.36 2321.51 (PINE 6 8)PINE 6 8 6
3177 72+20.5 6.69 2321.53 (PINE 20 20)PINE 20 20 20
3178 72+35.5 6.98 2321.50 (PINE 11 8.2)PINE 11 8.2 11
3179 72+62.5 15.56 2321.53 (OAK 28 23)OAK 28 23 28
3182 72+64.6 -7.03 2321.52 (PINE 12 10)PINE 12 10 12
3180 72+91.1 8.82 2321.57 (OAK 7 8)OAK 7 8 7
3181 73+04.1 11.69 2321.60 (OAK 16 17.5)OAK 16 17.5 16
2944 73+33.1 18.37 2321.61 (OAK 12 16.4)OAK 12 16.4 12
2920 73+34.4 -20.34 2323.84 (FIR 8 11.5)FIR 8 11.5 8
2943 73+49.7 19.39 2321.63 (OAKX2 11 19.3)OAKX2 11 19.3 11
2942 73+62.7 14.08 2324.23 (OAK 9 9.1)OAK 9 9.1 9
2921 73+70.7 -16.79 2321.66 (OAK 16 16.5)OAK 16 16.5 16
2922 73+76.8 -16.86 2326.03 (OAK 16 18.5)OAK 16 18.5 16
2925 73+99.7 -16.83 2321.68 (OAK 7 17.5)OAK 7 17.5 7
2941 74+07.7 18.87 2321.66 (OAK 9 20.2)OAK 9 20.2 9
PAGE 13 OF 20
2940 74+20.4 8.73 2321.67 (OAK 24 20)OAK 24 20 24
2926 74+27.6 -16.82 2321.73 (OAK 15 17.5)OAK 15 17.5 15
2939 74+33.0 17.22 2329.00 (OAK 10 30)OAK 10 30 10
2927 74+40.7 -14.53 2324.15 (OAK 9 26)OAK 9 26 9
9002928 74+47.0 -17.39 0.00 (oak 8 15)oak 8 15 8
2938 74+50.7 11.56 2326.91 (OAK 11 8.3)OAK 11 8.3 11
2928 74+58.6 -17.79 2324.44 (OAKX3 16 20)OAKX3 16 20 16
2937 74+65.1 12.59 2321.72 (OAKX3 12 13.7)OAKX3 12 13.7 12
2929 74+73.5 -11.61 2321.84 (FIR 8 8.7)FIR 8 8.7 8
2936 74+74.5 9.51 2321.68 (OAK 7 10.3)OAK 7 10.3 7
2930 74+88.3 -14.82 2323.81 (OAK 22 9)OAK 22 9 22
2931 74+98.1 -19.00 2324.10 (OAK 23 40)OAK 23 40 23
2935 75+00.6 15.90 2326.16 (OAK 14 6.8)OAK 14 6.8 14
2932 75+10.0 -10.25 2322.55 (FIR 9 15.2)FIR 9 15.2 9
2934 75+20.4 15.51 2321.71 (FIR 12 12.8)FIR 12 12.8 12
2933 75+28.4 15.01 2321.64 (OAK 12 12.5)OAK 12 12.5 12
2840 75+53.9 13.09 2321.73 (OAK 12 18)OAK 12 18 12
2841 75+59.4 21.51 2321.74 (OAKX3 10 15)OAKX3 10 15 10
2839 75+62.2 13.84 2321.73 (PINE 12 14)PINE 12 14 12
2842 75+64.8 -12.75 2322.09 (FIR 14 14)FIR 14 14 14
2838 75+98.1 19.31 2321.76 (OAKX2 6 19)OAKX2 6 19 6
2837 75+98.1 23.94 2321.81 (OAKX2 9 23.5)OAKX2 9 23.5 9
2836 76+11.7 16.38 2330.44 (OAKX3 10 23)OAKX3 10 23 10
2835 76+33.6 10.02 2322.09 (OAKX4 6 13)OAKX4 6 13 6
2843 76+36.3 -15.04 2324.71 (OAK 16 18)OAK 16 18 16
2834 76+72.8 18.10 2322.02 (OAKX3 7 16.5)OAKX3 7 16.5 7
2704 76+84.2 7.96 2322.06 (FIR 8 10)FIR 8 10 8
2705 76+98.9 10.52 2322.17 (FIR 7 9)FIR 7 9 7
2714 77+89.8 -17.73 2324.91 (FIR 12 22)FIR 12 22 12
2713 77+90.6 -18.94 2324.93 (FIR 9 12)FIR 9 12 9
2712 78+27.6 -25.97 2324.71 (OAK 24 24.5)OAK 24 24.5 24
2709 78+28.0 16.05 2322.06 (MADRONE 6 11 X3)MADRONE 6 11 X3 6
2708 78+42.1 16.65 2322.16 (MADRONE 9 11 X2)MADRONE 9 11 X2 9
9002711 78+42.6 -9.12 0.00 (FIR 6 10)FIR 6 10 6
2707 78+46.8 15.91 2322.23 (MADRONE 11 16)MADRONE 11 16 11
2711 78+47.5 -16.69 2324.59 (FIR 6 4.5)FIR 6 4.5 6
2710 78+49.2 -7.69 2324.49 (FIR 7 7)FIR 7 7 7
2652 78+53.9 5.51 2324.92 (FIR 13 13.5)FIR 13 13.5 13
9002710 78+54.1 -8.45 0.00 (FIR 6 8)FIR 6 8 6
2706 78+55.3 5.29 2324.64 (FIR 11 11)FIR 11 11 11
2640 78+59.8 9.01 2324.39 (MADRONE 6 6.5)MADRONE 6 6.5 6
2641 78+74.8 -21.87 2324.80 (FIR 13 12)FIR 13 12 13
2651 78+81.4 14.66 2324.91 (MADRONE 13 24)MADRONE 13 24 13
PAGE 14 OF 20
2642 78+82.0 -8.04 2324.49 (FIR 14 9 DEAD)FIR 14 9 DEAD 14
2643 78+85.9 -27.29 2324.67 (FIR 14 12)FIR 14 12 14
2644 78+90.6 -27.30 2324.75 (FIR 12 13.5)FIR 12 13.5 12
2645 78+92.5 -28.82 2324.79 (FIR 9 10)FIR 9 10 9
2646 78+97.6 -24.47 2324.79 (FIR 22 16.5)FIR 22 16.5 22
2650 78+99.1 5.64 2324.72 (FIR 9 13)FIR 9 13 9
2648 79+05.7 9.24 2324.96 (FIR 13 16.5)FIR 13 16.5 13
2649 79+08.8 6.59 2324.90 (FIR 6 15.5)FIR 6 15.5 6
2647 79+27.5 17.92 2322.28 (MADRONE 13 17)MADRONE 13 17 13
3265 79+42.2 11.20 2324.61 (OAK 7 10)OAK 7 10 7
3267 79+47.2 9.01 2324.79 (FIR 10 16.5)FIR 10 16.5 10
3266 79+47.3 9.59 2324.72 (MAD 10 17.3)MAD 10 17.3 10
3268 79+47.7 11.35 2325.16 (OAK 6 15)OAK 6 15 6
3288 79+57.0 -22.85 2325.16 (OAK 16 30)OAK 16 30 16
3269 79+58.7 17.12 2322.22 (OAK 8 16.2)OAK 8 16.2 8
3270 79+59.3 20.90 2322.22 (OAK 7 8)OAK 7 8 7
3271 79+63.6 18.49 2322.22 (MADX2 9 16)MADX2 9 16 9
3272 79+71.8 15.69 2322.20 (OAKX2 10 16)OAKX2 10 16 10
3273 79+74.5 10.33 2322.22 (MAD 7 15)MAD 7 15 7
3274 79+79.7 14.11 2322.23 (OAK 11 26)OAK 11 26 11
3275 79+88.2 16.89 2322.30 (FIR 6 10)FIR 6 10 6
3276 79+92.4 14.77 2322.27 (OAKX2 8 16)OAKX2 8 16 8
