© 2021 Hitachi Energy. All rights reserved.2021-11-02
1
Remote Terminal Units (RTUs)Customer Reference Cases
© 2021 Hitachi Energy. All rights reserved.
World market leader
in medium and large RTU applications
RTU500 series installed worldwide
RTU500 installed base
2
More than 2,000 customers buy
around 10,000 RTUs per year.
More than 150,000 installed RTUs
spread over more than 100 countries active portfolio since45 years
RTU560
RTU540
RTU530
RTU520
© 2021 Hitachi Energy. All rights reserved.
Bangalore Electricity Supply Company Ltd. (BESCOM)
4
Bangalore Electricity Supply
Company Ltd. (BESCOM) is
responsible for the distribution
of electricity in three operating
zones, including the Bangalore
Metropolitan Area Zone
(BMAZ). The BMAZ
distribution network includes
more than 800 11 kV feeders
across an area of 1,600 km2,
serving almost 3 million
customers. The objective of
the upgrade project is to
improve the reliability,
efficiency and safety of the
BMAZ distribution network..
Web story
Customer benefits
About the project Solution
• Project name: Distribution system upgrade
• Location: Bangalore, India
• Customer: BESCOM
• Completion date: 2013
• Scope of supply for the Bangalore distribution
system includes the design, engineering,
manufacturing, testing, delivery, installation and
commissioning of the 700 RTU560 units
• Ensure the safety of operators and maintenance
staff working on the network
• High flexibility and compact design
• Ensure reliable and accurate data acquisition and
transmission of control commands
© 2021 Hitachi Energy. All rights reserved.
Elektra Baselland (EBL)
5
The development zone Salina
Raurica, in which a new city
district is being built, is located
in the northern municipality of
Pratteln, Switzerland. Here,
the Swiss retailer Coop is
constructing its new
manufacturing center with the
goal of finishing it in 2017.
Web story
Customer benefits
About the project Solution
• Project name: Raurica substation
• Location: Pratteln, Switzerland
• Customer: EBL
• Completion date: 2016
• Delivered protection and control equipment for
50 kV as well as 13.6 kV systems.
• Using the FOX515 communication device and
RTU560 as SA system, the substation was
connected to the control center of EBL.
• Local control at the substation is enforced via
RTU560 using a web-browser HMI.
• Reliable power supply
• Commissioning took place exactly according to
schedule.
© 2021 Hitachi Energy. All rights reserved.
Stadtwerke Weinheim
6
The Stadtwerke Weinheim
GmbH supplies the population,
industry and commerce in the
town of Weinheim, Baden-
Wuerttemberg/ Germany, and
its remaining supply area with
energy and drinking water. It
also operates supply networks
for natural gas and local heat
as well as an indoor swimming
pool.
Web storyCustomer benefits
About the project Solution
• Project name: Substation automation project
• Location: Germany
• Customer: Stadtwerke Weinheim
• The system configuration used is based on the
RTU 560 as station unit as well as the bay
control IEDs of the new IED 670 product family
• High availability of local as well as remote control
and monitoring
• Compact solution for reliable control with one bay
control IED for four switchgear bays
• Minimal service interruption
• Extensibility of the bay level with additional
functionality
• Sustainable migration strategy with flexibility for
selective modernization and future extension
© 2021 Hitachi Energy. All rights reserved.
AEW Energie AG - Dättwil substation project
7
AEW Energie AG, grid
operator in the canton of
Aargau; Switzerland, operates
multiple transformer
substations for the regional
power supply and is therefore
responsible for all medium-
and low- voltage network
services in the region. AEW
contracted Hitachi Energy
Switzerland to modernize the
control and protection
equipment for Dättwil
substation.
Web story
Customer benefits
About the project Solution
• Project name: Dättwil substation project
• Location: Switzerland
• Customer: AEW Energie AG
• Completion date: 2013
• Station control has been realized by using Hitachi
Energy’s SAS605 unit with IEC 61850
communication for the control and protection
equipment for the 110kV/16kV system.
• The RTU560 hardware is executed redundantly. In
case of loss of communication to one of the two
control centers the RTU560 automatically switches
to the redundant communication path.
• HMI control is web-browser based and an integrated
part of the RTU560
• Rigid solution, easy to configure and operate
• Enables full flexibility in the configuration of the
control system for the substation
• Provide assistance and support at any time
© 2021 Hitachi Energy. All rights reserved.
