Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
EIA/EMP REPORT Of
World Trade Centre Commercial Project
Plot No. 2, Block D, Aerocity, SAS Nagar, Mohali, Punjab
For M/s WTC NOIDA Development
Company Pvt. Ltd
Prepared By
GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD.
(An ISO 9001:2008 Certified Co.Accredited by QCI / NABET)
F-374-375, Sector-63, Noida, U.P. Ph.: 0120- 4044630, Telefax: 0120- 2406519
Email: [email protected], [email protected]
Website: http://www.grc-india.com
GRC INDIA TRAINING & ANALYTICAL LABORATORY (Accrediated by NABL, Recognized by MoEF, GoI)
A unit of GRC India
TABLE OF CONTENTS
Table No. Description Page No.
CHAPTER 1 Introduction 1-13 1.1 Preamble 1 1.2 General information on project 1 1.3 Environment clearance process 1 1.4 Validity of Environment clearance 2 1.5 Post Environmental clearance monitoring 3 1.6 Transferability of Environment clearance 3 1.7 Generic structure of Environment impact assessment 3 1.8 Profile of project proponent 4 1.9 Brief description of project 5 1.10 Applicable legal requirement 7 1.11 Need of the EIA study 10 1.12 Scope of study 11 1.13 Study methodology 12 1.14 EIA methodology 13 CHAPTER 2 Project Description 14-40 2.1 Introduction 14 2.2 Goals and objective of the Project 15 2.3 Description of Project site and surroundings 15 2.4 Geology 17 2.5 Climate and meteorology 18 2.6 Brief Project features 21 2.7 Population details 23 2.8 Power Supply 24 2.9 Requirement of Natural Resources and their sources 25 2.10 Design Consideration 25 2.11 Parking 25 2.12 Water requirement and waste water generation 27 2.13 Solid Waste Generation 33 2.14 Landscape 36 2.15 Man power Requirement 36 2.16 Fire fighting System 37 2.17 Details of construction materials 38 2.18 Project Implementation schedule 40 CHAPTER 3 Description of the Environment 41-86 3.1 Introduction 41 3.2 Study period 41 3.3 Study area 41 3.4 Baseline monitoring of environmental component 41
CHAPTER 4 Anticipated Environmental Impacts & Mitigation Measures
87-147
4.1 Introduction 87 4.2 Impact matrix 88 4.3 Pollution sources 112 4.4 Impact identification 113 4.5 Assessment of Environmental Impacts During Development and
Construction Phase 115
4.6 Assessment of the environmental impacts during post construction phase
126
CHAPTER 5 Analysis of Alternative 148-162 5.1 Introduction 148
5.2 Building Materials 148
5.3 Natural Hazard Prone areas 152
5.4 Environment Friendly Development 153
5.5 Community issues 155
5.6 Energy conservation 155
5.7 Transportation 157
CHAPTER 6 Environmental Monitoring Program 163-167
6.1 Introduction 163
6.2 Performance indictors 163
6.3 Data Management 167
6.4 Reporting Schedules 167
6.5 Budgetary implementation for EMP 167
CHAPTER 7 Additional Studies 168-178
7.0 Introduction 168
7.1 Risk assessment And Disaster Management Plan 168
7.2 Response In Case of earthquake 173
7.3 Response For LPG leakage 175
7.4 Response In case of fire 175
7.5 Resource conservation 176
7.7 Resettlement and rehabilitation 178
7.8 Social Impact Assessment 178
CHAPTER 8 Project Benefits 179-180
8.1 General 179
8.2 Physical infrastructure 179
8.3 Social Infrastructure 179
8.4 Economic Benefits 179
CHAPTER 9 Environmental Management Plan 181-214
9.1 Introduction 181
9.2 Environmental Management Strategies 182
9.3 Overall mitigation measures and environmental management plan 197
CHAPTER10 Summary And Conclusion 215-221
10.1 Project background 215
10.2 Project site 216 10.3 Project features 216 10.4 Environmental setting of the study area 217 10.5 Environmental Management Plan 220 CHAPTER11 Disclosure of consultants engaged 222-225 11.1 Accreditations from quality council of India QCI 223
LIST OF TABLES
S. No.
Table No. Particular Page No.
1. 1.1 Legal Requirements Applicable to the Project
8
2. 2.1 Geographical Coordinates of Project Site 15 3. 2.2 Monthly average temperature 19 4. 2.3 Monthly average rainfall 20 5. 2.4 Detailed Area Statement 22 6. 2.5 Built-up Area Details 22 7. 2.6 Population Break-up 23 8. 2.7 Water Demand and waste water
calculation during Construction phase 27
9. 2.8 Daily Water Demand 29 10. 2.9 Waste Water Calculation 30 11. 2.10 Solid Waste Calculation 34 12. 3.1 Meteorological Data for Oct 2013 to Dec
2013 42
13. 3.2 (a) Location of Ambient Air Quality Monitoring Stations (Knowledge Park, GMADA)
43
14. 3.2 (b) Location of Ambient Air Quality Monitoring Stations (World Trade Centre)
43
15. 3.3(a) Ambient Air Quality with respect to PM2.5 (GMADA)
45
16. 3.3(b) Ambient Air Quality with respects to PM10 (GMADA)
46
17. 3.3(c) Ambient Air Quality with respect to SO2 47 18. 3.3(d) Ambient Air Quality with respects to
NO2 (GMADA) 48
19. 3.3(e) Ambient Air Quality with respects to 49
CO(GMADA)
20. 3.3 (f) Ambient Air Quality with respect to PM2.5 (WTC)
50
21. 3.3 (g) Ambient Air Quality with respects to PM10 (WTC)
51
22. 3.3 (h) Ambient Air Quality with respect to SO2 52 23. 3.3 (i) Ambient Air Quality with respects to
NO2 (WTC) 53
24. 3.3 (j) Ambient Air Quality with respects to
CO(WTC)
54
25. 3.4 (a) Noise Level Monitoring Stations (Knowledge Park, GMADA)
56
26. 3.4 (b) Noise Level Monitoring Stations (World Trade Centre)
57
27. 3.5 Ambient Quality Standards in Respect of Noise
57
28. 3.6 (a) Hourly Leq Noise Level at Knowledge Park, GMADA
58
29. 3.6 (b) Hourly Leq Noise Level (World Trade Centre)
59
30. 3.7 (a) Location of water sampling sites (Knowledge Park, GMADA)
60
31. 3.7 (b) Location of water sampling sites (World Trade Centre)
60
32. 3.8 Water Quality Criteria as per Central Pollution Control Board
61
33. 3.9 (a) Ground water quality in study area of GMADA Project (Oct 2013)
63
34. 3.9 (b) Ground water quality in study area of GMADA Project (Nov 2013)
64
35. 3.9 (c) Ground water quality in study area in study area of GMADA Project (Dec 2013)
66
36. 3.9 (d) Ground water quality in study area in study area of WTC Project (12th May to 12th JUN.2016)
68
37. 3.10 (a) Location of Soil Quality Monitoring Stations (Knowledge Park, GMADA)
71
38. 3.10 (b) Location of Soil Quality Monitoring Stations (World Trade Centre)
71
39. 3.11 Frequency and Methodology for Soil Sampling & Monitoring
72
40. 3.12 (a) Soil Quality Data (Nov 2013) 73 41. 3.12 (b) Soil Quality Data (12th MAY to 12th
JUN., 2016) 74
42. 3.13 Floral Composition of the Study Area 76 43. 3.14 List of Fauna in the Study area 77 44. 3.15 Demographic Profile and Socio-economic
status of study area based on 2001 Census data
82
45. 4.1 Environmental and Social Assessment Checklist
88
46. 4.2 Project activity wise impact and mitigation
90
47. 4.3 Pollution Sources 112 48. 4.4 Environment impacts of project other than
Pollution 115
49. 4.5 Stack and Emission Details 140 50. 4.6 Meteorological data for the 24-hour
average maximum predicted Concentration under worst meteorological condition
141
51. 4.7 Predicted GLC 142 52. 4.8 Plantation List 145 53. 5.1 Energy savings calculation 156 54. 5.2 Mode of transport 157 55. 5.3 Gross floor areas of building activities 158
56. 5.4 Workers Contribute To Morning Peak 158 57. 5.5 Forecasted Trips 159 58. 5.6 Person Trips vehicle category –wise 159 59. 5.7 Vehicular Traffic in the Morning Peak
Hour 159
60. 5.8 PM peak generation 160 61. 6.1 Environmental Monitoring Plan 165 62. 6.2 Expenditure on Environmental Matters 167 63. 7.1 Activities during construction and
operation along with mitigation measures 168
64. 9.1 Environmental Management Plan during construction and operation phases of the project
198
65. 10.1 Salient Features of the project 216
LIST OF FIGURES
S.No. Figure No. Particular Page No.
1. 1.1 Proposed site location 6 2. 1.2 Site Photograph 7 3. 2.1 Perspective view 14 4. 2.2 Windrose diagram (May 12, 2016 to
June 12, 2016) 21
5. 2.3 Water Balance diagram during Construction Phase
28
6. 2.4 Water Balance Diagram during Summer Season
31
7. 2.5 Water Balance Diagram during Winter Season
32
8. 2.6 Water Balance Diagram during Monsoon Season
33
9. 2.7 Construction schedule 40 10. 3.1 Concentration of PM2.5 (GMADA) 46 11. 3.2 Concentration of PM10 (GMADA) 47 12. 3.3 Concentration of SO2 (GMADA) 48 13. 3.4 Concentration of NO2 (GMADA) 49 14. 3.5 Concentration of CO (GMADA) 50 15. 3.6 Concentration of PM2.5 (WTC) 51 16. 3.7 Concentration of PM10 ( WTC ) 52 17. 3.8 Concentration of SO2 ( WTC ) 53 18. 3.9 Concentration of NO2 ( WTC) 54 19. 3.10 Concentration of CO ( WTC) 55
20. 3.11 Land Use Pattern of the Project Site within 10 km
70
21. 3.12 Occupational structure of the study area based on 2001 census data
82
22. 4.1 Solid Waste Management Scheme (Construction Phase)
127
23. 4.2 Solid Waste Management Scheme (Operation Phase)
128
24. 4.3 Schematic Diagram of STP 132 25. 4.4 RWH Pit design detail 136 26. 4.5 Wind Rose (Summer Season for 12th
May to 12th June - 2016) 139
27. 4.6 Spatial distribution of 24-hours average NO2 maximum incremental GLC
143
28. 9.1 Waste Management Flow Diagram (Operation Phase)
184
29. 10.1 Environment Management Cell Structure
220
LIST OF ANNEXURE
Particular Annexure No.
Minute of meeting (ToR) Annexure 1
ToR Compliance Annexure 2
Master Plan Annexure 2(a)
5 Km Buffer Map showing Nala Annexure 2(b)
Landscape Plan Annexure 2(c)
Energy saving calculation Annexure 2(d)
Water Tanker Agreement Annexure 2(e)
water sewerage, water supply, solid waste permission Annexure 2(f)
Corporate Social Responsibility Annexure 2(g)
Land document Annexure 3
Google Earth image of 500m Annexure 4(a)
Eco Sensitive Buffer Map Annexure 4(b)
Contour map Annexure 4(c)
Drainage Map Annexure 4(d)
Composite Map of Monitoring locations Annexure 5
Lab Report Annexure 6
Receiving of Forest NOC Annexure 7
Receiving of wild Life NOC Annexure 8
All Plans Annexure 9
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 1
CHAPTER 1: INTRODUCTION 1.1 PREAMBLE
Early identification and characterization of critical environmental impacts allow the public and
the government to form a view about the environmental acceptability of a developmental project
and what measures should be applied to mitigate or reduce the risks and impacts.
EIA is a technical exercise, to establish baseline environmental conditions and predict
environmental impact, assess their significance and provide recommendations for their
mitigation. The impact assessment covers both construction and operation phase of the project.
This report covers areas environmental impacts such as noise, air quality, ecology, water quality,
hydrology, local architecture, landscape & visual character, sustainability and socio-economics.
EIA/ EMP assists planners and government authorities in the decision making process by
identifying the key impacts/ issues and formulating mitigation measures.
1.2 GENERAL INFORMATION ON PROJECT
M/s. WTC NOIDA Development Company Pvt. Ltd. has proposed to develop ‘World Trade
Centre’ a commercial project at Block–D, Aerocity, Mohali, Punjab on a land measuring 8.034
acre (32,512.44 m2). The Project comprises of offices, retails/shops, food court, multiplex,
service apartments. It’s in close proximity to the Mohali airport.
1.3 ENVIRONMENTAL CLEARANCE PROCESS
As per EIA Notification, 2006 & its amendments, all building construction and area development
projects covering an area of 50 ha or greater and/ or built up area greater than 1,50,000 m2 are
designated as 8 (b) as per the schedule of the notification and are required to obtain prior
environmental clearance from State Environmental Impact Assessment Authority (SEIAA). The
application for environmental clearance comprises submission of Form 1, Form 1A, and
Conceptual Plan along with Proposed ToR.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 2
The EIA/EMP is prepared on the basis of Terms of Reference (ToR) and submitted to the SEAC
for appraisal. Following the appraisal of the project by SEAC, the recommendations are
forwarded to SEIAA, for grant/rejection of Environmental Clearance.
Since, the project has plot area 32,512.44 m2 and proposed built up area 1, 51,314 sq.m, the
project falls under 8 (b) of the schedule of the EIA Notification, 2006.
As per the provisions of EIA notification, M/s. WTC NOIDA Development Company Pvt. Ltd.
submitted the application to State Level Environment Impact Assessment Authority (SEIAA),
Punjab. The project was considered in 145th SEAC meeting held on 11th May, 2016 and
additional ToR was granted. Following this, the project was taken up in the agenda of 108th
SEIAA meeting held on 03rd June, 2016. The EIA/EMP report has been prepared according to
the conditions of ToR specified in the minutes of SEAC & SEIAA meeting. A copy of the ToR
is attached as Annexure - 1. Point-wise compliance of ToR conditions is enclosed as Annexure
- 2.
With the permission of SEAC, the baseline environment study carried out for the project
"Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS Nagar, Mohali, Punjab during
post-monsoon season October to December 2013 has been used for this project with additional
one month study for on the, project site. The monitoring locations selected for GMADA project
fall within the 10 km radius of proposed ‘World Trade Centre’ Commercial project by WTC
NOIDA Development Company Pvt. Ltd.
1.4 VALIDITY OF ENVIRONMENTAL CLEARANCE
As per the provisions of the EIA Notification, 2006 & its amendments, the environmental
clearance granted is valid for a period of seven years. This may be extended by a maximum of
seven years, provided an application is submitted to the regulatory authority within the validity
period with updated Form 1, Form 1A and Conceptual Plan and Environmental Impact
Assessment Report.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 3
1.5 POST ENVIRONMENTAL CLEARANCE MONITORING
It is mandatory for the project proponent to submit half-yearly compliance report in respect of
the stipulated prior environmental clearance terms and condition in hard and soft copy to the
concerned regulatory authorities on 1st June and 1st December of each calendar year.
All such compliance report submitted by the project management shall be public documents.
1.6 TRANSFERABILITY OF ENVIRONMENTAL CLEARANCE
A prior environmental clearance granted for a specific project or activity to an applicant may be
transferred during its validity to another legal person entitled to undertake the project or activity,
on application by the transferor or the transferee with a written “no objection” by the transferor,
to, and by the regulatory authority concerned, on the same terms and conditions under which the
prior environmental clearance was initially granted, and for the same validity period.
1.7 GENERIC STRUCTURE OF ENVIRONMENT IMPACT ASSESSMENT
The environmental impact assessment has been carried out to assess the impact of the
Commercial project on various environmental components. The methodology and findings of the
study are detailed in the different chapter/headings as under:
Introduction- Provides background information about the project, category as defined in EIA
Notification 2006, the Project Proponent, the legal and administrative framework.
Project Description– Discusses the project features while elaborating on component bearing
environmental consequences.
Description of the Environment– Discusses the baseline data of environmental attributes such
as air, water, soil, noise and socioeconomic environment of the area based on primary and
secondary data collection at the site. Study of existing environment at the site and in the
surrounding area.
Anticipated Environmental Impacts & Mitigation Measures – Predicts the environmental
impacts of the various activities of the project during construction and operation phase to
highlight concern areas requiring mitigation measures. Accordingly, it suggests control and
mitigation measures to offset/ minimize the adverse impact while optimizing the positive
benefits of the project.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 4
Analysis of Alternatives (Technology and site) – Explores the alternative sites and plans that
have been considered for the project and evaluates the different scenarios in environmental
context.
Environmental Monitoring Programme – Outlines the monitoring programme for different
environmental parameters during construction and operation phase.
Additional Studies – Discusses all studies that have been carried out for the purpose of better
understanding of environmental impacts of the project. It also highlights pertinent findings from
the study that will aid in decision-making.
Project Benefits – Brings out the positive impacts of the project.
Environmental Management Plan – Organizes the suggested mitigation measures to aid
implementation through formulation of performance indicators, reporting structure and
pronounced implementation periods.
Summary & Conclusion – Summarizes the important report findings and concludes the
environmental sustainability of the project.
Disclosure of Consultants engaged – Gives the names of technical team involved in the report
preparation with accreditation status of consultant from the Quality Council of India.
1.8 PROFILE OF PROJECT PROPONENT
‘World Trade Centre’ a commercial project at Block–D, Aerocity, Mohali, Punjab is proposed by
M/s. WTC NOIDA Development Company Pvt. Ltd.
Name and Contact Address
The company has nominated Mr. Harjit Singh as the authorized signatory to represent the
company before the different competent authorities for several approvals of the project. Contact
details are as given below:
Mr. Harjit Singh,
Senior Manager (Planning and Coordination),
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 5
M/s. WTC NOIDA Development Company Pvt. Ltd.
GF-09, Plaza M-6, Jasola Distt. Centre , New Delhi -110025
Contact No. : 9818662374, 011-40714000
Email id: [email protected]
1.9 BRIEF DESCRIPTION OF PROJECT
1.9.1 Project Background
The project ‘World Trade Centre’ is located at Block–D, Aerocity, Mohali, Punjab on a land
measuring 8.034 acre (32,512.44 m2). The land ownership/possession documents are enclosed as
Annexure - 3.
The proposed built up area measures 1,51,314 sq.m.. The geographical coordinates of the project
site are 30°38’ 34.90” N; 76° 45’08.85” E.
Project site location is shown below:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 6
Figure 1.1: Proposed site location
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 7
There is neither any litigation (s) pending against the project and / or any directions or order
passed by any court of law/any statutory authority.
1.9.2 Site Description
The project site is well connected via. road, railway and airway. The nearest railway station is
Sahibzada Ajit Singh Railway Station which is 2.5 km away from the project site in NW
direction. Mohali International Airport is at a distance of 3.5 km from the project site in NE
direction.
NIPER and Fortis Hospital are 5 km away.
Latest site photograph of project site is shown below:
Figure 1.2: Site Photograph
1.10 APPLICABLE LEGAL FRAMEWORK
Under the Environment Impact Assessment Notification, 2006 and its amendments, the project
proponent will obtain environment clearance. The project proponent will abide by all applicable
provisions of the Environment Protection Act, 1986 and rules formed there under.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 8
As per the Air (Prevention & Control of Pollution) Act 1981, Water (Prevention & Control of
Pollution) Act 1974, and Hazardous Waste (Management, and Handling) Rules, 1989 and its
amendments the project shall obtain No Objection Certificate from Punjab Pollution Control
Board (PPCB) and also obtain Consent to Operate before the operation phase.
This section describes all relevant existing legal and institutional framework related to
environmental management for infrastructure development projects in India including clearance
requirements as per Government of India. Table 1.1 highlights the relevant environmental
legislations applicable to the project.
Table 1.1: Legal Requirements Applicable to the Project
S. No. Legal Framework Co-ordinating
agency
Objective/Highlights of framework
Enviro Legal framework
1. Water (Prevention and
Control of pollution) Act
1974
CPCB, PPCB Prohibits the discharge of pollutants
into water bodies beyond a given
standard, and lays down penalties
for non-compliance
2. Water (Prevention and
Control of pollution)
Rules, 1975 as amended
in 1989
CPCB, PPCB Defines the procedures for
conducting meetings of the boards,
the powers of the presiding officers,
decision-making etc.
3. Water (Prevention and
Control of Pollution)
Cess Act, 1977 as
amended in 2003
PPCB Provides for a levy and collection
of a cess on water consumed by
industries and local authorities
4. Air (Prevention and
Control of Pollution) Act,
1981 as amended in 1988
CPCB, PPCB Provides means for the prevention,
control and abatement of air
pollution
5. The Air (Prevention and
Control of Pollution)
CPCB, PPCB Defines the procedures for
conducting meetings of the boards,
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 9
Rules,
1982
the powers of the presiding officers,
decision-making etc.
6. The Noise
Pollution(Regulation and
Control) Rules, 2000
CPCB, PPCB Provides means for the control and
abatement of noise pollution.
7. Environment (Protection)
Act, 1986 (EPA)
followed by amendment
in May 1994
(Schedule-I)
Ministry of
Environment
and Forests
(MoEF&CC)
Ensures that appropriate measures
are taken to conserve and protect
the environment before
commencement of operations.
8. Environmental Impact
Assessment Notification
2006, and its subsequent
addenda/ deletion/
alteration and updation
till
date
Ministry of
Environment
and Forests
(MoEF&CC)
It makes Environmental Clearance
mandatory as mentioned in
Schedule of EIA notification S.O...
1533, dated 14-09-2006 and its
subsequent amendments
9. The Environment
(Protection) Rules, 1986
PPCB ,MoEF&CC Lay down the procedures for setting
standards of emission or discharge
of environmental pollutants.
Other relevant legal framework
10 Forest (Conservation)
Act, 1980 with
Amendments in 1988
Forest (Conservation)
Rules, 2003
Forest Department, MoEF&CC
The purpose of this Act is to foster
recognition of the forest as a
common heritage and promote
sustainable forest development in
order to meet the economic,
environmental and social needs of
present and future generations
while giving proper consideration
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 10
to other potential uses of the
territory.
11 Area under Sections 4 &
5 of Punjab Land
Preservation Act 1900
Revenue Department, MoEF&CC
An act to provide for the better
preservation & Protection of certain
portion of the territories. It extends
to whole of Haryana.
12 Hazardous Wastes
(Management and
Handling and Trans
boundary Movement)
Rules, 2008 and its
amendments till date
PPCB, MoEF&CC Providing for making effective
procedure for inventory, control,
handling and disposal of hazardous
waste provide for setting up of
disposal sites/landfill sites design,
operation and closure.
13 Central Motor Vehicles
Act
1988
Ministry of Road Transport and Highways
To control vehicular air and noise
pollution. To regulate development
of the transport sector, check and
control vehicular air and noise
pollution.
1.11 NEED OF THE EIA STUDY
The project activities must co-exist in harmony with its surrounding environment, to reduce the
environmental impact, which is likely to arise during various project activities.
To safeguard the environment from adverse effects of developmental activities, the MoEF & CC
has issued various regulations and guidelines to optimize the use of natural resources and protect
environment for sustainable development. As per the EIA notification dated 14.09.06,
Environmental Clearance is mandatory for any building/construction project with built-up area
more than 20,000 m2 and EIA/EMP is required for the Projects covering an area of 50 ha and/ or
built up area greater than 1,50,000 m2. As the built-up area of the project is 1,51,314 sq.m. it
comes under schedule 8 (b) of the notification. Hence, an Environment Impact Assessment
Report has been prepared for the project. This study would facilitate M/s. WTC NOIDA
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 11
Development Company Pvt. Ltd. to obtain Environmental Clearance (EC) from the
SEIAA/SEAC Punjab.
1.12 SCOPE OF STUDY
The scope of the study is:-
Baseline environmental and social study within a radius of 10 km around the project site
based on field study covering one season i.e. October – December 2013 and additional one
month baseline study (12th May to 12th June, 2016) for core zone as well as secondary data
Identification, prediction and evaluation of potential environmental impacts expected during
construction phase due to activities like:
Excavation work and filling of foundations
Plain Concreting, RCC Civil foundations and Erection Activities
Heavy fabrication works
Laying of underground and aboveground pipelines
Surface Treatment, Coating and Painting
Final Clearing of Site
and operation phase of the project:
Increase in traffic
Water Supply and Sewerage system
Socio-economic impacts
Landscaping
Solid waste
E-waste from office complex
Indoor air quality
Preparation of Environmental Management Plan (EMP) with mitigation measures and
Monitoring Programme.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 12
1.13 STUDY METHODOLOGY
The approach followed in conducting the EIA study is in accordance to the applicable regulatory
framework. The main stages followed are described below:
Stage -I
Review of design and operational information of the project through various plans,
drawing and identification of sources of major potential impacts.
Stage -II
An initial review of the project site and status of the physical environment around the
project site vicinity;
Understanding regarding project design and operation as well as macro environmental
aspects. The major issues needed to be addressed with due care were identified and monitoring
plan for the environmental baseline was prepared;
Baseline environmental assessment was conducted within the study area of 10 km radius
around the project site;
Monitoring and primary field data collection of environmental components viz. Ambient
Air Quality, Water (Surface and Ground water) use and its Quality, Soil Quality, Noise Level,
Traffic Volume, Micro-Meteorological Condition, etc.;
Survey study to assess the status of flora & fauna and socio-economic profile of the study
area
Information collected through Secondary sources like Department of Census, District and
City Offices, National Institutes (Survey of India, National Information Centre, etc.), District
Head Quarters and other Government Offices etc. as well relevant Published Literature.
.
Stage –III
Compilation of the Environmental Baseline Study.
Stage –IV
Assessment of Environmental Impacts by predicting the scale and extent of changes associated
with the project and their subsequent effects on the baseline environmental condition and
evaluating the significance of such impacts
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd Page 13
Stage -V
Identification and preparation of significant impacts and measures by proposing
applicable alternatives and control measures;
Finally, development of appropriate Environmental Management and Monitoring Plan to
ensure that the proposed mitigation measures are in place.
1.14 EIA METHODOLOGY
A project may have impact on environment attributes such as air, water, noise level, soil quality,
hydrology and drainage pattern and meteorology of surrounding environment. In assessing the
environmental impacts; collection, collation and interpretation of baseline data is of prime
importance. Long term data sets help us to get better assessment. The objective of EIA study is
to predict and address potential environmental problems/concerns at an early stage of project
planning and design. This study assists in the decision making process by identifying the key
impacts/ issues as a results of the activities and formulating mitigation measures, leading to an
improvement in environmental quality.
In order to achieve the said objectives, the following steps have been followed during the study:-
Collection, collation and analysis of regional and local environmental status for various
environmental attributes (like topography, geology, ambient air quality, meteorology, water
quality, noise level, soil characteristics and land use, transport, settlement status and socio
economic aspects etc.) to assess baseline status of the environment.
Identification of environmental impacts lead will help decide the feasibility of the project and
suggest mitigation measures to control pollution.
Evaluation of impacts leading to preparation of environmental management and monitoring
plan.
Environment Monitoring Plan and annual budget – one time and recurring cost of EMP.
This report is based on scientific principles and professional judgment with resultant subjective
interpretation. Professional judgments expressed herein are based on the available data and
information.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 14
CHAPTER 2: PROJECT DESCRIPTION 2.1 INTRODUCTION M/s. WTC NOIDA Development Company Pvt. Ltd. has proposed to develop ‘World Trade
Centre’ a commercial project at Block–D, Aerocity, Mohali, Punjab. The Group has made
concerted efforts towards creating environment friendly human habitation projects in line with
customer needs. Good Business and Quality Practices, Quality Products, Integrity, Customer and
Product Value, guide our vision towards building a great institution. The present project provides
world class infrastructure to the users. The project comprises following facilities:
Offices
Retail/Shops
Food Court
Multiplex
Service Apartments
Project proposed to have 3 blocks A, B and C
Block A having G+17 floors including office complex.
Block B having G+12 floors is further divided into Block B1, B2 and B3. G+2 floor in
front is retail and 3rd to 12th floor is office. G+5 in back of Block B is Multi level Car
Parking. 3rd floor will have multiplex and food court.
Block C have G+15 floors and it includes service appartment.
Perspective view of the project is shown in Figure 2.1 below:
Figure 2.1: Perspective view
Block A (Office) Block B1 (Office) 3rd to 12th
Block B2 (Office)
Block B3 (Office)
Block B (G+2) Retail
Block B (G+5) MLCP
Multiplex & Restaurant
Service apartment
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 15
2.2 GOALS AND OBJECTIVE OF THE PROJECT
It is proposed to provide commercial project of large scale comprising of offices, retails,
multiplex, banquet hall, service apartment etc. Commercial Project of this scale results in boost
of overall economy. It will provide considerable livelihood and job opportunities. The project
will develop elite infrastructure.
The project will have positive impact on the local economy in a convenient way. The
construction phase of the project will engage a large number of construction workers, whether
skilled, semi-skilled or unskilled. The workers will also be ensured welfare facilities such as
drinking water, sheds for resting, medical facilities. Public transport facilities are also likely to be
increased in link with the development of the area.
2.3 DESCRIPTION OF PROJECT SITE AND SURROUNDINGS 2.3.1 Geographical Co-ordinates of the area: The land area is vacant land. There is no major
settlement in the area. The entire area is monotonously flat. The geographical coordinates of the
site are given in the table 2.1 below:
Table 2.1: Geographical Coordinates of Project Site
S. No.
Latitude Longitude
1 30°38’ 34.90” N 76° 45’ 08.85” E 2 30°38’ 32.43” N 76° 45’ 05.52” E 3 30°38’ 39.37” N 76° 44’ 58.77” E 4 3038’ 41.59” N 76° 45’ 02.74” E
Google image (500 m) of site & Toposheet map within 15 km showing project site &
surroundings are attached as Annexure IV (a and b).
Details of surrounding areas are as follows:
North: Aerocity Road (NH-21 Bypass)
East: Aerocity Road (NH-21 Bypass)
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 16
South: Aerocity Mohali
West: IT city sec 82 GMADA
2.3.2 Connectivity: Site selection is one of the important criteria for development of any project,
as this is a commercial project employing large number of staff, it is required that site should be
well connected and easy accessible with nearby areas of necessity such as main transport
corridors, medical & health facilities etc. The site is well connected with transport facilities.
Nearest railway station is Sahibzada Ajit Singh Railway Station which is 2.5 km away from the
project site in NW direction. The Mohali International Airport is at a distance of 4.0 km from the
project site in NE direction) . NIPER and Fortis Hospital are 5 km away.
2.3.3 Ecological Sensitivity: Core zone is devoid of any plantation, Sukhna Lake reserve forest
is 15.40 km away from Project site. City Bird Sanctuary is 10.20 km from the project site.
2.3.4 Impact of existing activities on the proposed activity: No impact is foreseen as there is
no major activity exists in nearby the side. The nearby areas are mainly commercial only.
2.3.5 Population: As per 2011 census Mohali's urban agglomeration had a population of
176,152, out of which males were 92,407 and females were 83,745. The literacy rate was 93.04
per cent. The sex ratio of Mohali is 906 females over 1000 males.
2.3.6 Festivals and Fairs: Festivals and fairs are an integral part of religious life. The common
festivals celebrated by the Hindus are Holi, Janam Ashtami, Dussehra and Diwali. The other
festivals are Shivratri, Gugga Naumi, Solono and Bhaiya Duj. Mela Masani mata or Sitla Mata
ka mela and mela Chhat Bhadon or Baldev Chhat are the more important fair held in the district.
Mela Pir, mela Burha Baba or Mela Vankhandeshwat, Mela Suraj Kund, Mela of Ravan of Meos
and Mela Jhirka are locally important fairs.
2.3.7 Availability of Infrastructure Facilities & Amenities: A review of infrastructure
facilities available in the study area has been done by survey basis. The study area has a good
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 17
level of infrastructure facilities and amenities like education, health, drinking water,
electrification, and transport and communication network.
i. Educational Facilities: The study area has schools at primary, middle, matriculation
levels, colleges, and Universities.
ii. Medical Facilities: The medical facilities in villages within the study are good.
iii. Transport and Communication: The mode of communication and transportation facility
within the study area is good.
iv. Economy: Mohali district is the most important district in Punjab as far as the industrial
and commercial sector as concerned. The last two decades have witnessed continued and
accelerated industrial progress with the expansion of infrastructural network and
provision for attractive incentive including large flow of institutional credit to
entrepreneurs. The people of both sexes are participating in the economic activities so as
to augment the household income in order to improve their standard of living.
Various advantageous features of the site were the main:
1. Availability of raw material of proper quality and quantity in abundance from the nearby sites.
2. Environmental Consideration such as statutory distance from major roads and safety distance
from nearby villagers, wind direction and speed etc.
3. Good facility for Transportation of raw materials and fuel to the site and Finished product to
the markets.
4. Availability of infrastructure facilities such as water supply, roads and power.
5. Availability of social infrastructure and man power.
2.4 GEOLOGY
2.4.1 Physiography
Physiography refers to the study of physical features of the area and their relationship with one
another including the factors and processes responsible for the evolution of landforms. The state
of Punjab forms a part of Indo-Gangetic alluvial plain and is composed of sediments of Shiwalik
hills and Himalayas brought down and laid by the rivers of Indus system. The exact depth of the
alluvium has not been ascertained, though it varies from a few metres to over 2000 metres.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 18
2.4.2 Topography
The Topography of the district is even. It is mostly a plain of alluvial type. It also has Loam to
heavy loam and sand to sandy loam soils in certain parts of the district. Soil is rich in nutrients
and suitable for crops like wheat, Paddy, Maize, potato and Vegetables etc. The contour varies
from 98.610 to 99.63 m. The land is thus gently flat. This area is now distributed into Sectors up
to 127 in number and different projects as per Master Plan are coming up. Contour map is
attached at Annexure IV (c).
2.4.3 Flood
As there is no surface water source in the vicinity .The area is not flood prone. No endemic
disease has been reported in the area.