3277 79+99.9 17.33 2322.30 (OAKX2 8 16.5)OAKX2 8 16.5 8
3278 80+04.0 7.12 2322.44 (FIR 9 13)FIR 9 13 9
3279 80+30.1 16.26 2322.37 (FIR 12 18)FIR 12 18 12
3287 80+35.2 -22.07 2325.10 (MADX3 9 12)MADX3 9 12 9
3286 80+39.6 -22.43 2325.06 (OAK 12 18)OAK 12 18 12
3280 80+40.4 25.91 2322.42 (OAKX2 10 26)OAKX2 10 26 10
3281 80+51.0 18.74 2322.41 (MADX3 7 23)MADX3 7 23 7
3282 80+53.5 14.06 2322.41 (MADX4 7 17.7)MADX4 7 17.7 7
3285 80+55.2 -24.06 2325.15 (MAD 20 15)MAD 20 15 20
3283 80+64.5 15.46 2322.34 (MADX2 9 25)MADX2 9 25 9
3284 80+78.0 -7.63 2322.44 (FIR 10 9)FIR 10 9 10
2532 80+92.1 -20.76 2325.06 (OAK 16 22)OAK 16 22 16
2533 80+98.8 -5.31 2325.02 (FIR 7 9)FIR 7 9 7
2534 81+08.6 -22.52 2325.31 (OAK 18 23)OAK 18 23 18
2542 81+12.0 15.94 2320.54 (MADRONE 7 16)MADRONE 7 16 7
2541 81+12.4 17.38 2320.54 (OAK 7 7)OAK 7 7 7
2540 81+14.2 8.66 2320.50 (FIR 6 11)FIR 6 11 6
2535 81+15.0 -20.39 2325.31 (PINE 9 7)PINE 9 7 9
2539 81+40.8 24.57 2322.58 (OAK 12 23 X3)OAK 12 23 X3 12
2538 81+56.2 20.85 2322.54 (OAK 10 22)OAK 10 22 10
2537 81+73.6 21.41 2322.58 (OAK 18 22)OAK 18 22 18
2536 81+75.8 -17.24 2325.47 (PINE 16 22)PINE 16 22 16
PAGE 15 OF 20
2501 81+86.6 -25.83 2325.45 (OAK 16 15)OAK 16 15 16
2502 81+96.1 -23.61 2322.63 (OAK 20 25.5)OAK 20 25.5 20
2503 82+14.8 -23.56 2325.42 (MADRONE 6 12)MADRONE 6 12 6
2507 82+18.1 10.68 2325.08 (FIR 16 16)FIR 16 16 16
2504 82+19.2 -22.17 2325.39 (FIR 10 12.5)FIR 10 12.5 10
2505 82+33.7 -21.17 2325.37 (PINE 12 10.5)PINE 12 10.5 12
2506 82+56.3 -17.62 2325.20 (OAK 18 28)OAK 18 28 18
9002458 83+29.1 13.42 0.00 (MADRONE 12 11)MADRONE 12 11 12
2456 83+34.0 -17.37 2325.16 (OAK 41 32)OAK 41 32 41
2458 83+42.4 7.98 2322.82 (MADRONE 12 11)MADRONE 12 11 12
9002459 83+52.3 8.86 (MADRONE 12 11)MADRONE 12 11 12
2457 83+57.4 -15.27 2325.19 (MADRONE 12 11)MADRONE 12 11 12
2390 83+94.2 5.48 2325.16 (OAK 9 9)OAK 9 9 9
2398 83+99.8 -13.84 2322.98 (OAK 8 13)OAK 8 13 8
2389 84+12.9 19.37 2322.89 (FIR 20 18)FIR 20 18 20
2391 84+14.2 -16.49 2323.01 (OAK 18 18)OAK 18 18 18
2388 84+24.9 14.02 2323.02 (MADRONE 8 14.5)MADRONE 8 14.5 8
2392 84+26.8 -10.86 2323.05 (OAK 10 10)OAK 10 10 10
2376 84+42.1 15.26 2325.42 (OAK 8 21)OAK 8 21 8
2375 84+53.0 9.03 2323.07 (FIR 10 12)FIR 10 12 10
2339 84+72.2 14.83 2323.11 (OAK 11 15)OAK 11 15 11
2331 84+77.8 -15.18 2325.49 (OAK 12 20)OAK 12 20 12
2330 84+78.9 -23.74 2325.45 (OAK 15 17)OAK 15 17 15
2324 85+02.7 14.78 2327.66 (MADRONE 10 16)MADRONE 10 16 10
2323 85+04.4 15.08 2327.81 (OAK 13 18)OAK 13 18 13
2273 85+09.2 -14.46 2324.99 (OAK 12 19)OAK 12 19 12
2272 85+21.9 7.45 2328.64 (OAK 6 6)OAK 6 6 6
2271 85+40.3 7.76 2329.32 (FIR 10 15)FIR 10 15 10
2274 85+44.5 -18.63 2324.06 (FIR 10 9)FIR 10 9 10
2275 85+55.1 -17.19 2325.58 (FIR 10 13)FIR 10 13 10
2278 85+58.2 -18.20 2328.19 (OAK 10 26)OAK 10 26 10
2270 85+60.5 7.04 2328.13 (MADRONE 6 13)MADRONE 6 13 6
2279 85+63.0 -17.79 2328.67 (FIR 10 15)FIR 10 15 10
2277 85+63.2 -15.75 2326.89 (FIR 10 16)FIR 10 16 10
2276 85+74.4 -12.49 2329.29 (TREE 10)TREE 10 10
2269 85+82.8 16.20 2329.94 (OAK 18 9)OAK 18 9 18
2268 85+88.0 7.91 2330.37 (FIR 28 19)FIR 28 19 28
2280 85+93.7 -20.30 2327.22 (FIR 18 12)FIR 18 12 18
2281 86+01.3 -17.77 2326.38 (OAK 18 16)OAK 18 16 18
2267 86+08.5 8.01 2328.58 (FIR 10 7)FIR 10 7 10
2266 86+12.8 7.84 2327.74 (OAK 6 12)OAK 6 12 6
2263 86+34.6 7.05 2326.76 (FIR 8 9)FIR 8 9 8
2265 86+39.6 12.48 2333.88 (OAK 10 8)OAK 10 8 10
2264 86+42.3 10.76 2333.69 (OAK 8 13)OAK 8 13 8
PAGE 16 OF 20
2306 86+43.4 -8.83 2332.12 (FIR 10 12)FIR 10 12 10
2305 86+61.2 -9.23 2329.09 (PINE 10 9)PINE 10 9 10
2262 86+61.4 10.59 2333.68 (FIR 8 10)FIR 8 10 8
2261 86+64.6 10.76 2333.79 (FIR 8 13)FIR 8 13 8
2304 86+67.1 -9.59 2329.71 (FIR 10 12)FIR 10 12 10
2302 86+70.9 -16.52 2329.91 (FIR 10 9)FIR 10 9 10
2303 86+76.4 -9.64 2330.67 (FIR 10 18)FIR 10 18 10
2260 86+82.7 7.66 2327.78 (FIR 8 13)FIR 8 13 8
2259 86+92.4 5.81 2330.29 (PINE 24 16)PINE 24 16 24
2162 87+27.8 5.00 2330.76 (PINE 12 11)PINE 12 11 12
2163 87+31.1 16.33 2329.97 (MAPLE 12 18)MAPLE 12 18 12
2161 87+76.5 -14.56 2328.27 (FIR 24 20)FIR 24 20 24
2160 88+09.4 12.79 2330.93 (PINE 12 12)PINE 12 12 12
2156 88+18.0 -13.24 2325.32 (FIR 12 12)FIR 12 12 12
2155 88+26.1 -16.79 2329.64 (FIR 12 11)FIR 12 11 12