ELMŰ-ÉMÁSZ is one of
the largest Distribution
Utilities in Hungary. The
group and its member
companies provide
electricity to about two
million customers in
Budapest and its
agglomeration, Borsod-
Abaúj-Zemplén, Heves
and Nógrád counties, as
well as in some parts of
Jász-Nagykun-Szolnok
and Pest counties.
9
ELMŰ-ÉMÁSZ (Secondary distribution)
Key for success
Solution
• Project name: ELMU secondary distribution
• Location: Hungary
• Customer: ELMŰ-ÉMÁSZ
• Supplier: HAPG
• Completion date: Won procurement for the next 3-
year period. Deliveries will start with K1 and A24
variants in 2021Q4.
About the project
• Frame Agreement for total 1485 cabinets. Indoor
and outdoor variants, based on RTU530 product
line and CVD90 & CVD21
• Remote control of the switches, condition
monitoring of the switchgear, phase and residual
current and 1x line voltage measuring, non-
directional fault detection
• Early involvement of SLS AC (e.g. Roadshow in
Budapest, 2019)
• Successfully positioned new RTU530 product line
inside solution
• Excellent collaboration between local and global
organization during the whole tenderA1: Indoor for 2 switch with 1x FCD (550pcs.)
A2: Indoor for 4 switch with 1x FCD (135pcs.)
A24: Indoor for 4 switch with 4x FCD (200pcs.)
K1: Outdoor for 1 pole mounted switch with 1x
FCD (600pcs.)
Prototype of ETM A24 indoor cabinet
© 2021 Hitachi Energy. All rights reserved.
Elmű-Émász
10
ELMŰ-ÉMÁSZ is one of the
largest Distribution Utilities in
Hungary. The group and its
member companies provide
electricity to about two million
customers in Budapest and its
agglomeration, Borsod-Abaúj-
Zemplén, Heves and Nógrád
counties, as well as in some
parts of Jász-Nagykun-
Szolnok and Pest counties.
Web storyCustomer benefits
About the project Solution
• Project name: Elmű-Émász
• Location: Hungary
• Customer: ELMŰ-ÉMÁSZ
• Completion date: 2018
• Monitoring and control of pole-top overhead line
switches and Secondary Substations via Hitachi
Energy RTU520 series remote terminal units
(RTUs) Communications based on IEC870-5-
104 via the public GPRS network to the DMS
system; and UPS battery backup
• Provides a highly customizable design, and
enables input and output module adaptions
specific to unique application requirements
• Provides a flexible, open platform to
accommodate a future smart grid, and has
reduced both the frequency and duration of
power interruptions
• Solution is designed to operate maintenance-free
for more than 20 years
© 2021 Hitachi Energy. All rights reserved.
AEW Energie
11
The Swiss utility AEW Energie
AG based in Aargau is
responsible for operating and
maintaining a large number of
substations as well as the
medium- and low-voltage
networks in its region. AEW
commissioned Hitachi Energy
Switzerland to develop,
engineer and commission a
concept for monitoring a
secondary transformer station.
Web Story
Customer benefits
About the project Solution
• Project name: Swiss utility AEW Energie
• Location: Aargau, Switzerland
• Customer: AEW Energie
• Completion date: 2017
• RTU520 Remote Terminal Units
• Integration of protection IED‘s with RS-485
communication (IEC 60870-5-103)
• Ethernet Switch for the IEC 60870-5-104
communication to the control system
• Binary input card for common alarms
• Wall mounted cabinet
• HW schematics
• Option: Remote control and status supervision of
the primary equipment with digital I/O modules
• Future proof system with easy and fast extension
options for further projects
• Increased grid visibility enabling AEW to take the
right decision at the right time
• The solution allows for operational cost
reductions, as the transformer can be monitored
and controlled remotely
• Cost effective solution thanks to the small and
compact RTU520
© 2021 Hitachi Energy. All rights reserved.
Lopburi solar plant
13
The Lopburi solar plant in
Thailand is a 73 megawatt
field of photovoltaic cells,
covering an area around 250
football pitches. It delivers
enough electricity to power
70,000 local households.