2.4.4 Drainage
The area is fairly plain and has good slope from North-South. The area is well drained and takes
the entire rain water flows to local Choes. Drainage map is enclosed as Annexure IV (d).
2.4.5 Seismic Zone
The whole country has been divided into 5 seismic zones as per maximum intensity of “Modified
Mercalli Scale” (MSK).This proposed township project lies in seismic Zone IV as shown in
Figure No. 2.1
2.5 CLIMATE AND METEOROLOGY
2.5.1 Climate
Mohali has a sub-tropical continental monsoon climate characterized by a seasonal rhythm: hot
summers, slightly cold winters, unreliable rainfall and great variation in temperature (−1 to 44 °C
or 30 to 111 °F). In winter, frost sometimes occurs during December and January. The average
annual rainfall is recorded at 617 millimeters (24.3 in). The city also receives occasional winter
rains from the west. Monthly average temperature given in Table No.2.2
2.5.2 Average Temperature
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 19
i. Summer: The temperature in summer may rise to a maximum of 47 °C (117 °F) @2014.
Temperatures generally remain between 30 and 40 °C (86 and 104 °F).
ii. Autumn: In autumn, the temperature may rise to a maximum of 36 °C (97 °F).
Temperatures usually remain between 15 and 26 °C in autumn. The minimum
temperature is around 10 °C
iii. Winter: Average temperatures in winter (November to February) remain at (maximum) 5
to 15 °C (45 to 59 °F) and (minimum) 1 and 5 °C (34 and 41 °F).
iv. Spring: spring temperatures vary between (min) 15 and 26 °C (61 and 77 °F) (max).
Table 2.2: Monthly average temperature
Month Maximum Minimum
January 20 5
February 23 10
March 28 15
April 34 20
May 38 24
June 40 26
July 34 25
August 32 24
September 33 24
October 32 17
November 27 11
December 22 7
2.5.3 Rainfall The rainfall in the Zone is caused by the South-West monsoon. It starts in the month of July and
extends up-to the end of September. During this period the monsoon rain-fall contributes about
75 to 80% of the total annual rainfall. The average annual rain fall is in the range of 1000 to 1100
mm. The annual number of rainy days on an average is about 51 in a year, out of which about 31
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 20
falls in the monsoon period of July to September. Monthly rainfall data for this zone is given in
Table No.2.3
Table 2.3: Monthly average rainfall
Month Rainfall (mm) Average no. of
rainy days
January 44 3
February 41 2.5
March 30 2.0
April 12 0.1
May 24 2.0
June 110 5.0
July 290 12.0
August 295 13
September 184 6
October 43 2
November 7 1
December 20 2
Total 1100 (mm) 51
Source: 2004-2009 IMD, Chandigarh
2.5.4 Humidity
In summer months of April, May and June, which is the driest part of the year, the afternoon
humidity comes down to 23% to 25% while the relative humidity during monsoon months
goes up-to 75% to 80%.
2.5.5 Cloudiness
During monsoon season skies are over cast with moderate to heavy clouds. During rest of
the year, the sky is mostly clear. It is lightly clouded occasionally during winter season.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 21
2.5.6 Wind
The Wind direction in the area is mostly from North-West to South-East. During January to May
the winds are quite strong while July to October is calm months. The general trends of various
meteorological data from meteorological observatory at Chandigarh and field observations are
used to draw Wind Rose Diagram.
Figure 2.2: Windrose diagram (May 12, 2016 to June 12, 2016)
2.6 BRIEF PROJECT DETAILS
The plot area is 32,512.44 m2 and estimated built-up area is 1, 51,314 m2. The detailed area
statement is given below in Table 2.4 & 2.5:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 22
Table 2.4: Detailed Area Statement
S. No. Particulars Area (in m2) 1. Plot Area 32,512.44 2. Permissible Ground Coverage (@ 40%) 13,004.98 3. Proposed Ground Coverage (@ 39.67%) 12,899.45 4. Permissible FAR (@ 3) 97,537.33 5. Total Proposed FAR (@2.99) 97,446.22 6. Non-FAR:
Basement Area Non-FAR on upper floors Mumty
53,867.46 26,273.36 26,778.61 815.49
7. Total Built-Up Area 1,51,314 8. Landscape Area 9517
9. Maximum Height of the Building (m) 79 m
Table 2.5: Built-up Area Details
S. No. FLOORS FAR(m2) Non-FAR (m2) Built-up Area (m2)
1. Ground Floor 8855.08 4044.37 12,899.45 2. 1st Floor 5715.62 5993.45 11,713.71 3. 2nd Floor 5598.74 5993.45 11,591.72 4. 3rd Floor 10,362.49 10,178.55 5. 4th Floor 8863.46 8863.46 6. 5th Floor 7289.39 7289.39 7. 6th Floor 6157.33 6157.33 8. 7th Floor 6142.72 6142.72 9. 8th Floor 6472.92 6472.92 10 9th Floor 6344.99 6344.99 11. 10th Floor 6098.7 6098.7 12. 11th Floor 6382.71 6382.71 13. 12th Floor 6414.22 6414.22 14. 13th Floor 1780.92 1780.92 15. 14th Floor 1763.46 1763.46 16. 15th Floor 1751.57 1751.57
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 23
2.7 POPULATION DENSITY During Construction Phase
100-200 labours will be employed during the construction phase of the project
During Operation Phase
Total population of the project during Operation Phase is estimated to be around 13,528 persons.
The detailed population break-up during operation phase is given below in Table 2.6.
Table 2.6: Population Break-up
S. No. Particulars Area (m2)
Basis Population
A.) BLOCK A & B: 1. Tower 1 (Office) 18,444 2035 Staff
Visitor 10 sqm /person
@ 10% of fixed population 1850 185
2. Tower 2 (Office) 16,849 1860 Staff
Visitor 10 sqm /person
@ 10% of fixed population 1690 170
3. Tower 3(Office) 15,824 1750 Staff
Visitor 10 sqm /person
@ 10% of fixed population 1590 160
4. Tower 4 (Office) 17,273 1905 Staff
Visitor 10 sqm /person
@ 10% of fixed population 1730 175
5. Food court Visitor Staff
1284.3 1.5 sq.m/person @10 % of floating population
950 860 90
6. Food shops Ground Floor (160 persons) Upper Floors (70 persons) Staff
869.5 465.7 403.8
3 sq.m/person 6 sq.m/person
230 90
17. 16th Floor 614.37 614.37 18. 17th Floor 641.36 641.36 19. Mezanine floor 1 190.02 3854.35 4044.37 20. Mezanine floor 2 190.02 5803.43 5993.44 21. Basement floor 26,273.36 26,273.36 22. Service Floor 1089.55 1089.55 23. Mumty 815.49 815.49 TOTAL 97,446.22 53,867.45 1,51,313.67
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 24
Visitor 140 7. Retails/Shops area
Street Floor (410 persons) Upper Floors (350 persons) Staff Visitor
3293.8 1205.8 2088.0
3 sq.m/person 6 sq.m/person
760 330 430
8. Multiplex Staff Visitor
820 82 738
9. Anchor stores Ground Floor (530 persons) Upper Floor (450 persons) Staff Visitor
4243.8 1561.6 2682.2
3 sq.m/person 6 sq.m/person
980 425 555
B.) SERVICE APARTMENTS (BLOCK – C): 10. Banquet hall
Visitor Staff
2329.8 1.5 sq.m/person
1720 1560 160
11. Restaurant (1,2,3,4) Visitors Staff
71 1.5 sq.m/person
60 50 10
12. Suites (218 units) Guests Staff
2 persons/unit
458 436 22
Total Population 13,528
2.8 POWER REQUIREMENT During Construction Phase
The power will be supplied by Punjab State Power Corporation Ltd. Demand load during
Construction phase is estimated to be around 25 kW for which permission has been obtained,
further if demand rises same will be obtained.
During Operation Phase
The power will be supplied by Punjab State Power Corporation Ltd. The Maximum demand load
for the project will be approx. 7544KW, which will be supplied through 6 nos. of 1600 kVA
11/0.433 kV dry type transformer.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 25
Details of D.G Sets
7 no. of D.G sets of total capacity 11000 kVA (3 x 2000 + 3 x 1500 + 1 x 500 kVA) will be
provided that will be equipped with acoustic enclosure to minimize noise generation and
adequate stack height for proper dispersion. Out of 7, one DG set will be kept as standby.
2.9 REQUIREMENT OF NATURAL RESOURCES
It is proposed to use environment friendly construction materials for the project that are locally
available to reduce concerns related to transportation of materials as well as achieve cost-
effectiveness.
It is proposed to use fly ash mixed cement, and bricks for the construction of the project. The use
of timber will be minimal with the provision of aluminum frames for windows. Paints with low
VOC and no ammonia are proposed to be used for all residential buildings.
All means of reducing water consumption during project construction and operation phase will
be adopted.
2.10 DESIGN CONSIDERATION
The project structures have been designed after due study of local architecture. Likewise, the
building has been planned with modern design and facilities with large stretches of open spaces.
The following standards and bye-laws will be followed for designing the project:
National Building Code (2005).
Relevant IS Codes of Practice Published by the bureau of Indian standards.
CPHEEO Manual on Sewerage and Water issued by the Ministry of Urban Development
NewDelhi.
Building bye laws–Local Municipal Corporation bye-laws, etc
2.11 PARKING FACILITIES
Adequate provision will be made for car/vehicle parking at the project site. The details of
parking required and parking proposed are given below.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 26
Parking required as per MoEFCC norms:
For Commercial facilities = 1 ECS/50 m2 FAR area
= 97,481.63/50 =1950 ECS
As per Bye-laws:
For Commercial area =2 ECS/100 m2 FAR area
= 97,481.63/100 x 2 = 1950 ECS
Parking Proposed:
Area proposed for open parking = 2300 m2
Area required for 1 ECS in open parking =23 m2
Parking proposed for open parking =100
Total parking proposed in open = 100 ECS
Area proposed for basement parking = 19181.95 m2
Area required for 1 ECS in basement parking =32 m2
Parking proposed for basement parking =600 + 388ECS (Stack mechanized
parking)
Total parking proposed in basement = 988 ECS
Area proposed for Ground Floor = 3620.21 m2
Area required for 1 ECS of Ground Floor parking =28 m2
Parking proposed on Ground Floor = 129 + 129 (second/mezzanine
floor)
= 258 ECS
Area proposed for 1st Floor = 6042.07 m2
Area required for 1 ECS of 1stFloor parking =28 m2
Parking proposed on 1stFloor = 202+202 (second/mezzanine floor)
= 404 ECS
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 27
Area proposed for 2nd Floor = 5665.417 m2
Area required for 1 ECS of 2nd Floor parking = 28 m2
Parking proposed on 2nd Floor = 202 ECS
Total Parking proposed = 100+988+258+404+202 ECS
= 1952 ECS
2.12 WATER REQUIREMENT AND WASTE WATER GENERATION
During Construction Phase
Water requirement for Construction activity is estimated to be around 757 ML and fresh water
requirement for laborer is estimated to be around 25.4 KLD. 10 KLD of wastewater is estimated
to be generated during construction phase. Water during construction phase will be provided
from Private water tanker (Rupinder Singh). Copy of permission is enclosed as Annexure II (e)
The water requirement and waste water generation calculation during Construction phase is
given below in Table 2.7 :
Table 2.7: Water Demand and waste water calculation during Construction phase
S. No. Purpose Water Requirement Wastewater generation @85%
Quantity (KLD) Remarks Quantity (KLD) Remarks
1. Domestic water
for labour
9.0 @ 40
lpcd for 200
workers
(Assumed)
7.6 Arrangement
for domestic
water
requirement
will be met by
contractor
2. Dust
suppression
1.0 - - Losses
3. Washing of
construction
equipment
3.0 - 2.40 Approx. 20%
loss (0.6
KLD) on
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 28
washing; rest
will be
collected and
reused for
curing after
necessary
treatment.
4. Concrete Curing 12.40 (including
2.4 KLD
recycled water
from washing)
- - Losses
Total 25.4 10
Figure 2.3: Water Balance diagram during Construction Phase
During Operation Phase
Daily water Demand (25.4 KLD)
Domestic water for labour camp (9 KLD)
Dust suppression (1 KLD)
Washing of construction equipment (3 KLD)
Concrete curing (10 + 2.4 KLD)
Septic Tank (7.6 KLD)
Losses
Losses(20%) (0.6 KLD)
After treatment (2.4 KLD)
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 29
The water will be sourced from GMADA. The total water requirement is approx. 1127 KLD out
of which domestic water demand is 652.32 KLD. The total fresh water requirement is approx.
632 KLD.
The daily water requirement and waste water generation calculation is given below in Table 2.8
& 2.9:
Table 2.8: Daily Water Demand
S.
No.
Description
Total
occupancy
Rate of
water
demand
(lpcd)
Total water
requirement
(KLD)
A. DOMESTIC WATER:
1. Tower 1 to 4
(Offices)
Staff
Visitor
7550
6860
690
45
15
319.05
308.70
10.35
2. Banquet hall, food
court & restaurant
Staff
Visitor
2730
260
2470
45
70
184.6
11.70
172.90
3. Anchor store, Food
shop & retail/shops
area
Staff
Visitor
1970
845
1125
45
15
54.91
38.03
16.88
4. Multiplex
Staff
Visitor
820
82
738
45
15
14.76
3.69
11.07
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 30
5. Suites
Guests
Staff
458
436
22
180
45
79
78
1
Total Domestic water requirement 652.32 KLD
B. HVAC/DG Cooling 400
C. Water body 10
D. Swimming pool 13
E. Horticulture 5.5 l/sqm 52
Total water requirement 1127 KLD
Table 2.9: Waste Water Calculation
Flushing water (@70% of the domestic water requirement) 457 KLD
Fresh water (@ 30% of total domestic water requirement) 196 KLD Waste water generated (@ 80% of the total domestic water requirement) 522 KLD
STP capacity 627 KLD
The water balance diagram for summer, winter and rainy seasons are shown below in figure 2.4
to 2.6:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 31
Figure 2.4: Water Balance Diagram during Summer Season
Treated effluent
FRESH WATER (196 KLD)
WASTE WATER GENERATED (522 KLD)
STP CAPACITY (627 KLD)
HORTICULTURE @5.5 l/sqm (52 KLD)
@ 80%
FLUSHING (457 KLD)
Waste waterwaterwaterwatFresh water
39 KLD
TOTAL DOMESTIC WATER DEMAND
(652.32 KLD)
457 KLD @95% 496 KLD
HVAC/DG COOLING (400 KLD)
SWIMMING POOL (13 KLD)
13 KLD
400 KLD
13 KLD
WATER BODY (10 KLD)
10 KLD
TOTAL FRESH WATER (196 + 13 + 400 + 13 + 10
= 632 KLD)
196 KLD
@ZERO EXIT DISCHARGE
Total water requirement is 1127 KLD
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 32
Figure 2.5: Water Balance Diagram during Winter Season
Treated effluent
FRESH WATER (196 KLD)
WASTE WATER GENERATED (522 KLD)
STP CAPACITY (627 KLD)
HORTICULTURE @ 1.8 l/sqm (17 KLD)
@ 80%
FLUSHING (457 KLD)
Waste waterwaterwaterwatFresh water
17 KLD
TOTAL DOMESTIC WATER DEMAND
(652.32 KLD)
457 KLD @95%
496 KLD
HVAC/DG COOLING (400 KLD)
SWIMMING POOL (13 KLD)
378 KLD
13 KLD
WATER BODY (10 KLD)
10 KLD
TOTAL FRESH WATER (196 + 378 + 13 + 10 =
597 KLD)
196 KLD
@ZERO EXIT DISCHARGE
Total water requirement is 1093 KLD
22 KLD
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 33
Figure 2.6: Water Balance Diagram during Monsoon Season
The project will generate approx. 522 KLD of waste water. The waste water is proposed to be
treated in onsite STP of capacity 627 KLD generating approx. 496 KLD of treated effluent which
will be recycled for the purpose of flushing, horticulture and HVAC/DG cooling to achieve zero
exit discharge.
2.13 SOLID WASTE GENERATION
Solid waste would be generated during construction as well as operation phase.
Treated effluent
FRESH WATER (196 KLD)
WASTE WATER GENERATED (522 KLD)
STP CAPACITY (627 KLD)
HORTICULTURE @ 0.5 l/sqm
(5 KLD)
@ 80%
FLUSHING (457 KLD)
Waste waterwaterwaterwatFresh water
5 KLD
TOTAL DOMESTIC WATER DEMAND
(652.32 KLD)
457 KLD @95% 496 KLD
HVAC/DG COOLING (400 KLD)
SWIMMING POOL (13 KLD)
366 KLD
13 KLD
WATER BODY (10 KLD)
10 KLD
TOTAL FRESH WATER (196 + 366 + 13 + 10 =
585 KLD)
196 KLD
34 KLD
@ZERO EXIT DISCHARGE
Total water requirement is 1081 KLD
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 34
During Construction Phase
The solid waste expected to be generated during the construction phase will comprise of
excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc.
During Operation Phase
During the operation phase, waste will comprise domestic and landscape waste. The estimated
quantity of the waste is approx. 3877 kg per day (@ 0.5 kg/capita/day for suite, @ 0.15 kg/capita
per day for visitors, @ 0.25 kg per capita per day for staff and @ 0.2 kg/acre/day). Solid waste
calculations are given below in Table 2.10:
Table 2.10: Solid Waste Calculation
S.
No.
Category Kg/capita/day Waste generated (kg/day)
1. Offices (Tower 1 to 4)
Staff
Visitor
6860 @ 0.25 kg/day
690 @ 0.15 kg/day
1715
103.5
2. Banquet hall, food court
& restaurant
Staff
Visitor
260 @ 0.25 kg/day
2470 @ 0.5 kg/day
65
1235
3. Anchor store, Food shop
& retail/shops area
Staff
Visitor
845 @ 0.25 kg/day
1125 @ 0.15 kg/day
211.25
168.75
4. Multiplex
Staff
Visitor
82 @ 0.25 kg/day
738 @ 0.1 kg/day
20.5
73.8
5. Suites
Guests
Staff
436@ 0.5 kg/ day 22@ 0.25 kg/ day
218
5.5
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 35
6. Landscape waste
(2.35 acre) @ 0.2 kg/acre/day 0.47
7. STP Sludge 60.29
Total solid waste generated 3877 kg/day (Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment
Engineering Organization, Ministry of Urban Development, (Government of India, May 2000)
E-waste
E-waste will be generated during operation phase of the project from the staff of Office complex
(i.e. 6,860) . Calculation of E-waste generated during operation phase:
• E-waste generation from 1 unit personal computer (includes desktop, portables and CPU)
= 8 kg
• E-waste generation from keyboard + Mouse = 0.8 kg
• E-waste generation from hardcopy device (printers, scanner etc.) per unit = 8.6 kg
• E-waste generation from Laptop = 3 kg
• Average life period of a PC is considered as 5 years, for laptop average life period of 3
years is considered, for hard-copy devices, keyboard and mouse average life period of 2
years is considered.
• Total staff is estimated to be 6,860 so accordingly we consider 6,000 Nos. of personal
computers and 860 Nos. of laptops. 1 Hard-copy device is considered per 15 PC/laptop,
so 457 Nos. of hardcopy devices are considered.
Estimation of E-waste:
=6,000 X 8 X 1/5 +6,000 X 0.8 X 1/2 + 860 X 3 X 1/3 + 457 X 8.6 X 1/2
= 9,600+ 2,400 + 860 + 1,965.1= 14,825.1 or 14 Tonnes/ year.
Source:
Electronics Waste Management in the United States Through 2009,” U.S. EPA, May 201
1, EPA 530‐R‐11‐
002 http://www.epa.gov/wastes/conserve/materials/ecycling/docs/fullbaselinereport2011.pdf
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 36
2.14 GREEN AREA
Total green area measures 9517 m2 which will include green belt and organized green. Evergreen
and deciduous indigenous species are proposed to be planted inside the premises.
2.15 MANPOWER REQUIREMENT
During the construction phase, a large number of professionals and workers will be engaged in
various related activities. An approximation of the manpower requirement for the project is
around 200-300 workers which include skilled, semiskilled and unskilled.
As a responsible corporate, the proponent will comply with all applicable Acts related to
employees’ service and their welfare of the Government of India in terms of working hours,
basic amenities and welfare facilities such as given below:
Minimum Wages Act, 1948,
Contract Labour (Regulation & Abolition) Act, 1970,
Inter-State Migrant Workmen (Regulation of Employment & Conditions of Services)
Act,1979,
The Building and other Construction Workers (Regulation and Employment of Service)
Act, 1996,
The Building and other construction workers Welfare Cess Act, 1996.
All workers and technicians will be provided with clean drinking water, sheds for resting and
sanitary facilities as mobile toilets/ toilets connected to septic tanks. Camps will also be
organized for health check up every six months. No child will be employed in labour work.
Facilities and care will be made available to labor as per applicable laws and rules.
Safety measures for construction workers
Necessary PPEs will be provided
First aid room with first aid kit
Doctor on call
Beds for patient till ambulance arrives
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 37
Use of proper radium signage for displaying first aid box location
Location of first aid displayed in the literature
Mock drills, training on safety awareness
Following basic facilities will be provided for construction workers as per Building and
Other Construction Workers Act, 1996 and maximum employment to the local people.
On site sanitation facilities
Hygienic condition will be maintained to avoid any health problems
Proper PPE will be provided
Proper water supply for workers
First aid room with first aid kitEmployment of about 150 local construction workers
Welfare facilities
2.16 FIRE FIGHTING SYSTEM
The project site falls under residential occupancies according to National Building Code 2005.
Following provisions are required to be made according to National Building Code 2005. The
fire fighting system has been designed considering the following codes, manual and guidelines;
National Building Code of India (NBC);
IRI guidelines;
As per requirement of fire officer/local fire approving authorities; and
As per Indian Standard Code for Fire Protection (IS Codes)
Following items are envisaged for firefighting:
Fire-Water Connections;
Firewater inlet and outlet connections will be provided to the water storage tanks;
External main fire ring, having 150 mm diameter and hydrants @ 45 m3/s spacing will be
provided. This external fire ring will be separated from the Sprinkler Main Systems;
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 38
All flow switches, test valves, drain pipes etc. will be provided as per NFPA guidelines
on the sprinkler system;
All pump installation and arrangements will be in accordance with IRI guidelines and
NFPA-20;
All pumps and accessories and electrical controllers will be as per UL/FM lists, tested,
approved and certified; and
By-pass arrangements will to be provided (150 mm diameter nominal bore) with NRV
and gate valve and bulk flow meter on the discharge header of each pump to check the duties of
pumps.
Storage tanks are provided in the basement for the supply of water for the firefighting
facility.
The fire extinguishers provided should be in conformance with Ozone Depleting
Substances (Regulation and Control) Rules 2000.
2.17 DETAILS OF CONSTRUCTION MATERIAL
List of building materials being used at site:
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
9. CLC fly ash blocks
10. Crazy (white marble) in grey cement
11. P.V.C. conduit
12. MDS, MCBs
13. 2 1/2'’ thick paver tiles
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 39
14. PPR (ISI marked)
15. PVC waste water lines
16. S.W. sewer line up to main sewer
17. PVC rain water down take
18. Stainless steel sink in kitchen
19. Joinery hardware- ISI marked
2.17.1 MATERIALS USED FOR CONSTRUCTION & THEIR U VALUES
2.17.2 LIST OF MACHINERY USED DURING CONSTRUCTION (i) Dumper (viii) RMC Plant
(ii) Concrete mixer with hopper (ix) Bulldozer
(iii) Excavator (x) Hoist
(iv) Concrete Batching Plant (xi) Labor Lifts
(v) Cranes (xii) Pile Boring Machines
(vi) Road roller (xiii) Concrete pressure pumps
(vii) Tower Cranes (xiv) Mobile transit mixer
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 40
2.18 PROJECT IMPLEMENTATION SCHEDULE
Project is scheduled to be completed in 3 phases
Phase I: 16th August 2016 to 5th April 2020
Phase II: 27th April 2017 to 31st Oct 2020
Phase III: 29th Nov. 2017 to 03rd Oct 2021
Figure 2.7: Construction schedule
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 41
CHAPTER 3: DESCRIPTION OF ENVIRONMENT
3.1 INTRODUCTION
Information on the existing environmental status is essential for assessing the likely
environmental impacts of the project. In order to get an idea about the existing state of the
environment, various environmental attributes such as meteorology, air quality, water quality,
soil quality, noise level, ecology and socio-economic environment have been studied/
monitored.
3.2 STUDY PERIOD
With the permission of SEAC, the baseline environment study carried out for the project
"Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS Nagar, Mohali, Punjab during
post-monsoon season October to December 2013 has been used for this project with
additional one month study (12th May, 16 to 12th Jun., 16). The monitoring locations selected
for GMADA project fall within the 10 km radius of proposed ‘World Trade Centre’
Commercial project by WTC NOIDA Development Company Pvt. Ltd.
As per the MoEF&CC Office Memoranda dated 12th April 2016, the primary data used for
and EIA study should not be older than three years.
Apart from field study, additional data was also collected from secondary sources like
irrigation department, India Meteorological Department (IMD), Central Ground Water Board,
Geological Survey of India, State Ground Water Department, State Pollution Control Board,
Census of India and Local Forest Department, Non - Government Agencies, etc.
3.3 STUDY AREA
The present report covers baseline environmental data generated in the core and buffer zone
(10 Km radius all around the project site for land use and the sample selection for monitoring
are done within 5 km radius of the project site).
3.4 BASELINE MONITORING OF ENVIRONMENTAL COMPONENTS
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 42
In order to get an idea about the existing state of the environment, various environmental
attributes such as meteorology, air quality, water quality, soil quality, noise level, ecology
and socio-economic environment have been studied/monitored.
3.4.1 METEOROLOGY
Meteorological data was generated during the October- December 2013. The following
parameters were recorded at hourly intervals continuously during monitoring period:
Air Temperature
Wind speed
Table - 3.1 gives summarized meteorological data for the monitoring period (Oct- Dec 2013).
Table 3.1: Meteorological Data for Oct 2013 to Dec 2013
3.4.2 AIR ENVIRONMENT
The prime objective of the baseline study with respect to ambient air quality is to establish
the present air quality and its conformity to National Ambient Air Quality Standards. This
data has been further used during impact assessment to predict the final air quality. This
section describes the sampling locations, frequency of sampling and methodology adopted for
monitoring ambient air quality.
To quantify the impact of the project on the ambient air quality, it is necessary at first to
evaluate the existing ambient air quality of the area. The existing ambient air quality, in terms
of Particulate Matter – 10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide (SO2),
Oxides of Nitrogen (NO2), and Carbon Monoxide (CO), has been measured through a
planned field monitoring.
To assess the ambient air quality level, 5 (five) monitoring stations were set up. Table - 3.2
gives location of the ambient air quality monitoring stations gives location of the ambient air
Month
Temperature, °C Wind Speed, m/sec
Min Max Monthly
average Min Max
Aver
age
Oct 2013 14.7 24.6 19.6 40.5 72.5 49.7
Nov 2013 12.5 24.1 18.3 38.5 75.3 51.7
Dec 2013 8.5 19.2 20.15 41.1 78.2 52.3
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 43
quality monitoring stations and a composite map showing the ambient air quality monitoring
stations of both the sites is attached as Annexure - 5 (a).
Table 3.2(a): Location of Ambient Air Quality Monitoring Stations (Knowledge Park,
GMADA)
Locations code Locations Direction Distance (Km)
AAQ1 Project Site - -
AAQ2 Saneta W 6.4
AAQ3 Nagari WSW 7.37
AAQ4 Shekhan SW 5.59
AAQ5 Naraingarh SE 3.18
Table 3.2(b): Location of Ambient Air Quality Monitoring Stations (World Trade
Centre)
Locations code Locations Direction Distance (Km)
AAQ1 Project Site - -
AAQ2 Saneta W 8.6
AAQ3 Nagari WSW 9.1
AAQ4 Shekhan SW 6.6
AAQ5 Naraingarh SE 3.2
3.4.2.1 Monitoring Schedule
Ambient air quality monitoring was carried out twice a week with a frequency of 24 hours for
12 weeks.
3.4.2.2 Methods of Sampling and Analysis
The brief methodology of the parameter analyzed is as follows:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 44
I. Particulate Matter (PM2.5): (CPCB Method) Particulate Matter (PM2.5) was analyzed
by Fine particulate Sampler Envirotech Model APM 550. PM 2.5 was collected on 47mm
diameter filter paper. The mass concentration of (PM2.5) fine particles in ambient air was
calculated as the total mass of collected particles divided by the volume of air sampled.
II. Particulate Matter (PM10): Particulate Matter (PM10) was carried out by respirable
dust sampler envirotech Model APM 460 BL. The cyclone of this instrument is used for
fractionating the dust into two fractions. PM 10 dust is accumulated on the filter paper
(8ʺ×10ʺ size) while coarse dust is collected in a cup placed under the cyclone.PM 10 was
calculated as per IS: 5182 (Part 23):2006. The mass of these particles was determined by the
difference in filter weight prior to and after sampling. The concentration of PM 10 in the
designated size range was calculated by dividing the weight gain of the filter by the volume
of air sampled.
III. Sulphur dioxide (SO2): SO2 was monitored with the help of APM 411 assembly
attached with APM 460 BL using the impinge. It was absorbed by aspirating a measured air
sample through a solution of Potassium tetrachloromercurate (TCM). This procedure resulted
in the formation of a dichlorosulphitemercurate complex. The complex was made to react
with pararosaniline and methylsulphonic acid. The absorbance of the solution was measured
by means of spectrophotometer.
IV. Nitrogen Dioxides: NO2 was monitored with the help of APM 411 assembly attached
with APM 460 BL using the impinge. It was collected by bubbling air through a solution of
sodium hydroxide and sodium arsenite. The concentration of nitrite ion produced during
sampling was determined colorimetrically by reacting with the nitrite ion with phosphoric
acid, sulphanilamide and NEDA and absorbance of highly colored azo-dye was measured at
540nm.
V. Carbon Monoxide: It is measured using CO Analyser. This analyser is used to
measure CO in ambient air, in the range of 0-200 ppm (220 mg/m3) to a sensitivity of 0.05
ppm (55µg/m3). The Serinus 30 combines the benefits of Microprocess control with Non-
Dispersive Infrared Spectrophotometry technology. CO concentration is automatically
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 45
corrected for gas temperature and pressure changes. CO was monitored on hourly basis
whereas other parameters were monitored on 24 hourly bases.
3.4.2.3 Results and Discussions
The monitoring reports are enclosed as Annexure-6 and summarized in the tabular form
below. The results when compared with National Ambient Air Quality Standards
(NAAQS) of Central Pollution Control Board (CPCB) for "Industrial, Residential,
Rural and Other Areas" show that the average values of ambient air quality parameters are
well within the stipulated limit.
The results of ambient air quality monitoring for Oct-Dec 2013 for “Knowledge Park” project
are summarized in the Tables below:
Table 3.3 (a) Ambient Air Quality with respect to PM2.5
PM2.5 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 30.7 43.2 39.8 36.8 37.8
Max 52.8 56.2 58.6 47.4 44.6
Average 39.8 49.4 47.4 42.0 41.0
98 Percentile 51.3 55.1 55.2 46.3 44.0
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 46
Figure 3.1: Concentration of PM2.5
The values of PM2.5 in study area are presented in Table 3.3 (a). The seasonal minimum,
maximum, and average values of PM2.5 were observed 30.7, 52.8 and 39.8 respectively at the
project site. The seasonal minimum, maximum and average values ranged between 30.7- 43.2
µg/m3, 44.6- 58.6 µg/m3 and 39.8- 49.4 µg/m3 respectively in the study area.
Table 3.3 (b) Ambient Air Quality with respects to PM10
PM10 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 70.6 76.1 74.7 71.5 78.7
Max 92.3 90.7 93.1 81.9 90.6
Average 79.4 82.4 86.4 77.1 84.0
98 Percentile 92.3 89.6 92.0 81.9 90.0
0
10
20
30
40
50
60
70
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f P
M2
.5
Air Quality Monitoring Station
Concentration of PM2.5
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 47
Figure 3.2: Concentration of PM10
The values of PM10 in study area are presented in Table 3.3 (b). The seasonal minimum,
maximum, and average values of PM10 were observed 70.6 µg/m3, 92.3 µg /m3, 79.4µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 70.6-78.7 µg/m3, 81.9- 93.1 µg/m3 and 77.1-86.4 µg/m3 respectively in the study
area.
Table 3.3 (c) Ambient Air Quality with respect to SO2
SO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 5.1 5.1 5.1 5.0 5.5
Max 7.2 6.7 6.5 6.8 6.7
Average 5.9 5.6 5.5 5.6 5.9
98 Percentile 7.1 6.5 6.2 6.6 6.5
0
20
40
60
80
100
120
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f P
M 1
0
Air Quality Monitoring Station
Concentration of PM10
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 48
Figure 3.3: Concentration of SO2
The values of SO2 in study area are presented in Table 3.3 (b). The seasonal minimum,
maximum, and average values of SO2 were observed 5.1 µg/m3, 7.2 µg /m3, 5.9 µg/m3
respectively at the project site.. The seasonal minimum, maximum and average values ranged
between <5.0- 5.5 µg/m3, 6.5- 7.2 µg/m3 and 5.5-5.9 µg/m3 respectively in the study area.
Table 3.3 (d) Ambient Air Quality with respects to NO2
NO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 15.6 17.2 19.1 19.7 20.5
Max 24.6 28.3 28.5 26.7 29.1
Average 18.7 21.1 21.7 23.3 25.0
98 Percentile 23.1 27.4 26.7 26.6 28.1
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f SO
2
Air Quality Monitoring Station
Concentration of SO2
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 49
Figure 3.4: Concentration of NO2
The values of NO2 in study area are presented in Table 3.3 (d). The seasonal minimum,
maximum, and average values of NO2 were observed 15.6 µg/m3, 24.6 µg /m3, 18.7 µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 15.6- 20.5 µg/m3, 24.6-29.1µg/m3 and 18.7-25.0 µg/m3 respectively in the study
area.