2158 88+26.9 8.23 2332.38 (PINE 10 8)PINE 10 8 10
2159 88+28.5 11.20 2332.67 (TREE 6)TREE 6 6
2157 88+30.6 8.45 2332.66 (PINE 12 11)PINE 12 11 12
2154 88+39.6 -17.74 2327.68 (OAK 8 28)OAK 8 28 8
2149 88+52.7 9.28 2331.53 (PINE 10 8)PINE 10 8 10
2153 88+65.7 -8.54 2332.72 (FIR 14 18)FIR 14 18 14
2152 88+69.0 -19.35 2332.97 (FIR 14 12)FIR 14 12 14
2148 88+69.7 13.13 2331.65 (FIR 14 13)FIR 14 13 14
2151 88+70.9 -11.05 2326.23 (PINE 14 18)PINE 14 18 14
2150 88+78.4 -10.43 2331.18 (PINE 10 11)PINE 10 11 10
2147 88+81.0 11.24 2333.59 (PINE 18 25)PINE 18 25 18
2169 89+33.1 17.54 2333.35 (PINE 24 25)PINE 24 25 24
1958 89+69.6 -13.08 2328.68 (OAK 8 16)OAK 8 16 8
9001958 90+17.0 -7.44 (MADRONE 6 10)MADRONE 6 10 6
1959 90+37.4 -10.29 2330.19 (FIR 12 9)FIR 12 9 12
1960 90+55.0 -9.40 2327.94 (FIR 10 12)FIR 10 12 10
1901 90+72.7 10.31 2335.13 (FIR 24 14)FIR 24 14 24
1869 90+92.3 -16.63 2324.48 (PINE 12 15)PINE 12 15 12
1870 91+00.8 -16.09 2324.20 (PINE 12 15)PINE 12 15 12
1871 91+05.7 15.82 2325.03 (PINE 12 15)PINE 12 15 12
1875 91+19.4 -17.04 2323.89 (PINE 12 15)PINE 12 15 12
1873 91+19.6 -17.38 2324.69 (PINE 12 18)PINE 12 18 12
1874 91+29.0 -17.66 2325.15 (PINE 12 15)PINE 12 15 12
1872 91+39.5 -11.36 2329.40 (PINE 12 18)PINE 12 18 12
1902 91+42.1 13.96 2331.27 (FIR 10 14)FIR 10 14 10
1903 91+50.1 6.01 2331.91 (TREE 10)TREE 10 10
1904 91+60.2 6.03 2330.40 (OAK 10 20)OAK 10 20 10
1905 91+61.7 6.51 2330.28 (OAK 10 20)OAK 10 20 10
1907 91+85.5 -17.01 2328.39 (FIR 36 19)FIR 36 19 36
PAGE 17 OF 20
1906 91+94.8 5.49 2330.07 (FIR 10 10)FIR 10 10 10
1908 91+96.9 -16.39 2327.16 (FIR 18 16)FIR 18 16 18
1909 92+08.1 -16.39 2325.93 (FIR 14 14)FIR 14 14 14
9001906 92+13.1 6.81 (FIR 14 18)FIR 14 18 14
1910 92+23.0 -16.96 (FIR 24 25)FIR 24 25 24
9000082 92+44.8 16.60 (FIR 8 18)FIR 8 18 8
1801 92+81.6 -25.69 2326.63 (FIR 20 16)FIR 20 16 20
1800 92+91.2 -24.08 2327.84 (OAK 16 25)OAK 16 25 16
1799 92+98.6 -19.02 2328.83 (FIR 16 18)FIR 16 18 16
1798 93+09.3 -17.85 2329.44 (FIR 20 17)FIR 20 17 20
1796 93+15.3 8.81 2333.11 (MADRONE 8 8)MADRONE 8 8 8
1795 93+20.9 10.05 2333.08 (MADRONE 8 5)MADRONE 8 5 8
1664 93+21.2 14.25 2336.50 (FIR 6 14)FIR 6 14 6
1794 93+22.6 8.52 2332.11 (MADRONE 8 15)MADRONE 8 15 8
1797 93+38.6 -16.81 2325.79 (OAK 16 37)OAK 16 37 16
1792 93+81.8 -14.74 2326.61 (FIR 6 8)FIR 6 8 6
1791 93+94.7 -17.63 2326.02 (OAK 12 18)OAK 12 18 12
1790 93+96.6 -16.01 2325.57 (OAK 12 18)OAK 12 18 12
1789 94+07.3 -13.93 2327.36 (OAK 12 19)OAK 12 19 12
1793 94+12.4 6.54 2329.84 (OAK 6 11)OAK 6 11 6
1788 94+18.5 -15.79 2329.67 (FIR 12 16)FIR 12 16 12
1679 94+36.0 -14.29 2326.32 (OAK 12 18)OAK 12 18 12
1680 94+36.6 -12.61 2327.86 (OAK 10 14)OAK 10 14 10
1681 94+39.2 -12.65 2327.29 (OAK 8 18)OAK 8 18 8
1684 94+42.2 17.79 2334.03 (OAK 12 12)OAK 12 12 12
1683 94+43.5 9.50 2331.47 (OAK 10 10 DEAD)OAK 10 10 DEAD 10
1685 94+58.7 5.17 2330.66 (FIR 8 15)FIR 8 15 8
1682 94+61.8 -14.71 2329.11 (OAK 10 15)OAK 10 15 10
1687 94+63.3 24.99 2339.29 (OAK 8 15)OAK 8 15 8
1678 94+63.7 -15.26 2326.53 (OAK 12 15)OAK 12 15 12
1686 94+70.0 21.50 2337.97 (OAK 8 13)OAK 8 13 8
1677 94+87.4 -18.01 2324.72 (MADRONE 14 20)MADRONE 14 20 14
1688 94+87.6 25.56 2339.96 (FIR 12 18)FIR 12 18 12
1691 94+92.6 17.95 2335.92 (OAK 10 18)OAK 10 18 10
1690 94+97.1 16.43 2335.46 (MADRONE 8 20)MADRONE 8 20 8
1689 94+98.0 17.00 2335.65 (MADRONE 6 18)MADRONE 6 18 6
1694 95+04.5 25.49 2339.14 (MADRONE 8 14)MADRONE 8 14 8
1692 95+08.8 14.08 2334.97 (OAK 6 25)OAK 6 25 6
1693 95+11.7 15.37 2334.88 (OAK 8 22)OAK 8 22 8
1676 95+16.2 -12.78 2327.46 (OAK 10 8 DEAD)OAK 10 8 DEAD 10
1695 95+27.3 12.51 2334.45 (MADRONE 6 20)MADRONE 6 20 6
1675 95+42.1 -22.46 2325.09 (FIR 6 10)FIR 6 10 6
1696 95+43.7 9.97 2333.19 (MADRONE 8 15)MADRONE 8 15 8
1697 95+45.6 9.77 2333.21 (MADRONE 8 15)MADRONE 8 15 8
PAGE 18 OF 20
1674 95+53.9 -20.25 2322.21 (FIR 8 9)FIR 8 9 8
1672 95+56.7 -11.51 2329.97 (OAK 12 9)OAK 12 9 12
1671 95+60.9 -13.23 2330.17 (MADRONE 12 14)MADRONE 12 14 12
1698 95+63.5 13.93 2334.83 (MADRONE 8 15)MADRONE 8 15 8
1699 95+63.5 10.70 2333.70 (MADRONE 8 17)MADRONE 8 17 8
1673 95+69.2 -21.33 2327.30 (MADRONE 8 10)MADRONE 8 10 8
1700 95+79.5 6.11 2332.04 (MADRONE 10 18)MADRONE 10 18 10
1670 96+00.3 -16.13 2325.19 (OAK 12 20)OAK 12 20 12