Web story
Customer benefits
About the project Solution
• Project name: Lopburi Solar project
• Location: Thailand
• Customer: Lopburi solar plant
• Completion date: 2018
• MicroSCADA Pro system
• 29 Remote Terminal Units (RTUs)
• Ensure the greatest possible efficiency in
generation and maintenance of the site
• Centralized monitoring enables disturbances to
be quickly identified and addressed, reducing the
impact on operations and minimizing the
disruption from failure in any part of the network
© 2021 Hitachi Energy. All rights reserved.
Enbag Bortel AG
14
At Bortelsee, which is around
2,400 meters above sea level,
the position of the turbine jets
for the water flow is controlled.
Furthermore, the water
catchment tunnel also
contains a throttle valve for
emergency closing of the
pressure pipe. This function
can be triggered by the control
center, and the water level of
the Bortelsee is also
transmitted to the control
center.
Web story
Customer benefits
About the project Solution
• Project name: RTU renewal and IEC-104
implementation
• Location: Bortelsee , Switzerland
• Customer: Enbag Bortel AG (Bortel power plant)
• Completion date: 2011
• The existing P160 control system (Indactic15)
with RTU P214 was replaced by RTU560 as part
of the renewal and implementation of the IEC-
104 protocol. Six new RTU560s were installed in
total.
• Simplified commissioning and the RTU560 was
integrated into the system more quickly
• Reduced the overall costs
© 2021 Hitachi Energy. All rights reserved.
Itaipu Binacional
15
The water power plant Itaipu
located on the Paraná river
has an installed capacity of
14000 MW. The storage lake
has a volume of up to 29
billion m3 with a surface of
1350 km2, which is more than
twice the size of the Bodensee
in Europe. The output of the
water plant covers 17% of the
electricity demand of Brazil
and 72% of the demand of
Paraguay.
Web story
Customer benefits
About the project Solution
• Project name: Hydroelectric plant/Monitoring of
Substation
• Location: Brazil and Paraguay
• Customer: Itaipu Binacional
• The scope included 126 pieces of the compact and
flexible 560CIG10 of RTU540 product line, PLC
devices with a high process data speed and, as a
supervising system with HMI, MicroSCADA pro.
• Competitive price
• Comprehensive system for the monitoring of
switches, breakers and transformers of
substations
© 2021 Hitachi Energy. All rights reserved.
Solarco project
16
The Solarco Project, a joint
venture between Yanhee Solar
Power and Thailand’s first
independent power producer,
the Electricity Generating
Public Company Limited
(EGCO), includes five sites in
Nakhon Pathom, and one in
Suphan Buri province. All sites
are blessed with an estimated
4.9 kWh of sunshine per
square meter, waiting to be
gathered.
Web story
Customer benefits
About the project Solution
• Project name: Solarco project
• Location: Thailand
• Customer: Yanhee Solar Power and Thailand’s
first independent power producer, the Electricity
Generating Public Company Limited (EGCO)
• FOX515
• RTU540
• AFS Switches
• MicroSCADA Pro
• Greater use of renewable energy sources
• Ensuring that the power flows as smoothly as
possible
• Automatically monitors site conditions and
photovoltaic panel temperature in real-time
• Efficient control with easy configuration
© 2021 Hitachi Energy. All rights reserved.
High Speed Rail HS1
18
HS1 is the UK’s first high-
speed railway and forms an
essential part of the country’s
infrastructure and its efforts to
promote greener, more
sustainable transport. UK
Power Networks Services is
responsible for all traction and
non-traction power as-sets on
this 109km rail line connecting
the United Kingdom with
mainland Europe.
Web story
Customer benefits
About the project Solution
• Project name: Digitalize High-Speed rail
• Location: UK
• Customer: High Speed 1 (HS1)
• Completion date: 2020
• Hitachi ABB Power Grids’ RTU500 platform, with
MicroSCADA X for automation and control
solution overlaid with Asset Performance
Management (APM)
• Simplify the interaction with the power network
and provide operators, regardless of their
location, with a fast, clear real-time overview of
the network landscape
• Predict and prevent strategy for maintenance and
asset management
© 2021 Hitachi Energy. All rights reserved.
Ferrocarrils de la Generalitat de Catalunya (FGC)
19
The railway company,
Ferrocarrils de la Generalitat
de Catalunya (Catalan
Government Railways), or
FGC, operates rail lines in the
region of Catalonia, in
northeastern Spain. FGC
operates about 300 km of rail
lines that include conventional
and rack railways and four
funicular lines, comprising four
different gauges.