Table 3.3 (e) Ambient Air Quality with respects to CO
CO (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 410.0 660 630 570 750
Max 780.0 1120 1050 940 1120
Average 614.2 889 828 774 958
98 Percentile 766.2 1102 1041 926 1106
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f N
O2
Air Quality Monitoring station
Concentration of NO2
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 50
Figure 3.5: Concentration of CO
The values of CO in study area are presented in Table 3.3 (e). The seasonal minimum,
maximum, and average values of CO were observed 410 µg/m3, 780 µg /m3, 614.2 µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 410- 750 µg/m3, 780 - 1120 µg/m3 and 614.2- 958 µg/m3 respectively in the study
area.
Additional One Month Study:
The results of ambient air quality monitoring for 12th May to 12th June, 2016 for World Trade
Centre as Project site are summarized in the Tables (3.3 f to 3.3j ) below:
Table 3.3 (f) Ambient Air Quality with respect to PM2.5
PM2.5 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 41.0 49.3 49.4 30.1 40.8
0
500
1000
1500
2000
2500
3000
3500
4000
4500
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f C
O
Air Quality Monitoring Station
Concentration of CO
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 51
Max 56.8 58.5 59.1 50.4 45.9
Average 46.8 55.4 55.7 40.3 43.4
98 Percentile 56.3 58.4 58.9 49.9 45.8
Figure 3.6: Concentration of PM2.5
The values of PM2.5 in study area are presented in Table 3.3 (f). The seasonal minimum,
maximum, and average values of PM2.5 were observed 41.0 µg/m3 , 56.8 µg/m3 and 46.8
µg/m3 respectively at the project site. The seasonal minimum, maximum and average values
ranged between 30.1- 49.4 µg/m3, 45.9- 58.5 µg/m3 and 40.3- 55.7 µg/m3 respectively in the
study area.
Table 3.3 (g) Ambient Air Quality with respects to PM10
PM10 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 144.6 113.1 118.7 87.5 88.8
0
10
20
30
40
50
60
70
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f P
M2
.5
Air Quality Monitoring Station
Concentration of PM2.5
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 52
Max 166.3 124.1 134.6 97.9 97.2
Average 151.9 119.0 130.2 91.7 92.7
98 Percentile 165.9 124.0 134.4 97.6 97.1
Figure 3.7: Concentration of PM10
The values of PM10 in study area are presented in Table 3.3 (b). The seasonal minimum,
maximum, and average values of PM10 were observed 144.6 µg/m3, 166.3 µg /m3, 151.9
µg/m3 respectively at the project site. The seasonal minimum, maximum and average values
ranged between 87.5-144.6 µg/m3, 97.2- 166.3 µg/m3 and 91.7-151.9 µg/m3 respectively in
the study area.
Table 3.3 (h) Ambient Air Quality with respect to SO2
SO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 5.2 6.9 5.2 5.1 5.1
Max 7.8 8.5 6.9 6.9 6.8
0
20
40
60
80
100
120
140
160
180
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f P
M1
0
Air Quality Monitoring Station
Concentration of PM10
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 53
Average 6.1 7.7 6.0 6.0 6.0
98 Percentile 7.6 8.5 6.8 6.9 6.8
Figure 3.8: Concentration of SO2
The values of SO2 in study area are presented in Table 3.3 (h). The seasonal minimum,
maximum, and average values of SO2 were observed 5.2 µg/m3, 7.8 µg /m3, 6.1µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 5.1- 6.9 µg/m3, 6.8- 8.5 µg/m3 and 6.0-7.7 µg/m3 respectively in the study area.
Table 3.3 (i) Ambient Air Quality with respects to NO2
NO2 (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 14.3 14.1 14.8 14.6 14.5
Max 18.3 18.8 19.6 19.2 19.7
Average 16.3 16.9 17.0 17.1 17.4
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f SO
2
Air Quality Monitoring Station
Concentration of SO2
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 54
98 Percentile 18.2 18.7 19.6 19.2 19.6
Figure 3.9: Concentration of NO2
The values of NO2 in study area are presented in Table 3.3 (i). The seasonal minimum,
maximum, and average values of NO2 were observed 14.3 µg/m3, 18.3 µg /m3, 16.3µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 14.1- 14.8 µg/m3, 18.3-19.7µg/m3 and 16.3-17.4 µg/m3 respectively in the study
area.
Table 3.3 (j) Ambient Air Quality with respects to CO
CO (µg/m3)
Location AAQ 1 AAQ 2 AAQ 3 AAQ 4 AAQ 5
Min 780.0 820 740 820 920
Max 950.0 990 950 930 1090
Average 838.8 900 813 875 991
98 Percentile 938.8 990 942 929 1089
0
10
20
30
40
50
60
70
80
90
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f N
O2
Air Quality Monitoring Station
Concentration of NO2
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 55
Figure 3.10: Concentration of CO
The values of CO in study area are presented in Table 3.3 (e). The seasonal minimum,
maximum, and average values of CO were observed 780 µg/m3, 950 µg /m3, 838.8µg/m3
respectively at the project site. The seasonal minimum, maximum and average values ranged
between 740-920 µg/m3, 930 - 1090 µg/m3 and 813-991 µg/m3 respectively in the study area.
3.4.3 NOISE LEVELS
Noise is one of the most undesirable and unwanted by-products of our modern life style. It
may not seem as insidious or harmful as air and water pollutants but it affects human health
and well-being and can contribute to deterioration of human well-being in general and can
cause neurological disturbances and physiological damage to the hearing mechanism in
particular. It is therefore, necessary to measure both the quality as well as the quantity of
noise in and around the site.
To assess the ambient noise quality level, 5 (five) monitoring stations were set up. Table - 3.4
gives location of the ambient noise quality monitoring stations gives location of the ambient
air quality monitoring stations and a composite map showing the ambient noise quality
monitoring stations of both the sites is attached as Annexure - 5 (b).
0
500
1000
1500
2000
2500
3000
3500
4000
4500
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Co
nce
ntr
atio
n o
f C
O
Air Quality Monitoring Station
Concentration of CO
Min conc
Max. conc
98 Percentile
As per CPCB Limit
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 56
3.4.3.1 Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is
expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an
additional circuit (filters) is provided, which modifies the received signal in such a way that it
replicates the sound signal as received by the human ear and the magnitude of sound level in
this scale is denoted as dB (A). The sound levels are expressed in dB (A) scale for the
purpose of comparison of noise levels, which is universally accepted by the international
community.
Noise levels were measured using an Integrating sound level meter manufactured by Pulsar
Instruments Plc, Model No. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq.
Keeping the mode in Lp for few minutes and setting the corresponding range and the
weighting network in “A” weighting set the sound level meter was run for one hour time and
Leq was measured at all locations.
The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels,
during 10.00 pm to 6.00 am at all the 5 locations, which covers residential areas, commercial,
industrial areas, silence area if available within 5 km radius of the study area.
3.4.3.2 Sampling Locations
A preliminary survey was undertaken to identify the major noise generating sources in the
area. The noise survey was conducted to assess the background noise levels in different
zones. Gazette Notification (S.O. 123(E)) of MoEF dated December 14, 2000 on ambient air
quality standards has different noise levels for different zones viz. project site, industrial, and
residential zones. Four sampling locations were selected for the sampling of noise levels. The
sampling locations are given in Table - 3.4 below. The noise quality at the GMADA site and
other locations within the 10 km impact zone was monitored during Oct 2013 and additional
one month baseline study (12th May to 12th June, 2016) was conducted on project site. The
monitoring reports are given in details in Annexure-6 and summarized in the tabular form.
Table 3.4(a) Noise Level Monitoring Stations (Knowledge Park, GMADA)
Location Code Locations Type of Area Direction Distance
(Km)
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 57
NQ1 Project Site Commercial Area Centre 0
NQ2 Saneta Residential Area W 6.4
NQ3 Nagari (Near Primary
School)
Silence Area
WSW 7.37
NQ4 Shekhan Residential Area SW 5.59
NQ5 Naraingarh Residential Area SE 3.18
Table 3.4(b) Noise Level Monitoring Stations (World Trade Centre)
Location Code Locations Type of Area Direction Distance
(Km)
NQ1 Project Site Commercial Area Centre -
NQ2 SAS Nagar Phase 9 Industrial NW 3.0
NQ3 Nagari (Near Primary
School)
Silence Area
WSW 9.1
NQ4 Shekhan Residential Area SW 6.6
NQ5 Naraingarh Residential Area SE 3.2
Ministry of Environment & Forests (MoEF) has notified the noise standards vide gazette
notification dated December 14, 2000 for different zones under the Environment Protection
Act (1986). These standards are given in Table - 3.5.
Table 3.5 Ambient Quality Standards in Respect of Noise
Area Code Category of Area Noise dB(A) Leq
Day time* Night time*
A Residential Area 55 45
B Silence Zone 50 40
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 58
C Industrial Area 75 70
D Commercial Area 65 55
Note:
1. Daytime is from 6.00am to 10.00 pm and Night time is from 10.00 pm to 6.00 am.
2. Silence zone is defined as area up to 100 meters around premises of hospitals, educational institutions
and courts. Use of vehicle hours, loud speakers and bursting of crackers are banned in these zones.
3.4.3.3 Results and Discussion
Table 3.6 (a): Hourly Leq Noise Level at Knowledge Park, GMADA
Noise Quality data October 2013
S.No. Locations ZONE LIMIT (as per
CPCB
Guidelines),Leq
RESULT (Leq)
DAY* NIGHT* DAY* NIGHT*
1
Project Site
Industrial
Area
75 70 51.4
41.7
2
Saneta
Residential
Area
55 45 52.8
42.1
3 Nagari (Near Primary
School)
Silence Area 50 40 53.1
41.8
4
Shekhan
Residential
Area
55 45 51.2
40.8
5
Naraingarh
Residential
Area
55 45 52.7
41.9
* Day time (6.00AM
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 59
The noise data compiled on noise levels during October, 2013 is given in Table - 3.6. The
ambient noise level at the project site (Knowledge Park, GMADA) during the day was found
to be 51.4 dB which is within the limit and during night it was 41.7dB (A), which is within
the limit. For reducing additional noise from the project, plantation and traffic management
during the operation phase are suggested.
The results of noise quality monitoring of project site(World Trade Centre) is summarized in
the Table below:
Table 3.6(b): Hourly Leq Noise Level (World Trade Centre)
Noise Quality data May-June 2016
S.
No.
Locations ZONE LIMIT (as per CPCB
Guidelines),Leq
RESULT (Leq)
DAY* NIGHT* DAY* NIGHT*
1 Project Site Commercial Area 65 55 64.2 56.8
2 SAS Nagar Phase-9 Industrial Area 75 70 68.2 57.9
3 Nagari (Near
Primary School)
Silence Zone 50 40 52.3
42.6
4 Shekhan Residential Area 55 45 56.3 44.1
5 Naraingarh Residential Area 55 45 50.3 41.9
* Day
time
(6.00AM TO
10.00PM)
** Night
time
(10.00PM TO
6.00AM)
TO
10.00PM)
** Night time (10.00PM
TO
6.00AM)
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 60
3.4.4 WATER ENVIRONMENT
3.4.4.1 Water Quality
Water quality assessment is one of the essential components of EIA study. Such assessment
helps in evaluating the existing health of water body and suggesting appropriate mitigation
measures to minimize the potential impact from development projects. Water quality of
ground water has been studied in order to assess proposed water-uses in construction,
drinking, cooling and horticulture purpose.
The water quality at GMADA site and other locations within the 10 km impact zone was
monitored during Oct 2013 to Dec 2013 and additional one month baseline study (12th May
to 12th June, 2016) was conducted on project site. The locations of the monitoring sites are
depicted in composite map is enclosed as Annexure 5 (c) and the result of the monitoring
and analysis of groundwater is presented in the Annexure 6.
Table 3.7(a): Location of water sampling sites (Knowledge Park, GMADA)
Location No. Location Name Distance & Direction from
project site
GW – 1 Project Site Center
GW – 2 Saneta W, 6.4
GW- 3 Naugiari WSW, 7.37
Table 3.7(b): Location of water sampling sites (World Trade Centre)
Location No. Location Name Distance & Direction from
project site
GW – 1 Project Site Center
GW – 2 Saneta W, 8.6
GW- 3 Naugiari WSW, 9.1
3.4.4.2 Sampling Frequency and Sampling Techniques
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 61
Samples were studied at monthly intervals in the study period. Quality of ground water was
compared with IS: 10500: 1991 (Reaffirmed 1993 with Amendment No.3 July 2010) for
drinking purposes. Surface water quality was analyzed for parameters as mentioned in the
‘Annexure IV of CPCB guidelines’ and it was rated according to the CPCB Water Quality
Criteria (Designated Best Use). Water samples were collected in a 5 liter plastic jerry can and
500 ml sterilized clean glass bottles for physio-chemical and bacteriological tests
respectively. GW sampling was done after flushing out the source (minimum 10 minutes) to
get the fresh ground water and grab sampling method was used. River water samples were
collected about 10cm below the water surface. All sampling, preservative and sample
handling techniques were in accordance with APHA for Examination of Water &
Wastewater/ IS: 3025 (Part-1)/ IS: 1622. The samples were analyzed as per Indian standard
/APHA latest edition. The surface water quality is compared with CPCB water quality criteria
mentioned in Table 3.8
The water quality in the impact zone was assessed through physico-chemical and
bacteriological analysis of ground samples. The results have been compared with the drinking
water quality standards specified in IS: 10500.
Table 3.8: Water Quality Criteria as per Central Pollution Control Board
Designated-best-use Class Criteria
Drinking water source
without conventional
treatment
but after disinfection
A
Total Coliform Organism MPN/100ml shall be 50 or less
pH between 6.5 and 8.5 Dissolved Oxygen 6mg/l or more
Biochemical Oxygen Demand 5 days 20°C 2mg/l or less
Outdoor bathing
(Organised)
B
Total Coliform Organism MPN/100ml shall be 500 or less
pH between 6.5 and 8.5; Dissolved Oxygen 5mg/l or more
Biochemical Oxygen Demand 5 days 20°C 3mg/l or less
Drinking water source after
conventional treatment and
disinfection
C
Total Coliform Organism MPN/100ml shall be 5000 or less
pH between 6 to 9; Dissolved Oxygen 4mg/l or more
Biochemical Oxygen Demand 5 days 20°C 3mg/l or less
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 62
Propagation of Wild life and
Fisheries
D
pH between 6.5 to 8.5
Dissolved Oxygen 4mg/l or more
Free Ammonia (as N) 1.2 mg/l or less
Irrigation, Industrial
Cooling, Controlled Waste
disposal
E
pH between 6.0 to 8.5
Electrical Conductivity at 25°C micro mhos/cm Max.2250
Sodium absorption Ratio Max. 26
Boron Max. 2mg/l
Below-
E
Not Meeting A, B, C, D & E Criteria
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 63
Table 3.9(a): Ground water quality in study area of GMADA Project (Oct 2013)
"Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS Nagar, Mohali, Punjab Ground water Quality Oct- 2013
S.No Parameter
Limit (as per
IS:10500 :2012) Unit GW1 GW2 GW3
Desirable
Limit Permissible Limit Project
Site Saneta Naugiar
e 1 Colour 5 15 Hazen <5 <5 <5
2 Odour Agreeable Agreeable - Agreeable
Agreeable
Agreeable
3 Taste Agreeable Agreeable - Agreeabl
e Agreea
ble Agreeabl
e 4 Turbidity 1 5 NTU <1 <1 <1 5 pH 6.5-8.5 No Relaxation - 7.41 7.42 7.35
6
Total Hardness (as CaCO3) 200 600 mg/l 281 262 274
7 Iron (as Fe) 0.3 No Relaxation mg/l 0.15 0.14 1.3
8 Chlorides (as Cl) 250 1000 mg/l 91 86 81
9 Fluoride (as F ) 1 1.5 mg/l 0.7 0.6 0.5
10 TDS 500 2000 mg/l 628 570 605
11 Calcium(as Ca2+) 75 200 mg/l 67 63 66
12 Magnesium (as Mg2+) 30 100 mg/l 27 25 26
13 Copper (as Cu) 0.05 1.5 mg/l <0.01 <0.01 <0.01
14 Manganese(as Mn) 0.1 0.3 mg/l 0.07 0.04 0.03
15 Sulphate (as SO4) 200 400 mg/l 87 75 92
16 Nitrate(as NO3) 45 No Relaxation mg/l 13 15 16
17
Phenolic Compounds (as C6H5OH) 0.001 0.002 mg/l <0.001 <0.001 <0.001
18 Mercury (as Hg) 0.001 No Relaxation mg/l <0.001 <0.001 <0.001
19 Cadmium (as Cd) 0.02 No Relaxation mg/l <0.001 <0.001 <0.001
20 Selenium ( as 0.01 No Relaxation mg/l <0.01 <0.01 <0.01
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 64
Table 3.9 (b): Ground water quality in study area of GMADA Project (Nov 2013)
"Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS Nagar, Mohali, Punjab Ground water Quality NOV- 2013
S.No Parameter Limit (as per IS:10500 :2012)
Unit GW1 GW2 GW3
Desirable Limit Permissible
Limit Project
Site Saneta Naugiare 1 Colour 5 15 Hazen <5 <5 <5
2 Odour Agreeable Agreeable - Agreeable
Agreeable Agreeable
3 Taste Agreeable Agreeable - Agreeabl
e Agreeab
le Agreeable 4 Turbidity 1 5 NTU <1 <1 <1
5 pH 6.5-8.5 No
Relaxation - 7.45 7.47 7.61
6 Total Hardness 200 600 mg/l 270 271 278
Se )
21 Arsenic (as As) 0.01 0.05 mg/l <0.01 <0.01 <0.01
22 Cyanide (as CN ) 0.05 No Relaxation mg/l <0.01 <0.01 <0.01
23 Lead (as Pb) 0.01 No Relaxation mg/l <0.01 <0.01 <0.01 24 Zinc (as Zn) 5 15 mg/l 0.08 0.04 0.03
25
Anionic Detergent (as MBAS) 0.2 1 mg/l <0.01 <0.01 <0.01
26 Chromium (as Cr6+) 0.05 No Relaxation mg/l <0.01 <0.01 <0.01
27 Mineral oil 0.5 No Relaxation mg/l <0.1 <0.1 <0.1
28 Alkalinity (as CaCO3) 200 600 mg/l 261 243 250
29 Aluminum (as Al) 0.03 0.2 mg/l <0.02 <0.02 <0.02
30 Boron (as B) 0.5 1 mg/l 0.2 0.1 0.1
Bacteriological Parameter
1 Total Coliform
Shall not be detectable
MPN/100ml ND(<2)
ND(<2) ND(<2)
2 E.coli Shall not be detectable
E.coli /100ml Absent Absent Absent
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 65
(as CaCO3)
7 Iron (as Fe) 0.3
No Relaxation mg/l 0.13 0.09 0.11
8 Chlorides (as Cl) 250 1000 mg/l 85 91 104
9 Fluoride (as F ) 1 1.5 mg/l 0.6 0.5 0.5
10 TDS 500 2000 mg/l 605 580 630
11 Calcium(as Ca2+) 75 200 mg/l 65 65 67
12
Magnesium (as Mg2+) 30 100 mg/l 26 26 27
13 Copper (as Cu) 0.05 1.5 mg/l <0.01 <0.01 <0.01
14 Manganese(as Mn) 0.1 0.3 mg/l 0.06 0.03 0.04
15 Sulphate (as SO4) 200 400 mg/l 84 81 90
16 Nitrate(as NO3) 45
No Relaxation mg/l 12 16 14
17
Phenolic Compounds (as C6H5OH) 0.001 0.002 mg/l <0.001 <0.001 <0.001
18 Mercury (as Hg) 0.001
No Relaxation mg/l <0.001 <0.001 <0.001
19 Cadmium (as Cd) 0.02
No Relaxation mg/l <0.001 <0.001 <0.001
20 Selenium ( as Se ) 0.01
No Relaxation mg/l <0.01 <0.01 <0.01
21 Arsenic (as As) 0.01 0.05 mg/l <0.01 <0.01 <0.01
22 Cyanide (as CN ) 0.05
No Relaxation mg/l <0.01 <0.01 <0.01
23 Lead (as Pb) 0.01
No Relaxation mg/l <0.01 <0.01 <0.01
24 Zinc (as Zn) 5 15 mg/l 0.07 0.04 0.05
25
Anionic Detergent (as MBAS) 0.2 1 mg/l <0.01 <0.01 <0.01
26 Chromium (as Cr6+) 0.05
No Relaxation mg/l <0.01 <0.01 <0.01
27 Mineral 0.5 No mg/l <0.1 <0.1 <0.1
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 66
oil Relaxation
28
Alkalinity (as CaCO3) 200 600 mg/l 250 237 241
29 Aluminum (as Al) 0.03 0.2 mg/l <0.02 <0.02 <0.02
30 Boron (as B) 0.5 1 mg/l 0.2 0.1 0.2
Bacteriological Parameter
1 Total Coliform
Shall not be detectable
MPN/100ml ND(<2) ND(<2) ND(<2)
2 E.coli Shall not be detectable
E.coli /100ml Absent Absent Absent
Table 3.9(c): Ground water quality in study area in study area of GMADA Project (Dec 2013)
"Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS Nagar, Mohali, Punjab Ground water Quality Dec- 2013
S.No Parameter Limit (as per IS:10500 :2012)
Unit GW1 GW2 GW3
Desirable Limit Permissible
Limit Project
Site Saneta Naugiare 1 Colour 5 15 Hazen <5 <5 <5
2 Odour Agreeable Agreeable - Agreeable
Agreeable Agreeable
3 Taste Agreeable Agreeable - Agreeabl
e Agreeab
le Agreeable 4 Turbidity 1 5 NTU <1 <1 <1
5 pH 6.5-8.5 No
Relaxation - 7.52 7.44 7.38
6
Total Hardness (as CaCO3) 200 600 mg/l 261 255 269
7 Iron (as Fe) 0.3 No
Relaxation mg/l 0.11 0.15 0.16
8 Chlorides (as Cl) 250 1000 mg/l 79 114 120
9 Fluoride (as F ) 1 1.5 mg/l 0.5 0.6 0.5
10 TDS 500 2000 mg/l 567 662 696
11 Calcium(as Ca2+) 75 200 mg/l 62 61 65
12 Magnesium 30 100 mg/l 25 25 26
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 67
(as Mg2+)
13 Copper (as Cu) 0.05 1.5 mg/l <0.01 <0.01 <0.01
14 Manganese(as Mn) 0.1 0.3 mg/l 0.04 0.03 0.04
15 Sulphate (as SO4) 200 400 mg/l 78 94 102
16 Nitrate(as NO3) 45
No Relaxation mg/l 10 14 16
17
Phenolic Compounds (as C6H5OH) 0.001 0.002 mg/l <0.001 <0.001 <0.001
18 Mercury (as Hg) 0.001
No Relaxation mg/l <0.001 <0.001 <0.001
19 Cadmium (as Cd) 0.02
No Relaxation mg/l <0.001 <0.001 <0.001
20 Selenium ( as Se ) 0.01
No Relaxation mg/l <0.01 <0.01 <0.01
21 Arsenic (as As) 0.01 0.05 mg/l <0.01 <0.01 <0.01
22 Cyanide (as CN ) 0.05
No Relaxation mg/l <0.01 <0.01 <0.01
23 Lead (as Pb) 0.01 No
Relaxation mg/l <0.01 <0.01 <0.01 24 Zinc (as Zn) 5 15 mg/l 0.05 0.04 0.03
25
Anionic Detergent (as MBAS) 0.2 1 mg/l <0.01 <0.01 <0.01
26 Chromium (as Cr6+) 0.05
No Relaxation mg/l <0.01 <0.01 <0.01
27 Mineral oil 0.5 No
Relaxation mg/l <0.1 <0.1 <0.1
28 Alkalinity (as CaCO3) 200 600 mg/l 239 245 250
29 Aluminum (as Al) 0.03 0.2 mg/l <0.02 <0.02 <0.02
30 Boron (as B) 0.5 1 mg/l 0.2 0.2 0.1
Bacteriological Parameter
1 Total Coliform
Shall not be detectable
MPN/100ml ND(<2) ND(<2) ND(<2)
2 E.coli Shall not be detectable
E.coli /100ml Absent Absent Absent
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 68
Table 3.9(d): Ground water quality in study area in study area of WTC Project (12th May to 12th JUN.2016)
World Trade Centre Mohali Punjab Ground water Quality 12th May to 8th JUN.2016
S.No Parameter
Limit (as per IS:10500
:2012) Unit GW1 GW2 GW3
Desirable
Limit Permissible
Limit Project
Site Saneta Nagari 1 Colour 5 15 Hazen <5 <5 <5
2 Odour Agreeable Agreeable - Agreeable Agreeable Agreeable
3 Taste Agreeable Agreeable - Agreeabl
e Agreeable Agreeable 4 Turbidity 1 5 NTU <1 <1 <1
5 pH 6.5-8.5 No
Relaxation - 7.65 7.82 7.49
6 Total Hardness (as CaCO3) 200 600 mg/l 320 290 274
7 Iron (as Fe) 0.3 No
Relaxation mg/l 0.1 0.11 0.15 8 Chlorides (as Cl) 250 1000 mg/l 72 60 55 9 Fluoride (as F ) 1 1.5 mg/l 0.6 0.5 0.4
10 TDS 500 2000 mg/l 630 600 570 11 Calcium(as Ca2+) 75 200 mg/l 76 69 66
12 Magnesium (as Mg2+) 30 100 mg/l 31 28 26
13 Copper (as Cu) 0.05 1.5 mg/l <0.01 <0.01 <0.01 14 Manganese(as Mn) 0.1 0.3 mg/l 0.04 0.03 0.04 15 Sulphate (as SO4) 200 400 mg/l 75 92 88
16 Nitrate(as NO3) 45 No
Relaxation mg/l 22 20 18
17
Phenolic Compounds (as C6H5OH) 0.001 0.002 mg/l <0.001 <0.001 <0.001
18 Mercury (as Hg) 0.001 No
Relaxation mg/l <0.001 <0.001 <0.001
19 Cadmium (as Cd) 0.02 No
Relaxation mg/l <0.001 <0.001 <0.001
20 Selenium ( as Se ) 0.01 No
Relaxation mg/l <0.01 <0.01 <0.01 21 Arsenic (as As) 0.01 0.05 mg/l <0.01 <0.01 <0.01
22 Cyanide (as CN ) 0.05 No
Relaxation mg/l <0.01 <0.01 <0.01
23 Lead (as Pb) 0.01 No
Relaxation mg/l <0.01 <0.01 <0.01 24 Zinc (as Zn) 5 15 mg/l 0.05 0.04 0.03 25 Anionic Detergent 0.2 1 mg/l <0.01 <0.01 <0.01
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 69
(as MBAS)
26 Chromium (as Cr6+) 0.05
No Relaxation mg/l <0.01 <0.01 <0.01
27 Mineral oil 0.5 No
Relaxation mg/l <0.1 <0.1 <0.1
28 Alkalinity (as CaCO3) 200 600 mg/l 310 280 265
29 Aluminum (as Al) 0.03 0.2 mg/l <0.02 <0.02 <0.02 30 Boron (as B) 0.5 1 mg/l 0.2 0.2 0.1
Bacteriological Parameter
1 Total Coliform Shall not be detectable
MPN/100ml ND(<2) ND(<2) ND(<2)
2 E.coli Shall not be detectable
E.coli /100ml Absent Absent Absent
3.4.4.3 Results and Conclusion
The result of Ground water quality monitoring of Oct-Dec 2013 is summarized in Table 3.9
(a-c). Ground water quality monitoring has also been done from 12th May to 12th June 2016
at Project site (World Trade Centre) and two more location i.e., Saneta and Nagari.
Core zone is taken as project site. From the above table it is clear that water at project site is
neutral (pH- 7.49-7.82). Other parameters T.D.S (570-630 mg/l), Chloride (55-72 mg/l) and
Magnesium (26-31 mg/l) are within the permissible limits as per drinking water standards
(IS-10500:2012). Water can be used for domestic purposes after treatment with RO and using
disinfectant
Comparing the values of pH, DO, BOD and total coliforms with ‘Use based classification of
surface waters’ published by Central Pollution Control Board; it can be seen that the
analyzed surface waters can be compared with class ‘E’ and can be used only for irrigation,
industrial cooling, controlled waste disposal. Bacteriological examination of surface water
indicates the presence of total coli forms, which may be due to human activities observed
during the study period.
3.4.5 LAND ENVIRONMENT
The land use pattern of the area is mainly settlements, agricultural land, open land, open
scrub and water bodies.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 70
The land use data of project site within 10 km is presented below.
Table 3.15: Land use pattern of project within 10 km
LAND USE CLASS AREA (Ha) Area
In Percentage %
Settlement 9651.13 30.003
Water bodies 39.02 0.121
Forest 477.06 1.483
River 335.79 1.043
River with Dry Channel 150.55 0.468
Vegetation 453.36 1.409
Open land 2005.52 6.234
Open scrub 268.83 0.835
Agricultural land 18785.82 58.400
TOTAL 32167.08 100
Figure 3.11: Land Use Pattern of the Project Site within 10 km
3.4.5.1 Topography
Slope form: Contour plan shown that land is flat land with highest contour level as
99.63 m and lowest contour level as 98.61 m. Project will not cause any change in natural
slope.
Settlement
Water bodies
Forest
River
River with Dry Channel
Vegetation
Open land
Open scrub
Agricultural land
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 71
Landform and Terrain analysis: According to the study of 10 km radius around the
project in topographical map of scale 1:50000, it was found that measure land use are
agricultural land i.e. 58.40 %. Complete details are given in figure 3.11 above.
3.4.5.2 Soil
3.4.5.2.1 Type & characteristics: To assess the soil quality of the area, following
stations were selected. Soil profile and quality was studied at 5 different locations. Location
of Soil sampling stations is described below in Table 3.10 a and b. The locations of the
monitoring sites are depicted in composite map is enclosed as Annexure 5 (d) and the result
of the monitoring and analysis of soil is presented in the Annexure 6.
Table 3.10 (a): Location of Soil Quality Monitoring Stations (Knowledge Park,
GMADA)
Station
No.
Location Direction Distance
SQ1 Project Site - -
SQ2 Saneta W 6.4
SQ3 Nagari WSW 7.37
SQ4 Shekhan SW 5.59
SQ5 Naraingarh SE 3.18
Table 3.10(b): Location of Soil Quality Monitoring Stations (World Trade Centre)
Locations code Locations Direction Distance (Km)
SQ1 Project Site - -
SQ2 Saneta W 8.6
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 72
SQ3 Nagari WSW 9.1
SQ4 Shekhan SW 6.6
SQ5 Naraingarh SE 3.2
3.4.5.2.2 Sampling procedure & Analysis
The soil samples were collected once during the study period from each location. The
sampling was done using Augur Sampler and samples were filled in polythene bags, labeled
in the field with number and site name and sent to laboratory for analysis. Sampling &
analysis of soil was done as per ISO/ IS:2720/ Soil Chemical Analysis by M.L. Jackson.
Table 3.11: Frequency and Methodology for Soil Sampling & Monitoring
Particulars Details
Frequency One *grab sample from each station– once during the Study Period
Methodology Composite grab samples of the topsoil were collected from 3 depths,
and mixed to provide a representative sample for analysis. They were
stored in airtight Polythene Bags and analyzed at the laboratory *Grab sample- a single sample or measurement taken at a specific time or over as a short period as feasible.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 73
Table 3.12 (a): Soil Quality Data (Nov 2013)
Knowledge Park, IT Park, SAS Nagar, Mohali, Punjab
Soil Quality Data Nov.2013
S.
No
Parameter Unit SQ-1 SQ-2 SQ-3 SQ-4 SQ-5
Project
Site
(GMADA)
Saneta
Naug
iari Shekhan
Narai
ngrh
1
Texture -
Sandy
Clay Loam
Sandy
Clay Loam Loam
Sandy
Clay Loam
Clay
Loam
Sand % 56.8 58.3 49.6 55.3 45.8
Silt % 23.1 21.4 27.2 23.0 25.9
Clay % 20.1 20.3 23.2 21.7 28.3
2 pH (1:2) - 7.85 7.78 7.89 8.12 7.92
3
Electrical
Conductivity
(1:2)
µmhos/
cm 456 326 483 502 368
4
Cation exchange
capacity
meq/10
0 gm 16.5 14.8 18.1 15.7 18.1
5
Exchangeable
Potassium mg/kg 59 45 67 55 85
6
Exchangeable
Sodium mg/kg 103 92 125 78 107
7
Exchangeable
Calcium mg/kg 2365 2217 2635 2364 2872
8
Exchangeable
Magnesium mg/kg 491 386 503 412 362
9
Sodium
Absorption Ratio - 0.50 0.47 0.58 0.39 0.50
10
Water Holding
Capacity % 26.2 25.3 28.7 25.9 30.2
11 Porosity % 37.2 38.2 33.5 35.2 32.6
12 Phosphorus (as P) mg/kg 8.9 6.3 8.9 12.7 15.2
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 74
13 Avl.Nitrogen mg/kg 92 71.5 81.3 63 92
14 Total Nitrogen % 0.041 0.038 0.041 0.035 0.048
15 Organic Carbon % 0.45 0.33 0.35 0.32 0.39
16 Sulphur % 0.021 0.025 0.027 0.021 0.032
Table 3.12 (b): Soil Quality Data (12th MAY to 12th JUN., 2016)
World Trade Centre, Mohali, Punjab
Soil Quality Data 12th MAY to 12th JUN. 2016
S.