1701 96+01.3 15.49 2337.06 (MADRONE 8 18)MADRONE 8 18 8
1665 96+43.4 6.04 2331.84 (FIR 6 9)FIR 6 9 6
1667 96+64.7 22.43 2338.63 (MADRONE 8 18)MADRONE 8 18 8
1668 96+66.9 25.19 2340.07 (MADRONE 8 18)MADRONE 8 18 8
1663 96+80.4 -17.45 2326.29 (OAK 14 25)OAK 14 25 14
1666 96+86.2 7.31 2331.47 (MADRONE 8 11)MADRONE 8 11 8
1669 96+87.7 21.00 2337.70 (FIR 8 12)FIR 8 12 8
1662 96+97.0 -26.40 2324.41 (MADRONE 14 24)MADRONE 14 24 14
1660 97+10.2 5.90 2331.43 (MADRONE 8 20)MADRONE 8 20 8
1661 97+20.1 -20.58 2326.63 (MADRONE 8 22)MADRONE 8 22 8
1654 97+32.2 -13.98 2325.09 (OAK 12 18)OAK 12 18 12
1656 97+32.4 -16.52 2325.21 (MADRONE 6 8)MADRONE 6 8 6
1659 97+37.7 13.41 2336.07 (MADRONE 10 19)MADRONE 10 19 10
1653 97+40.2 -12.35 2326.32 (MADRONE 10 9)MADRONE 10 9 10
1658 97+42.6 9.80 2333.63 (FIR 8 11)FIR 8 11 8
1655 97+57.2 -22.50 2324.86 (MADRONE 12 23)MADRONE 12 23 12
1657 97+62.6 7.55 2335.51 (FIR 8 14)FIR 8 14 8
1651 97+83.3 10.40 2337.91 (FIR 24 10)FIR 24 10 24
1652 97+88.1 -20.01 2324.10 (MADRONE 10 11)MADRONE 10 11 10
1650 97+92.1 12.24 2337.25 (FIR 21 10)FIR 21 10 21
1649 97+95.1 -13.90 2326.45 (MADRONE 12 11)MADRONE 12 11 12
1557 98+25.6 -12.44 2326.32 (TREE 10)TREE 10 10
1556 98+41.3 -12.52 2326.68 (OAK 10 14)OAK 10 14 10
1555 98+43.3 -15.69 2323.81 (MADRONE 10 17)MADRONE 10 17 10
1554 98+73.5 -17.11 2321.88 (FIR 10 22)FIR 10 22 10
1553 98+87.0 -16.82 2322.79 (MADRONE 8 16)MADRONE 8 16 8
1552 99+00.9 -16.27 2323.29 (MADRONE 12 14)MADRONE 12 14 12
1551 99+09.6 -12.40 2325.46 (MADRONE 8 15)MADRONE 8 15 8
1592 99+10.6 9.53 2334.98 (MADRONE 6 6)MADRONE 6 6 6
1550 99+16.5 -19.46 2320.11 (MADRONE 10 5)MADRONE 10 5 10
1591 99+19.0 14.96 2338.95 (MADRONE 6 10)MADRONE 6 10 6
1549 99+23.4 -21.25 2321.67 (MADRONE 7 10)MADRONE 7 10 7
1547 99+38.7 -20.15 2324.84 (MADRONE 8 10)MADRONE 8 10 8
1590 99+40.8 7.08 2333.79 (MADRONE 6 5)MADRONE 6 5 6
1545 99+47.0 -22.83 2322.00 (MADRONE 8 8)MADRONE 8 8 8
1546 99+50.4 -24.33 2320.44 (MADRONE 8 8)MADRONE 8 8 8
PAGE 19 OF 20
1544 99+52.3 -17.88 2325.08 (MADRON 8 9)MADRON 8 9 8
1543 99+55.7 -10.92 2330.42 (MADRON 15 9)MADRON 15 9 15
1541 99+63.7 -11.05 2327.37 (MADRONE 15 8)MADRONE 15 8 15
1537 100+19.3 11.98 2337.02 (FIR 12 12)FIR 12 12 12
1536 100+25.1 11.70 2334.15 (FIR 12 8)FIR 12 8 12
1540 100+31.2 -25.81 2326.74 (FIR 18 12)FIR 18 12 18
1535 100+33.4 8.43 2337.35 (FIR 12 12)FIR 12 12 12
1534 100+33.9 8.80 2335.72 (FIR 18 9)FIR 18 9 18
1459 100+34.4 8.58 2336.09 (FIR 10 22)FIR 10 22 10
1539 100+36.4 -19.71 2324.83 (OAK 10 9)OAK 10 9 10
1533 100+45.0 6.98 2340.43 (FIR 18 15)FIR 18 15 18
1458 100+45.2 6.58 2335.25 (FIR 10 22)FIR 10 22 10
1457 100+53.7 12.12 2336.62 (FIR 8 19)FIR 8 19 8
1538 100+55.3 -18.17 2320.56 (OAK 12 8)OAK 12 8 12
1456 100+84.7 6.86 2331.84 (FIR 6 15)FIR 6 15 6
1478 101+28.8 14.34 2335.11 (FIR 22 40)FIR 22 40 22
1444 101+66.5 -20.75 2328.27 (FIR 30 50)FIR 30 50 30
1431 101+84.4 15.61 2334.87 (MADRONE 8 14)MADRONE 8 14 8
1443 102+20.7 8.13 2326.07 (MADRONE 14 20)MADRONE 14 20 14
1417 102+54.2 -23.50 2328.52 (MADRONE 8 14)MADRONE 8 14 8
1427 102+91.7 21.91 2334.65 (MADRONE 6 12)MADRONE 6 12 6
1406 102+99.9 -21.34 2328.19 (MAPLE 6 18)MAPLE 6 18 6
1395 103+49.6 14.57 2334.47 (OAK 6 13)OAK 6 13 6
1394 103+78.8 8.40 2329.91 (PINE 6 11)PINE 6 11 6
1382 104+00.4 14.69 2335.30 (MADRONE 18 28)MADRONE 18 28 18
1381 104+05.1 21.41 2335.30 (OAK 6 13)OAK 6 13 6
1303 104+74.0 -25.57 2328.87 (MADRONE 15 24)MADRONE 15 24 15
1312 104+79.6 19.42 2337.62 (PINE 18 24)PINE 18 24 18
1291 104+89.6 16.75 2335.08 (MADRONE 8 14)MADRONE 8 14 8
1292 104+92.8 15.44 2334.98 (OAK 6 13)OAK 6 13 6
1288 105+11.3 22.21 2334.41 (OAK 6 13)OAK 6 13 6
1257 106+01.1 -22.27 2328.39 (PINE 12 18)PINE 12 18 12
1239 106+37.0 -28.90 2328.54 (OAK 8 19)OAK 8 19 8
1174 106+64.9 13.86 2334.34 (PINE 14 20)PINE 14 20 14
1219 106+70.4 -30.23 2328.56 (OAK 10 23)OAK 10 23 10
1173 106+84.7 14.11 2331.89 (PINE 2 7)PINE 2 7 2
53 107+03.7 -29.34 2325.99 (OAK 6 20)OAK 6 20 6
64 107+03.9 -34.00 2325.99 (OAK 6 20)OAK 6 20 6
1109 107+04.2 -31.56 2325.99 (OAK 6 20)OAK 6 20 6
1015 107+59.5 10.55 2334.53 (PINE 6 11)PINE 6 11 6
1016 107+68.8 9.55 2335.14 (PINE 6 11)PINE 6 11 6
Out of Range: The Point is not adjacent to alignment.