Web story
Customer benefits
About the project Solution
• Project name: FGC
• Location: Spain
• Customer: FGC, GEDLux (Partner)
• Completion date: 2018
• Deliveries include MicroSCADA X systems and
RTUs (RTU560) to modernize substations
• Increases system reliability
• Provides greater clarity, security and reduced
• runtime tasks
• Entire system migration will be performed in
stages whilst maintaining the existing system
operable
© 2021 Hitachi Energy. All rights reserved.
telent
20
The new SCADA master
station system will control
traction power and distribution
for Network Rail as an
essential part of the planned
electrification investment being
made in the UK Rail network.
The new system will provide
the complete control interface
for Network Rail to monitor the
network remotely, carry out
isolations and implement
automatic execution and
service restoration
Web story
Customer benefits
About the project Solution
• Project name: telent’s Network Rail
• Location: UK
• Customer: telent
• Completion date: 2017
• The RTUs (RTU540) will provide the vital
telemetry and remote control links to the main
traction substation equipment, including
transformers, rectifiers, switchgear and circuit
breakers as well as important ancillary services
such as door entry alarms and other security
functions. Using high-speed fibre optic
connectivity, the RTUs will interface with telent’s
head end SCADA system in Network Rail’s
control centre.
• Flexible, scalable and compact solution that
delivers maximum functionality within the
restricted space available in trackside substation
enclosures
© 2021 Hitachi Energy. All rights reserved.
Finnish Railway
21
Liikennevirasto (the Finnish
Transport Agency) runs almost
six thousand kilometers of
tracks, crisscrossing Finland to
provide some of the most
beautiful passenger routes in
the world. The rail lines are
used by the government-
owned passenger service; VR
Group.
Web story Customer benefits
About the project Solution
• Project name: Finnish rail network
• Location: Finland
• Customer: Finnish Railway
• Completion date: 2018
• MicroSCADA Pro system and RTU560 units
• Provide engineering staff on call at all the time,
24 hours a day and every day of the week.
Critical faults will be fixed within four hours, while
less critical infrastructure will be attended to
within 24 hours
• Cost-effective solution
• Reliable monitoring and control of power system
• Preventive maintenance of the system to
minimize the risk of failure
© 2021 Hitachi Energy. All rights reserved.
European Rail Company
22
This rail company is the
country’s largest unregulated
electricity customer and has a
network to match. One electric
utility feeds into that network,
supplying power for trains
across the capital and other
major cities, but as the trains
go electric that network needs
rebuilding to carry the extra
load. The network
communications is managed
by a partner company, who’s
asked Hitachi Energy to
provide several hundred
RTU540s.
Web Story
Customer benefits
About the project Solution
• Project name: European Rail Company
• Location: Europe
• Customer: Anonymous
• Completion date: 2017
• 242 RTU540s connected up and reports every
detail of the power flowing around the rail
network
• SCADA system helps operators to monitor the
condition of the equipment and the power
running through it
• Reduces the impact of component failure through
preventative maintenance and keep the trains
running for the maximum possible time
• Reduced the carbon emissions by 20-35%
• Increased reliability and availability
© 2021 Hitachi Energy. All rights reserved.
Warsaw Metro
23
Metro Line 2 (M2) is a large
rail infrastructure project in
Warsaw, the Polish capital.
With nearly two million
residents, the EU considers
Warsaw one of Europe’s most
congested cities, so the
ongoing strategy is to expand
sustainable transportation and
reduce chronic traffic
congestion and emissions.
The M2 rail line runs East-
West and supplements the
existing North-South Metro
Line 1.
Web story
Customer benefits
About the project Solution
• Project name: Warsaw Metro Line 2
• Location: Warsaw, Poland
• Customer: Warsaw Metro
• Completion date: 2018
• MicroSCADA Pro monitoring and control system
• Relion relays, REF615
• RTU560 Remote Terminal Units
• Immediate access to all relevant data in real time
• Reduce operating costs and enhance the line’s
energy efficiency
• Reduce CO2 emissions by an estimated 42,000
metric tons annually
© 2021 Hitachi Energy. All rights reserved.