No
Parameter Unit SQ-1 SQ-2 SQ-
3
SQ-4 SQ-5
Project
Site
(WTC)
Saneta
Nag
ari Shekhan
Narain
garh
1
Texture -
Sandy
Clay Loam
Sandy
Clay Loam
Loa
m
Sandy
Clay Loam
Clay
Loam
Sand % 52.8 58.3 49.6 55.3 45.8
Silt % 23.1 21.4 27.2 23.0 25.9
Clay % 22.3 20.3 23.2 21.7 28.3
2 pH (1:2) - 7.85 7.78 7.89 8.12 7.92
3
Electrical
Conductivity
(1:2)
µmhos/
cm 456 326 483 502 368
4
Cation exchange
capacity
meq/10
0 gm 16.5 14.8 18.1 15.7 18.1
5
Exchangeable
Potassium mg/kg 59 45 67 55 85
6
Exchangeable
Sodium mg/kg 103 92 125 78 107
7
Exchangeable
Calcium mg/kg 2365 2217
263
5 2364 2872
8 Exchangeable mg/kg 491 386 503 412 362
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 75
Magnesium
9
Sodium
Absorption Ratio - 0.50 0.47 0.58 0.39 0.50
10
Water Holding
Capacity % 26.2 25.3 28.7 25.9 30.2
11 Porosity % 37.2 38.2 33.5 35.2 32.6
12 Phosphorus (as P) mg/kg 8.9 6.3 8.9 12.7 15.2
13 Avl.Nitrogen mg/kg 92 71.5 81.3 63 92
14 Total Nitrogen % 0.041 0.038
0.04
1 0.035 0.048
15 Organic Carbon % 0.45 0.33 0.35 0.32 0.39
16 Sulphur % 0.021 0.025
0.02
7 0.022 0.032
3.4.5.2.3 Result:
Results are summarized in Table 3.12(a and b); the result shows that texture of the
core(project site) is sandy clay loam. The results of buffer zone show that texture is sandy
clay loam to loam. pH ranges from 7.78-8.12.
3.4.6 BIOLOGICAL ENVIRONMENT
Ecological assessment of the study area of around the project site was conducted in the post
monsoon season. A participatory and consultative approach was followed for the Ecological
Assessment. A field visit was undertaken for the ecological assessment and survey of the
vegetation in the study area.
For the purpose of floristic surveying the vegetation, quadrates were laid to record
phytosociological features of the vegetation. Detailed notes on ecological features, including
the habitat types were also taken along the selected locations. The fauna in the study area
were also assessed through phyto-sociological survey. Identification process of biodiversity
aspects of flora and fauna are done for estimating flora and fauna species diversity.
Besides measuring these parameters, other biodiversity aspects in the form of endemic status,
conservation status and life form have been enumerated. For all the plant species found in the
area during ecological survey, Red Data Books of the Botanical survey of India have been
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 76
screened to verify their conservation status. For wild animal species schedule 1 of the
Wildlife Protection Act (1972) has been screened.
Terrestrial Ecology
The study of terrestrial ecology within the study area has been carried out through field
investigation.
Plants / animals and environment are inter-related to each other. With the change in
environmental conditions the vegetation cover as well as animals reflects several changes in
its structure, density and composition.
The main species of plants found in the study area are Dalbergia sissoo, Morus alba,
Prosopis spicigera, Acacia nilotica, Parkinsonia aculeate, Acacia gamesiana, Butea
monospema, Zizyphus mauritiana, Albizia lebbek, Melia benghlensis, Tamarix articulate,
Melia azedarach and Azadirachta indica. Among the grasses, Desmotachya bipinnata and
Saccharum spontaneum are abundant. Other species found are shown in Table 3.13
Table 3.13: Floral Compositionof the Study Area
S. No. Common Name of the plant Botanical Name
1 Neem Azadrichta indica
2 Seasame Dalbergia sisoo
3 Amaltas Cassia fistula
4 Kikkar Acacia
5 Jamun Syzygium cumini
6 Mango Mangifera indica
7 Bargad Ficus benghalensis
8 Pipal Ficus religiosa
9 Asoka Saraca asoka
10 Gulmohar Delonix regia
11 Bahida Terminalia bellerica
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 77
12 Papdi Holoptelia
antidysenterica
13 Arjun Terminalia arjuna
14 Baon Melia azedirach
15 Simbal Bombax cieba
16 Siriss Albizia procera
17 Saptaparni Alestonia scholaris
18 Amla Phyllantus indica
The study area is a mix of agricultural and urban population. As a result of increasing
emphasis on intensive cultivation of available land and bringing more and more area under
the urbanization, there is very little possibility of wild animals in the study area. The various
species of fauna present in the study area are detailed in Table 3.14.
Table 3.14: List of Fauna in the Study area
S. No. Common Name Zoological Name
1 Deer (Hog Deer) Cervidae
2 Rhesus Monkey Macaca mulatto
3 Hyena Hyaena hyaena
Avian
1 Sparrow House Passer domesticus
2 Pied kingfisher Ceryle rudis
3 Common Myna Acridotheres tristis
4 Bank Myna Acridotheres ginginianus
5 Pied bush chat Saxicola caprata
6 Babblers Turdoides caudatus
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 78
7 Crows – Common Corvus splendens
8 Crows – Jungle Corvus macrorhynchos
9 Indian cuckoo Cyculus micropterus
10 Tree pye Dendrocotta vagabunda
11 Pariah kite Milvus migrans
12 Cattle egret Bubulcus ibis
13 Little egret Egretta garzetta
14 Medium egret Mesophoyx intermedia
15 Peacocks Pavo crostatus
Migratory Birds
1 Shovellar Anas clypeata
2 Coot Pulica atra Linnaeus
3 Grayleq goose Anser anser
4 Bar headed goose Anser indicus
5 Gargney teal Ana queraquedula
6 Common pochard Aythya ferina
7 White eye pochard Aythya nyroca
8 Little cormorant Phala niger
9 Large cormorant Phalacrocorax carbo
10 Black ibis Pseudibis papillosa
11 White ibis Threskiornis
melanocepalus
12 Spot billed duct Anas poecilorhyncha
Aquatic Ecology
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 79
There is no aquatic organism found in the study area.
Planktons
There is no aquatic organism found in the study area.
Rare and Endangered Species
During the study no endangered species of flora and fauna were found with respect to Red
Book of Botanical Survey of India and Wildlife (Protection) Act 1972.
3.4.7. SOCIO ECONOMIC IMPACT ASSESSMENT
3.4.7.1 Introduction
Socio-Economic Impact Assessment (SEIA) refers to the systematic analysis of various
social and economic characteristics of the human beings living in a given geographical area
during the period of study. The geographical area is called Study Area or Impact Area. SEIA
is carried out separately but concurrently with Environment Impact Assessment (EIA). The
study area consists of core and buffer area encircling the project area. The Socio-Economic
Impact Assessment focuses on the likely effect of the project on social and economic well-
being of the community. The impact may be direct or indirect, positive or negative.
OBJECTIVES OF SEIA:
The prime objective of the current study is to assess the likely impact of the proposed project
on socio-economic characteristics of people living in the study area. Further, it is to be
established whether the impact would be direct or indirect. Furthermore, it is to be examined
whether the said impact would be positive or negative. Lastly, it is to be comprehended if the
impact is positive how long it would sustain or if it is negative how soon the same could be
eased.
SCOPE:
The Scope of the study is as follows:
a) To collect baseline data of the study area
b) To comprehend socio-economic status of the people living in the study area.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 80
c) To assess the probable impact of the project on social and economic aspects in the study
area.
d) To evaluate the likely impact of the project on Quality of Life of the people living in the
study area.
e) To ensure sustainability of the positive impact.
f) To suggest mitigation measures and agency responsible for taking action in case of
adverse impact.
METHODOLOGY:
For Socio-Economic Impact Assessment of the proposed project, we carry out systematic
analysis of the various socio-economic characteristics, both in terms of quality and quantity.
Accordingly, both qualitative and quantitative data was collected from secondary sources.
The secondary data was collected from the published data/information of the Census
Authority. Records of the state and district administration were also referred to.
For collection of primary data, a sample survey was conducted in the study area. In each
selected habitation (village/town), a specified number of representative households were
selected scientifically for collection of information through face to face interview with head
of the household or any responsible member of the family.
Census-cum Sample Survey in the Core Area
As the likely impact of the project will be greatest in the core area and it diminishes
progressively when move away from the core area to the periphery of the study area, a
Census-cum-Sample Survey was conducted in the core area for the collection of socio-
economic data.
It is treated as a Census Survey because all the villages/towns located in the core area
were surveyed for the collection of information. Further, in each village/town a
household survey was conducted by drawing representative samples from a list of
households prepared. Since, collection of information from all the households in a
village/town is time consuming and expensive, the Sample Survey approach was adopted
for collection of information from the selected households in the villages/towns.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 81
Sample Survey in the Buffer Area
In the buffer area, where the impact of the project progressively reduces with the distance
from the project area, Sample Survey was conducted for the collection of data.
Sample Design
Two-Stage Sampling Design was adopted in the study area. The First Stage Units were
Census villages/towns and the Ultimate Stage Units were households in the selected
villages/towns.
Selection of First Stage Units (Villages/Towns)
In buffer area the sample villages/towns were selected from the list of Census villages/towns
by adopting the method of Probability Proportional to Size (PPS), the size being number of
households in a given village/town.
Selection of Ultimate Stage Units (Households)
The sample households were selected from the list of households by adopting the method of
Circular Systematic Sampling. This method was adopted since the sampling frame i.e. the
complete list of households was readily available.
SURVEY INSTRUMENTS:
The following Schedules/Questionnaires were developed for collection of Primary data:
Questionnaire-1A: Village Particulars
Questionnaire-1B: Town Particulars
Questionnaire-2: Household Particulars.
Each Questionnaire is divided into several blocks and there are both open-ended and closed-
ended questions.
CHRONOLOGY OF VARIOUS STEPS TO PREPARE THE SEIA REPORT IS AS
UNDER:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 82
The occupational structure of the study area is presented in Figure-3.12. The male and female
populations of other workers in study area are 66.4% and 55.5%, respectively.
Fig. 3.12: Occupational structure of the study area based on 2001 census data
Table 3.15: Demographic Profile and Socio-economic status of study area based on 2001
Census data
Literature Review
Referring to Terms of Reference (ToR)
Identification of the Study Area and
Important Landmarks
Preparation of List of Habitations located in
the study Area
Grouping of Habitations falling under Core and
Buffer Zones
Site Visit to collect the facts through observations
Firming up of Approach & Methodology
Finalization of Questionnaire
/Schedules Collection of Secondary
Data
Collection of Primary Data from Sample
Habitations & Households
Manual scrutiny of Field-in-Schedules
Data Entry & Data Validation Generation of Tables
Data Analysis
Preparation of Report
Occupational structure of Study Area
33%
5%
62%
'Total Main Worker'
'Total Marginal Worker'
'Total Non Worker'
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 83
S. No. Description
Status in 2001
1 Population 1247322
2 Percentage of male 56
3 Percentage of Female 44
4 Percentage of SC 16.4
5 Percentage of ST 0.0 %
6 Literate 73.2%
8 Main worker 33.1%
9 Non worker 62%
10 Marginal worker 4.9%
Marginal Workers
The marginal workers are those workers who are engaged in some work for a period less than
six months during the reference year prior to the census survey. The total number of marginal
workers in the study area is 10367, the male and female marginal workers in the villages are
3571 and 6796 respectively.
Non-Workers
The non-workers include those engaged in unpaid household duties, students, retired persons,
dependents, beggars etc. The total number of non-workers population is 62 % of the total
population.
CORPORATE SOCIAL RESPONSIBILITY (CSR)
As per section 135 of the Companies Act, 2013 Corporate Social Responsibility (CSR) is
mandatory part of any development project.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 84
As per the guidelines issued on dated 27th Feb, 2014 (Schedule-VII) by the Ministry of
Corporate Affairs, Government of India the suggested ten major CSR activities by giving
importance to the corporate philosophy with the objective to improve the quality of life and
socio-economic scenario with special attention to the people residing in the study area are
given below:
I. Hunger, Poverty and Malnutrition, Promoting Preventive Health Care and Sanitation
and making available Safe Drinking Water
II. Promoting Education, including Special Education and Employment Enhancing
Vocation Skills Especially among Children, Women, Elderly, and the Differently-
Able and Livelihood Enhancement Projects
III. Promoting Gender Equality, Empowering Women, setting up Homes and Hostels for
Women and Orphans, setting up Old Age Homes, Day Care Centers and such other
Facilities for Senior Citizens and measures for Reducing Inequalities faced by
Socially and Economically Backward Groups
IV. Ensuring Environmental Sustainability, Ecological Balance, Protection of Flora and
Fauna, Animal Welfare, Agro-forestry, Conservation of Natural Resources and
Maintaining Quality of Soil, Air and Water
V. Protection of National Heritage, Art and Culture Including Restoration of Buildings
and sites of Historical Importance and Works of Art, setting up Public Libraries,
Promotion and development of Traditional Arts and Handicrafts
VI. Measures for the benefit of Armed Forces Veterans, War Widows and their
Dependents
VII. Training to Promote Rural Sports, Nationally Recognized Sports, Paralympics sports
and Olympic sports
VIII. Contribution to the Prime Minister's National Relief Fund or any other fund set up by
the Central Government for socio-economic development and relief and welfare of
the Scheduled Castes, the Scheduled Tribes, other backward classes, minorities and
women
IX. Contributions or funds provided to technology incubators located within academic
institutions which are approved by the Central Government
X. Rural Development Projects.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 85
Based on the above suggested activities by the Government of India, the project proponent
may set out to do the following CSR activities by giving importance to their corporate
philosophy in order to achieve the objective to improve the quality of life and socio-economic
scenario with special attention to the people residing in the study area:
1. For Improvement of Health Status-
Health Checkups and Medical Camps in the project village and other part of the
study area
Providing free medicines and medical equipments to the Primary Health Centers
falling under the study area
2. For Promoting Education-
Spreading the light of Education by providing sponsorship or financial assistance
to underprivileged children and meritorious students
Providing uniforms and books to the school children
3. For Promoting Agriculture & Agro-based Activities-
Promotion of Agro-based activities by providing financial backing to the farmers
of the study area for purchasing seeds, fertilizers and pesticides
4. Promoting Self-Employment by providing Vocational Training for Skill
Development and Women Empowerment-
Providing vocational training to the students and unemployed youths for up-
gradation of technical & employment skills
Providing training to the women for self-help to be self-dependent and to improve
their skill and economic condition.
5. For Promoting Sports, Art & Culture-
Providing financial assistance for distributing sports goods and musical
instruments to the local clubs located in the study area
Organizing sports events and tournaments and providing financial assistance to
the eligible candidates for coaching and proper training.
A certain part of budgetary amount (2% of the project cost) i.e., approximately INR 2.62
Crore have been paid to “The Punjab State Cancer & Drug Addiction Treatment
Infrastructure Fund” as CSR activities.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 86
CONCLUSION
The Socio-Economic standard of people living in the study area will improve due to
employment opportunities created due to the project. This will lead to better quality of life
and will also set a standard for future development in the study area.
Due to the project the infrastructure of the study area surroundings will improve by setting up
of schools, hospitals, bus shelters and by the development of roads, parks, play grounds etc.
This will give a boost in the quality of life of people of the study area.
In the study area, however there is good scope of improving health and education facilities. It
is expected that same will improve with opening of the project, associated business activities
and the CSR activities promoted by the project proponent.
The overall impact of the project is expected to be positive for the habitants of the area and
the persons associated with the project.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 87
CHAPTER 4
ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION
MEASURES
4.1 INTRODUCTION
This chapter discusses identification and appraisal of various environmental impacts due to the
Commercial Project. Generally, the environmental impacts can be categorized as either primary or
secondary. The development, construction and functional/operational phase of the project comprise
various activities, each of which may have some impact on environmental parameter. Various
impacts during the development, construction and operation phase on the environmental parameters
have been studied to estimate the impact on environment.
In development phase, basic infrastructure facilities like internal road, sewerage system, storm
water drainage, street lighting, etc. will be developed.
For proper evaluation and assessment of the environmental impacts due to development,
construction and functional phase of project understanding to the various activities associated with
the Project is essential. Various activities related to the project would be different, in terms of
nature during the development, construction and functional phase.
The impact identification and prediction process aims to:
Identify potential source or cause of impact throughout the life of project.
Characterize the potential impacts affecting a target or receptor (physical, human and socio-
economic).
Assess the potential of changing likelihood of impact through Environmental Management
Plan (EMP)
Prediction of the impacts due to the development, construction and functional activities
encompass the developmental processes to be undertaken during construction and
functional phases.
For each component of environment (such as ambient air quality, water quality, soils, land, etc,) the
potential impacts of activities during development & construction and functional phases have been
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 88
identified. Pollution sources & its characteristics, the potential impacts and magnitude of the
impacts have been assessed and discussed in detail in following sub sections. In each case,
cognizance has been taken to mitigation measures inherited in the development & construction and
functional phase.
Impact on various environmental parameters can be broadly categorized into two phases, namely:
Construction phase: Impact during this phase may be regarded as temporary or short term;
and
Operation phase: Impact during this phase shall have long-term effects.
Various impacts during these two phases have been envisaged and are discussed in the subsequent
sections.
4.2 IMPACT MATRIX
Various activities from the project are likely to have some impact on the environmental constituents
during its construction as well as operational phase. The impact assessment matrix given in Table
4.1 reveals the impact associated with each activity of the project on various environmental
parameters during construction and function phase respectively before any mitigation measures are
implanted. To assess the severity of the impacts, they are categorized as follows:
Table 4.1: Environmental and Social Assessment Checklist
Features likely to
be affected
Positive
significant
Impact
Insignificant
Impact
Negative
significant
Impact
Impact Mitigation
measures
required or
not
Forestry/
Vegetation
-
Birds -
Fisheries -
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 89
Other
wildlife/animals
-
Air quality Long term
Noise
environment
Immediate
Water quality Short term
Water availability -
Soil quality Long term
Land use and
topography
Long term
Drainage patterns Long term
Sedimentation/erosion Short term
Food production -
Climate -
Groundwater table -
Industrialization -
Housing (involuntary
resettlement)
-
Employment/training -
Income and livelihood -
Other socio-economic
activities
-
Health and safety -
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 90
Communications -
Scenic views and
vistas
-
Tourism -
Table 4.2: Project activity wise impact
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 91
S.No.
Project Activity
Final Impact on Environmental Aspect Impact &
Mitigation* Air Noise Soil and Water Land SE
A) CONSTRUCTIONAL PHASE : 1). Camps
work force arrangement
- - About 25.4 KLD of water will be required for drinking purposes. About 10 KLD of domestic wastewater will be generated.
- About 150-200 labourers will get employment.
a) Workers will be working in 8 hr. shifts at the site and will stay in labour camp.
b) Local workers
will be
employed, as
far as possible. c) The wastewater
will be disposed into soak-pits and septic tank provided at labour camp.
2). Excavation work and filling of foundations
Dust and air emission particularly due to the
Construction noise mainly due to excavation, practice of
Contamination of soil due to leakage of oil from vehicles. Accumulation of water in excavations.
- - a) Provision of spraying water to reduce dust emission on roads and particularly
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 92
leveling, construction and movement of vehicles resulting in air pollution.
vehicles, operations of cranes etc.
near existing settlements.
b) Excavated earth (soil) will be generated due to footing; leveling etc. generated earth will be used in landscaping development.
c) The amount of exposed ground and stockpiles will be minimized so that re-suspension due to wind and subsequent dust fall is prevented.
d) Arrangement of the soil will be such that existing drainage pattern, though
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 93
altered, will still ensure that runoff does not carry away topsoil but reaches the water bodies with which it is linked.
e) Ensuring all vehicles and generators are well maintained and regularly serviced.
f) The contamination of soil will be avoided by suitable management of oil and fuel.
g) Care will be taken to compact the soil after refilling so that, soil erosion and
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 94
consequent soil import is avoided
h) Wherever possible care will be taken to prevent water from entering excavations. Cut-off ditches will prevent entry of surface water and well point dewatering or cut-off walls for groundwater. The corner of the excavation will be used as a pump sump.
i) The vehicles used will be with the standard limiting noise output.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 95
j) The use of ear mufflers will be encouraged in case of noisy operations.
k) Regularly Lubrication & Maintenance of the equipment will be carried out.
l) Certain type of Equipment which are a source of high noise pollution will be restricted
m) Ensuring equipment will have quality mufflers installed
n) To engage On site technician to ensure Noise Compliance Monitoring To
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 96
follow specifying stringent noise emission limits.
o) Wherever this cannot be achieved then the area will be earmarked as high noise level area requiring use of ear protection gadget
3 Plain Concreting, RCC Civil foundations and Erection Activities
Dust and other exhaust atmospheric emissions generated by vehicle movement, concrete mixing machinery, concrete conveyers, bucket
Noise mainly due to blowers, vibrators breaking, cutting, plying of vehicles, welding machines, operations of cranes etc.
Soil and Groundwater contamination Spillage of concrete mixture containing additives and plasticizers. Spillage of construction material containing heavy metals, paints, coatings, liners, etc.
Storage and Handling of Concrete
- a) The construction workers will be provided with appropriate protective equipments wherever high particulate emission is expected.
b) It is also recommended that the workers
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 97
conveyers, air bowers, pneumatic vibrators, mechanical vibrators and water tankers
will not be allowed to work over a long exposure period.
c) All fuel, oil and chemical storage will be placed on an impervious base within a bund and secured place. The base and bund walls will be impermeable to the material stored and of an adequate capacity.
d) Storage at or above roof level will be avoided.
e) Leaking or empty oil drums will be removed from
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 98
the site immediately and disposed of via a licensed waste disposal contractor.
f) Special care will be taken during deliveries of construction materials, especially when fuels and hazardous materials are being handled.
g) It will be ensured that all deliveries are supervised by a responsible person, that storage tank levels are checked before delivery to prevent
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 99
overfilling and that the product is delivered to the correct tank.
h) Ensure that workers know what to do in the event of a spillage.
i) Liquid wastes will be stored securely on the site while they await disposal or recovery and cannot escape into drains, watercourses or surrounding ground and that any accidental spills can be properly and effectively contained.
j) Spill control procedures will be used in case
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 100
of spillage of materials. The spilled construction material will be immediately removed and disposed off at secured landfill site.
4. Heavy fabrication works
Particulate emission due to machinery and instrument operation for cleaning, welding and cutting of different steel sections. Fumes and gases near the work area due to welding activities.
Noise mainly due to blowers, vibrators, breaking, cutting, plying of vehicles, welding machines, operations of
cranes etc.
Soil and groundwater contamination Spillage of heavy fabrication waste material containing heavy metals, coating material, and paints.
- - a. Training in welding or use of competent staff.
b. Minimize welding wastes.
c. PPE’s will be used during welding.
d. Ensure that workers know what to do in the event of a spillage.
e. Spill control procedures will be used in case of spillage of
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 101
materials. The spilled construction material will be immediately removed and disposed off at secured landfill site.
5 Laying of underground and aboveground pipelines
Emission due to excavation, cutting, heating, welding and vehicle movement. Generation of fumes and
exhaust gases
Construction noise mainly due to blowers, breaking, cutting, plying of vehicles, welding machines, operations of cranes
etc.
Soil and groundwater contamination due to Spillage of coat & wrap materials, scales, cuttings and scrap materials and construction material during handling and transportation and erection. Generation of wastewater during hydraulic testing such as flushing sludge
- - f. Water sprinkling will be resorted to in case of dust emissions.
g. Care will be taken to compact the soil after laying the underground pipes so that, soil erosion and consequent soil import is avoided.
h. Hazardous wastes will be sent to the
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 102
and waste pigs secured landfill facility nearby.
i. Ensure that water consumption is optimized and explore reuse /recycling options
j. Take care in disposal of wastewater generated such that soil and
k. groundwater resources are protected. Any solid waste generated will be disposed such that damage to soil and groundwater is avoided.
l. Flushing sludge and waste pigs, ifgenerated,
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 103
will be sent to the nearest secured landfill.
m. Inspection and monitoring of thepipeline programme will include leak detection.
6 Surface Treatment, Coating and Painting
Air emission mainly solvent fumes and aerosols due to surface treatment, coating and painting activities.
. Noise due to
Spraying machinery
Soil and groundwater contamination Spillage of coating material, painting waste containing heavy metals and hazardous substances. Spillage of coat and wrap materials, scales, cuttings and scrap materials Generation of waste empty drums of solvents, paints
- - a) Care will be taken to avoid direct contact and spillage of these materials with ground during these operations. It is recommended to cover ground with protecting sheets to avoid damage to soil and groundwater.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 104
and coat wraps materials
7. Final Clearing of Site
Dust emission due to removal of scrap materials, remaining and waste construction materials, construction machinery, dismantling and removal of temporary structures, site cleaning and disposal of these materials. Air emissions emission like NOx, SO2, PM10 & PM2.5 due to movement of lorries, dozers, mobile generators, cranes etc
Construction noise mainly due to breaking, cutting, plying of vehicles, welding machines, operations of
cranes etc.
Soil and Groundwater Contamination due to Waste construction material and scrap dismantled material containing heavy metals, paints, coatings, liners, insulation materials etc.
Storage and Handling of Raw Materials
- a) The dismantled material will be immediately removed and Hazardous waste if any will be disposed off at secured landfill site.
b) Before any container/tank is move or perforated at the end of a contract or particularly during demolition works, all contents and residues will be emptied by a competent operator for
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 105
Fumes and gases near the work area due to welding, and cutting activities.
safe disposal. c) Pipes may
contain significant quantities of oil or chemicals, and will be carefully drained and then capped, or valves closed, to prevent spillage.
B) OPERATION PHASE
1. Increase in traffic
When engines burn fuel (gasoline or diesel), chemicals such as fine particulate matter, nitrogen oxides, carbon monoxide, and volatile organic compounds (VOCs) are emitted.
Important Sources are , E ngine Inlet Exhaust , pro pulsion & transmission in cluding gears, brakes, horns, chas is body structure, Load in vehicle, door slamming etc.
Fuel and oil spills from motor vehicles are washed on road sides and enter the soil.
- - a) Maintain record of vehicles
b) Exhausts from vehicles will be minimized by use of fuel efficient vehicles.
c) Vehicles
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 106
Traffic related emissions are a key contributor to the formation of smog.
Motor cycles, scooter, tempos, and minibuses are generally noiser as compared to passenger cars
will be well maintained and will have Pollution Under Check (PUC) certificate.
d) Green belt development.
e) Use of horn will be discouraged within the project premises.
f) Adequately wide road will be provided (as per Bye-laws) to ensure
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 107
there is no traffic congestion/jam which is the major cause of air pollution otherwise sufficient parking (as per norms) will be provided so that no public place is used for vehicles coming to project site and hence avoid traffic congestion
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 108
in vicinity.
2. Water Supply and Sewerage system
- - Total water requirement will be 1127 KLD. This would include the drinking water requirement of 436 Guests in suites, 5,023 visitors, 8,069 staff and water requirement for HVAC and DG Cooling, Horticulture, water body and swimming pool. However domestic water requirement is 652 KLD About 522 KLD of wastewater will be generated.
- - a) A STP of 672 KLD capacity will be provided within the premises based on MBBR method.
b) The treated water from STP will be used for landscaping purposes, and toilet flushing in summer season and leading to zero exit discharge.
3. Socio-economic
- - - - Local person will be
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 109
impacts
provided direct employment opportunities. In addition employment opportunities will be provided for persons engaged in operation and maintenance activities.
4. Landscaping Various species of trees will be planted in the site to enhance the indoor environment
Improved air quality. Trees, shrubs and turf remove smoke, dust and other pollutants from the air. Grasses absorb carbon dioxide and break it down into oxygen and carbon.
Trees acts as noise buffer by entrapping or absorbing sound
vibrations
Proper landscaping reduces nitrate leaching from the soil into the water supply and reduces surface water runoff, keeping phosphorus and other pollutants out
Overall positive impact on land environment. Landscaping provides a natural refuge for wildlife.
Lower incidences of stress, have lower health care costs, and have an improved quality of life. workers who could view nature from their
Development of a good landscaping (29.27% of the plot area) inside the premises
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 110
of our waterways and preventing septic system overload. A dense cover of plants and mulch holds soil in place, keeping sediment out of lakes, streams, storm drains and roads; and reducing flooding, mudslides and dust storms
desks had much better job and life satisfaction and better health.
5. Solid waste
Foul smell due to waste. Release of
methane if dumped in open.
- Leaching of waste may cause soil
and groundwater contaminati
on
Generation of solid waste
mainly, plastic, kitchen waste,
glassand
Negatively affect the aesthetics of the vicinity.
a) About 3877 KG/day of solid waste is estimated to be generated daily during the operation phase. The
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 111
paper waste solid waste would be segregated into biodegradable waste and recyclable waste and handed over to NGOs/authorized venders for proper management.
6. E-waste from office complex
Air emissions of brominated
dioxins, heavy metals, and PAHs
- Lead, barium and other
heavy metals leaching into the ground water and release of
toxic phosphor.
Tin and lead contamination of surface
and groundwater
Generation of waste like Plastics from
printers, keyboards, monitors, computer wires etc.
- a) E-waste i.e., 14 tonnes/year will be managed as per E-waste (Management), Rules, 2016
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 112
4.3 POLLUTION SOURCES
Pollutants generated in the development of project during both, the construction and functional phases
are solid, liquid and gaseous in nature. Also the generation of pollution could be continuous, periodic
or accidental. Sources of pollutants and their characteristics during the construction and functional
phase are given below in Table 4.3
Table 4.3: Pollution Sources
S. No. Activity / Area Pollutant Sources Frequency
CONSTRUCTION PHASE 1. Site
preparation and construction activities
Air emission- SO2, & NO2.
Dust from construction activities and excavation. Particulates matter, NO2 and CO from vehicle exhaust
Temporary during construction phase only. Bulk of the emissions is expected from ground work and leveling.
Earth/Solid waste
Solid waste from construction activity and excavation.
Periodic.
Hazardous waste generation such as used oil and paints.
From D.G. Sets and painting of the buildings.
Periodic and temporary
Noise Noise generated from construction equipment and machinery
Temporary lasting the construction phase.
2. Labour Camps
Sewage Sewage generated from temporary labor camps on site.
Temporary-during the initial construction phase
Solid Waste Solid Waste generated from temporary labor camps on site.
Temporary- during the initial construction phase
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 113
S. No. Activity / Area Pollutant Sources Frequency
OPERATIONAL PHASE 1. Vehicular
movement Air emissions and noise
Vehicle exhaust emissions
Continuous/ periodic
2. Diesel generators
Air emissions SO2, NO2, PM, CO from fuel burning
Occasional- during power failure
Noise Noise due to running of equipment
Occasional - during power failure
Hazardous Waste Used Oil Generation
Occasional- during oil changes
3. Maintenance / House- keeping
Wastewater Floor washing Sewage
Continuous
Solid waste Residential, Commercial and garden wastes
Continuous
4. Vehicle Parking
Oil spills Minor oil leaks Parking space
Continuous
5. Storm water drains
Rainwater Contamination discharge from site-mainly suspended solids
During rainy season
4.4 IMPACT IDENTIFICATION
The areas of environmental concerns for which the impacts and their predictions are taken
carefully into consideration mainly:
Air Environment
Water Environment
Noise Environment
Land Environment
Biological Environment
Socio economic Environment
Aesthetics Environment
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 114
The impacts can be further categorized as positive impacts and negative impacts depending upon
their nature, potential and magnitude.
4.4.1 Environmental Aspects of Development & Construction Operations
Generation, storage and disposal of construction wastes;
Noise pollution due to plant, machinery, equipments and vehicle movement;
Air pollution due to plant, machinery, equipments and vehicle movement;
Generation and disposal of wastewater;
Impact on ecology;
Consumption of resources such as water, electricity, and diesel.
Physical change in landscape due to earth work excavation and related activities.
Soil erosion caused due to loss of vegetation and other construction activates.
4.4.2 Environmental Aspects of Building Planning and Use
Impacts identified during operation of the project includes:
Disposal of domestic (sewage) effluent generation
Disposal of solid wastes generated in the Project from studio apartment , commercial and
horticulture
Increase in noise levels due to transport
Consumption of water and impact on water resources
Impact on traffic on the road
Storm water during rains
Management and maintenance project
Environmental impacts of the project are not just limited to pollution but also relate to energy
conservation, water conservation and other issues, which are mentioned in Table 4.4.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 115
Table 4.4: Environment impacts of project other than Pollution
S. No. Area Aspect I. Energy
conservation Solar Heating, Day Lighting, Design Natural Ventilation,
Thermal Transfer value of Building Material, Energy Efficient Building Services and Equipment,
Public Area Lighting and Exterior Lighting
II. Water conservation
Reuse of Recycled Water Gardening Water sources Rainwater Harvesting
III. Internal Roads and Accesses
Pedestrian Access Ramps for Disabled persons Road painting and Signage Speed Breakers
IV. Material Use Construction Materials Selection
Paint Selection Use of Recycled Materials Use of Timber
4.5 ASSESSMENT OF ENVIRONMENTAL IMPACTS DURING DEVELOPMENT AND
CONSTRUCTION PHASE
4.5.1 Topography
Impact: Topography around the project is fairly flat. Therefore, topography and physiography of
the area will not be affected due to leveling during the construction and post construction phase
of the project. Hence, no significant impact is anticipated on the topography and physiographic
from project.
Mitigation Measure: Since there is no significant impact on topography from the project, no
detailed mitigation measures are proposed. It is however proposed that apart from the proposed
plantation greens, turfing with local species will be carried out extensively.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 116
4.5.2 Land Use Pattern
Impact: Land use of the project site is commercial and has been allotted by Greater Mohali
Area Development Authority. Therefore, land use pattern of the area will not be affected
significantly by project.