PAGE 20 OF 20
Appendix D
Adkins Consulting Engineering, LLP
Page D-1
Photo 1: Dual CMP Crossing at Leonard Street
Photo 2: Starlite Monitoring Station
Appendix D
Adkins Consulting Engineering, LLP
Page D-2
Photo 3: Typical Cast in Place Turnout
Photo 4: Cipoletti Weir & Trash Rack
Appendix D
Adkins Consulting Engineering, LLP
Page D-3
Photo 5: Potential Conflicting Tree
Photo 6: Balcony Over Canal Easement
Appendix D
Adkins Consulting Engineering, LLP
Page D-4
Photo 7: S. Mountain Avenue Crossing
Photo 8: North Basin
Appendix D
Adkins Consulting Engineering, LLP
Page D-5
Photo 9: 12-inch Steel Drainage Pipe
Photo 10: 12-inch CPP Drainage Pipe
Appendix D
Adkins Consulting Engineering, LLP
Page D-6
Photo 11: Roof/Footing Drain
Photo 12: Trail Section
Appendix D
Adkins Consulting Engineering, LLP
Page D-7
Photo 13: Seepage Test Dam Construction
Photo 14: Seepage Test Dam
Appendix D
Adkins Consulting Engineering, LLP
Page D-8
Photo 15: Staff Gauge from Seepage Test
Photo 16: Seepage Test 1 at 944 Pinecrest Street
Appendix D
Adkins Consulting Engineering, LLP
Page D-9
Photo 17: Seepage Test 2 South of Woodland and Leonard Street
Photo 18: Seepage Test 2 Site Condition
Appendix D
Adkins Consulting Engineering, LLP
Page D-10
Photo 19: Seepage Test 3 East of Elkader Street
Photo 20: Canal Liner Cracking Due To Tree Roots at Seepage Test 3
Ashland Canal Piping Project Crossing 3 and Roca Creek
100 ft
N
➤➤
N© 2018 Google
© 2018 Google
© 2018 Google
Ashland Canal Piping Project
U.S. Fish and Wildlife Service, National Standards and Support Team,[email protected]
WetlandsEstuarine and Marine DeepwaterEstuarine and Marine Wetland
Freshwater Emergent WetlandFreshwater Forested/Shrub WetlandFreshwater Pond
LakeOtherRiverine
August 30, 2018
0 0.2 0.40.1 mi
0 0.35 0.70.175 km
1:12,980
This page was produced by the NWI mapperNational Wetlands Inventory (NWI)
This map is for general reference only. The US Fish and Wildlife Service is not responsible for the accuracy or currentness of the base data shown on this map. All wetlands related data should be used in accordance with the layer metadata found on the Wetlands Mapper web site.
Hydric Rating by Map Unit—Jackson County Area, Oregon, Parts of Jackson and Klamath Counties
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
8/30/2018Page 1 of 5
4669
200
4669
400
4669
600
4669
800
4670
000
4670
200
4670
400
4669
200
4669
400
4669
600
4669
800
4670
000
4670
200
4670
400
4670
600523500 523700 523900 524100 524300 524500 524700 524900 525100 525300 525500
523500 523700 523900 524100 524300 524500 524700 524900 525100 525300 525500
42° 11' 13'' N12
2° 4
2' 5
8'' W
42° 11' 13'' N
122°
41'
22'
' W
42° 10' 27'' N
122°
42'
58'
' W
42° 10' 27'' N
122°
41'
22'
' W
N
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 10N WGS840 450 900 1800 2700
Feet0 100 200 400 600
MetersMap Scale: 1:10,100 if printed on A landscape (11" x 8.5") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)Area of Interest (AOI)
SoilsSoil Rating Polygons
Hydric (100%)
Hydric (66 to 99%)
Hydric (33 to 65%)
Hydric (1 to 32%)
Not Hydric (0%)
Not rated or not available
Soil Rating LinesHydric (100%)
Hydric (66 to 99%)
Hydric (33 to 65%)
Hydric (1 to 32%)
Not Hydric (0%)
Not rated or not available
Soil Rating PointsHydric (100%)
Hydric (66 to 99%)
Hydric (33 to 65%)
Hydric (1 to 32%)
Not Hydric (0%)
Not rated or not available
Water FeaturesStreams and Canals
TransportationRails
Interstate Highways
US Routes
Major Roads
Local Roads
BackgroundAerial Photography
The soil surveys that comprise your AOI were mapped at 1:20,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause misunderstanding of the detail of mapping and accuracy of soil line placement. The maps do not show the small areas of contrasting soils that could have been shown at a more detailed scale.
Please rely on the bar scale on each map sheet for map measurements.
Source of Map: Natural Resources Conservation ServiceWeb Soil Survey URL: Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator projection, which preserves direction and shape but distorts distance and area. A projection that preserves area, such as the Albers equal-area conic projection, should be used if more accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as of the version date(s) listed below.
Soil Survey Area: Jackson County Area, Oregon, Parts of Jackson and Klamath CountiesSurvey Area Data: Version 15, Oct 5, 2017
Soil map units are labeled (as space allows) for map scales 1:50,000 or larger.
Date(s) aerial images were photographed: Jul 3, 2014—Sep 27, 2016
The orthophoto or other base map on which the soil lines were compiled and digitized probably differs from the background imagery displayed on these maps. As a result, some minor shifting of map unit boundaries may be evident.
Hydric Rating by Map Unit—Jackson County Area, Oregon, Parts of Jackson and Klamath Counties
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
8/30/2018Page 2 of 5
Hydric Rating by Map Unit
Map unit symbol Map unit name Rating Acres in AOI Percent of AOI
100B Kubli loam, 3 to 7 percent slopes
3 9.7 1.8%
109E Manita-Vannoy complex, 20 to 40 percent slopes
2 1.1 0.2%
127A Medford silty clay loam, 0 to 3 percent slopes
3 0.0 0.0%
164B Shefflein loam, 2 to 7 percent slopes
4 9.9 1.9%
164D Shefflein loam, 7 to 20 percent slopes
3 121.2 22.6%
165E Shefflein loam, 20 to 35 percent north slopes
2 245.5 45.8%
166E Shefflein loam, 20 to 35 percent south slopes
2 33.1 6.2%
188G Tallowbox gravelly sandy loam, 35 to 70 percent north slopes
0 90.2 16.8%
189G Tallowbox gravelly sandy loam, 35 to 60 percent south slopes
0 25.2 4.7%
Totals for Area of Interest 535.9 100.0%
Hydric Rating by Map Unit—Jackson County Area, Oregon, Parts of Jackson and Klamath Counties
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
8/30/2018Page 3 of 5
Description
This rating indicates the percentage of map units that meets the criteria for hydric soils. Map units are composed of one or more map unit components or soil types, each of which is rated as hydric soil or not hydric. Map units that are made up dominantly of hydric soils may have small areas of minor nonhydric components in the higher positions on the landform, and map units that are made up dominantly of nonhydric soils may have small areas of minor hydric components in the lower positions on the landform. Each map unit is rated based on its respective components and the percentage of each component within the map unit.
The thematic map is color coded based on the composition of hydric components. The five color classes are separated as 100 percent hydric components, 66 to 99 percent hydric components, 33 to 65 percent hydric components, 1 to 32 percent hydric components, and less than one percent hydric components.
In Web Soil Survey, the Summary by Map Unit table that is displayed below the map pane contains a column named 'Rating'. In this column the percentage of each map unit that is classified as hydric is displayed.
Hydric soils are defined by the National Technical Committee for Hydric Soils (NTCHS) as soils that formed under conditions of saturation, flooding, or ponding long enough during the growing season to develop anaerobic conditions in the upper part (Federal Register, 1994). Under natural conditions, these soils are either saturated or inundated long enough during the growing season to support the growth and reproduction of hydrophytic vegetation.