Gornergrat railway (GGB)
24
The Gornergrat railway (GGB)
connects the tourist town
Zermatt with the mountain
station on the Gornergrat
ridge, which is a popular
tourism destination, housing
also a high-elevation Alpine
research station. The railroad
stretches for 9.3 km from the
elevation of 1604 m to 3089
m, the maximum slope
reaches 20%. It is the highest
outdoor toothed gear railroad
in Europe.
Web story
Customer benefits
About the project Solution
• Project name: Upgrade of the remote-control
system and its connection to the network control
system
• Location: Switzerland
• Customer: GGB, Matterhorn Gotthard Bahn
• MicroSCADA Pro Control system
• RTU560 Remote Terminal Unit
• RTU520 Remote Terminal Unit
• The commissioning of single transformer stations
was completed without shutting down the
Gornergrat railway. This made it possible to avoid
costly downtimes in operation.
• Owing to the continuous communication and
intensive personal meetings, the needs of the
client could be determined clearly, guaranteeing
a smooth progress of the project.
© 2021 Hitachi Energy. All rights reserved.
Zurich airport
26
For an airport like the one in
Zürich, reliable power supply
is the highest priority. The
power supply of the airport
includes more than two main
supplies from two independent
substations each in all its
sectors. The airport also has
several emergency power
supply groups
Web story Customer benefits
About the project Solution
• Project name: Reliable power supply for Zurich
airport
• Location: Zürich, Switzerland
• Customer: Zurich airport
• Completion date: 2018
• RTU560 remote Terminal Unit with HMI,
communication devices, Relion® REF615
protection relays
• Downstream Communication/Process
connection: IEC 61850, SPAbus, RP570,
Parallel IO
• Upstream communication: IEC 61850, IEC
60870-5-104
• The modern control system is designed in a very
flexible and cost-effective way, ensuring high
reliability
• Easily upgrade its power supply to the latest
reliable technology
© 2021 Hitachi Energy. All rights reserved.
RTU Use Cases
Self-Healing Applications
• Fault Detection Isolation and Restoration
• Volt-Var Management
• ATS Automatic Transfer System
Renewables Integration
Cybersecurity
Non-Electrical Applications
28
© 2021 Hitachi Energy. All rights reserved.
Self-Healing: Pudong (CN) Fault Detection Isolation Restoration
29
Think of Shanghai, of the
bustling financial markets and
the soaring skyline, and you
are certainly thinking of
Pudong. Pudong needed a
power delivery system flexible
enough to serve those
markets, and cope with future
expansion, and fast enough to
respond automatically when
things go wrong
Web storyCustomer benefits
About the project Solution
• Project name: Fault Detection Isolation
Restoration (FDIR) with RTU540
• Location: Pudong, China
• Customer: Anonymous
• Completion date: 2018
• RTU540 with the addition of the multimeter
500CVD21
• Communication uses IEC 61850
• Deliver the five-nines (99.999%) reliability
• Thanks to the decision-making capabilities of the
RTUs, power is restored to the almost all the
operational network in less than 15 seconds
• Reducing the outage times to a minimum
© 2021 Hitachi Energy. All rights reserved.
Self-Healing: BKW Group (Fault Detection Isolation Restoration)
30
BKW Group is one of
Switzerland’s largest energy
companies and with its
partners supplies around one
million people in both rural and
urban areas with electricity.
BKW is future oriented and
invests in smart grid
technologies to stabilize
fluctuating voltage due to the
increase of distributed
generation
Web story
Customer benefits
About the project Solution
• Project name: Integrating renewable energy with
RTU540
• Location: Switzerland
• Customer: BKW group
• Completion date: 2017
• RTU540
• Improved the power quality with distributed energy
resources on its network
• Provides a secure VPN over the public
communications network
• Highest cyber security standards
• Remotely monitor and control the voltage and load
situation
• Operational savings due to its convenient remote
access and controls
© 2021 Hitachi Energy. All rights reserved.
Automatic Transfer System (ATS): Split airport
31
To handle the increasing
number of passengers one of
the most important airports in
Croatia succeeded in a
reliable and efficient power
supply for the complete
network. For this, our external
partner Koncar set up a retrofit
project which took four months
during winter season, a time
when the airport is frequented
by smaller number of
passengers
Web story
Customer benefits
About the project Solution
• Project name: Successful automatic network
reconfiguration with RTU540
• Location: Split, Croatia
• Customer: Split airport
• Completion date: 2018
• Primary switchgear consisting of two substations
was retrofitted with new equipment.