4.5.3 Land Environment
Impact: The soil excavated during construction will be first temporarily stored in an area
earmarked and then shall be used to fill up low lying area in and around the project site and rest
of the soil shall be transported by road to fill up low lying areas elsewhere. Proper drainage
system shall be provided to deal with the storm water in case of rain. The impact on soil during
construction phase will be marginal and reversible in the nature.
Mitigation: It is proposed to remove vegetative cover only from the specific site on which
construction is to take place and allowing minimal disturbance to the vegetation in adjacent
areas. Land clearing activities only confined to necessary areas. The top soil will be stripped
from constructional areas and stockpiled for later reuse in landscaping. The number, frequency
and area of movement of heavy machinery will also be restricted.
4.5.4 Water Environment
4.5.4.1 Surface Water Quality
Impact: The primary concerns relating to surface water quality associated with construction
activities are pointed out below:
Runoff related to unpaved and excavated areas during the rain shower.
Sediments transported to runoff from the construction site.
Run off related to area where lubricant, fuel other materials are stored, used and disposed, off.
Surface water quality may be affected with the discharge of the runoff from the project site. The
impact to the surface water bodies could arise from the increased soil erosion from excavated site
only causing increase in the suspended particles and turbidity of runoff water from the site.
However, this impact will be temporary in the nature and would be observed in first rain only
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 117
and as soon as rain is over excavated soil at site would be stabilized. Therefore, the surface water
quality during rains will be impacted marginally for very short duration.
Mitigation Measures: During the construction phase, surface water quality is likely to be
affected due to soil erosion during first rain and generation of wastewater mainly from
construction labour camp. However, this phenomenon will be temporary and restricted to close
vicinity of construction site. The impact on surface water quality can be minimized by adopting
following measures;
Excavation during dry season and proper management of excavated soils,
Clearing all debris from site as soon as construction is over.
By providing proper hutment and toilet facilities for construction labour,
Through the proper disposal of waste water generated at site.
4.5.4.2 Ground water Quality
Impact: Building construction involves a large variety of construction activities. Wastewater
would be generated from concreting, plastering, cleaning and polishing, internal decoration and
similar activities. Direct discharge of wastewater into storm drains pollutes the water quality of
receiving water body. Ground water quality could be polluted by debris and waste generation.
Mitigation:
A suitably designed wastewater collection system should be provided on site to divert all
the wastewater to the sedimentation facility.
If necessary, pH adjustment should be undertaken to neutralize the wastewater.
Good housekeeping should be adopted to reduce generation of construction wastes and
the potential water pollution
Drainage channels should be provided on site to convey storm water to sand/silt traps for
removal of soil particles
Regular cleaning and maintenance of the sediment removal facilities should be
implemented to ensure that the facilities are in normal function at all times
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 118
Provision of earth bunds or sand bags in areas where a large amount of exposed soils
exists would be required
The construction works should be properly programmed to minimise soil excavation in
rainy seasons to prevent soil erosion from exposed soil surfaces
Excavated trench should be backfilled in short sections
Exposed stockpiles should be covered with tarpaulin or impervious sheets before a
rainstorm occurs
Suitable locations should be selected on site to place the stockpiles so as to avoid release
of materials into the drainage channels
Final surface of earthworks should be compacted and protected by permanent work
Intercepting channels should be provided to prevent storm runoff from washing across
exposed soils surfaces; and
It is recommended to pave haul roads with concrete and protect temporary access roads
using crushed stone or gravel.
4.5.4.3 Surface and Ground Water Hydrology
Surface Water Hydrology
Impact: The project site is not falling in flood plain. Runoff during rains takes way to natural
drain and in storm water drains laid in the area. During construction phase, there is no impact
anticipated on the drainage pattern of the project area.
Mitigation Measures: Project proponent will ensure no interception on water runoff flow routes
and drainage pattern of the area throughout the construction of the project by providing adequate
water channel.
Ground Water Hydrology
Impact: Water requirement during construction phase will vary depending upon construction
activities and will be met through authorized private water tankers. Water will be required for
site preparation activities dust settlement, consolidation, compaction and curing as well as
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 119
building construction and drinking water requirement. The requirement of construction water
will not put sudden pressure on the available ground water recourses of area. Therefore, impact
on ground water resources will be insignificant during construction of project.
Mitigation Measures: Although no impact is anticipated on the groundwater regime, it is
proposed to carry out the following to further minimize the water demand:
Curing water will be sprayed on concrete structures and free flow of water not allowed.
After liberal curing on the first day, all concrete structures will be painted with curing chemical
to save water to stop daily water curing hence save water.
Concrete structures will be covered with thick cloth/gunny bags and then water sprayed on
them to avoid water rebound and ensure sustained and complete curing.
Ponds will be made using cement and sand mortar to avoid water flowing away from the flat
surface while curing.
Water ponding will be done on all sunken slabs. This will also highlight the importance of
having an impervious formwork.
4.5.5 Air Environment
Emission Source: The potential sources of air emissions during the construction and
development phase of the project will be as follows:
Dust from earth works (during site clearance and preparation);
Emissions from power generator at site;
Emissions from the operation of construction equipment and machines;
Fugitive emissions from vehicles running to site;
Fugitive emissions during the unloading of material at the site;
Fugitive emissions during mixing of cement with other building materials during development
and construction activities;
Air emissions other than dust arise from combustion of hydrocarbons. The pollutants of
concerns are NO2, SO2, CO, particulate etc.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 120
Potential Impacts: Ambient air quality effects are normally assessed in relation to their
potential to cause;
Health deterioration and nuisance to local communities
Health deterioration amongst onsite workers
Assessment of the impacts from Dust Emissions: During the excavation of channels,
foundations, unloading of construction material, cement bags and mixing of cement with other
building materials such as brick and silica dust, wood dust, fugitive dust emissions may be
emitted at construction site. During construction, curtaining floors from all sides will be done to
prevent cement dust from becoming airborne. It may be noted that all the emissions will be in the
form of coarse particulate matter and settle down ultimately in closed vicinity of construction
site.
Assessment of the impact from Diesel Generators: Emissions from the D.G. Set during
construction phase may cause some localized impact on ambient air quality for short duration, as
it will be operated during power failure only. It may be noted that the D.G. Set power will be
used to operate construction equipment only if required. Adequate height of stacks and acoustic
erective will be provided to the D.G. Set as per guidelines of CPCB to facilitate the dispersion of
flue gases into the atmosphere.
Mitigation Measures: It is proposed to provide adequate dust control systems in the form of
installation of batch plants, and loose material handling in covered sheds. Dust suppression
system is also to be provided where necessary. Ultra-low sulphur based DG sets will be used. It
is further proposed to cover scaffolding, hosing down road surfaces and cleaning/washing of
vehicles especially during the dry season. Avenue and curtain plantation on the internal roads
and peripheral plantation around the site will also be developed for mitigation of air pollution.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 121
4.5.6 Noise Environment
During the construction phase of project, noise will be generated from various sources. Some
major sources of noise generation at project site are listed here:
Generation of noise during movement of vehicles carrying materials and loading & unloading
activities.
Generation of noise from excavation machines, concrete mixer and other construction
machines,
Generation of noise during the operation of D.G. Set
Generation of noise during concreting, hammering, etc.
All the above-mentioned sources of development and construction activities would be
intermittent and experienced occasionally. It may also be noted that most of the construction
activities would be carried out only during the daytime.
The expected noise levels from various activities are given hereunder:
From vehicles bringing materials to the site 70 dB (A)
D.G. Set 85 dB (A)
Excavation 80 dB (A)
Concrete Mixtures 80 dB (A)
Hammering 85 dB (A)
Resultant Noise Level:
The combined effect of above sources can be determined as per the following equation:
Lp (total) = 10 log (10(Lpl/10) + 10(Lp2/10) + 10(Lp3/10) +……..) ……. (1)
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 122
Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in dB (A). The
resultant maximum noise level for the above sources as calculated using equation (1) is 89.3 dB
(A).
For an approximate estimation of dispersion of noise in the ambient air from the sources point, a
standard mathematical model for sound wave propagation is used. The sound level generated by
noise source decrease with increasing distance from the source due to wave divergence. An
additional decrease in sound pressure level from the source is expected due to atmospheric effect
or its interaction with objects in the transmission path.
For hemispherical sound wave propagation through homogenous loss of free medium, noise
levels at various locations can be calculated due to different sources using model based on the
first principles as per the following, equation:
Lp2 = Lp1 -20 log (r2) – 8 ………. ( 2 )
Where: Lp2 and Lp1 – Sound Pressure Level (SPLs) at points located at sources and at distance
of r2 from the source respectively in dB (A).
Assuming no environmental attenuation factors, noise modeling has been done, which shows
that noise level will be mingle with baseline noise level with in short distance.
The noise produced during, development and construction phase will have temporary impacts on the
existing, ambient noise levels at project site but restricted to small distance and only during daytime.
Therefore, the impact of noise levels on surrounding area will be insignificant during the development
and construction phase.
Mitigation: To minimize impacts of noise generation following measures will be adopted:
Provision of Personal Protective equipments (PPE) such as muffles/plugs to the workers.
Acoustic enclosures to be provided for compressors for drills and rock cutter.
DG set for backup power to be provided with adequate acoustic enclosure and to be fitted with
muffler to reduce the noise in adherence with the regulatory equipments.
All plants and construction equipments shall be fitted with noise control measures.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 123
Servicing of all construction vehicles and machinery to be done regularly and during routine
servicing operation, the effectiveness of exhaust silencers will be checked and if found
defective to be replaced.
To have the provisions of noise barriers in form of dense tree belt around the periphery and
particularly facing residential area. Shrubs can reduce noise by about five to ten decibels-or
about 50 percent as perceived by the human ear, (According to the USDA National Agro
forestry Center). Some Examples include Neem, Manngo, Tamarind, Gulmohar , Peepal,
Ashoka
The DG sets should also be provided with proper exhaust muffler with insertion loss of
minimum 25 dB (A).
Vehicle for bringing construction material at site shall conform to the noise emission standards
and to be operated during non peak hours.
Ambient noise level monitoring shall be conducted at suitable locations at periodic intervals
during construction phase to conform to the stipulated standards during both day and night
time. Data shall be reviewed and analyzed by the project manager for adhering to any strict
measures.
4.5.7 Terrestrial Ecology
Impact: There is no loss of forestland due to the development of proposed project. No tree felling is
involved, as the site is devoid of vegetation.
Birds and other domesticated biodiversity observed near the project site are common and already
adapted to thrive in human - colonized habitats. The project will not have any major negative
ecological impact.
Mitigation Measures: However, it is to develop extensive green areas/ open area in the project site to
improve the aesthetics of the area which will also help in reduction of air pollution, noise pollution and
provide suitable habitat for local birds and animal species.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 124
4.5.8 Economic Impacts
Impact: Relatively long-lived economic impacts of the development and construction phase are likely
to be experienced in local area for the duration of construction phase as workers make everyday
purchases from local traders in nearby areas. This is likely to give a short-lived stimulus to the traders
that may disappear as soon as the construction is complete. Noticeable, flow-on economic impacts
will be experienced in other sectors of economy as a result of purchase of construction materials and
the payment of wages and salaries to the personnel engaged in the development and construction of
colony. Once the development and construction of the project is complete, there will be some long-
term positive impact on the economic structure of the area. People in the area will get direct and
indirect employment opportunities and other benefits from the proposed project. Therefore, overall
positive impact is anticipated on economy of the area due to development and construction activity of
the Project.
4.5.9 Socio-Economic
During the development and construction of project, about 200 to 300 skilled and semiskilled and
unskilled workers per day will get direct employment opportunity, which will have beneficial impact
on the local people and improve socio-economic conditions of the area.
4.5.10 Construction Camp
Impact: During the development and construction phase, most of the laborers will be from local areas.
Therefore, laborer camps will be constructed to accommodate the laborers at the project site. This may
lead to sanitation problems in the absence of adequate facilities.
Mitigation: Suitable measures will be taken at the construction camps to mitigate anticipated impacts
due to temporary accommodation of laborers such as provision of adequate drinking water, adequate
toilet facilities, water and solid waste disposal system.
Other safety precautions to be maintained at work site including provision of PPEs, guarding of
dangerous machine parts, maintenance of equipments as hoists and lifts etc, and adequate provision of
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 125
different types of fire extinguishers will be made. All applicable rules and regulations pertaining to
workplace health and welfare of workers will be adhered to.
4.5.11 Solid Waste Management
Impact: The construction waste includes debris, concrete (often recycled and reused at the site), steel
and other metals, pallets, packaging and paper products, wood beams, joists, studs, baseboards,
cabinets and cupboards, railings, brick, doors and casings, interior windows, bathroom fixtures, light
fixtures, ceiling grid and tile, furnishings. All wastes generated during the construction phase shall be
collected and segregated for disposal as per the standard practice.
During the development and construction phase, some amount of debris, cuttings of construction
materials may be observed at construction site. However, the quantity of these waste materials would
be very small and limited up to the construction site only. There will be no contamination due to this
waste as it will be collected time to time during construction phase and disposed accordingly.
Mitigation Measures: After due waste segregation, recyclable wastes will be sold off to scrap dealers
and vendors, while inert wastes will be disposed off in landfills. Hazardous wastes will be disposed off
as per the provisions of the Hazardous Wastes (Management & Handling Rules, 1989).
4.5.12 Transport Linkage and Traffic
Impact: During development and construction phase, construction labour and construction materials
bringing vehicles will approach the project site. The Project is well connected to neighborhood, where
public transport facility, like, buses and minibuses are easily available in the area as transport linkage.
During construction phase, some impact is anticipated on the transport linkage of the area, however
increase in traffic will not adversely affect the local traffic pattern since the site is well connected by
broad road and present traffic load on these road are not significant.
Mitigation: Through careful planning, the movement of the heavy vehicles will be scheduled to
reduce load on existing traffic such that the peak hours are avoided. It shall also be ensured that all the
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 126
vehicles to the site will be provided with Parking space such that there is no waiting time along the
access roads.
4.6 ASSESSMENT OF THE ENVIRONMENTAL IMPACTS DURING POST
CONSTRUCTION PHASE
4.6.1 Land Environment
Impact: During the operation phase of the project, the soil may get polluted/ contaminated from
littering of various kinds of wastes generated within the site such as food items, paper, wood pieces,
paints, pesticides, oil & grease etc. However, owing to the proposed solid waste management system,
no significant impact is anticipated.
Mitigation Measures: To ensure against any chances of soil pollution, it is imperative to establish a
well-planned solid waste collection system covering all areas of the project site apart from door to
door for the residential units. An identified area shall be designated for storage and segregation of the
wastes which will be treated/ disposed as per their characteristics.
The following steps are proposed to be followed for the management solid waste:
Construction yards are proposed for storage of construction materials.
The excavated material such as topsoil and stones will be stacked for reuse during later stages
of construction
Excavated top soil will be stored in temporary constructed soil bank and will be reused for
landscaping of the commercial project.
Remaining soil will be utilized for refilling / road work / rising of site level at locations/ selling
to outside agency for construction of roads etc.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 127
Solid Waste
Construction
Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling,
raising site level
Sold to agency for
recycling
Excavated Soil
Top soil conserved for landscaping,
balance used in re-
filling
Figure 4.1: Solid Waste Management Scheme (Construction Phase)
Following arrangements will be made at the site in accordance to Municipal Solid Wastes
(Management and Handling) Rules:
Collection and Segregation of waste
1. Collection system will be provided for collection in colored bins.
2. Adequate number of colored bins (Green and Blue & dark grey bins– separate for Bio-
degradable and Non Bio-degradable) are proposed to be provided at the strategic location.
3. Litter bins will also be provided in open area.
4. A local vendor will be hired for segregation of solid waste and its treatment/disposal.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 128
Treatment of waste
Bio-Degradable waste
1. Bio-degradable waste will be converted into manure through the vendor.
2. STP sludge is proposed to be used for horticultural purpose.
3. Horticultural Waste is proposed to be composted and will be used for gardening.
Recyclable waste
i. Grass Recycling – The cropped grass will be spread on the green area. It will act as manure
after decomposition.
ii. Recyclable waste like paper, plastic, metals etc. will be sold off to recyclers.
Disposal
The Solid waste management scheme is depicted in the following figure.
Figure 4.2: Solid Waste Management Scheme (Operation Phase)
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 129
E-waste will be disposed off through approved vendor of CPCB as per Electronic Wastes as per E-
waste (Management), Rules, 2016.
4.6.2 Water environment
4.6.2.1 Surface water hydrology
Impact: During the post construction phase, no water will be taken from surface water bodies in the
area. Further, adequate drainage will be provided at the project site to channelize the storm water for
rainwater harvesting to recharge the ground water.
The sewage effluents generated from the project will be collected through the sewer line network
provided in the project site for treatment in the Sewage Treatment Plant (627 KLD), and the treated
effluent will be reused within the site Therefore, impact on the surface water hydrology will be
insignificant during the post construction phase.
Mitigation: It is proposed that water will be discharged to sewer after treatment.
Sewerage System
MBBR TECHNOLOGY
An external sewage network will collect the sewage from all units, and flows by gravity to the sewage
treatment plant. Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
The process has long retention time and can absorb shock load situation.
Reduced net daily water requirements, source for Flushing and Horticultural purposes by
utilization of the treated water.
Reduced dependence on the public utilities for water supply and sewerage systems.
The process produces a well-oxidized sludge in small quantities only, which can be removed and
used as manure.
a. Wastewater Details
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 130
(a) Daily load : 522 KLD
(b) Duration of flow to STP : 24 hours
(c) Temperature : Maximum 32oC
(d) pH : 6.5-8.0
(e) Color : Mild
(f) T.S.S. (mg/l) : 250-400 mg/l
(g) BOD5 (mg/l) : 250-350 mg/l
(h) COD (mg/l) : 450-600 mg/l
(i) Oil & Grease : 50 mg/l
b. Treated effluent
(a) pH : 6.0-8.5
(b) B.O.D. : <10 mg/l
(c) C.O.D. : <70 mg/l
(d) Total Suspended Solids : <10mg/l
(e) Oil & Grease : Nil
c. Treatment Technology
Moving bed biofilm reactor technology is based on the principle of attached growth process. Raw
sewage will be collected under gravity into the equalization tank after allowing to pass through the bar
screen. Screens will be provided in screen chambers and it will be manually cleaned by going down to
a platform. The bar screen, by removing coarse solids from the sewage help in protecting the raw
sewage pump.
Fully submersible centrifugal non clog sewage handling pump will be provided in the collection cum
equalization tank to pump the collected waste water to the next MBBR tanks. Automatic level
controller will be provided in the tank to turn the pump off at the low water level in the tank and to
start the pump when water level is high automatically. Air will be introduced in this tank to prevent
any potential foul smell problem & to provide the mixing of wastewater to avoid the sedimentation of
solids in this tank. Air Grid used for aeration purpose will be non-clog.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 131
The sewage collected in equalization tank is pumped the moving bed bioreactor. There will be two
nos. of bioreactors in series for the efficient working and removal of BODs for the required retention
time. The process inside the moving bed bioreactors consists of adding small cylindrical-shaped
polyethylene/polypropylene carrier elements in aerated basins to support biofilm growth. The small
cylinders are provided with a cross inside the cylinder and longitudinal fins on the outside. The
biofilm carriers are maintained in the reactor by the use of a perforated plate with appropriate slot at
the tank outlet. Air agitation or mixers are applied in a manner to continuously circulate the packing.
The packing may fill 25 to 50 percent of the tank volume. Specific surface area of the packing is about
450-500m2/m3 of bulk packing volume. The waste water from first bioreactor flows by gravity through
the perforated plate/mesh to the next bioreactor kept in series. Inside the bioreactors, aerobic bacteria
grow in an attached growth from around the moving plastic media inside the reactors. The bacteria
have to reduce BOD & COD of waste water in the presence of oxygen provided through the air grids
located at the bottom of the reactors. The Process does not require any return activated sludge flow or
backwashing.
From the bio-reactors, the effluent passes by gravity into the clarifier (Tube Settling Tank). Clarifier
will be a hopper bottom sedimentation tank provided with appropriate size PVC tube deck media. The
suspended solids will settle at the bottom of the tank & clear supernatant will overflow to filter feed
tank through outlet launder. The collected sludge at bottom will be transferred through pumps to
sludge holding tank.
The clear supernatant after clarifier will be collected in to filter feed tank. This tank will act as housing
tank for filter feed pumps. The clarified & dis-infected water will be then fed to filtration unit.
Filtration unit consisting of Dual Media sand filter, activated carbon filter and ultra-filtration system
(optional) will remove the residual impurities such as odor/color, suspended solids, BOD/COD. The
treated water after the filtration unit will be collected in Irrigation cum Flushing water storage tank
from where it is transferred to flushing water tank at terrace & Irrigation System.
Excess sludge from the bottom of the settling tank will be removed and transferred to sludge holding
tank. Air grid will be provided in this tank to avoid conversion into anaerobic conditions, thickening of
sludge and keep sludge in homogenous condition. The digested & thickened sludge will be further
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 132
thickened through Sludge Dewatering System (Filter press with screw pump) and disposed off
periodically through closed tanker or can be reused as manure.
Figure 4.3 : Schematic Diagram of STP
4.6.2.2 Ground water hydrology
Impact: During post construction phase, the total water requirement of the Project is approx. 1127
KLD which will be sourced from GMADA. Therefore, no impact is anticipated on ground water
resources due to project.
Mitigation Measures: The rainwater harvesting will recharge groundwater aquifers from the open
areas as well as roof top of the buildings/surface runoff. Treated water from the site will be recycled
for landscaping and flushing. DG set cooling to further reduce demand on freshwater resources.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 133
Water meters conforming to ISO standards should be installed at the inlet point of water sources and at
the discharge point to monitor the daily water consumption. To further lower the water consumption,
options of low flow flushing systems, sensor based fixtures, and tap aerators, etc will be explored.
RAIN WATER HARVESTING
The storm water collection system for the premises will be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon many
factors such as intensity and duration of precipitation, characteristics of the tributary area and the time
required for such flow to reach the drains. The drains will be located near the carriage way along
either side of the roads. Taking the advantage of road camber, the rainfall run off from roads will flow
towards the drains. Storm water from building will be connected to adjacent drain by a pipe through
catch basins. Therefore, it has been calculated to provide 8 rainwater harvesting pits at selected
locations, which will catch the maximum run-off from the area.
1) Since the existing topography is congenial to surface disposal, a network of storm water pipe
drains is planned adjacent to roads. All building roof water will be brought down through rain water
pipes.
2) Proposed storm water system consists of pipe drain, catch basins and tanks at regular intervals
for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm water
storage tank. This water will be pumped out to the nearest external storm water drain.
4) The peak hourly rainfall is 45 mm/hr. will be considered for designing the storm water
drainage system.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak hourly
rainfall has been considered as 45 mm/hr. The recharge pit is constructed for recharging the water. The
recharge pits of 3 m dia. and 4 m depth is constructed for recharging the water. Inside the recharge pit,
recharge bore will be constructed of sufficient diameter and depth. The bottom of the recharge
structure is kept 5 m above the ground level. At the bottom of the recharge pits, a filter media is
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 134
provided to avoid choking of the recharge bore. Design specifications of the rain water harvesting plan
are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged allowing
release of material into the water. Roof painting has been avoided since most paints contain toxic
substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags and paper
pieces will get arrested by the mesh at the terrace outlet and to prevent contamination by ensuring that
the runoff from the first 10-20 minutes of rainfall is flushed off.
No sewage or wastewater would be admitted into the system. No wastewater from areas likely
to have oil, grease, or other pollutants has been connected to the system.
Calculations for storm water load:
Roof-top area = Ground Coverage = 12,899.45m2
Green Area = 9517 m2
Paved Area = Total plot area – (Roof top area + Green Area)
= 32,512.44- (12899.45+ 9517) = 10095.99m2
Runoff Load
Roof-top Area = 12899.45 ×0.045 × 0.80
= 464.38 m3/hr
Green Area = 9517 × 0.045× 0.1
= 42.83m3/hr
Paved Area = 10095.99× 0.045× 0.7
= 318.02m3/hr
Taking 15 minutes retention time-Total volume of storm water
For Roof –top-Area = 464.38/4
= 116.09 m3
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 135
Taking the effective Dia. and depth of a Recharge pit 3 m and 4 m respectively, Volume of a single
Recharge pit = πr2h =3.14 x 1.5 x 1.5 x 4 = 28.26 m3
Hence No. of pits required = 116.09 /28.26 = 4.10 pits. ~ 4 pits.
For Green Area = 42.83/4
= 10.72 m3
Taking the effective Dia. and depth of a Recharge pit 3 m and 4 m respectively, Volume of a single
Recharge pit = πr2h =3.14 x 1.5 x 1.5 x 4 = 28.26 m3
Hence No. of pits required = 10.72 /28.26 = 0.37 pit. ~ 1 pit.
For Paved Area = 318.02/4
= 79.5 m3
Taking the effective Dia. and depth of a Recharge pit 3 m and 4 m respectively, Volume of a single
Recharge pit = πr2h =3.14 x 1.5 x 1.5 x 4 = 28.26 m3
Hence No. of pits required = 79.5 /28.26 = 2.81 pits. ~ 3 pits.
Total No. of pits required/proposed= 8
Therefore, a total of 8 Rain Water Harvesting pits are proposed within the project premises for
artificial ground water recharge.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 136
Figure 4.4: RWH Pit design detail
4.6.2.3 Surface Water Quality
Impact: The sewage effluents generated from the Project will be collected through the sewer line
network provided in the premises of the project site, and treated in an onsite Sewage Treatment Plant
(STP) of capacity 627 KLD..
Mitigation Measures: As no impact is anticipated on the water bodies of the region, no mitigation
measures are suggested.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 137
4.6.2.4 Ground Water Quality
Impact: The storm water from the site will be used for recharging groundwater resources after
adequate treatment of the storm water through oil, grease traps and filtration. The wastewater from the
site is proposed to be used for landscaping, flushing, HVAC cooling to achieve zero exit discharge.
Hence, no adverse impact is anticipated on the groundwater quality form the project.
Mitigation Measures: The project premises will be well maintained. Solid waste management
practices will be followed as per norms to prevent groundwater pollution.
4.6.3 Air Environment
Prediction of Impacts
Vehicular emissions and DG sets emission will be major sources of air pollution from building
construction projects. During the post construction phase, cars, scooter/motorcycle will be owned by
the population of such project. Ground Level Concentration of pollutants (as added by the project)
will depend upon the following:
Emission of pollutants from additional traffic on the roads due to the project.
Meteorological conditions.
Emission sources from D.G. Sets.
PM, NO2, SO2 and CO will be the main pollutants of primary concern released from traffic movement
and DG sets. Assuming that under cross wind condition perpendicular to the road, the dispersion of
vehicular emissions would be confined within limited distance from the road and concentration will
decrease with the increase in distance from road. It was anticipated that the contribution of vehicular
emissions from the exhaust in ambient air quality will be marginal as Pollution under Control (PUC)
Certified vehicles and branded make operated vehicle with low sulphur diesel will be used. Ground
Level Concentration (GLC) of pollutants is found to be well within the stipulated National Ambient
Air Quality Standards due to traffic movement and vehicles used inside the premises. DG sets will be
main source of Air Pollution in the project. CPCB/ MoEF approved USEPA dispersion model -
ISCST3 was used for prediction of impacts caused by DG sets. Stack & emission data was used as per
design value provided by standard make and stipulated standards. Other primary data used as input for
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 138
model were hourly meteorological data of Wind speed, direction, temperature, cloud amount and
mixing height. Mixing height used in the model was taken from secondary data source “Atlas of
Hourly Mixing Height Assimilative Capacity of Atmosphere in India published in 2008 by IMD,
Delhi”. Hourly meteorological monitored at site during study period data was compared with long
term data available from the nearest India Meteorological station or any other authorized source/Govt.
agencies.
In this project, 7 DG sets of total 11,000 kVA (3 x 2000 + 3 x 1500 + 1 x 500 kVA) capacity have
been proposed, for back up of electricity supply during power failure. This will cause emission of PM,
SO2, NO2 and CO in the Ambient Air Quality. In the project D.G. sets will be used only during power
failure and low sulphur diesel will be used as fuel to minimize SO2 emission. Therefore, incremental
load in the ambient air environment will be very low as given in the report. An adequate stack height
of D.G. sets will be provided as per the stipulated guidelines of Central Pollution Control Board
(CPCB)/ National Building Code Manual to facilitate proper dispersion of pollutants and to minimize
the impact on Ambient Air Quality under the influence of local meteorology.
Meteorology –Hourly Meteorological data of wind speed & direction, temperature, cloud amount and
rainfall were monitored at site for 1 month for the dispersion model. Wind rose (Figure - 4.1) was
prepared in sixteen directions as per standards. It was observed that westerly and northwesterly was
prevalent wind during the study period. Average wind speed was 2.78 m/sec and calm condition was
00.00% during 12th May-12th June 2016.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 139
Figure 4.5: Wind Rose (Summer Season for 12th May to 12th June - 2016)
Model details and Frame work of Computation:
The predictions for air quality during operation phase were carried using CPCB/MoEF approved
“USEPA, Industrial Source Complex (Version - ISCST3)” Dispersion model developed by the US
Environmental Protection Agency (USEPA) for prediction of pollutants dispersion from single or
multiple point sources using emission and hourly meteorological data of the study period.
Assumption used in the model was as follows:
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 140
The plume rise is limited to that of the mixing layer as published by IMD in the Catalogue of
Atlas of Mixing Heights in India for the site
Stack down-wash is not considered.
Flat terrain is used for computations;
It is assumed that the pollutants do not undergo any physico-chemical transformation.
Chemical and scavenging process occurred in the atmosphere in the pollutants released at the
stack exit is not considered.
Prediction is based on single/multiplepoint sources, pollution released at stack exit and
dispersed on the ground under influence of local meteorological conditions during the season.
ISCST3 dispersion model was used to predict GLC caused by a single point source (4 stacks) at each
receptor of 40 m x 40 m of grid network covering total area of 2000 m x 2000m around the proposed
source with stack & emission values and 1-hourly meteorological data. It was observed that SO2,
NO2, Co and PM were significant pollutants released from the fuel of the D.G. sets. Emission of PM,
CO and SO2 were found insignificant with low values compared to NO2. In this project, NO2 was the
worst affected pollutant released into the atmosphere (Table 4.5) with high emission value.
Table 4.5 Stack and Emission Details
Stack
No.
DG set
Capacity
(kVA)
Stack & Flue details Pollutants Emission
Height
(m)
velocit
y
(m/s)
Temp
(K)
Diamete
r (m)
NO2
(g/s)
SO2
(g/s)
PM
(g/s)
CO
(g/s)
1. 2000
kVA 85 25 809 0.533
0.68 0.124 0.038 0.077
2. 2000
kVA 85 25 809 0.533
0.68 0.124 0.038 0.077
3. 2000
kVA 85 25 809 0.533
0.68 0.124 0.038 0.077
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 141
Note: DG set will be operated during power failure for maximum 6-Hours
Discussion of Results
ISCST3 - Dispersion model was used to predict GLC of all pollutants; SO2, NO2, CO and PM with
stack & emission and hourly meteorological data. 24-hours average maximum Incremental GLC of
NO2 was to be 3.62 µg/m3occurred at (2000m,00m), East from the DG sets fitted with 85 m
chimney.It was found that GLC of NO2 was less than the permissible limit of 80µg/m3 (as per CPCB
guidelines) under worst meteorological condition (Table 4.6) with meteorological data monitored on
4th June 2016.
Table 4.6 Meteorological data for the 24-hour average maximum predicted Concentration
under worst meteorological condition
Year Month Day Hour Wind
Direction Wind Speed Temp (K)
2016 6 4 1 270 1.5 303 2016 6 4 2 270 1.5 303 2016 6 4 3 270 1 302 2016 6 4 4 270 1 301 2016 6 4 5 270 1 301 2016 6 4 6 270 1 301 2016 6 4 7 270 1 303
4. 1500
kVA 85 25 809 0.487
0.57 0.097 0.032 0.065
5. 1500
kVA 85 25 809 0.487
0.57 0.097 0.032 0.065
6. 1500
kVA 85 25 809 0.487
0.57 0.097 0.032 0.065
7. 500 kVA 85 25 773 0.271 0.25 0.031 0.007 0.097
Total Emission in g/s 11000 kVA (3 x 2000 + 3 x 1500 +
1 x 500 kVA)
4 0.694 0.217 0.523
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 142
2016 6 4 8 270 1 306 2016 6 4 9 292.5 3.6 308 2016 6 4 10 292.5 3.6 310 2016 6 4 11 292.5 3.6 312 2016 6 4 12 292.5 4.1 314 2016 6 4 13 292.5 4.6 315 2016 6 4 14 292.5 4.6 316 2016 6 4 15 270 4.6 316 2016 6 4 16 292.5 4.6 316 2016 6 4 17 292.5 4.6 316 2016 6 4 18 270 4.1 315 2016 6 4 19 270 2.6 312 2016 6 4 20 270 1 310 2016 6 4 21 270 1 308 2016 6 4 22 270 1 307 2016 6 4 23 270 1 306 2016 6 4 24 270 1 305
Spatial distribution of NO2 is shown in Isopleth Figure 4.2. It was observed that GLC closed to the
proposed source will be not significant. 24-h maximum incremental GLC was 3.62 µg/m3 occurred at
the distance 2000 m, East of the project site.
Conclusion
Maximum Incremental GLC of NO2 is 3.62 µg/m3 due to DG sets in the Commercial project. High to
moderate wind speed and minimum stack height of 85 m facilitates dispersion at the distance of 2000
m east under the influence of local meteorology. Low GLC of pollutants was predicted due to high
Stack height of 85 m fitted with DG sets. Predicted GLC of all pollutants are given in Table 4.7 as
below:
Table 4.7 Predicted GLC
S.
No.