The NTCHS definition identifies general soil properties that are associated with wetness. In order to determine whether a specific soil is a hydric soil or nonhydric soil, however, more specific information, such as information about the depth and duration of the water table, is needed. Thus, criteria that identify those estimated soil properties unique to hydric soils have been established (Federal Register, 2002). These criteria are used to identify map unit components that normally are associated with wetlands. The criteria used are selected estimated soil properties that are described in "Soil Taxonomy" (Soil Survey Staff, 1999) and "Keys to Soil Taxonomy" (Soil Survey Staff, 2006) and in the "Soil Survey Manual" (Soil Survey Division Staff, 1993).
If soils are wet enough for a long enough period of time to be considered hydric, they should exhibit certain properties that can be easily observed in the field. These visible properties are indicators of hydric soils. The indicators used to make onsite determinations of hydric soils are specified in "Field Indicators of Hydric Soils in the United States" (Hurt and Vasilas, 2006).
References:
Federal Register. July 13, 1994. Changes in hydric soils of the United States.
Federal Register. September 18, 2002. Hydric soils of the United States.
Hydric Rating by Map Unit—Jackson County Area, Oregon, Parts of Jackson and Klamath Counties
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
8/30/2018Page 4 of 5
Hurt, G.W., and L.M. Vasilas, editors. Version 6.0, 2006. Field indicators of hydric soils in the United States.
Soil Survey Division Staff. 1993. Soil survey manual. Soil Conservation Service. U.S. Department of Agriculture Handbook 18.
Soil Survey Staff. 1999. Soil taxonomy: A basic system of soil classification for making and interpreting soil surveys. 2nd edition. Natural Resources Conservation Service. U.S. Department of Agriculture Handbook 436.
Soil Survey Staff. 2006. Keys to soil taxonomy. 10th edition. U.S. Department of Agriculture, Natural Resources Conservation Service.
Rating Options
Aggregation Method: Percent Present
Component Percent Cutoff: None Specified
Tie-break Rule: Lower
Hydric Rating by Map Unit—Jackson County Area, Oregon, Parts of Jackson and Klamath Counties
Natural ResourcesConservation Service
Web Soil SurveyNational Cooperative Soil Survey
8/30/2018Page 5 of 5
WETLAND DETERMINATION DATA FORM – Western Mountains, Valleys, and Coast Region Project/Site: Ashland Canal Piping City/County: Ashland, Jackson Sampling Date: 5/15/18 Applicant/Owner: City of Ashland State: OR Sampling Point: 1 Investigator(s): Sue Brady Section, Township, Range: T39S R1E Section 16 Landform (hillslope, terrace, etc.): hillslope Local relief (concave, convex, none): concave Slope (%): 5 Subregion (LRR): LLR A Lat: 42.1805 Long: -122.7054 Datum: W.M. Soil Map Unit Name: Shefflein loam, 20 to 35 percent north slopes NWI classification: R4SBC Are climatic/hydrologic conditions on the site typical for this time of year? Yes (if no, explain in Remarks.) Are Vegetation , Soil , or Hydrology significantly disturbed? Are “Normal Circumstances” present? yes Are Vegetation , Soil , or Hydrology naturally problematic? (If needed, explain any answers in Remarks.) SUMMARY OF FINDINGS – Attach site map showing sampling point locations, transects, important features, etc.
Hydrophytic Vegetation Present? no Hydric Soil Present? no Wetland Hydrology Present? no
Is the Sampled Area within a Wetland? no
Remarks:
VEGETATION – Use scientific names of plants.
Tree Stratum (Plot size: 25m2 ) 1. Quercus garryana 2. 3. 4. Total Cover =30
Absolute % Cover
30
Dominant Species?
Y
Indicator Status FACU
Dominance Test worksheet: Number of Dominant Species That Are OBL, FACW, or FAC: 1 (A) Total Number of Dominant Species Across All Strata: 5 (B) Percent of Dominant Species That Are OBL, FACW, or FAC: 20 (A/B)
Sapling/Shrub Stratum (Plot size: 25m2 ) 1. Rubus sp 2. Rosa sp. 3. Rubus parviflorus 4. 5. Total Cover = 50
30 10 10
Y Y Y
FACU FACU FAC
Prevalence Index worksheet: Total % Cover of: Multiply by: OBL species x 1 = FACW species x 2 = FAC species 20 x 3 = 60 FACU species 80 x 4= 320 UPL species 40 x 5= 200 Column Totals: 140 (A) 580 (B) Prevalence Index = B/A = 4.14
Hydrophytic Vegetation Indicators:
1 – Rapid Test for Hydrophytic Vegetation 2 - Dominance Test is >50% 3 - Prevalence Index is ≤ 3.01
4 - Morphological Adaptations1 (Provide
supporting data in Remarks or on a separate sheet)
5 – Wetland Non-Vascular Plants1
Herb Stratum (Plot size: 4m2 ) 1. Bromus diandrus 2. Anthriscus caucalis 3. Galium trifolium 4. Toxicodendron diversilobum 5. 6. 7. 8. 9. 10. 11. Total Cover = 60
10 30 10 10
N Y N N
UPL UPL
FACU FAC
Woody Vine Stratum (Plot size: ) 1. 2. Total Cover = % Bare Ground in Herb Stratum: 40
Problematic Hydrophytic Vegetation1 (Explain)
1Indicators of hydric soil and wetland hydrology must be present, unless disturbed or problematic.
Hydrophytic Vegetation Present? no
Remarks:
SOIL Sampling Point: 1 Profile Description: (Describe to the depth needed to document the indicator or confirm the absence of indicators.) Matrix Redox Features
Depth (inches)
0-6 6-24
Color (moist)
10YR 3/3 10YR 4/3
%
100 100
Color (moist)
%
Type1
Loc2
Texture Silty clay loam Silty clay loam
Remarks
1Type: C=Concentration, D=Depletion, RM=Reduced Matrix, CS=Covered or Coated Sand Grains. 2Location: PL=Pore Lining, M=Matrix
Hydric Soil Indicators: (Applicable to all LRRs, unless otherwise noted.) Indicators for Problematic Hydric Soils3:
Histosol (A1) Histic Epipedon (A2) Black Histic (A3) Hydrogen Sulfide (A4) Depleted Below Dark Surface (A11) Thick Dark Surface (A12) Sandy Mucky Mineral (S1) Sandy Gleyed Matrix (S4)
Sandy Redox (S5) Stripped Matrix (S6) Loamy Mucky Mineral (F1) (except MLRA 1) Loamy Gleyed Matrix (F2) Depleted Matrix (F3) Redox Dark Surface (F6) Depleted Dark Surface (F7) Redox Depressions (F8)
2 cm Muck (A10) Red Parent Material (TF2) Very Shallow Dark Surface (TF12) Other (Explain in Remarks)
3Indicators of hydrophytic vegetation and wetland hydrology must be present, unless disturbed or problematic.