• RTU540 with remote input/output (I/O) modules
and PLC functions according to IEC 61131 were
installed.
• Multimeter 560CVD03.
• Improved reliability and efficient power supply for
the complete network
• Average power outage time could be lowered to
less than three seconds which contributes
significantly to the higher safety of the air traffic
• Automatic Transfer System implemented in PLC
© 2021 Hitachi Energy. All rights reserved.
Renewables: RTUs for Solar
32
Solar is already an important
source of energy in Thailand:
in 2014 the country had
enough capacity to deliver
1,300MW of solar energy, but
in 2015 that’s on track to
double as the country plans
investments worth more than
$20bn. The plan is to get solar
generation up to 6,000MW by
2036, making extensive use of
ground-breaking, thin-film,
photovoltaic panels to harness
the 5kW/h of sunlight that falls
on the ground every day.
Web story
Customer benefits
About the project Solution
• Project name: RTU Solar
• Location: Thailand
• Customer: Anonymous
• Completion date: 2015
• Full range of electrical components for
connecting photovoltaic panels to the grid, from
low-voltage inverters to high-capacity batteries
for when the sun isn’t shining, and Remote
Terminal Units (RTUs) for managing the
infrastructure once it’s been deployed
• 29 RTUs linked to MicroSCADA Pro installation
• Compact and powerful solution, with integrated I/O
modules increasing flexibility while reducing costs
• Easy to use engineering software means
configuration takes only minutes, including direct
measurement of voltage and current, and
additional informational feeds from around the site
• Efficiently monitoring environmental conditions as
well as operational parameters
© 2021 Hitachi Energy. All rights reserved.
Renewables: Guatemalan hydropower plants
33
For the automation of several
small hydropower plants in
Guatemala Hitachi Energy’s
certified partner COMCARSA
delivered a complete
protection, control and
supervision panel. The
hydropower plants each have
only a limited reservoir
capacity, so the control of the
water level represents a
critical input for the operation
of the whole system.
Web story
Customer benefits
About the project Solution
• Project name: Hydropower plants
• Location: Guatemala, US
• Customer: Guatemalan hydropower plants,
COMCARSA (Partner)
• For the modernization and automation of the
hydropower plants Hitachi Energy and
COMCARSA provided several RTUs which were
installed in the substation and at the dams.
• Thanks to the remote access through standard
protocols problems within the network can be
quickly detected and restored.
• Compact system minimized the field control
wiring and the start-up times.
• Modern and easy to- understand equipment also
enables the companies operating the generation
complex to work with only minimal training.
© 2021 Hitachi Energy. All rights reserved.
Renewables: Solar PV Power Plant (Thailand)
34
The customer, Serm Sang
Palang Ngan Co., Ltd., wanted
a single SCADA (supervisory
control and data acquisition)
monitoring and control system
to oversee its new solar plant
from the PV modules to the
115 kilovolt (kV) substation, in
order to maximize the plant’s
performance.
Web story
Customer benefits
About the project Solution
• Project name: Solar PV power plant
• Location: Thailand
• Customer: Serm Sang Palang Ngan Co., Ltd
• Completion date: 2018
• Hitachi Energy delivered a MicroSCADA Pro
solution including integration equipment
consisting of string monitoring, solar inverters,
RTU540 remote terminal units as well as
Relion® RED670 relays for line differential
protection, REF630 relays for feeder protection,
and RET630 relays for transformer protection, as
well as a meteorological module from a third-
party supplier
• Central monitoring capacity improves operational
reliability and efficiency by quickly identifying and
addressing disturbances
• Enables predictive management by integrating
with weather sensors to ensure peak operating
efficiency at all times
© 2021 Hitachi Energy. All rights reserved.
Renewables: Angola solar
35
The MCA Group offers
various solutions in the
rural and urban
electrification market as
well as streamlined and
clean integrated energy
production technologies,
including transportation
and distribution
Customer benefits / Purpose
About the project Solution
• Project name: Angola Solar Farms
• Location: Angola
• Customer: MCA/PRODEL
• Supplier: Hitachi ABB Power Grids, Sweden
• Completion date: Totally 63 Inverter station skids
in 5 contracts, completion at site end of 2022. First
delivery to site in November 2021.