Pollutants Maximum Incremental
GLC (µg/m3)
Distance of occurrence
1 NO2 3.62 2000 m, East
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 143
Low incremental value was predicted from DG sets due to high stack height of 85 m. No significant
impact was envisaged due to proposed DG sets to be installed at site.
Fig. 4.6: Spatial distribution of 24-hours average NO2 maximum incremental GLC (3.62 µg/m3).
Moderate to high wind speed and stack height of 85 m facilitates dispersion at long distance of
2000 m, East under the influence of local meteorology
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 144
Mitigation Measures: The project proponent will develop a green belt inside the premises of the
project site and along the internal road, which will work as barrier for the movement of pollutants and
help in pollution control.
4.6.4 Noise Environment
Impact: The main sources of noise from the project are running of D.G. Sets and vehicular traffic.
D.G. Sets will provide emergency electricity supply during power failure. This will be intermittent and
for short durations. The vehicles playing within the site will be mainly of the residents and are hence
not expected to cause unnecessary noise. Hence, during this phase, no major impact on noise
environment is anticipated.
Mitigation Measures:
During the construction stage, expected noise levels shall be in the range of 80-85 dB (A) which will
decrease with increase in distance as per the Inverse Square Law. Considering that the project site is
away from populated area, it would not have any adverse effect outside the development area.
Administrative as well as engineering control of noise will be implemented. Isolation of noise
generation sources and temporal differentiation of noise generating activities will ensure minimum
noise at receiver’s end. To prevent any occupational hazard, ear muff / ear plug shall be given to the
workers working around or operating plant and machinery emitting high noise levels. Use of such
plant or machinery shall not be allowed during night hour. Careful planning of machinery operation
and scheduling of operations shall be done to minimise such impact.
4.6.5 Terrestrial Ecology
Impact: The project proposes 9517 m2 of green area that will be planted with local species with
aesthetic appeal that will attract local bird and insect species. As against the existing barren stretch of
land, the project will add to the greenery and beauty of the region.
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 145
Mitigation Measures: Various kinds of plantation such as curtain, avenue and ornamental plantation
and lawns will be started during the construction phase itself and maintained during the operation
phase. Open space and Parks will be fenced through the grasses and ornamental plants. Local and low
water demanding plants that will also be effective as sinks for various pollutants and attract birds will
be grown in the site that will contribute in positive to the local ecology.
Table 4.8: Plantation List
Botanical Name Common Name Notes C/C Spacing (m)
TREES Albizzia lebek Siris Native 5 Anthocephalus cadamba Kadamb Native 5 Azadirachta indica Neem Naturalized 5 Buauhinia purpurea Kachnar Naturalized 3.5 Butea monosperma Flame-of-the-Forest Native 4 Cassia fistula Amaltas Native 4.5 Cassia nodosa Pink Cassia 4.5 Dalbergia sissoo Sheesham Native 5 Erythrina indica Mandar Native 4 Ficus infectoria Pilkhan Native 6 Melia azaderach Bakain Native 4 Phoenix dactylifera Date palm Native 4 Polyalthea longifolia Ashok Naturalized 4.5 Schleichera oleosa Kusum Native 5 Tecoma gaudichaudi 3.5 SHRUBS Caeselpinia pulcherrima Gulmohar shrub 1.8 Cestrum nocturnum Raat ki Rani 1.2 Hamelia patens Hamelia 1.5 Murraya exotica Kamini 0.6 Nerium oleander Kaner 1.2 Pennisetum rubrum Red Fountain grass 0.75 Pennisetum setaceum Fountain grass 0.75 Rosa "Summer Snow" 0.5 Tabernaemontana coronaria Chandni 1.8
World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. 146
4.6.6 Socio-economic Impact
Impact: During operational phase of the project, more than 8000 persons will get employment
opportunities as staff for management, maintenance and security. As an estimate, during post
construction phase, more than 300 persons will get marginal employment opportunities from the
residents of Project who would work as domestic helpers. This will help in improving the quality of
life of economically weaker sections of the local area.
Mitigation Measures: To further improve the socio-economic conditions of the area, it may be
proposed to employ mainly local people as workers. Much of the maintenance arrangements may also
be made with local companies and purchase of new parts from the local market.
4.6.7 Transport Linkage and Traffic
Impact: The vehicle from the project will increase car and two wheeler traffic load along the road
during peak hours. However, since present load is lean, increase in traffic load may not lead to traffic
congestion problem.
Mitigation Measures: As per the conceptual plan, the entrance to the project site is proposed along
the road. The available width of road provided shall have sufficient merging space for the vehicles
while meeting the road.
4.6.8 Energy Resources
Impact: During the operation phase of the project, electricity supply will be provided by State
Electricity Board. Mitigation Measures: To promote energy conservation, it is proposed to provide
the buildings with efficient energy consuming fixtures and maximize availability of natural light.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 148
CHAPTER 5: ANALYSIS OF ALTERNATIVES
5.1 INTRODUCTION
This chapter discusses the assessment of various options that may be available for different
components of the project in terms of environmental suitability. Lately, there are a number of
options available for the use of building materials, means of energy conservation and methods of
transportation. The various applicable options are thus evaluated for their suitability to project
and environment.
5.2 BUILDING MATERIALS
The choice of building materials plays an important role in terms of energy efficiency of the
building. The manufacture of building materials should also be assessed to ensure the use of
environment friendly and recycled/ recyclable construction materials.
5.2.1 Wall
Conventionally, sun burnt clay bricks are cemented in the construction of walls. The strength of
these construction materials cannot be compromised which will otherwise pose a threat to the life
and property of the occupants. However, presently, materials with similar properties are easily
available that are made of waste products, thereby reducing the waste burden and conserving
natural resources. Thus, the project proposes the use of the following for walls:
Brick and block products with waste and recycled contents such as fly ash (15 to 35%),
blast furnace slag (20 to 25%), sewage sludge, waste wood fibre etc.
Fly ash based lightweight aerated concrete blocks – flyash being a waste product of
thermal power plant poses the challenge of disposal. Hazardous in powder form, it is rendered
harmless when moulded as bricks. Fly ash-based lightweight aerated concrete
blocks are manufactured for walling and roofing purposes by mixing fly ash, quick lime, or
cement and gypsum with a foaming agent like aluminum powder
Fal-G products – are manufactured by use of two waste products being fly ash, calcined
gypsum (a byproduct of phosphogypsum or natural gypsum) along with lime.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 149
Perforated bricks
Materials proposed for use in the wall openings such as doors and windows include:
Precast thin lintels, use of Ferrocement-sunshade cum lintel etc.
Renewable timber
Steel manufactured from recycled content
Aluminum manufactured from verified recycled content
Saw dust based doors and window frames
Ferrocement shutters, PVC doors and windows, Rice husk boards, Natural fibre-
reinforced
Polymer composite door panels
The finishing for the openings will be by the use of Fly ash, Ceramic tiles, Terrazzo
floors.
5.2.2 Roof
The conventional material used for roofing is RCC, as it is suitable for longer spans. The
constituents of RCC, i.e. cement, sand, aggregate and steel are energy intensive materials and
high embodied energy content.
Alternately, it is proposed to use lightweight synthetic aggregates such as fly ash based
aggregates, which is suitable for manufacture of brick, blocks, and is good substitute for clinker
and natural aggregates. When pre-cast/aerated cellular concrete walling blocks and roofing slabs
are used in multi- storied structures, they reduce the weight, resulting in a more economical
design. They have high rating to fire resistance and provide better insulation and thus improved
energy efficiency. These are manufactured by the aerated cellular concrete manufacturing
process.
5.2.3 Insulation of Roof and wall
Roof will be insulated with required thickness with PUF or equivalent to achieve Roof U
Value. Window Glass will be double reflective type to minimize energy consumption. Roof/wall
insulation will be scope of Civil works.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 150
5.2.4 Superstructure
Structural frame of building comprises of footing, columns, beams and lintels, over which the
envelope of building is supported. A variety of metals are used in buildings. The major building
material used structurally is steel. Steel has a high-embodied energy and recyclable content, as
well as scrap value. Aluminum forms the second most common material used for roofing sheets,
window frames, and cladding systems, which has the highest recyclable content. Hence, bulk of
the metal needs for the building will be met by steel and aluminum.
Problem with RCC. The choice of cement will be:
Use of fly ash and/or blast furnace slag concrete: The amount of cement used in
concrete can be reduced by replacing a portion of the cement with coal fly ash (waste material
from coal burning power plants) and/or GGBF (ground granulated blast furnace) slag in
conventional mixes.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 151
Recycled aggregates: Recycled aggregates include crushed concrete, brick, glass, or
other masonry waste can also be used in conventional mixes
Lightweight concrete: Aluminum powder when added to lime reacts and form hydrogen
bubbles, and a lightweight cementation material is formed which could be used in conventional
mixes.
5.2.5 Roads and open spaces
Roads and open spaces consist of compound walls, grills, roads, sidewalks, parking lots, drains,
curbs, landscaped areas, street furniture, tree covers, and flowerbeds.
In line with environment friendly design it is proposed to provide:
Permeable paving- Permeable (porous) paving will be provided to control surface water
runoff by allowing storm water to infiltrate the soil and return to the ground water. The traffic
areas will however continue to be impermeable.
Gravel/crusher fines - Loose aggregate materials from masonry wastes will be used to
cover pedestrian surfaces.
Use of grass pavers on the road, parking and pedestrian areas to reduce the heat island
effect.
Use of steel in fencing, grills, tree covers, and benches and even in streetlights will be
replaced by bamboo in the parks and green landscaped areas.
5.2.6 Material of construction for plumbing and sanitary works
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 152
5.3 NATURAL HAZARD PRONE AREAS
The project site falls in Seismic Zone- IV. Special attention has been given to the structural
design of foundation, elements of masonry, timber, plain concrete, reinforced concrete, pre-
stressed concrete, and structural steel. All applicable guidelines (IS Codes) will be followed in
this regard to ensure structural safety of the building.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 153
5.4 ENVIRONMENT FRIENDLY BUILDING
As a responsible corporate, M/s. WTC NOIDA Development Company Pvt. Ltd. has proposed
to design and construct the Commercial Project in line with the requirements of Environment
friendly building. Care will be taken to achieve energy efficiency, water consciousness, etc. This
will be achieved through:
a. Minimal disturbance to landscape and site condition
The project aims to integrate the new development with the local existing surroundings. Efforts
are made to minimize on-site tree cutting by careful and detailed layout planning. Tree felling
will be undertaken only after receiving requisite permissions and under strict supervision. The
original landscape of the site has also been integrated with the design of the Commercial Project
such that there is no alteration in the site topography.
b. Resource Conservation and Environmental Friendly Building Materials
To reduce the ecological footprint of the development, use of recycled material for construction
and conserving natural resources is of primary importance. In this light, the use of recyclable
building materials has been proposed for various building materials. It is also proposed to reuse
building components, minimization of construction wastes etc.
The project is also committed towards conservation of water. This includes use of treated water,
rainwater harvesting, provision of low water flow fixtures and raising awareness on means of
water conservation.
c. Efficient use of Water and Water Recycling
The need for water conservation in the face of impending water crisis cannot be overemphasized.
The project will follow a three pronged management for water resource viz: water resource
development, minimize use of water and recycle water generated within the site.
Rainwater harvesting across the entire project area is proposed to recharge groundwater. A
detailed storm water drainage system and water harvesting procedures are proposed to achieve
this.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 154
The water demand is proposed to be brought down by the use of water efficient fixtures,
implement best management practices for water in both Commercial Project and horticultural
activities. An important means for achieving this is spreading awareness to the occupants for
generating water conservation awareness.
To reduce the freshwater demand of the project, waste water from the project will be treated in
an onsite STP and recycled treated effluent will be reused for landscaping, flushing, HVAC.
d. Use of Energy Efficient design and Eco-Friendly Equipment
The commercial project will be designed such that there is optimal solar energy utilization,
especially for natural light availability. Shading will be provided on sides that will otherwise
reduce the energy efficiency of the building. Energy conservation will be one of the focuses
during the planning, development, construction and operation stages.
Use of Renewable Energy
The electrical supply is largely dependent on thermal power plants that are largely responsible
for accelerating the phenomenon of global warming and consumption of limited natural
resources. It is of paramount importance to shift focus on other renewable sources of energy to
achieve sustainable development in the energy sector. The project area in S.A.S Nagar receives
adequate hours and intensity of sunlight for effective solar energy generation. Taking full
cognizance of the availability of natural sunlight and technology, the project proposes the use of
solar energy to reduce the power demand of the project.
Solar energy will be used for the use of renewable energy.
e. Indoor Air Quality for Human Safety and Comfort
To provide the occupants with a safe building is the primary responsibility of a developer. Indoor
pollution sources that release gases or particles into the air are the primary cause of indoor air
quality problems in homes. Inadequate ventilation can increase indoor pollutant levels by not
bringing in enough outdoor air to dilute emissions from indoor sources and by not carrying
indoor air pollutants out of the home. High temperature and humidity levels can also increase
concentration of some pollutants. Likewise, it is proposed to use all user friendly building
materials such as:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 155
i. The buildings will be painted with low VOC, ammonia free paints.
ii. Asbestos will not be used.
iii. Adequate ventilation will be provided in each unit and floor
iv. Adequate openings for sunlight to enter the building, thereby reducing chances of microbial
growth.
v. All building maintenance and cleaning materials will be kept in an isolated and well
ventilated room with restricted entry.
f. Effective Controls and Management Systems
It is proposed to establish a Management System that will comprise modern equipment as well as
an efficient team of maintenance staff.
i. Each tower as well as common area will be provided with fire alarm as well as water
sprinklers. All essential services such as lifts and water supply will be provided with power
back up.
ii. A security system for the entire ‘World Trade Centre’ Commercial project, will be provided
comprising intercom facility, closed circuit camera to the entrance and round-the-clock
manning.
iii. . The staffs’ vehicles will be provided with identification stickers while visitors’ vehicles
will be monitored through security guards at the entrances.
The project further proposes extensive green areas as avenues, parks and roadside plantations.
The plants not only serve various direct environmental facilities, but also have indirect positive
environmental impacts such as reduction in overall energy use in buildings.
5.5 COMMUNITY ISSUES
Apart from the site occupants, all efforts will be made to ensure that the exiting neighborhood is
not adversely affected by the project.
5.6 ENERGY CONSERVATION
To achieve conservation of energy, appropriate design of a building is of paramount importance.
Accordingly, it is proposed to incorporate the guidelines of Energy conservation Building Code,
2005 for the structures of the Commercial Project.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 156
Effective measures have been incorporated to minimize the energy consumption in following
manners:
• Use of LED lamps instead of GLS lamps commercial project.
• Use of LED instead of GLS lamps for Common area.
• T5 lamps are used instead of Normal Fluorescent lamps in Basements
• Using electronic ballast for Discharge Lamps
• Hot water system
Hot water for domestic use for Service Apartment will be provided through Heat Pumps.
Hot water temperature of 60C (140F) will be maintained to avoid grow of legionnaires
disease bacteria.
Solar Water Heating System will be provided to meet the Hot water requirement for Food
Court/Restaurant/Food Shop and pre heating for hot water system for Hotel/Service
apartment proposed.
It has been proposed 16.56 % energy savings to be achieved in the project
Table 5.1: Energy savings calculation
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 157
5.7 TRANSPORTATION
A well planned road network is proposed within the project premises as per NBC norms.
Adequate parking will be provided during construction phase to ensure that all heavy vehicles
visiting the site are parked within the site. There will be no parking on the public roads. The
movement of the vehicles will also be scheduled such that the peak hours are avoided.
In the operation phase, entry and exits will be from separate gates to minimize disturbance to the
approach roads to the project site. To avoid congestion of the approach roads, space will be
provided for vehicles waiting checking. Adequate parking is proposed as per norms to ensure
there is no parking along the roads.
In absence of detailed model split data for the Chandigarh city, collateral data from the
Chandigarh Master Plan- 2030 and RITES Comprehensive Traffic and Transportation plan were
considered in estimating the traffic patterns for the project.
Chandigarh Master Plan has recorded the present composition of traffic on roads at 80%
constituting of cars and two wheelers and also indicated that the vehicle ownership is high at 86
% of house- holds have car, two-wheeler or both.
Comprehensive Traffic and Transportation Plan of Chandigarh prepared by the RITES assumed
that the mass transport for the city would cater to the 54% of the total traffic trips that generated
for the year 2014 and that it would increase its share for the future years. Having accepted the
split of mass transport as 54% the balance 46% of the trips obviously shared by the Cars, Two
Wheelers and Taxis/ Cabs.
Having considering the collateral inputs from the above two traffic connected reports the model
split that likely to occur is tabulated in Table -5.2
Table 5.2: Mode of transport
Sl. No Mode Percentage 1 Mass transport 54 2 Cars 28
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 158
3 Two wheelers 12 4 Taxis/cabs 6 5 Total 100
Source : Based on collateral data from Chandigarh Master Plan & RITES report.
Traffic analysis Floor areas are the basis on which the traffic generated is estimated, but those activities that contribute to traffic is considered either in full or partially according to the occasion to which it is sought. Floor areas of traffic generating activities are shown at Table 5.3
Table 5.3 Gross floor areas of building activities
Sl.No. Activity Gross area sqm 1 0ffices 74930 2 Retail shops 11339 3 Multiplex 4005 4 Hotel 19633
Source: Architectural plan Critical Time for Traffic Morning peak being critical for offices , the same is considered for design purpose of traffic related issues. Evening peak is important but it will not effects the office functioning , it is only home based movement. Estimation of working force. Workers who contribute the morning peak traffic are analyzed from the building activities. Multiplex activity is not considered for the said peak event. About 50% of shop activity is considered for the morning peak. Table 5.4 shows the work force that contribute the morning peak hour and net area is considered as 80% of gross area and 10 sqm/ per is taken as occupancy rate.
Table 5.4 Workers Contribute To Morning Peak
Sl.No. Activity Block
Gross area sqm
Net area sqm
Estimated Workers
Contribution to Morning peak
1 Offices 74030 59224 5922 5922 2 Shops 11339 9071 907 453 3 Total 85369 68295 6829 6375
Source: NBC 2005 on area/ worker Effect of Serviced Apartments in the complex.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 159
One of the theme of integrated land use planning is that the traffic on roads would be reduced if some of the residential requirement is met within the complex. Assuming that the occupants of the hotel/serviced units work in the offices then the traffic generated would get reduced. It is estimated that about 10% of trips from the offices category would be discounted on this principle. Table 5.5 shows the final traffic generating trips after discounting.
Table 5.5: Forecasted Trips Sl.No Activity
category Estimated workers Discounted
trips due to hotel(10%)
Trips used for forecasting
1 Offices 5922 592 5330 2 Shops 907 - 907 3 Total 6829 592 6237 Trips at dis-aggregate level. By adopting the model split parameters that were discussed in chapter 1, the possible volume of person trips are calculated. The table 5.6 shows the person trips activity wise as well as vehicle wise.
Table 5.6: Person Trips vehicle category –wise
Activity. Person trips (100%)
Mass transport share (54%)
Car (28%)
Two wheeler (12%0
Taxi/cab (6%)
Total of private modes(46%)
Offices 5330 2878 1492 640 320 2452 Shops 543 293 152 65 33 250 5873 3171 1644 705 353 2702
Source : based on RITES report & Chandigarh master Plan Vehicular Trips . Leaving aside the mass transport trips which would be taken care of by the public authorities the vehicular trips by private vehicles are analyzed hereunder. Vehicular traffic is arrived by adopting the occupancy levels.
Table 5.7: Vehicular Traffic in the Morning Peak Hour
Sl.No Vehicle Trips Occupancy factor Total Vehicle Trips
1 Cars 1644 1.5 1096 2 Two wheelers 705 1.2 587 3 Taxi/cab 353 4.0 88
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 160
Total 2702 1771 Source: IRC: 64 1990 Traffic Estimated by another method ( ITE ) Traffic generations are also estimated based on the traffic generation rates provided by the Institute of Traffic Engineers ITE, time to time published in their Manuals. Table shows the PM peak generation as per the gross floor areas of the project. In this calculation Multiplex traffic is included as it is in the evening period. The evening peak hour traffic is usually more than the morning and as such the aforesaid projection is in tune with the accepted procedure. The traffic estimation is therefore crosschecked and found to be satisfactory.
Table 5.8: PM peak generation
Sl.no Activity Gross Area sqm
Gross area sft
Trip generation Rate per 1000sft .hr.
PM peak Traffic hr.
1 Offices 74032 796584 1.49 1185 2 Shops 11339 122007 3.71 453 3 Multiplex 4005 43094 4.91 211 1849 Source: Based on Trip Generation Manual, 9th edition, ITE
Traffic at site in Passenger Car Units (PCU) The morning peak hour traffic that hit the project complex would be 1478 PCU. Since the project is located very close to a four-way junction the destined traffic to the site enters through the cut available in front of the project. A part of front segment of the service road to the project could reach congesting condition in the morning peak. Sl.no. Vehicle type Vehicles Pcu conversion
factor Volume in PCUS
1 Cars 1096 1.0 1096 2 Two wheeler 587 0.5 294 3 Taxi.cab 88 1.0 88 4 Total 1771 - 1478 IRC : 64: 1990 on conversion factors
Traffic Carrying Capacity of the Access road to the project.
As the access road is said to be 50 ft or 15 m wide road its carriage width could be 3 lane
therefore it can carry the peak traffic load. Volume – Capacity ratio indicate a fairly clear state
of road performance against traffic flows on it. V-C categorizes the level of service ranging
from A to E from free flow to extent of congestion . The volumes in this case is 1478 pcus.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 161
The capacity of the access road is 2000 pcus. The V/C ratio for the road is 0.739, . This
gives a level of service of B which is without congestion and graded to have free flow.
Surface movements and Entry& Exit .
As per the road configuration at the project there is least possibility of traffic entering from the
rear road. High proportion of traffic enter from the front arriving from all four sides of the
junction. About 1800 vehicles would be coming to enter in to the parking and drop off. The
traffic would enter the premises through the internal road between commercial complex and the
hotel. Almost 50% of it enter in to the basement and the other 50% go to MLCP. Therefore
entry will be from the front side.
It makes traffic flow hassle free if all the exits are proposed towards the rear side road. Therefore
the exit will be to the rear side road.
This arrangement will also avoid multiple check points.
The arrangement also makes the surface vehicular movement hassle free straight forward.
Entry and Exit Ramps.
Vehicular Loads on ramps :
Basement ramps
Subject to final figures of parking the basement to have 540 ECS of single stack parking and if
upgraded to double- stack parking it would increase to 1000ECS. Each ramp can discharge 500
units per hour. This is at highest possibility. Therefore two ramps are adequate.
MLCP ramps
Similarly MLCP parking figures for each level comes to 163 ECS. Total count would be 815
units as the ramps are on multi- levels the discharge capacity would be limited to about 400
units
However it require minor changes for vehicular ramps for basement and MLCP.
The following suggestions are made in view of circulation and capacity requirements 1. The present descending ramp of basement be converted in to two-lane ramp of width 8 mtr (
front side one)
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 162
2. Basement exit ramp from hotel side to remain as it is.
3. Another exit ramp for basement to rear side road would be better.
4. Ascending ramps for MLCP will be two-lane, up to third level and from third level to 5th level it
will be single with.
5. Entry point of ascending ramp will be from inside the building as was shown in earlier dwg as it
facilitates security check space as well as waiting space to enter in rush hours.
6. Descending ramps for MLCP will be one lane width down to 3rd level and from 3rd level to rear
side road level with two-lane width.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 163
CHAPTER 6: ENVIRONMENTAL MONITORING PROGRAM
6.1 INTRODUCTION
The purpose of the monitoring programme is to ensure that the specified mitigation measures
defined in the EMP are complied with and leads to the desired benefits for the target area and
its population. To ensure the effective implementation of the EMP and gauge the efficiency
of the mitigation measures, monitoring will be undertaken both during the construction and
operation period of the project.
6.2 PERFORMANCE INDICATORS (PIs)
The physical, biological and social components are of particular significance to the project is
as listed below:
Air quality
Water quality
Noise levels
Solid Waste Management
Replantation success / survival rate
Of these, the following are selected as the Performance Indicators (PIs) and will be
monitored, since these are well known and comparative data series exist:
Air Quality
Noise levels
Water Quality
Flora
To ensure the effective implementation of the mitigation measures and environmental
management during construction and operation phase of project road, it is essential that an
effective Environmental Monitoring Plan be designed and followed as given in Table 6.1.
6.2.1 Ambient Air Quality (AAQ) Monitoring
Ambient air quality parameters recommended for monitoring with regard to constructional
activities are PM, CO, SO2, and NO2. Monitoring will be carried out twice a week for one
month in each season during construction phase in accordance to the National Ambient Air
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT CHAPTER 6
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 164
Quantity Standards. The locations with the pollution parameters to be monitored are detailed
out in the Environmental Monitoring Plan (Table 6.1).
6.2.2 Noise Level Monitoring
The measurements of noise levels will be carried out at all designated locations in accordance
to the ambient Noise Standards. Noise level will be monitored on twenty-four hourly bases.
Noise should be recorded at “A” weighted frequency using a slow time response mode of the
measuring instrument. The measurement location, duration and the noise pollution
parameters to be monitored are detailed in the Environmental Monitoring Plan (Table 6.1).
6.2.3 Success of Plantation
To ensure proper maintenance and monitoring of the proposed plantation activities, a regular
survey of the survival rate of the planted trees will be done.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 165
Table 6.1: Environmental Monitoring Plan
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Ground Water
Quality
Construction
Stage
Drinking water parameters Drinking water standards
(IS 10500)
Sites Half yearly
Operation
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Sites Once every year during the
dry season
Drinking water Construction
Stage
Drinking water parameters Drinking water standards
(IS 10500)
Supply water after
treatment
Half yearly
Operation
Phase
Drinking water parameters Drinking water standards
(IS 10500)
Supply water after
treatment
Half yearly
Treated
wastewater
Operation
Phase
pH, BOD, COD, TDS ,
TSS, DO,
General Standards for
discharge of effluents
Outlet of the Sewage
Treatment Plant
Every three months during
the project life cycle
Air Construction
Phase
PM, SO2, NO2, CO National Ambient Air
Quality Standards
1. Project Site
2. Saneta
3. Naugiari
4. Shekhan
5. Naraingarh
Continuos 24-hourly,
Half Yearly
Operation
Phase
PM, SO2, NO2, CO, National Ambient Air
Quality Standards
Project Site
Continuous 24-hourly,
HalfYearly
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT CHAPTER 6
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 166
Environment
Component
Project stage Parameter Standards Location Duration / Frequency
Noise Construction
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
1.Project Site
2. Saneta
3. Naugiari (Near
Primary School)
4. Shekhan
5. Naraingarh
One day hourly
measurement, Half Yearly
Operation
Phase
Noise Level in dB (A) As per Ambient Noise
Standards
Project site One day hourly
measurement, Half Yearly
Rainwater
harvesting
Operation
Phase
Inspection of storm water
drains and rainwater
harvesting pits
Design parameters Project site Prior to monsoons
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT CHAPTER 6
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 167
6.3 DATA MANAGEMENT
The monitoring will be carried out through MoEFCC/ NABL approved laboratory. All results
and records will be maintained at the project site and submitted to the SPCB as per norms.
6.4 REPORTING SCHEDULE
The environment management cell will be responsible for timely conduct of the monitoring
activities. The results of the analysis will be intimated to the project head. Any anomaly in
test results will be investigated into and proper corrective actions will be undertaken.
A complaint register will also be maintained to note any complaints from the staff and
visitors in the project or any other stakeholder.
To assess whether the implemented EMP is adequate, periodic environmental audits will be
conducted by the GMADA. These audits will be followed by Corrective Action Plans (CAP)
to correct various issues identified during the audits.
6.5 BUDGETARY IMPLEMENTATION FOR EMP
Environment management cost includes the cost for Environmental technology up gradation,
environment monitoring & Operation and maintenance. Cost for the EMP will be approx. Rs
107.16 lacs towards the capital investment cost. The budgetary cost estimate for the EMP is
given in Table No.6.2.
Table 6.2: Expenditure on Environmental Matters
Description Capital Cost INR Lakh)
Recurring Cost (INR Lakh)
STP 62.7 15.67 RWH 12 3 Solid waste management 7.75 1.93 Green belt development 5.71 1.42 Monitoring for air, water, noise & soil 9 9 Other as , solar lights, solar hot water systems 10 2.5
Total 107.16 33.52
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 168
CHAPTER 7: ADDITIONAL STUDIES 7.0 INTRODUCTION
This chapter broadly looks at various aspects related to disaster management and resource
conservation.
7.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN
Proposed ‘World Trade Centre’ commercial project will encompass the lives of a large number
of people. It involves installation of various structures to meet the comfort and needs of its users
but may also serious threat to the occupants in case of an accident. It thus becomes necessary to
carry out a risk assessment and disaster management plan for the project.
7.1.1 Risk Hazard & its control measures
It is attempted to plan and construct the buildings following all safety norms. However, it is not
always possible to totally eliminate such eventualities and random failures of equipment or
human errors. An essential part of major hazard control has therefore, to be concerned with
mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed
table showing activities during construction and operation phase along with mitigation measures
are given in Table 7.1.
Table 7.1: Activities during construction and operation along with mitigation measures
HAZARDS ASSOCIATED WITH
ACTIVITIES
(During Construction & Operation)
CONTROL/MITIGATION MEASURES
Manual Handling
- Strains and sprains due to incorrect lifting
by labour
- too heavy loads
-Twisting - bending - repetitive movement -
- Exercise/warm up
- get help when needed
- control loads
- rest breaks/no exhaustion
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 169
body vibration.
- no rapid movement /twisting/ bending /
repetitive movement
- good housekeeping.
Falls - Slips - Trips
- Falls on same level
- falls to surfaces below
- poor housekeeping
- slippery surfaces
- uneven surfaces
- poor access to work areas climbing on and
off plant
-
- Good Housekeeping
- tidy workplace
- guardrails, handholds, harnesses, hole cover,
hoarding, no slippery floors/trip hazards
- clear/ safe access to work areas
- egress from work areas
- dust/water controlled
- PPE.
Fire
- Flammable liquids/Gases like LPG, Diesel
Storage area and combustible building
materials
- poor housekeeping
- grinding sparks
- Open flames, absence of Fire hydrant
network.
- Combustible/flammable materials properly
stored/used
- good housekeeping
- fire extinguishers made available & Fire hydrant
Network with reserve Fire water (As per NFPA
Code)
- Emergency Plan in case of Fire or collapse of
structure.
Absence of Personal Protective
Equipment
- Lack of adequate footwear
- head protection
- hearing/eye protection
- respiratory protection
- gloves
-goggles.
- Head/face
- footwear
- hearing/eye
- skin
- respiratory protection provided
- training
- maintenance
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 170
Defective or wrong Hand Tools
- Wrong tool
- defective tool
- struck by flying debris
- caught in or on
- missing guards
- Right tool for the job
- proper use of tools
- good condition/ maintenance guards
- isolation/ proper demarcation of work space
- eye/face protection
- flying debris controlled
Electricity
- Electrocution
- overhead/underground services
- any leads damaged or poorly insulated
- temporary repairs
-no testing and tagging
- circuits overloaded
- non use of protective devices.
- Leads good condition and earthed
- no temporary repairs
- no exposed wires
- good insulation
- no overloading
- use of protective devices
- testing and tagging
Scaffolding
- Poor foundation
- lack of ladder access insufficient
planking
- lack of guardrails and toe boards
- insufficient ties or other means
- all scaffolds incorrectly braced or
stabilized to prevent overturning.
- All scaffolds correctly braced and
stabilized
- 3:1 height to base ratio
- firm foundation, plumb and level
- ladder access provided and used
- proper platform (3 planks/675 mm)
- planks secured
- guardrails and toe boards
- 900mm to 1100mm high, within 200mm of
working face, mid-rail.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 171
Ladders
- Carrying loads
- not secured against dislodgement
- defective ladders
- not sufficient length
- wrong positions
- Incorrectly placed (angles, in access
ways, vehicle movements.
- Secured against movement or footed
- ladders in good condition
- regularly inspected
- extend 1m above platform
- 4:1 angle
- out of access ways, vehicle movements
- not carrying loads
- 3 points of contact
- no higher than 3rd step down
- use for access only, not working platforms
Excavations
- Trench collapse
- material falling in undetected underground
services
- falls
- Hazardous atmosphere struck by traffic
and mobile plant.
- Soil stability known
- no water accumulation
- existing services known
- material 600mm from edge
- clear of suspended loads
- hardhats/PPE
- ladders
- public protection
– atmospheric testing
- traffic controls
- Emergency Plan.
Gas Cutting and Welding
- Fire
- welding flash, burns, fumes,
electrocution in wet conditions
- flashback in oxygen set, leaking
cylinders, acetylene cylinders lying down
- Welding flash and burns controlled with
PPE and shields
- fumes controlled with ventilation and PPE
(in good condition and properly positioned),Gas
cylinders be kept upright & secured position
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 172
- Poorly maintained leads.
(properly tied)
- Combustible materials to be kept at
secured place to avoid fire & Fire Extinguishers to
be kept in fire prone area with training to people
for its use.
Noise
- Unknown noise levels
- known noise levels over 85 decibels
- Levels below 85 decibels
- Proper protection.
Falling Material
- Fall during carrying/Lifting
materials- dislodged tools and materials
from overhead work areas.
Materials to be secured
kept away from edge
toe boards
Use of hard hats.
Craneage & Lifts
- Display of carrying capacity i.e. load (No.
Of person), incorrectly slung, defective
lifting equipment, unsecured loads, craning
in close proximity to building people and
plant
- falls
- falling materials.
- Periodic testing by competent authority
- correctly slung/secured loads, lifting equipment
good condition
- use of proper hand signals
- falls while unloading controlled.
Visitors Presence at site
- Falls
- struck by dropped materials
- road accidents
- insufficient hoarding or fencing
- pedestrian access past site
- mechanical plant movement on and
off site.