Restrictive Layer (if present): Type: Depth (inches):
Hydric Soil Present? no
Remarks:
HYDROLOGY
Wetland Hydrology Indicators: Primary Indicators (minimum of one required; check all that apply) Secondary Indicators (2 or more required)
Surface Water (A1) High Water Table (A2) Saturation (A3) Water Marks (B1) Sediment Deposits (B2) Drift Deposits (B3) Algal Mat or Crust (B4) Iron Deposits (B5) Surface Soil Cracks (B6) Inundation Visible on Aerial Imagery (B7) Sparsely Vegetated Concave Surface (B8)
Water-Stained Leaves (B9) (except MLRA 1, 2, 4A, and 4B)
Salt Crust (B11) Aquatic Invertebrates (B13) Hydrogen Sulfide Odor (C1) Oxidized Rhizospheres along Living Roots
(C3) Presence of Reduced Iron (C4) Recent Iron Reduction in Tilled Soils (C6) Stunted or Stressed Plants (D1) (LRR A) Other (Explain in Remarks)
Water-Stained Leaves (B9 ) (MLRA 1, 2, 4A, 4B)
Drainage Patterns (B10) Dry-Season Water Table (C2) Saturation Visible on Aerial Imagery (C9) Geomorphic Position (D2) Shallow Aquitard (D3) FAC-Neutral Test (D5) Raised Ant Mounds (D 6)(LRR A) Frost-Heave Hummocks (D7)
Field Observations: Surface Water Present? no Depth (inches): Water Table Present? no Depth (inches): Saturation Present? no Depth (inches): (includes capillary fringe)
Wetland Hydrology Present? no
Describe Recorded Data (stream gauge, monitoring well, aerial photos, previous inspections), if available:
Remarks:
WETLAND DETERMINATION DATA FORM – Western Mountains, Valleys, and Coast Region Project/Site: Ashland Canal Piping City/County: Ashland, Jackson Sampling Date: 5/15/18 Applicant/Owner: City of Ashland State: OR Sampling Point: 2 Investigator(s): Sue Brady Section, Township, Range: T39S R1E Section 16 Landform (hillslope, terrace, etc.): hillslope Local relief (concave, convex, none): concave Slope (%): 2 Subregion (LRR): LLR A Lat: 42.1796 Long: -122.7040 Datum: W.M. Soil Map Unit Name: Shefflein loam, 20 to 35 percent north slopes NWI classification: R4SBC Are climatic/hydrologic conditions on the site typical for this time of year? Yes (if no, explain in Remarks.) Are Vegetation , Soil , or Hydrology significantly disturbed? Are “Normal Circumstances” present? yes Are Vegetation , Soil , or Hydrology naturally problematic? (If needed, explain any answers in Remarks.) SUMMARY OF FINDINGS – Attach site map showing sampling point locations, transects, important features, etc.
Hydrophytic Vegetation Present? no Hydric Soil Present? no Wetland Hydrology Present? no
Is the Sampled Area within a Wetland? no
Remarks:
VEGETATION – Use scientific names of plants.
Tree Stratum (Plot size: 25m2 ) 1. Pinus ponderosa 2. Quercus garryana 3. Arbutus menziesii 4. Total Cover = 50
Absolute % Cover
20 20 10
Dominant Species?
Y Y Y
Indicator Status FACU FACU UPL
Dominance Test worksheet: Number of Dominant Species That Are OBL, FACW, or FAC: 2 (A) Total Number of Dominant Species Across All Strata: 9 (B) Percent of Dominant Species That Are OBL, FACW, or FAC: 22 (A/B)
Sapling/Shrub Stratum (Plot size: 25m2 ) 1. Rubus parviflorus 2. Rubus sp. 3. 4. 5. Total Cover = 60
30 30
Y Y
FAC
FACU
Prevalence Index worksheet: Total % Cover of: Multiply by: OBL species x 1 = FACW species x 2 = FAC species 50 x 3 = 150 FACU species 90 x 4 = 360 UPL species 70 x 5 = 350 Column Totals: 210 (A) 860 (B) Prevalence Index = B/A = 4.10
Hydrophytic Vegetation Indicators:
1 – Rapid Test for Hydrophytic Vegetation 2 - Dominance Test is >50% 3 - Prevalence Index is ≤ 3.01
4 - Morphological Adaptations1 (Provide
supporting data in Remarks or on a separate sheet)
5 – Wetland Non-Vascular Plants1
Herb Stratum (Plot size: 4m2 ) 1. Anthriscus caucalis 2. Bromus diandrus 3. Bromus tectorum 4. Achillea millefolium 5. Fragaria vesca 6. Festuca rubra 7. 8. 9. 10. 11. Total Cover = 100
20 20 20 10 10 20
Y Y Y N N Y
UPL UPL UPL
FACU FACU FAC
Woody Vine Stratum (Plot size: ) 1. 2. Total Cover = % Bare Ground in Herb Stratum: 0
Problematic Hydrophytic Vegetation1 (Explain)
1Indicators of hydric soil and wetland hydrology must be present, unless disturbed or problematic.
Hydrophytic Vegetation Present? no
Remarks:
SOIL Sampling Point: 2 Profile Description: (Describe to the depth needed to document the indicator or confirm the absence of indicators.) Matrix Redox Features
Depth (inches)
0-8 8-18
18-25
Color (moist)
10YR 3/3 10YR 3/4 10YR 4/3
%
100 100 100
Color (moist)
%
Type1
Loc2
Texture Silty clay loam Silty clay loam Silty clay loam
Remarks
1Type: C=Concentration, D=Depletion, RM=Reduced Matrix, CS=Covered or Coated Sand Grains. 2Location: PL=Pore Lining, M=Matrix
Hydric Soil Indicators: (Applicable to all LRRs, unless otherwise noted.) Indicators for Problematic Hydric Soils3:
Histosol (A1) Histic Epipedon (A2) Black Histic (A3) Hydrogen Sulfide (A4) Depleted Below Dark Surface (A11) Thick Dark Surface (A12) Sandy Mucky Mineral (S1) Sandy Gleyed Matrix (S4)
Sandy Redox (S5) Stripped Matrix (S6) Loamy Mucky Mineral (F1) (except MLRA 1) Loamy Gleyed Matrix (F2) Depleted Matrix (F3) Redox Dark Surface (F6) Depleted Dark Surface (F7) Redox Depressions (F8)
2 cm Muck (A10) Red Parent Material (TF2) Very Shallow Dark Surface (TF12) Other (Explain in Remarks)
3Indicators of hydrophytic vegetation and wetland hydrology must be present, unless disturbed or problematic.
Restrictive Layer (if present): Type: Depth (inches):
Hydric Soil Present? no
Remarks:
HYDROLOGY
Wetland Hydrology Indicators: Primary Indicators (minimum of one required; check all that apply) Secondary Indicators (2 or more required)
Surface Water (A1) High Water Table (A2) Saturation (A3) Water Marks (B1) Sediment Deposits (B2) Drift Deposits (B3) Algal Mat or Crust (B4) Iron Deposits (B5) Surface Soil Cracks (B6) Inundation Visible on Aerial Imagery (B7) Sparsely Vegetated Concave Surface (B8)
Water-Stained Leaves (B9) (except MLRA 1, 2, 4A, and 4B)
Salt Crust (B11) Aquatic Invertebrates (B13) Hydrogen Sulfide Odor (C1) Oxidized Rhizospheres along Living Roots
(C3) Presence of Reduced Iron (C4) Recent Iron Reduction in Tilled Soils (C6) Stunted or Stressed Plants (D1) (LRR A) Other (Explain in Remarks)
Water-Stained Leaves (B9 ) (MLRA 1, 2, 4A, 4B)
Drainage Patterns (B10) Dry-Season Water Table (C2) Saturation Visible on Aerial Imagery (C9) Geomorphic Position (D2) Shallow Aquitard (D3) FAC-Neutral Test (D5) Raised Ant Mounds (D 6)(LRR A) Frost-Heave Hummocks (D7)
Field Observations: Surface Water Present? no Depth (inches): Water Table Present? no Depth (inches): Saturation Present? no Depth (inches): (includes capillary fringe)
Wetland Hydrology Present? no
Describe Recorded Data (stream gauge, monitoring well, aerial photos, previous inspections), if available:
Remarks:
WETLAND DETERMINATION DATA FORM – Western Mountains, Valleys, and Coast Region Project/Site: Ashland Canal Piping City/County: Ashland, Jackson Sampling Date: 5/14/18 Applicant/Owner: City of Ashland State: OR Sampling Point: 3 Investigator(s): Sue Brady Section, Township, Range: T39S R1E Section 15 Landform (hillslope, terrace, etc.): hillslope Local relief (concave, convex, none): concave Slope (%): 5 Subregion (LRR): LLR A Lat: 42.1781 Long: -122.6977 Datum: W.M. Soil Map Unit Name: Kubli loam, 3 to 7 percent slopes NWI classification: R4SBC Are climatic/hydrologic conditions on the site typical for this time of year? Yes (if no, explain in Remarks.) Are Vegetation , Soil , or Hydrology significantly disturbed? Are “Normal Circumstances” present? yes Are Vegetation , Soil , or Hydrology naturally problematic? (If needed, explain any answers in Remarks.) SUMMARY OF FINDINGS – Attach site map showing sampling point locations, transects, important features, etc.