• RTU530 in a compact enclosure with battery
back-up, network switch and FO splice box
• Compact solution for collection of signals on
inverter station (Power Block) skids to be
transferred to central PV SCADA.
• Hitachi delivered complete system including:
75 MVA Power transformers, HV & MV
switchgear, E-house, Control & Protection,
Auxiliary Power, Power Blocks (Auxiliary system
including RTU530), PV SCADA.
© 2021 Hitachi Energy. All rights reserved.
Volt-Var Management: EKS and ZHAW
36
Hitachi Energy, EKS
(Elektrizitätswerk des Kantons
Schaffhausen AG) and ZHAW
(Zürcher Hochschule für
Angewandte Wissenschaften)
ran a pilot project in 2016-
2017 on the topic of renewable
integration and Volt-VAr
management.
Web story
Customer benefits
About the project Solution
• Project name: Renewable integration
• and Volt-VAr management
• Location: Switzerland
• Customer: EKS and ZHAW
• Completion date: 2018
• The developed solution is based on an Hitachi
Energy LV-LVR (Line Voltage Regulator),
extended with an additional control logic running
on cost-effective remote terminal units (RTU540
and RTU520) and using a Hitachi Energy
TropOS wireless communication to two Hitachi
Energy TRIO PV inverters in order to coordinate
the power production according to the actual
conditions in the grid.
• Implemented voltage control substantially
improves the power quality in the grid.
• The local LVR control results in the desired
decrease of voltage in the “downstream” grid
branches independent of the end-customers
behavior and is fully under control of the grid
operator
© 2021 Hitachi Energy. All rights reserved.
Cybersecurity: National grid operator in Northern Europe
37
Hitachi Energy’s customer is a
national grid operator in
Northern Europe controlling
15,000 kms of power lines,
160 substations, switching
stations and 16 overseas
power connections.
Customer’s challenge was that
they didn’t have the ownership
of the substation buildings and
therefore control of the
physical access was not in
their hands.
Web story
Customer benefits
About the project Solution
• Project name: Secure RTU upgrade
• Location: Northern Europe
• Customer: Anonymous - National grid operator in
Northern Europe
• Completion date: 2017
• Upgrade remote terminal units (RTUs) in all its
substations
• Secure communication to all the substations
together with enabling TCP/IP communication
• Secure authentication of all network equipment,
based on the IEEE standard 802.1X.
• IEC 60870- 5-104 as a communication protocol
• Cost reductions for engineering and secures the
customer’s network communications system
• Providing protection against:
➢ Unauthorized network access (IEEE 802.1X)
➢ Unwanted cyber intrusions
➢Man-in-the-middle attacks
➢ IP spoofing (Certificates)
➢ Replay attacks (TLS encryption).
© 2021 Hitachi Energy. All rights reserved.
Cybersecurity: European transmission system operator (TSO)
38
Hitachi Energy’s customer is
one of Europe’s main
transmission system operators
(TSO) and responsible for
developing and managing
high-voltage and very high-
voltage electrical
transmissions throughout its
country. At the same time, they
are also the majority owner of
the country’s high-voltage
transmission grid.
Web story
Customer benefits
About the project Solution
• Project name: Secure control communications
• Location: Europe
• Customer: Anonymous - European transmission
system operator
• Completion date: 2017
• IEC 60870-5- 104 secure communication based
on the IEC 62351-3 standard and Simple
Network Management Protocol version 3
(SNMPv3)
• IEC 60870-5-104 communication protocol
combined with TLS encryption based on the IEC
62351-3 standard. The advantage of this kind of
communication is the end-to-end encryption
between RTUs and the network control centers
• Highest levels of cyber security, including user
access control, security logging, hardware
hardening, device monitoring and secure
communication based on standards
© 2021 Hitachi Energy. All rights reserved.
Migration: From RTU211 to RTU 500 Series (Stadtwerke Kaiserslautern)
39
Stadtwerke Kaiserslautern
provides electricity, gas, water
and district heating. The
company started in 1858
delivering gas, adding
electricity 1894, water and
district heat.
Web story
Customer benefits
About the project Solution
• Project name: Multi utility upgrade
• Location: Germany
• Customer: Stadtwerke Kaiserslautern
• Completion date: 2018
• Upgrade to the latest version of MicroSCADA
Pro.