- Sufficient hoarding
- fencing and barricades
- safe pedestrian access past site traffic
management for loading and delivery
- construction separated from occupied areas
of projects.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 173
7.1.2 Emergency Response Plan (ERP)
The overall objective of an Emergency Response Plan (ERP) is to make use of the combined
resources at the site and outside services to achieve the following:
1. To localize the emergency and if possible eliminate it;
2. To minimize the effects of the accident on people and property;
3. Effect the rescue and medical treatment of casualties;
4. Safeguard other people;
5. Evacuate people to safe areas;
6. Informing and collaborating with statutory authorities;
7. Initially contain and ultimately bring the incident under control;
8. Preserve relevant records and equipment for the subsequent enquiry into the cause and
circumstances of the emergency;
9. Investigating and taking steps to prevent reoccurrence
The ERP is therefore related to identification of sources from which hazards can arise and the
maximum credible loss scenario that can take place in the concerned area. The plan takes into
account the maximum credible loss scenario - actions that can successfully mitigate the effects of
losses/ emergency need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Main hazards identified for the project include hazards pertaining to fires in buildings and fire in
diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in
the following section.
7.2 RESPONSE IN CASE OF EARTHQUAKE
Response Procedures for Occupants
If indoors:
1. Take cover under a piece of heavy furniture or against an inside wall and hold on.
2. Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to
leave the building because objects can fall on you.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 174
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay
there until the shaking stops.
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses,
or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps
that might have been damaged by the quake.
After the earth quake
1. After the earthquake be prepared for aftershocks.
2. Although smaller than the main shock, aftershocks cause additional damage and may bring
weakened structures down. Aftershocks can occur in the first hours, days, weeks, or even months
after the quake.
Help injured or trapped persons.
1. Give first aid where appropriate. Do not move seriously injured persons unless they are in
immediate danger of further injury. Call for help.
2. Remember to help those who may require special assistance--infants, the elderly, and people
with disabilities.
3. Stay out of damaged buildings.
4. Use the telephone only for emergency calls.
Response Procedure for Emergency Team
1. Formulate an Emergency Response Team for earthquake response.
Using the public address system, inform residents of response procedures discussed above.
2. Inform the necessary authorities for aid.
3. Ensure no person is stuck beneath any debris, in case of a structural failure.
4. Ensure that all occupants standing outside near the buildings are taken to open areas.
5. Ensure that the first aid ambulance and fire tender vehicles are summoned if necessary.
6. Inform the nearby hospitals if there are any injuries.
7. Check the utilities and storage tanks for any damage.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 175
7.3 RESPONSE FOR LPG LEAKAGE
1. The affected area should be evacuated and cordoned off immediately
2. Initiate an Emergency Response Team for LPG leakage.
3. Shut down the main valves in the gas bank.
4. Ensure that only concerned personnel are present in the affected area and all other personnel
and visitors are moved to the nearest assembly points.
5. Rescue trapped personnel, also check if any personnel are unconscious in the area and
immediately move them outside and provide first aid. Ambulance should be summoned to take
injured personnel to the nearest hospital.
6. Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked
gas.
7. Source of leakage to be traced and isolated from all the other areas. And if required use
pedestal fans to bring down the gas concentration.
8. In case of a fire follow the instructions in case of fire.
7.4 RESPONSE IN CASE OF FIRE
1. Required response during in the event of a fire should be described in signs located in the
lobby.
2. On sighting a fire, it should be immediately informed to the environment manager
giving the exact location and type of fire in detail.
3. Initiate the Emergency Response Team for fires.
4. If the fire is small, engage in extinguishing the fire using the nearest fire extinguisher.
5. Guide the Emergency Response Team staff to the emergency assembly point.
6. The Emergency Response Team should immediately inform the nearest dispensary and
security force. If required a fire tender should be summoned.
7. The response team should immediately move to the point of fire and take all necessary steps to
stop the fire. If the fire is not controllable and spreads then the manager in charge should inform
the district authorities and call for external help.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 176
8. The Emergency Response Team will provide immediate relief to the injured residents at the
scene of incident. Any injured persons should be evacuated on priority to the dispensary or one
of the nearest hospitals based on their condition.
Instructions for occupants
1. Get out of buildings as quickly and as safely as possible.
2. Use the stairs to escape. When evacuating, stay low to the ground.
3. If possible, cover mouth with a cloth to avoid inhaling smoke and gases.
4. Close doors in each room after escaping to delay the spread of the fire.
5. If in a room with a closed door.
6. If smoke is pouring in around the bottom of the door or if it feels hot, keep the door closed.
7. Open a window to escape or for fresh air while awaiting rescue.
8. If there is no smoke at the bottom or top and the door is not hot, then open the door slowly.
9. If there is too much smoke or fire in the hall, slam the door shut.
10. Stay out of damaged buildings.
11. Check that all wiring and utilities are safe.
A state of the art firefighting system is proposed for the project to prevent and control fire
outbreaks. The firefighting system will consist of portable fire extinguishers, hose reel, wet riser,
yard hydrant, automatic sprinkler system, and manual fire alarm system. The ‘World Trade
Centre’ Commercial project buildings will also be provided with automatic fire detection and
alarm system.
7.5 RESOURCE CONSERVATION
The project will lead to utilization of various natural resources. As an environmentally
responsible corporate, the developers endeavor to conserve these resources by judicious
management and recycling and strive to build up these resources where possible.
Limited withdrawal of groundwater: The water during operational phase will be supplied by
GMADA.
Reduced use of water: To further minimize the use of available freshwater, various low flow
fixtures may be provided such as Low flow flushing systems, sensor based fixtures, , tap
aerators. Awareness will also be spread amongst the residents on the following lines:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 177
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Watering of lawn or garden during the coolest part of the day (early morning or
late evening, hours) when temperature and wind speed are lowest. This reduces
losses due to evaporation.
Planting of native and/or drought tolerant grasses, ground covers, shrubs and
trees. Once fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for
more than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the
water and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning
systems;
Equipping spring loaded shutoff nozzles on hoses;
Installation of float-controlled valve on the make-up line, closing filling line
during operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water;
Treatment and Recycling: The wastewater generated from the sites will be treated in an on-site
Sewage Treatment Plant. This will enable the treated wastewater to be used for flushing and
landscaping thereby reducing the requirement of freshwater for these purposes.
Rainwater harvesting: The increased hard surface increases the runoff as compared to the
otherwise barren land. It is proposed to harvest this rainwater runoff that will recharge the
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 178
groundwater resource while reducing the burden of storm water management of the city and
eventually natural water bodies. Apart from the open spaces, it is proposed to harvest the roof top
rainwater. The storm water will be treated through an oil and grease trap and allowed to flow
through layers of sand and gravel for filtration prior to reaching the water table, to avoid any
possibility of groundwater contamination.
Construction materials: Various kinds of natural construction materials such as sand, gravel etc
will be used. It is proposed for prior estimation of required quantities of these materials and
procurement only as per requirement. This will also result in cost-efficiency. Excavated soil from
the project site will be used within the site to the extent feasible. Excess soil will be made
available to the construction sites, as per need.
Energy: To conserve the energy resources, good practices will be followed during the
construction phase such as turning off lights and equipments when not in use, ensuring fuel
efficiency of motors and vehicles through proper maintenance and minimal work at night. The
principles of energy conservation will also be embedded in the buildings through use of energy
efficient fixtures, maximum availability of natural light and use of solar energy for street
lighting.
7.6 RESETTLEMENT AND REHABILITATION
The project will not result in displacement of any local population and hence, does not require a
resettlement and rehabilitation.
7.7 SOCIAL IMPACT ASSESSMENT
Social impact assessment has been discussed in Chapter 3 and Chapter 4.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 179
CHAPTER 8: PROJECT BENEFITS
8.1 GENERAL
The project site is situated at Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab. The
project will be developed on a total plot area of 32,512.44m2.
The salient features of the project include:
Offices
Retail/Shops
Food Court
Multiplex
Service Apartments
8.2 PHYSICAL INFRASTRUCTURE
The proposed project will help in meeting the growing needs of commercial facilities of the area.
It will provide state-of-the-art service apartments and encompasses world class facilities like
offices, Retail, Shop, Food court, multiplex, etc. Care has been taken to provide the occupants
and visitors with world class facilities.
8.3 SOCIAL INFRASTRUCTURE
A project of this scale sets overall development of the region, maintenance of existing
surrounding roads, power and water supply.
8.4 ECONOMIC BENEFITS
The project will entail positive impacts on the local economy. The construction phase of the
project will engage a large number of construction workers, skilled, semi-skilled or unskilled.
The workers will also be provided with facilities such as drinking water, sheds for resting,
medical aids, and aid in children’s education.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 180
The project will provide employment opportunities to approx. 8000 persons during the operation
phase.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 181
CHAPTER 9: ENVIRONMENTAL MANAGEMENT PLAN
9.1 INTRODUCTION
Identification and prediction of impacts further needs to suggest the mitigation measures
which would play a vital role in prevention of environmental degradation during construction
and operational phase of the proposed ‘World Trade Centre’ commercial project. Therefore,
EMP forms an imperative part of EIA process.
The Environmental Management plan is a site specific plan developed to ensure that the
project is implemented in an environmentally sustainable manner where all contractors and
subcontractors, including consultants if any, understand the potential environmental risks
arising from the project and take appropriate actions to minimize those risks. EMP also
ensures that the project implementation is carried out in accordance with the planned design
and by taking appropriate mitigates actions to reduce adverse environmental impacts during
project’s life cycle.
The project will create certain inevitable impacts, mainly during construction phase, although
within permissible limits as mentioned in Chapter 4 and can be reduced significantly with the
help of effective implementation of a well-designed EMP. The potential environmental
impacts, which need to be regulated, are mentioned below:
Air pollution due to the emission of particulate matter and gaseous pollutants from
operation of D.G. Sets during power failure and vehicular movement;
Noise pollution due to various noise generating equipment as well as vehicular
movement;
Water resource management to ensure continuous water supply.
Wastewater generation from sanitary/domestic activities; and
Generation of municipal solid wastes from residences, maintenance of roads, parks,
common areas including constructional, electrical and plumbing wastes.
Energy conservation methods
Maintenance of Building Management Systems and emergency aids.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 182
To ensure better environment in & around the project site, effective EMP is developed
separately for construction and operational phase.
9.2 ENVIRONMENTAL MANAGEMENT STRATEGIES
Strategy for environmental management in construction work should be based on three-
pronged approach comprising of:
Pollution prevention.
Pollution control.
Protection of pollution recipients.
9.2.1 Topography and Physiography
During the development, construction and operation phase of the project, no significant
impact is anticipated on local or regional topography and Physiography; hence no
management plan is required. It is however proposed to carry out extensive turfing with local
species apart from proposed plantations and greens.
9.2.2 Soil
Development & Construction Phase
During the construction phase, various kinds of wastes are generated that will be disposed in
varied ways. The following measures will be taken to prevent soil contamination at site and
ensure waste management:
Vegetation and top soil management:
Plantation as proposed shall be started at the earliest.
The top soil will be stripped from constructional areas and stockpiled for later reuse in
landscaping.
Promote use of organic fertilizers.
Construction of erosion prevention troughs, as deemed necessary.
To prevent the erosion of excavated loose soil produced as a result of excavation, site
preparation activities and excavation work would be undertaken during dry season after
monsoon is over.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 183
Construction Debris:
Fuel and oil would be stored in cement lined storage yard and handled carefully to
prevent soil contamination through leakage or spillage.
All metal, paper, plastic wastes, debris and cuttings would be collected from site as
soon as particular construction activity is over.
During construction of flexible pavement, bitumen wastes will be collected (if any)
and disposed in environmentally sound manner.
The number, frequency and area of movement of heavy machinery will also be
restricted.
Recycling of construction wastes into aggregates for use in the project site.
Used oil from DG Sets should be stored in HDPE drums in isolated covered facility
and disposed-off as per the Hazardous Wastes (Management & Handling) Rules, 1989.
Wastes from the labour camps will be collected and disposed as per the existing
practices in the site.
Operation Phase
To prevent soil contamination at site, the most important aspect is to manage the solid wastes
that will be generated during the operation phase. The Environmental Management Plan for
the solid waste focuses on three major components during the life cycle of the waste
management system i.e. collection, transportation, and treatment or disposal.
Collection and segregation of wastes
Solid waste generated from project would be collected and segregated into
decomposable, recyclable and inert wastes.
Decomposable wastes will be decomposed and converted to manure to be used for
horticulture.
Recyclable waste would be sold to vendors.
Inert waste which comprises a very small amount of the total solid waste generated
would be temporarily stored within the project premises.
Waste bins would be placed at the strategic locations such as inter section of internal
roads, parks, common places, etc.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 184
To minimize littering and odors, waste will be stored in well-designed containers/
bins that will be located at strategic locations to minimize disturbance in traffic flow.
Care would be taken such that the collection vehicles are well maintained and
generate minimum noise and emissions. During transportation of the waste, it will be covered
to avoid littering.
Hazardous & bio medical Waste will be handled as per Hazardous Waste & Bio
Medical Waste Management Act.
Transportation
Only the non-recyclable and non-biodegradable waste will be transported to the designated
disposal site. The segregation, transportation and disposal of wastes will be done through a
local authorized agency that will take care of the solid waste management of the project.
Figure 9.1 Waste Management Flow Diagram (Operation Phase)
Disposal With regards to the disposal/ treatment of waste, the project proponent will take the
services of a local authorized agency.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 185
9.2.3 Hydrology
9.2.3.1 Surface water Hydrology
Development & Construction Phase
To ensure adequate passage of the storm water as per the regional drainage pattern, water
channels will be provided. It is also suggested to avoid excavation during monsoons.
Chemicals such as paints, varnishes and oil/ grease will be stored under covered and
cemented areas. Wash offs containing these chemicals will be drained into impervious trains
for disposal as hazardous wastes.
Operation Phase
It is proposed to provide rainwater harvesting across the project site. The roof tops of
buildings will also be connected to the rainwater collection system. This will not only reduce
the pressure of storm water management system of the city and eventually the water bodies
but also recharge groundwater.
9.2.3.2 Ground water Hydrology
Development & Construction Phase
The water requirement during the construction period will be from private water tanker. The
following are also proposed to further reduce the demand of freshwater:
Curing water will be sprayed on concrete structures and free flow of water not
allowed.
After liberal curing on the first day, all concrete structures will be painted with curing
chemical to save water to stop daily water curing hence save water.
Concrete structures will be covered with thick cloth/gunny bags and then water
sprayed on them to avoid water rebound and ensure sustained and complete curing.
Pools will be made using cement and sand mortar to avoid water flowing away from
the flat surface while curing.
Water ponding will be done on all sunken slabs. This will also highlight the
importance of having an impervious formwork.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 186
Operation Phase
It is proposed to conserve groundwater resources through the combined means of water
resource development, minimized water consumption and reuse of treated water to reduce
freshwater demand.
Water Resource Development
Keeping in view the rainfall, storm water drainage system will be developed to carry the
runoff.
The storm water disposal system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary
area and the time required for such flow to reach the drains. The drains shall be located near
the carriage way along either side of the roads. Taking the advantage of road camber, the
rainfall run off from roads shall flow towards the drains. Storm water from various buildings
shall be connected to adjacent drain by a pipe through catch basins. 8 Rainwater harvesting
pits are proposed for recharging the ground water level of the area. Rain water harvesting
details are given in Chapter 2.
Storm water management system
Since the storm water on site will be harvested for ground water recharge, proper
management of this resource is necessary to prevent contamination. Hence, regular inspection
and cleaning of storm drains shall be carried out. Use of fertilizers and pesticides will be
avoided prior to monsoons. Clarifiers or oil/ water separators shall also be installed in all the
parking areas.
Minimal Water Consumption
To reduce the water consumption, awareness along the following lines will be spread
amongst the management and maintenance team:
Installation of water meters conforming to ISO standards at inlet and outlet point of
water supply.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 187
To further lower the water consumption, options of low flow flushing systems, sensor
based fixtures, , and tap aerators, etc will be explored.
Leak detection
Use of low-volume, low-angle sprinklers for lawn areas.
The message of water conservation will be spread amongst the residents through awareness
campaigns and pamphlets. Following tips shall be provided to the residents for conserving
water.
Timely detection and repair of all leakages;
Turning off tap while brushing teeth;
Use of mug rather than running water for shaving;
Avoiding/minimizing use of shower/bath tub in bathroom;
Turning off faucets while soaping and rinsing clothes;
Using automatic washing machine only when it is fully loaded;
Avoiding use of running water while hand-washing;
Avoiding use of running water for releasing ice tray ahead of time from freezer;
Turning off the main valve of water while going outdoor;
Avoiding use of hose for washing floors; Use of broom may be preferred;
Watering of lawn or garden during the coolest part of the day (early morning or late
evening, hours) when temperature and wind speed are lowest. This reduces losses due to
evaporation.
Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees.
Once fully grown, they need not to be watered frequently.
Avoiding over watering of lawns. Good rains eliminate the need for watering for more
than a week.
Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
Avoiding installation or use of ornamental water features unless they recycle the
water and avoiding running them during drought or hot weather;
Installation of high-pressure, low-volume nozzles on spray washers;
Replacement of high-volume hoses with high-pressure, low-volume cleaning systems;
Equipping spring loaded shutoff nozzles on hoses;
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 188
Installation of float-controlled valve on the make-up line, closing filling line during
operation, provision of surge tanks for each system avoid overflow;
Washing vehicles less often, or using commercial car wash that recycles water.
Re-use of treated wastewater
Treated wastewater from the site will be recycled for landscaping, flushing and HVAC/DG
Set cooling to further reduce demand of freshwater resources. This will be achieved by
treating the wastewater generated from the project in an onsite Sewage Treatment Plant of
(627 KLD). The details of STP are given in Chapter 2.
Surface water Quality
Development & Construction Phase
To mitigate the impacts of soil erosion during first rain and generation of wastewater from
construction labour camps, the following measures are proposed;
Excavation during dry season and proper management of excavated soils,
Clearing all debris from site as soon as construction is over,
Provision of proper hutment and toilet facilities for construction labour,
Proper disposal of wastewater generated at site.
Ground water Quality
Development and Construction Phase
To ensure against any groundwater pollution through leaching of soil, solid waste
management plan ensuring timely collection of wastes will be followed. The collected wastes
will be stored at designated area and disposed as per the standard procedures in line with the
statutory requirements.
Operation Phase
The ground water pollution can arise from improper waste handling or by recharge of
groundwater through contaminated storm water. A well planned solid waste management as
discussed in chapter 2 is proposed for the operation phase that will ensure against any
chances of soil or groundwater pollution on this account.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 189
Storm water collects dirt and garbage along its flow. Contamination of this water with spilled
oil/ grease is especially of concern when recharging is proposed. Hence, preliminary
treatment for oil, grease and filtration through layers of sand and gravel is proposed prior to
recharge of the groundwater.
Landscaping water enters the soil and finally the groundwater. It is thus of utmost importance
that only clean water is used for horticulture purposes. The water from the households will
contain significant amounts of detergent and soap that is undesirable for plants, soil and in
groundwater. Hence, it is proposed to treat wastewater from the sites up to tertiary level, and
be used for landscaping only thereafter regular monitoring of treated wastewater shall be
carried out to ensure that all parameters are within acceptable levels.
9.2.4 Air Quality
Development and Construction Phase
The construction phase of the project will continue for about 5-6 years. It will cause
marginal, temporary impact on ambient air quality from constructional activities, unloading
of construction materials, cement, soil and vehicular movement etc. The main pollutant of
concern is PM 2.5& PM 10 (dust). Likewise, following mitigation measures will be adopted
during this phase to mitigate the impacts on ambient air:
Loading and unloading of cement and other material in covered shed.
Providing dust suppression system in unloading area (as per requirement).
Developing avenue and curtain plantation on the internal roads and peripheral
plantation around the site to protect the movement of dust and other pollutants.
Cover scaffolding, hosing down road surfaces and cleaning of vehicles.
On-Road- Inspection for black smoke generating machinery.
Vehicles having pollution under control certificate will be allowed to ply.
Use of covering sheets for trucks to prevent dust dispersion from the trucks.
Reducing the speed of a vehicle to 20 km/hr to reduce emissions on site.
All material storages will be adequately covered and contained.
Training to the workers to reduce idling time of machines that otherwise tends to
produce hydrocarbons ad carbon monoxide.
Best practices for maintenance and repair of all machineries and equipment.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 190
Operation Phase
During the operation phase, following measures will be adopted for pollution control:
Adequate stack height for DG Sets
Traffic pollution management
Plantation development
DG Set: The running of DG sets will result in emission of various pollutants. To achieve
adequate natural dispersion, adequate stack height will be provided as per guidelines of
Central Pollution Control Board (CPCB) for 11,000 kVA capacity DG sets.
Traffic pollution management: Internal roads would be maintained in good conditions to
control the dust emissions. Awareness will be raised amongst the residents for use of low
sulphur fuel.
Plantation development: Vegetation is an effective means for controlling air pollution due
its dual action of acting as a barrier between the source of emission and receptors and also as
a sink for various pollutants. It is proposed to develop plantation of species effective in
absorption of expected pollutants at site, along the internal roads and on the periphery of the
project site. Suggested species for plantation are:
Acacia nilotica (Babul)
Mangifera indica (Mango)
Dalbergia sisoo (Shisham)
Ficus religiosa (Pipal)
Ficus glomerata (Goolar)
9.2.5 Noise Levels
Development and Construction Phase
During the construction phase, some noise will be generated through the operation of
construction machines, excavators, DG set, etc. Following measures would be taken; into
consideration to mitigate the noise at construction site:
Use of well-maintained equipment fitted with silencers and providing noise shields
near the heavy construction operations
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 191
Acoustic enclosures would be provide to DG sets at the construction site,
Earmuff and other protection devices shall be provided to laborers working in high
noise generating machines.
High noise activities shall be carried out during daytime.
Operation Phase
The main sources of noise during this phase are the intermittent use of DG Sets and traffic.
The principles of noise emission control and screening are proposed for the two different
scenarios of noise generation.
Noise emission control
All D.G. Sets will be provided with acoustic enclosures ensuring 25 dB (A) insertion loss or
for meeting the ambient noise standards whichever is higher as per CPCB norms. It will be
ensured that the manufacturer provides acoustic enclosures as an integral part with Diesel
Generator Sets.
Barriers
Trees having thick and fleshy leaves with flexible petioles having capacity to withstand
vibration are suitable. Heavier branches and trunk of the trees also deflect or refract the sound
waves. The following species are proposed to be used in a greenbelt of the project.
Acacia nilotica (Babul)
Dalbergia sisoo (Shisham)
Ficus religiosa (Pipal)
9.2.6 Biological Environment
Development and construction phase
During the development, construction and operation phase, no tree will be cut and therefore
no impact is anticipated on terrestrial ecology. Site clearing shall be carried out strictly as per
plan. Workers shall be advised against cutting, uprooting, coppicing of trees or small trees
present in and around the project site for cooking. Workers shall also be discouraged from
wandering in nearby areas with plantation or dense vegetation.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 192
Further, peripheral plantation along the internal roads of project site will be developed during
the construction phase itself that will act as a curtain to restrict the movement of pollutants
from either side of the project and improve site aesthetics.
Operation phase
During the operation phase, peripheral plantation will be developed along with organized
green spaces. Ornamental plant species and grasses will be planted in open space within the
premises. Green area measures 9517 m2. Proposed list of species for plantation is as follows:
9.2.7 Demographic and Socio-Economic Environment
Development and Construction Phase
During the development and construction phase of the project, more than 200 skilled,
semiskilled and unskilled workers will get direct and indirect employment opportunities
which will have beneficial impact on the socio-economic conditions of the area.
Following suggestions are given to strengthen the beneficial impacts on the socio-economic
environment.
S.
No.
Botanical name Local name
1. Anthocephalus cadamba Kadamb
2. Acacia nilotica Babul
3. Bombax ceiba Simal
4. Balanites roxburghii Hingan
5. Dalbergia sisoo Shisham
6. Ficus glomerata Goolar
7. Ficus religiosa Pipal
8. Mangifera indica Mango
9. Putranjiva roxbhurgii Putranjiva
10. Terminalia bellirica Behada
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 193
All the applicable guidelines under relevant acts and rules related to labor welfare and
safety shall be implemented during the construction work activities.
Proper sanitary and drinking water facilities should be provided to workers living in
the construction camps within the project premises.
Workers will be provided with appropriate PPEs during work.
Guarding of dangerous machine parts, maintenance of equipments as hoists and lifts
will be ensured
Adequate provision of different types of fire extinguishers will be made.
Construction Camps will be provided with clean and safe drinking water and toilet
facilities. Domestic refuse generated at the construction camps will be disposed off on a
regular basis. First Aid Medical facilities will also be provided for the construction workers.
Operation Phase
The project envisages addressing the wider goal of environmental protection through a social
investment strategy for the communities around the project. The project seeks to increase the
benefits to the local population and contribute towards meeting community’s expectation of
benefits from the project.
Some of the concerns raised by local people relate directly to the project. Concerns and
aspirations not directly related to the project were also solicited so as to identify areas that
could be addressed through socially responsible initiatives and interventions. These were:
a) Demand for employment opportunities.
b) Infrastructure development
The proposed strategy envisages addressing the wider goal of sharing benefits with the local
community. The following activities would be undertaken:
Income Generation Opportunity for local community
The local people will be given preference, although they will be recruited on their individual
merit. Tender specification for operation services will include favorable employment
opportunities towards the local population. The main principles of employment are outlined
below:
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 194
Employment strategy will provide for preferential employment during operation
phase.
General recruitment procedures will be transparent, public and open to all.
Recruitment procedures will be publicized at locally prominent locations in advance.
There will be no discrimination on basis of gender, caste or other factors.
Contractors would be required to abide by the Indian labour laws regarding standards
on employee working conditions, minimum wages for workers, safety and welfare measures.
Following the appointment of the contractor, information on employment will be available to
the local community at the Panchayat office or other prominent places like the school,
frequently visited spots in the village etc. Information on the following aspects would be
provided- scale and duration of employment, type of available work and demand projection.
Improved working conditions
The project would provide safe working conditions for the labor and other workers employed
at the facility during construction and operation phase. Conditions of employment should
address issues like minimum wages and medical care for the workers.
9.2.8 Vehicle Parking and Traffic Management
Development and Construction Phase
To ensure that the heavy vehicles transporting construction material to the site does not
burden the local traffic, it is proposed to:
Plan the movement of the heavy vehicles avoiding the peak hours (day time).
All the vehicles to the site will be provided with parking space such that there is no
waiting time along the access roads.
Operation Phase
The available road width will provide sufficient merging space for the vehicles while meeting
the external road.
Adequate provision has been made for car/vehicle parking in the project. Besides, wide
internal road will also provide space for off street parking.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 195
9.2.9 Energy Conservation
The project will be designed in such a way that natural light and air will be enhanced in the
residences. Houses at the Project will be energy efficient through use of low energy
consuming fixtures. Energy conservation will be achieved through various means as given
below.
Site Plan and building design
Maximum utilization of solar light will be done
Public areas will be cooled by natural ventilation as opposed to air-conditioning
Maximize the use of natural lighting through design
The orientation of the buildings will be done in such a way that maximum daylight is
available
The water bodies and green areas will be spaced, so that a significant reduction in the
temperature can take place.
Energy saving
Energy efficient lamps will be provided within the complex.
Constant monitoring of energy consumption and defining targets for energy
conservation
Adjusting the settings and illumination levels to ensure minimum energy used for
desired comfort levels
Awareness
Promoting resident awareness on energy conservation
Training staff on methods of energy conservation and to be vigilant to such
opportunities
9.2.10 Management and Maintenance System
Management and maintenance system is an important aspect. During the construction phase,
M/s. WTC NOIDA Development Company Pvt. Ltd. will take care of the implementation of
environmental management plan. They will review the effectiveness of implemented
mitigation measures adopted through contractors and sub-contractors from time to time. The
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 196
houses will be provided with water sprinklers and fire alarms and there will be provision of
adequate number of fire extinguishers. Back-up service will be provided for all emergency
equipment and machineries.
Operation, management and maintenance of the internal services laid in project will be done
by M/s. WTC NOIDA Development Company Pvt. Ltd.
Institutional Capacity Building
a. Reporting: For effective implementation of any system/ plan, a systematic reporting
system is essential. An Environmental Management Cell shall be set up for implementation
of the proposed Management Plan. Reporting of the results of all the management and
monitoring plan shall be submitted to the designated Project Head. The reports shall be
reviewed and parameters exceeding their limits should be identified and the reason for the
same investigated. Any requisite mitigation plan shall be taken up accordingly.
The Environment Management Cell will be a permanent organizational set up charged with
the task of ensuring its effective implementation of mitigation measures and conduct
environmental monitoring. The major duties and responsibilities of Environmental
Management Cell shall be as given below:
To implement the environmental management plan
To assure regulatory compliance with all relevant rules and regulations
To ensure regular operation and maintenance of pollution control devices
To minimize environmental impact of operations as by strict adherence to the EMP
To initiate environmental monitoring as per approved schedule
b. Review and interpretation of monitored results and corrective measures in case
monitored results are above the specified limit.
c. Maintain documentation of good environmental practices and applicable
environmental laws for a ready reference
d. Maintain environmental related records
e. Coordination with regulatory agencies, external consultants, monitoring laboratories
f. Maintenance of log of public complaints and the action taken.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 197
Hierarchical Structure of Environmental Management Cell
Normal activities of the EMP cell would be supervised by a dedicated person who will report
to the project Head.
Awareness and Training
Training and human resource development is an important link to achieve sustainable
operation of the facility and environment management. For successful functioning of the
project, relevant EMP would be communicated to residents and contractors.
Occupants would be made aware of the importance of waste segregation and disposal, water
and energy conservation. The awareness can be provided by periodic Integrated Society
meetings. They would be informed of their duties.
Environmental Audits and Corrective Action Plans
To assess whether the implemented EMP is adequate, periodic environmental audits will be
conducted by the project proponent’s Environmental division. These audits will be followed
by Correction Action Plan (CAP) to correct various issues identified during the audits.
9.3 OVERALL MITIGATION MEASURES AND ENVIRONMENTAL
MANAGEMENT PLAN
Overall impact assessment of anticipated environmental impacts and mitigation measures &
environmental management plan to mitigate the potential impacts during the development &
construction and operation phase are summarized in Table 9.1.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 198
Table 9.1: Environmental Management Plan during construction and operation phases of the project
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 199
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
1. Groundwater
Quantity
Ground water
depletion
Construction Phase
Waste water
generated from
temporary labor
hutments.
(Water requirement
for about 200
workers @ 45 lpcd
for floating and @
200 lpcd for
residential labors(150
X 45 LPCD + 50 X
200 LPCD) will be
17 KLD; Sewage
Generated @80%
will be 14 KLD.
No surface accumulation will
be allowed.
Wastewater generated during
construction phase from the
labor hutments will be
managed in the septic tank
which will be constructed near
the labor hutment site.
Impact will be
temporary as the
construction
phase will be
remaining for two
years only. Water
requirement
during
construction
phase will be 17
KLD only.
Previously the
land was
agricultural land
and the irrigation
demand was 3000
KLD. Approx.
99.4% of the
groundwater will
be saved during
the construction
14 KLD waste
water generated
during
construction phase
will be used for
dust suppression
and green belt
maintenance.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 200
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
Discharge from the
project:
The total domestic
water demand for the
project is 652 KLD
Wastewater @ 80%
of water requirement
522 KLD will be
generated. A STP of
627 KLD based on
MBBR technology
will be installed at the
site.
Fresh water supply i.e., 632
KLD will be from GMADA
and no groundwater
abstraction will be done.
Impact will be
minimal as the
wastewater
generated will be
522 KLD and the
same will be used
for flushing 457
KLD & 39 KLD
for irrigation.
Water requirement
from GMADA
during operation
phase will be 632
KLD only.
Rain water (run
off of
206.31cu.m.) will
be recharged
through recharge
pits.
Wastewater will
be used in
Flushing & for
irrigational
purposes
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 201
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
2. Groundwater
Quality
Ground Water
Contaminatio
n
Construction Phase
No use of ground
water for construction
Water from Private water
tanker will be used for
construction purposes. MoU
has been signed with Rupinder
Singh Private water tanker for
supply of water. The
wastewater from construction
phase will be domestic only
which will be treated in septic
tank.
Impact will be
temporary on the
ground water
quality because of
the discharge of
domestic sewage.
It will be assured
that the waste
water is treated in
septic tank &
stagnation will not
be allowed.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 202
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
The source of water
during operation
phase is GMADA.
The total water
demand for the
project is 1127 KLD.
Proponent will provide the
STP of 5 MLD to treat the
wastewater generated from the
project. Utilization of
wastewater through Flushing
1153 KLD & 768 KLD for
irrigation
Impact will be
marginal on the
ground water. As
wastewater will
be treated with
MBBR
technology by
achieving the
parameters COD
<30 mg/l & BOD
<10 mg/l and that
will not
deteriorate the
quality of ground
water in any
manner.
No stagnation will
be allowed as
treated water will
be used for
Flushing and
horticulture
purpose leading to
zero exit
discharge.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 203
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
3. Surface Water
Quality
Surface water
contamination
Construction Phase
No surface water will
be used during
construction
Silt traps and other measures such as additional on site diversion ditches will be constructed to control surface run-off during site development.
Impact will be nil.
Operation Phase Fresh Water requirement i.e, 632 KLD,597 KLD and 585 KLD respectively during summer, winter and monsoon season will be met through GMADA. Discharge of excess of storm water.
Separate line will be laid to meet the water requirement from GM to the project site to avoid any contamination. Storm water will be recharged through recharge pits.
Impact will be there on the surface water quality which will be mitigated.
Provision of pretreatment of storm water.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 204
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
4. Air Quality
Dust
Emissions
Construction Phase
Development work
will involve
construction of roads,
landscaping, external
lighting and
plumbing services.