Hydrophytic Vegetation Present? no Hydric Soil Present? no Wetland Hydrology Present? no
Is the Sampled Area within a Wetland? no
Remarks:
VEGETATION – Use scientific names of plants.
Tree Stratum (Plot size: 25m2 ) 1. Pseudotsuga menziesii 2. Arbutus menziesii 3. 4. Total Cover =40
Absolute % Cover
20 20
Dominant Species?
Y Y
Indicator Status FACU UPL
Dominance Test worksheet: Number of Dominant Species That Are OBL, FACW, or FAC: 4 (A) Total Number of Dominant Species Across All Strata: 8 (B) Percent of Dominant Species That Are OBL, FACW, or FAC: 50 (A/B)
Sapling/Shrub Stratum (Plot size: 25m2 ) 1. Pseudotsuga menziesii 2. Rubus parviflorus 3. Rubus sp. 4. 5. Total Cover =50
20 20 10
Y Y N
FACU FAC
FACU
Prevalence Index worksheet: Total % Cover of: Multiply by: OBL species x 1 = FACW species x 2 = FAC species 100 x 3 = 300 FACU species 70 x 4 = 280 UPL species 20 x 5 = 100 Column Totals: 190 (A) 680 (B) Prevalence Index = B/A = 3.58
Hydrophytic Vegetation Indicators:
1 – Rapid Test for Hydrophytic Vegetation 2 - Dominance Test is >50% 3 - Prevalence Index is ≤ 3.01
4 - Morphological Adaptations1 (Provide
supporting data in Remarks or on a separate sheet)
5 – Wetland Non-Vascular Plants1
Herb Stratum (Plot size: 4m2 ) 1. Festuca rubra 2. Toxicodendron diversilobum 3. Cynoglossum officinale 4. Festuca rubra 5. 6. 7. 8. 9. 10. 11. Total Cover =100
20 30 20 30
Y Y Y Y
FAC FAC
FACU FAC
Woody Vine Stratum (Plot size: ) 1. 2. Total Cover = % Bare Ground in Herb Stratum: 0
Problematic Hydrophytic Vegetation1 (Explain)
1Indicators of hydric soil and wetland hydrology must be present, unless disturbed or problematic.
Hydrophytic Vegetation Present? no
Remarks:
SOIL Sampling Point: 3 Profile Description: (Describe to the depth needed to document the indicator or confirm the absence of indicators.) Matrix Redox Features
Depth (inches)
0-8 8-17
17-24
Color (moist)
10YR 2/2 10YR 3/2 10YR 4/2
%
100 100 100
Color (moist)
%
Type1
Loc2
Texture Silty clay loam Silty clay loam Silty clay loam
Remarks
1Type: C=Concentration, D=Depletion, RM=Reduced Matrix, CS=Covered or Coated Sand Grains. 2Location: PL=Pore Lining, M=Matrix
Hydric Soil Indicators: (Applicable to all LRRs, unless otherwise noted.) Indicators for Problematic Hydric Soils3:
Histosol (A1) Histic Epipedon (A2) Black Histic (A3) Hydrogen Sulfide (A4) Depleted Below Dark Surface (A11) Thick Dark Surface (A12) Sandy Mucky Mineral (S1) Sandy Gleyed Matrix (S4)
Sandy Redox (S5) Stripped Matrix (S6) Loamy Mucky Mineral (F1) (except MLRA 1) Loamy Gleyed Matrix (F2) Depleted Matrix (F3) Redox Dark Surface (F6) Depleted Dark Surface (F7) Redox Depressions (F8)
2 cm Muck (A10) Red Parent Material (TF2) Very Shallow Dark Surface (TF12) Other (Explain in Remarks)
3Indicators of hydrophytic vegetation and wetland hydrology must be present, unless disturbed or problematic.
Restrictive Layer (if present): Type: Depth (inches):
Hydric Soil Present? no
Remarks:
HYDROLOGY
Wetland Hydrology Indicators: Primary Indicators (minimum of one required; check all that apply) Secondary Indicators (2 or more required)
Surface Water (A1) High Water Table (A2) Saturation (A3) Water Marks (B1) Sediment Deposits (B2) Drift Deposits (B3) Algal Mat or Crust (B4) Iron Deposits (B5) Surface Soil Cracks (B6) Inundation Visible on Aerial Imagery (B7) Sparsely Vegetated Concave Surface (B8)
Water-Stained Leaves (B9) (except MLRA 1, 2, 4A, and 4B)
Salt Crust (B11) Aquatic Invertebrates (B13) Hydrogen Sulfide Odor (C1) Oxidized Rhizospheres along Living Roots
(C3) Presence of Reduced Iron (C4) Recent Iron Reduction in Tilled Soils (C6) Stunted or Stressed Plants (D1) (LRR A) Other (Explain in Remarks)
Water-Stained Leaves (B9 ) (MLRA 1, 2, 4A, 4B)
Drainage Patterns (B10) Dry-Season Water Table (C2) Saturation Visible on Aerial Imagery (C9) Geomorphic Position (D2) Shallow Aquitard (D3) FAC-Neutral Test (D5) Raised Ant Mounds (D 6)(LRR A) Frost-Heave Hummocks (D7)
Field Observations: Surface Water Present? no Depth (inches): Water Table Present? no Depth (inches): Saturation Present? no Depth (inches): (includes capillary fringe)
Wetland Hydrology Present? no
Describe Recorded Data (stream gauge, monitoring well, aerial photos, previous inspections), if available:
Remarks:
APPENDIX F Works Cited
Agriculture, U. S. (2013, April 4). Bulletin 1780-2. Preliminary Engineering Reports for the
Water and Waste Disposal . Rural Utilities Services.
Business, O. o. (2016, December 12). Whitehouse.gov. Retrieved May 29, 2017, from
https://www.whitehouse.gov/sites/whitehouse.gov/files/omb/memoranda/2017/m-17-
10.pdf
Fipps, E. L. (2009). Measuring Seepage Losses from Canals Using the Ponding Test Method.
College Station, Texas: Texas A&M AgriLife.
Michael S. Thompson, P. (2016, February 8). naruc.org. Depreciation Rates for Water
Companies. National Association of Regulatory Utility Commissioners. Retrieved May
29, 2017, from National Association of Regulatory Utility Commissioners:
https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=3&cad=rja&uact
=8&ved=0ahUKEwjAud2T9avUAhUM02MKHVUsDbIQFgg4MAI&url=http%3A%2F
%2Fwww.azcc.gov%2FDivisions%2FUtilities%2Fforms%2FDepreciationRatesWater.do
c%2520-%25202016-02-08.doc&usg=AFQjCNH2LSL
Pluimer, M. (2006). Establishing 100-Year Service Life for Corrugated HDPE Drainage Pipe.
Plastic Pipe Institute.
Reclamation, B. o. (2002). Canal Lining Demostration Project Year 10 Report. Boise, Idaho: US
Department of Interior.
Siskiyou BioSurvey, LLC. (2018). Minimizing Ecological Risks Associated with the City of
Ashlands Piping of T.I.D. Water Between Starlight Station and Terrace Street Pumping
Station. Eagle Point, OR: Siskiyou BioSurvey Ecological Consultants.
The Galli Group. (2018). Ashland Canal Piping Project. Grants Pass, Oregon: The Galli Group
Engineering Consulting.
Western Regional Climate Center. (2018, December). Climate Services. Retrieved from
https://wrcc.dri.edu/Climate/comp_tables.php