• Migration to the RTU511 (Remote Terminal Unit)
replacing the earlier RTU211.
• Improved cyber security, support for Ethernet
protocols and better fault diagnosis.
© 2021 Hitachi Energy. All rights reserved.
Migration: ZESCO
40
The national power utility of
Zambia, ZESCO, took the
chance to upgrade their
installed RTU211 to the new
RTU511. The customer
wanted to profit from the
functionalities of high-end
RTUs while keeping the
significant number of installed
RTU211.
Web story
Customer benefits
About the project Solution
• Project name: Migration project
• Location: Zambia
• Customer: ZESCO
• Migration of the installed RTU211 to the state-of-
the-art RTU511 in only a few steps. The
migration kit 511MKM01 provided the brand-new
CMU module and a new housing which make
the migration possible in combination with the
appropriate license
• Migration allows to implement new features and
capabilities to existing RTU211 base with only a
minimum of time and effort.
© 2021 Hitachi Energy. All rights reserved.
Communication: EDS500 Modems (Hong Kong)
41
With a population of over
seven million people, Hong
Kong is among the most
densely populated places on
the planet. Rows of tower
blocks, terraced together into
a single monolith, pack
millions of people into the
world’s most valuable real
estate, and place an
enormous strain on electrical
infrastructure.
Web story Customer benefits
About the project Solution
• Project name: Telecommunication project
• Location: Hong Kong
• Customer: Anonymous
• 6000 analogue modems for copper lines
• Remote terminal unit
• Squeeze more data and more reliability out of the
existing infrastructure
• Shorten system outage times
• Improve system reliability
• Future proof solution
© 2021 Hitachi Energy. All rights reserved.
Water Irrigation: Irrigation control system
43
The community of Canal del
Zújar, 250 km south west of
Madrid, hosts 11,122 plots
across a vast 210 square-
kilometer belt of prime
agricultural land.
Web story
Customer benefits
About the project Solution
• Project name: Irrigation project
• Location: Spain
• Customer: Anonymous
• Hitachi Energy’s Neptuno system, which uses
SCADA (supervisory control and data
acquisition) technology, cloud computing and
M2M (machine to machine) solutions
• RTU
• Reduce production costs and minimize water
consumption
• Annual electricity bill has been reduced by almost
12 percent, and water consumption by 20
percent
• Enables farmers to monitor and control their
irrigation systems from smart phones or personal
computers.
© 2021 Hitachi Energy. All rights reserved.
Oil and Gas: Total Lindsey Oil Refinery (LOR)
44
LOR was established in the
1960s on a site five miles from
the Humber River estuary and
was the first UK refinery to
process North Sea Oil. It is
currently the country’s third
largest oil refinery, processing
10 millions tons of crude per
year – the equivalent of
200,000 barrels per day (bpd).
Web story
Customer benefits
About the project Solution
• Project name: Substation project
• Location: UK
• Customer: Total Lindsey Oil Refinery (LOR)
• Completion date: 2018
• Hitachi Energy supplied its RTU560 remote
terminal unit to meet all of LOR’s local HMI
(Human Machine Interface) requirements by
enabling the new substation to be integrated
within the previously localized 11 kV site
network, and to access equipment remotely
which had not previously been possible
• Future-proof protection and control technology
• Ensuring the ease of handling and installation of
the substation solution
• Blast-proof integrity of the completed substation
© 2021 Hitachi Energy. All rights reserved.
Water : Turkey Irrigation Project
45
Korkuteli is typical; until the
1960s the lowlands were
home to sheep and goat
herders as the otherwise-
fertile ground were too dry for
growing crops, but with proper
irrigation, farmers are now
growing fruits, grain, and
vegetable oils, thanks to a
network of open canals. Those
canals are getting old now,
and suffer from leakage into
the soil as well as evaporation,
so the General Directorate of
State Hydraulic works decided
to rebuild the network
Web story
Customer benefits
About the project Solution
• Project name: Turkey Irrigation Project
• Location: Korkuteli Turkey
• Customer: YEO (Partner)
• Completion date: 2018
• RTU520
• MicroSCADA Pro
• Immediately alerting the controllers if a pipe is
leaking or blocked and allowing remedial work to
be quickly undertaken
• Providing a real-time view of the weather