Vehicles movement
for the supply of raw
materials
Dust generation from
construction phase will be
suppressed through sprinkling
and wind barriers.
Vehicles will be covered
properly while their
movement.
Vehicles will regularly go
through the Pollution control.
Impact will be
temporary as dust
generation will be
temporary and
will settle fast due
to dust
suppression
techniques.
During
construction
phase, the
contractors will be
advised to
facilitate masks
for the labors.
Sprinklers as well
as wind barriers
will be used for
suppression of
dust during
construction
phase.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 205
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Emissions of
PM, SO2, NO2
and CO
Construction Phase
Operation of
construction
equipment and
vehicles during site
development.
Rapid on site construction
Improved maintenance of
equipment.
Emission quantity
will be very
insignificant.
Regular
monitoring of
emissions and
control measures
to reduce the
emission levels.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 206
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
Emissions from DG
Set during power
failure
Emission from
vehicular traffic in
use
Use of low sulphur diesel
Providing Footpath and pedestrian
ways within the site for the residents
Green belt with high canopy trees
will be developed with specific
species to help to reduce PM2.5 &
PM10 level (Tamarind (Tamarindus
indicus) will be planted as they have
smaller compound leaves which are
generally more efficient particle
collectors than larger leaves. Trees
like Mango (Mangifera indica),
Ashoka (Polyalthea longifolia),
Pongamia (Derris indica) and
Umbrella (Thespepsia populnea)
trees will be planted to capture the
high amounts of dust as compared to
other neighboring plants.
Not significant as
D.G. Set would
be used as power
back-up only.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 207
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
5. Noise
Environment
Noise
emissions
Construction Phase
Noise from
construction
activities.
Noise from DG set
No construction activity to be
taken up at night to avoid any
noise pollution.
Provision of noise shields near
the heavy construction
operations and construction
activity will be limited to day
time hours only.
Acoustic enclosures for DG
set.
Impact will be
temporary.
Acoustic enclosure
will be provided
with the DG sets
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 208
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
Noise from vehicular
movement
Noise from DG set
operation (DG set of
2000 KVA (3), 1500
KVA (3) and 500
KVA (1))
Green Belt Development.
Evergreen broad leaved trees
will be planted in a tightly-
spaced row as their broad-
leaves, thick foliage and
branches will act as curtains
against noise.
Development of silence zones
to check the traffic movement.
Impact will be
minimum due to
suitable width of
Greenbelt.
Green belt over
2.35 acres of green
area and DG sets
with inbuilt
acoustic enclosure.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 209
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
6. Land
Environment
Soil
contamination
Construction Phase
Disposal of
construction debris.
Construction debris will be
collected and suitably used on
site for the roads.
Approx. 78,820.08cum cutting
will be done and the same will
be used for filling purposes.
Impact will be
temporary as the
maximum portion
of land cut will
be used for the
filling purposes
within the project
premises. No soil
contamination.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 210
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
Generation of
municipal solid
waste:
During operation
phase, about 3877
Kg/day of solid waste
shall be generated (@
0.25 kg/cap/day for
staff population & @
0.15 kg/cap/day for
visitors population)
from the project site.
The solid waste will be
segregated into biodegradable
and non-biodegradable waste.
The recyclable inorganic waste
will be sold to local resellers.
Separate area is earmarked for
handling of solid waste.
Biodegradable waste shall be
recycled by using mechanical
composter.
Impact will be
positive. Compost
will be used
within the
premises for
green area
development and
excess will be
given to nearby
farmers after
proper testing for
using as manure.
No soil
contamination.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 211
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
7. Biological
Environment
(Flora and
Fauna)
Displacement
of Flora and
Fauna on site
Construction Phase
Cutting of trees.
In addition, 410 will be
planted in return and the same
will increase the chances of
development & emigration of
fauna.
Impact will be
positive.
--
Operation Phase
Increase in green
area and trees
2.35 acres/ 9517 sq.m. of
green area including green belt
will be provided within the
project site which will enhance
the beauty.
Impact will be
positive.
Aesthetic beauty
of the area will be
increased
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 212
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
8. Socio -Economic
Environment
Population
displacement
and economic
impact
Construction Phase
No relocation is
involved.
Constructional
activities
Compensation has been
provided to the land owners by
development authority.
Employment for labourers
No negative
impact
Beneficial impact
--
Operation Phase
Site operation
Project will provide
employment opportunities to
the local people in terms of
labor during construction and
service personnel (guards,
securities, gardeners etc)
during operations.
Impact will be
positive. Overall
development of
the area from
rural to urban
shift.
--
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 213
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
9. Traffic Pattern Increase of
Vehicular
traffic
Construction Phase
Heavy Vehicular
movement during
construction:
Transportation of
construction material
to be done by 15
vehicles (Grader,
Tandon Roller,
Vibratory roller,
Static roller, Tippers,
Water tankers, Paver)
Heavy Vehicular movement
will be restricted to daytime
only and adequate parking
facility will be provided for
the visitors during construction
phase..
Impact will be
minimum.
Most of the
movement will be
done during non-
peak hours. Also,
the LOS of the
connecting road is
very good as per
traffic study.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 214
Sl.
No.
Environmental
Components
Potential
Impacts
Potential source of
Impact
Controls through EMP &
Design
Impact
Evaluation
Remedial
Measures
Operation Phase
Traffic due to
residents once the
project is operational.
Vehicular movement will be
regulated inside the project
with adequate roads and
parking area developed by the
individual plot developers
Impact will be
minimum as per
the traffic study.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 215
CHAPTER 10: SUMMARY AND CONCLUSION
10.1 PROJECT BACKGROUND
M/s. WTC NOIDA Development Company Pvt. Ltd. intends to develop ‘World Trade Centre’ a
Commercial project located at Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab.
As per EIA Notification, 2006 & its amendments for development projects covering an area of
50 ha and/ or built up area greater than 1, 50,000 m2 are designated as 8 (b) as per the schedule
of the notification and require EIA/EMP study to obtain prior environmental clearance from
respective State Environmental Impact Assessment Authority (SEIAA).
This project is thus categorized as 8 (b) under Schedule of the Environmental Impact Assessment
Notification and requires Environmental Clearance from the State Environment Impact
Assessment Authority, Punjab as the built up area is 1,51,314 m2 so EIA/EMP study is required.
The EIA/EMP study has been carried out considering baseline environment study carried out
during for Oct- Dec 2013 of "Knowledge Park/IT Park" GMADA, Sector-66, 82 & 83, SAS
Nagar, Mohali, Punjab project with due permission of SEAC, Punjab. Additionally, one month
study (12th May to 08th June, 2016) has been carried out.
For the purpose of certain environmental components, the radius of impact has extended/studied
up to 10 km. The EIA has been conducted to establish the baseline environmental setting in the
study area, assessment of potential impacts on different environmental components, design of
mitigation measures so as to keep impacts within acceptable limits and strengthen the positive
impacts.
This chapter summarizes the findings of the EIA study to aid in decision making and provides
project related information and environmental impacts to non-technical sections of society. The
summary highlights the baseline environmental status, key environmental issues and their likely
impacts and also lists the major recommended mitigation measures to attenuate the impacts.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 216
10.2 PROJECT SITE
The project site is well connected via. road, railway and airway. The nearest railway station is
Sahibzada Ajit Singh Railway Station which is 2.5 km away from the project site in NW
direction. The nearest airport is Mohali International Airport at a distance of 4 km from the
project site in NE direction.
NIPER and Fortis Hospital are 5 km away.
10.3 PROJECT FEATURES
The total population of the project is 13,528 persons. Salient features of the project are as
presented in table below:
Table 10.1: Salient Features of the project
S. No. Description
1. Power Supply 7544 KW
2. D.G. Set 7 no. of D.G sets, 11000 kVA (3 x
2000 + 3 x 1500 + 1 x 500 kVA)
3. Parking Required = 1950 ECS
Proposed = 1952 ECS
4. Water Demand Total = 1127 KLD
Fresh water = 632 KLD
5. Wastewater generation 522 KLD
6. STP Capacity 627 KLD
7. Solid waste generation 3877 kg/day
8. Manpower requirement
(construction phase)
200-300
The project will be implemented over a span of four to fivee years from the commencement of
construction.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 217
10.4 ENVIRONMENTAL SETTING OF THE STUDY AREA
The baseline environmental status was assessed based on primary and secondary data collected
either through in-site field observation or obtained from agencies such as Irrigation Department,
India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of
India, State Ground Water Department, State Pollution Control Board, Census of India and Local
Forest Department, Non -Governmental Agencies. The baseline status established from analysis
of secondary and primary data and predicted impacts are discussed below. The proposed
mitigation measures are also provided along with.
10.4.1 Land Environment
The land is designated for development of commercial projects. The site is allotted to the project
pronpnet for development of commercial project by GMADA
.
The construction phase poses the threat of soil contamination and soil erosion, mainly during the
construction phase. Inadequate solid waste management may also cause soil contamination
during operation phase. The estimated waste generation during operation phase is 3877 kg/ day.
During construction phase, excavation related work will be avoided during the monsoons and
site clearing will be carried out for specific areas being developed. All wastes from site will be
regularly removed and disposed/ sold. An efficient solid waste management is proposed
comprising door-to-door waste collection, segregation of solid waste management facility within
the site, and their disposal. Solid waste will be disposed by sale of recyclable wastes to vendors.
10.4.2 Water environment
The water requirement during construction phase will be met from private water tankers. A
combination of efficient water management strategies will be adopted to reduce water
consumption, reuse of treated wastewater to reduce freshwater demand and rainwater harvesting
to replenish groundwater is proposed to have a positive bearing on the water environment of the
region.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 218
A Sewage Treatment Plant (STP) of capacity 627 KLD will be set up to treat and reuse
wastewater.
10.4.3 Air Environment
During construction phase, the major air pollutant of prime concern is PM 2.5, PM10 as impacts of
other emissions such as SO2, NO2, and CO will not be significant because the nature of sources
is such that the emissions are distributed spatially as well as temporal. Monitored average PM2.5,
PM10 level exceeded NAAQS at all the five locations. The levels of PM 2.5, PM10, NO2, SO2 and
CO at all the five locations were within the standards prescribed by NAAQS at all the five
locations. Thus dust emissions from construction activities shall require comprehensive
mitigation measures and best construction practices.
Adequate stack heights will be proposed for D.G. Sets of total 11,000 kVA capacity (3 x 2000 +
3 x 1500 + 1 x 500 kVA) above the ground to provide for sufficient dispersion of pollutants.
Water sprinklers will be used to suppress dust during construction. During the operation phase,
green belt and green area development is proposed to restrict and absorb air pollutants.
10.4.4 Noise Environment
Noise levels were observed at four locations within the study area. The noise emitted from
heavy-duty construction equipment’s during construction period being high shall require
occupational preventive measures and temporary noise barriers for noise attenuation. The
construction period being about four to five year duration, will require significant mitigation
measures such as restricted loud noise activities to daytime, provision of PPEs and acoustic
enclosures for D.G. Set.
In the operation phase, noise pollution will be checked through acoustic enclosures of DG Sets
and green belt plantation.
10.4.5 Biological environment
There is no tree cutting involved in the project. However, the project will have 9517 m2 of green
area during operational phase. There will be development of avenue plantations, lawns, etc. The
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 219
proposed landscaping will include native species that will attract local birds and insects, reduce
pollution and improve aesthetics and micro-climate of the region.
10.4.6 Socio-economic environment
The proposed project does not call for any land acquisition or change in the land use pattern. The
execution of the project will not disturb the people living in area as there will be no blasting and
large scale digging. The project will generate employment opportunities for both skilled and
unskilled workers in the vicinity, which will produce multiple effects on the life and economy of
the local people. Thus from socio-economic point of view the project is beneficial to the people
and can be executed with little hesitation.
10.4.7 Energy efficiency
The total energy demand of 7544 KW for the project will be met by Punjab State Power
Corporation Ltd. 7 D.G. sets of total capacity 11000 kVA (3 x 2000 + 3 x 1500 + 1 x 500 kVA)
are proposed to provide backup in case of power failure. Various provisions are made to reduce
the energy efficiency of the building, such as use of solar energy, provision of low energy
fixtures, design features to maximise sunlight and use of energy efficient material to improve
energy efficiency.
10.4.8 Other
Resource Conservation: A concerted effort is made towards resource conservation by way of
using recycled building materials, fly-ash bricks (up to 35%), reduced water consumption and
improving energy efficiency of the building.
Indoor Air Quality: Special attention will be given to maintaining indoor air quality through
use of low VOC paints, provision of adequate ventilation, proper storage of chemical and
cleaning materials.
Safety: A network of manned security gates, security men, closed circuit TV and intercom
facilities are proposed to ensure safety of the occupant. The buildings will also be provided with
adequate fire tenders, fire alarms and water sprinklers.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 220
10.5 ENVIRONMENTAL MANAGEMENT PLAN
Adequate environmental management measures will be incorporated during the entire planning,
construction and operating stages of the project to minimize any adverse environmental impact
and assure sustainable development of the area.
For the effective and consistent functioning of the campus, an Environmental Management
System (EMS) will be established at the site including an Environmental Management cell for
implementation of the EMP and monitoring plan, training and awareness, audits and
maintenance of records.
M/s WTC NOIDA Development Company Pvt. Ltd. manages the environmental
condition/compliance through an in house team. Environment Management Cell structure is
shown below:
Figure 10.1: Environment Management Cell Structure
MANAGING DIRECTOR
EXECUTIVE DIRECTOR
GENERAL MANAGER
ENVIRONMENT MANAGER
ENVIRONMENT MITIGATION MEASURES
IMPLEMENTATION OF ENVIRONMENT
MANAGEMENT PLAN
FOLLOW UP WITH STATE & CENTRAL ENVIRONMENTAL
DEPARTMENT
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 221
Based on the environmental assessment, the associated potential adverse environmental impacts
can be mitigated to an acceptable level by adequate implementation of the measures as stated in
the EIA and the EMP. Some of the benefits from the project are:
Use of solar energy for street lighting
Provision of green walls/green terraces
Use of fly ash bricks.
Use of steel manufactured from recycled content
Provide permeable paving to control surface water runoff
Rainwater harvesting
Meet all requirements for buildings in moderate earthquake prone areas.
Provision of fire alarms and water sprinklers
Provision of welfare scheme for workers
Extending educational and healthcare facilities to the local people
Commitment to engaging local people and businessmen for maintenance and repair work
Hence, it may be concluded that the project will have significant positive economic and social
impact on the local community without bearing any significant adverse environmental impacts.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 222
CHAPTER -11: DISCLOSURE OF CONSULTANTS
ENGAGED
Project Name: ‘World Trade Centre’ Commercial Project, Plot No. 2, Block-D, Aerocity, S.A.S Nagar, Mohali, Punjab Name and address of the Consultant
GRC, India (P) Ltd. F:374-375, Sector: 63, Noida, India
ISO 9001:2008 Certified, QCI-NABET Accredited.
Base line data GRC, India Training and Analytical Laboratory F- 375, Sector: 63, Noida, India
NABL Accredited &MoEF Recognized Laboratory. A unit of GRC India (P) Ltd.
The EIA/EMP report has been prepared under the guidance of following Coordinators
& Functional Area Experts:
EIA Coordinator Dr. P.R. Chaudhari
FAE-WP Dr. P.R. Chaudhari
FAE-AP Mr. K.D. Choudhury
FAE-AQ Mrs. Mudita Tomar Singh
FAE-LU Mr. P. Radhakrishnamoorthy
FAE-EB Dr. P.R. Chaudhari
FAE-NV Mr. K.D. Choudhury
FAE-SE Mr. Sudhir Saksena
FAE-HG Prof. Tapan Majumder
FAE-G Prof. Tapan Majumder
FAE-Soil Dr. P.R. Chaudhari
FAE-RH Mr. K.D. Choudhury
FAE-SHW Mr. Rajesh B.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 223
11.1 ACCREDITATION FROM QUALITY COUNCIL OF INDIA AND LIST OF
COORDINATORS.
Grass Roots Research & Creation India (P) Ltd., Noida is an EIA Consultant organization accredited by Quality Council of India, NABET. GRC India is accredited vide NABET Certificate No. – NABET/EIA/RA083/076 and validity of accreditation is till Feb 13, 2018. Certificate of Accreditation is attached for reference.
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 224
‘World Trade Centre’ Commercial project, Plot No. 2, Block-D, Aerocity,
S.A.S Nagar, Mohali, Punjab EIA/EMP REPORT
M/s. WTC NOIDA Development Company Pvt. Ltd. Page 225
As per the recently published QCI NABET ‘List of Accredited Consultant Organizations/Rev. 42/June 09, 2016’, listed in as accredited consultant, Category ‘A’ Sl. No. 84. The list of accredited consultants is published on QCI NABET and MoEF&CC websites as well. For reference, a snapshot of the list where GRC India’s name is listed is pasted below:
1
Proceedings of the 108th meeting of State Level Environment Impact Assessment Authority held on 03.06.2016 at 11.00 AM in Committee Room, Punjab Pollution Control Board, Regional Office, Mohali.
The following were present:
1. Sh. Darshan Singh Jaidka,
Chairman, SEIAA
2. Sh. Anil Kumar Sondhi,
Member, SEIAA
3. Sh. Tejinder Singh Dhaliwal, IAS
Member Secretary, SEIAA
At the outset, the Member Secretary (SEIAA) welcomed the members
of the State Environment Impact Assessment Authority (SEIAA) in 108th meeting.
Item No.108.01: Confirmation of the minutes of 107th meeting of SEIAA
held on 27.05.2016.
The SEIAA noted that the proceedings of 107th meeting of
SEIAA held on 27.05.2016, were circulated to all concerned vide letter no. 2492-93
dated 01.06.2016. No observation has been received from any of the members. As
such, SEIAA confirmed the said proceedings.
Item No.108.02: Action taken on the proceedings of 107th meeting of SEIAA held on 27.05.2016.
It was apprised that action taken on the proceedings of 107th
meeting of SEIAA held on 27.05.2016 is being taken and the action taken report will
be placed before the SEIAA in its next meeting.
Item No.108.03: Application for environmental clearance granted under EIA notification dated 14.09.2006 for the construction of Commercial Project Food Court Site No. 1 & 2 at Sector-62, SAS Nagar (Mohali), Punjab by M/s. PP Buildwell Private Limited. (Proposal no. SIA/PB/NCP/52475/ 2016)
The SEIAA observed that:
M/s. PP Buildwell Private Limited has applied for environmental
clearance under EIA notification dated 14.09.2006 for the construction of
Commercial Project Food Court Site No. 1 & 2 at Sector-62, SAS Nagar (Mohali),
14
Item No.108.04: Application for obtaining Environmental Clearance
under EIA notification dated 14.09.2006 for construction of Commercial Project "World Trade Centre" at Plot No.2, Block-D, Aerocity, in the revenue estate of SAS Nagar, Punjab by M/s WTC Noida Development Company Pvt. Ltd. (Proposal No. SIA/PB/NCP/10742/2016)
The SEIAA observed that:
M/s WTC Noida Development Company Pvt. Ltd. have
applied for obtaining the Environmental Clearance under EIA notification dated
14.09.2006 for commercial project namely “World Trade Centre" at Plot No.2, Block-
D, Aerocity, SAS Nagar, Punjab. The project is covered under category 8 (b) of the
Schedule appended to the said notification.
Thereafter, Environmental Engineer, Punjab Pollution Control Board, Regional Office, Mohali, vide email dated 18.04.2016 was requested to visit the project site and submit report regarding latest construction status.
The Environmental Engineer, Punjab Pollution Control Board, Regional Office, Mohali, vide letter no. 2580 dated 18.04.2016 has intimated that the site was visited by AEE of this office on 08.06.2015 and observed as under:
1. The site of the project is located at Block D, site-II, Aerocity road
Mohali, District SAS Nagar.
2. 3 no of MS containers have been placed at the site for using the same
for office purpose. The representative of the promoter company Sh.
Surinder Kumar Rana was contacted at the site and he informed that
the containers are portable type and shall be removed from the site as
soon as the construction activity will be completed.
3. Further, no construction activity has been carried out at the site except
securing of the land with GI corrugated sheets along the periphery of
the project site.
The case was considered by the SEAC in its 145th meeting held on
11.05.2016, which was attended by the following on behalf of project proponent:
(i) Sh. Harjit Singh, Senior Manager of the promoter company.
(ii) Sh. Parshant Gupta, Senior Manager of the promoter company.
(iii) Sh. Anil Kumar, Senior Director of the promoter company.
(iv) Smt. Nidhi, Environmental Consultant, GRC Pvt. Ltd., Noida, UP
on behalf of the promoter company.
Sh. Harjit Singh, Senior Manager of the promoter company submitted a
copy of resolution passed in the meeting of the Board of Directors in which he
15
alongwith Mr. Parshant Gupta & others have been authorized to represent the
company for all matters relating to the obtaining of various approvals like
Environmental clearance etc.
Thus, the SEAC allowed the Environmental Consultant of the promoter
company and he presented the salient features of the project as under:-
o The total land area of the project is 32512.44 sqm (8.034 acres) and the total
built up area will be 1, 51,314 sqm. The total cost of the project is Rs.
26165.64405 Lacs.
o The total water requirement for the project will be 1127 KL/day, out of which
632 KL/day will be met through MC supply/ Ground water and remaining 495
KL/day will be met through recycling of treated wastewater.
o The total wastewater generation from the project is 522 KLD, which is treated
in a STP of 627 KLD capacity within the project premises. In summer season,
the project proponent has proposed to utilize 13 KLD of fresh water and 39
KLD of treated waste water for horticulture purposes and remaining 457 KLD
for flushing purpose. In winter season, 17 KLD of treated waste water will be
utilized for horticulture purposes, 457 KLD for flushing and remaining 22 KLD
for HVAC/DG cooling purposes. In monsoon season, 05 KLD of treated waste
water will be utilized for horticulture purposes, 457 KLD for flushing and
remaining 34 KLD for HVAC/DG cooling purposes.
o The total quantity of solid waste to be generated from the proposed project
has been estimated as 3877 Kg/Day. The solid waste of the project will be
segregated into biodegradable waste and non-biodegradable. Biodegradable
waste and non biodegradable waste will be collected in separate bins.
Biodegradable waste will be converted into manure through the vendor. The
recyclable wastes will be sold to the recyclers. Non recyclable waste will be
finally disposed through govt. approved agencies.
o The total load of electricity required for proposed project is 7544 KW which is
supplied by PSPCL. The project proponent has proposed to install 7 DG sets
of total capacity 11000 KVA (3 x 2000KVA, 3 x 1500KVA & 1 x 500KVA) for
backup power supply.
o Used oil to be generated from the DG sets will be managed & handled as per
the provisions of the Hazardous Wastes (Management, Handling &
16
Transboundary Movement) Rules, 2008.
o The project proponent has submitted the “Terms of Reference”.
The SEAC observed that the project proponent has not listed the
activities and their likely impacts on the environment in the presentation. To this
querry of SEAC, the project proponent submitted a copy of list of activities and
their likely impacts which was taken on record by the SEAC. The project
proponent submitted that EIA study for Knowledge Park at Sector 66-B, 82-A &
101-A, Mohali has been carried by GMADA during the period Oct.2013-Dec2013
and the environmental clearance has been granted to the said project. The
monitoring locations selected in case of Knowledge Park and the proposed site
have been compared and found that monitoring locations selected GMADA site
are falling within ten km study region of proposed project. He requested to allow
use of the baseline data collected in case of Knowledge Park at Sector 66-B, 82-A
& 101-A, Mohali by GMADA during post monsoon season i.e. Oct.2013-Dec.2013.
The SEAC allowed the project proponent to use baseline data subject to the
condition that baseline data should not be more than three years old and also
minimum one month study be carried out in core Zone.
After detailed deliberations in the matter, the SEAC decided to
recommend to SEIAA to issue the following "Terms of Reference" to the project
proponent for preparation of the draft Rapid EIA report:
A. Construction stage
1. The project falls under category B-1 under item 8(b) Township and Area Development projects and requires an Environmental Impact Assessment Study for the entire site area.
2. The project proponent may use the baseline data data collected in case of Knowledge Park at Sector 66-B, 82-A & 101-A, Mohali by GMADA during post monsoon season i.e. Oct.2013-Dec.2013 subject to the condition that baseline data should not be more than three years old and also minimum one month study shall be carried out in core Zone.
3. Examine and submit the details of the environmental impacts due to change of land use and land cover including aspects such as hydrological characteristics, imperviousness of land and drainage pattern being altered.
4. Examine and submit the details of the environmental impacts at the stage of construction of boundaries & fencing including its impact on the pattern of natural drainage and flooding pattern and barriers being constructed for restricting wildlife movement into project area.
5. Examine and submit the details of the environmental impacts due to leveling and landscaping including aspects such as excavation & filling of soil, clearing
17
of vegetation, change of topography, development of plantation, green belt, lawns & parks and development of impervious areas.
6. Examine and submit the details of the environmental impacts due to excavation, transportation and filling of earth including aspects such as excavation, filling, sourcing, transportation and disposal of soil.
7. Examine and submit the details of the construction material to be used at the construction stage including aspects such as quarries and transportation, stone crushing and screening, mining & transportation of sand, soil excavation, transportation and filling.
8. Examine and submit the impacts being caused due to transportation of construction materials and men such as increase in traffic and load on public transportation facility, destruction and damage of transportation infrastructure, increase of risk due to road accident, pollution caused due to dust and tail pipe emissions and consumption of fuel by transport vehicles.
9. Examine and submit the details of the temporary housing and amenities to be created and used by the work force including aspects such as water supply, electrical energy and fuel supply.
10. Examine and submit the details of the environmental impacts at the stage of creation of roads, transportation facility and other physical infrastructure including aspects such as use of construction materials, excavation and /or filling of soil, generation of construction waste, creation of impervious surfaces, noise & suspended dust pollution and accidental risk.
11. Examine and submit the details of the noise pollution, air pollution, consumption of fuel and generation of scrap being caused due to operation and maintenance of construction machinery and equipment.
12. Examine and submit the details of the source and supply of water for construction activity.
13. Examine and submit the details of the source and quantity of power for construction activity.
14. Examine and submit the details of the fuel consumption, noise pollution, emissions of the exhaust gas, engine & coolant oil and batteries being discarded due to captive and emergency power generation.
15. Examine and submit the details of the handling of wastewater during construction including the domestic wastewater being generated from amenities.
16. Examine and submit the details of the environmental impacts at the stage of development of residential buildings, commercial, institutional and industrial infrastructure including aspects such as construction materials to be used, earth work (excavation and/or soil filling), generation of construction waste, lighting, HVAC units, waste generation from packaging, residual paints and chemicals and their cans, Generation of wooden, glass, metal and other scrap materials, plumbing and sanitary waste generation, creation of impervious surfaces, noise pollution, suspended dust pollution and risk of accidents.
17. Examine and submit the details of the environmental impacts due to the laying of the water supply system including aspects such as use of piping, fittings ad pumps, water pumping stations, earth work and water treatment plant.
18. Examine and submit the details of the environmental impacts due to the laying of the sewerage and sewage treatment and disposal system including aspects such as use of construction material, piping, fittings ad pumps, earth
18
work, laying of sewers & manholes, sewage pumping stations and sewage treatment plant.
19. Examine and submit the details of the environmental impacts due to the laying of the storm water drainage system including aspects such as use of construction material, piping, fittings and pumps, earth work, storm drains, storm water inlets and catch basins and storm water outfalls.
20. Examine and submit the details of the environmental impacts due to the electrical power system and street lighting to be provided including aspects such as construction materials to be used, distribution lines, cables, control panels, transformers and meters.
B. Operation stage
1. Examine and submit the details of the environmental impacts due to the residential, commercial, institutional, industrial, recreational, social, cultural & religious activities to be carried out.
2. Examine and submit the details of the environmental impacts due to the facilities to be provided such as water supply, electrical power supply, fuel supply & consumption including LPG, transportation and communication.
3. Examine and submit the details of the environmental impacts due to the coming up of the activities such as urban agriculture and animal husbandry.
4. Examine and submit the details of the environmental impacts due to the sewerage & sewage treatment and its disposal systems and storm water & its drainage system.
5. Examine and submit the details of the environmental impacts caused due to the generation of captive power & emergency power.
6. Submit the details of the management & handling of municipal solid waste, e-waste, hazardous waste, scrap, estate management, and construction and demolition waste management. The proposal of MSW should include the bio-composting of the organic waste.
7. Submit the details of the socio economic impact due to the employment to be generated from the household activities.
C. General
1. Other details as indicated in Appendix III of EIA Notification 2006 and the
manual titled as "EIA guidance Manual-Building, Construction, Township and
area Development projects" published by the Ministry of Environment &
Forests, New Delhi, should also be attended.
2. Environmental aspects identified under some of the project activities may not
be comprehensive and some of the significant aspects under some of the
activities of the project in question might not have been identified. All such
environmental aspects may be added to the list.
3. Some of the activities with their associated environmental aspects of the
project in question might be of significant magnitude and not included in the
list project activities. All such activities may be added to the list of project
activities.
4. The project proponent may add additional project activities and
environmental aspects, if any, fill the impact matrix (copy attached) and
carryout significance analysis for identifying the significant environmental
aspects. Scale, sensitivity and duration of impacts; type, size and frequency of
19
environmental aspects; applicable legal requirements; and concerns of
interested parties and local public may be used as the basis for the
significance analysis of the environmental aspects.
5. In the EIA study each of the environmental aspects listed in the TOR should
be quantified, their positive and negative impacts on different areas of
impacts should be identified and assessed and the results of such assessment
should be reported in the EIA report.
6. In the Environment Management Plan, management of each of the significant
environmental aspects (with identified and assessed significant environmental
impacts) for mitigating the impacts should be objectively stated.
7. Environment Management Plan should include technical and institutional
aspects for pre-treatment by constituent units.
8. Environmental Management Plan should be accompanied with Environmental
Monitoring Plan and environmental cost and benefit assessment.
9. Examine separately the details for construction and operation phases both for
Environmental Management Plan and Environmental Monitoring Plan.
10. Does the company have a well laid down Environment Policy approved by its
Board of Directors? If so, it may be detailed in the EIA report.
11. Does the Environment policy prescribe for standard operating process /
procedures to bring into focus any infringement / deviation / violation of the
environmental or forest norms / conditions? If so, it may be detailed in the
EIA.
12. What is the hierarchical system or Administrative order of the company to
deal with the environmental issues and for ensuring compliance with the EC
conditions. Details of this system may be given.
13. Does the company have a system of reporting of non compliances / violations
of environmental norms to the Board of Directors of the Company and / or
shareholders or stakeholders at large? This reporting mechanism should be
detailed in the EIA report.
14. Delineate the concrete proposal regarding activities to be undertaken under
Corporate Social Responsibility programme, which should be long lasting in
nature and should be as per the needs of a particular Village/area/ local
habitats/ stakeholders to be adopted by the promoter company, which can be
done by involving a person having knowledge and experience of socio-
economic activities.
A detailed draft EIA/EMP report should be prepared as per the above
TOR's and shall be submitted to the SEAC as per the provisions of the EIA
Notification dated 14.9.2006. The aforesaid 'Terms of Reference' will be valid for
a period of three years from its issuance.
The case was considered by the SEIAA in its 108th meeting held on
20
03.06.2016, which was attended by the following on behalf of project proponent:
(i) Sh. Harjit Singh, Senior Manager of the promoter company.
(ii) Sh. Parshant Gupta, Senior Manager of the promoter company.
(iii) Sh. Santosh Ram Kumar, Assistant Manager Environmental Consultant,
GRC Pvt. Ltd., Noida, UP on behalf of the promoter company.
Sh. Santosh Ram Kumar, Environmental Consultant of the promoter
company presented the salient features of the project before the SEIAA and
requested for issuance of ToRs.
The SEIAA looked into the details of the case and was satisfied with
the same. Therefore, the Authority decided to accept the recommendations of SEAC
and to issue Terms of Reference as proposed by the SEAC. The SEIAA also decided
that the project proponent shall submit final EIA / EMP based upon the ToRs to the
State Expert Appraisal Committee for Appraisal of its project.
Item No.108.05: Application for environmental clearance granted under
EIA notification dated 14.09.2006 for the commercial cum residential project namely "GBP Centrum" at Vill. Singhpura, Tehsil Dera Bassi, Zirakpur, Distt. Mohali by M/s Gupta Builders & Promoters Pvt. Ltd. (Proposal No. SIA/PB/NCP/34616/2015)
The SEIAA observed that:
M/s Gupta Builders & Promoters Pvt. Ltd. has applied for
environmental clearance under EIA notification dated 14.09.2006 for the commercial
cum residential project named "GBP Centrum" at Vill. Singhpura, Tehsil Dera Bassi,
Zirakpur, Distt. Mohali. The project is covered under category 8 (a) of the Schedule
appended to the said notification.
The case was considered by the SEAC in its 139th meeting held on
05.01.2016, but no one from the project proponent attended the said meeting.
However, the SEAC observed that the project proponent is required to submit the
following documents/information:
i. Documentary proof to the effect that Sukhna Wildlife Sanctuary and Bird
Sanctuary, Sector-21, Chandigarh and Khol Hi Rayta Sanctuary, Panchkula are
more than 10 kms from the project site. In case, these are within 10 kms
radius then, the project proponent will submit acknowledgement and copy of
1
Compliance to the ToR issued by SEAC, Punjab
Construction stage
1. The project falls under category B-1 under item 8(b) Township and Area Development
Projects and requires an Environmental Impact Assessment Study for the entire site area.
Reply: The total plot area of the 32,512.44 m2 or 3.25 ha. The built up area is 1, 51,314 m2.
However, this project comes under item 8b (Township and Area Development Projects) as per
the EIA notification 2006 and their amendments.
2. The project proponent may use the baseline data collected in case of Knowledge Park at
Sector 66-B, 82-A & 101-A, Mohali by GMADA during post monsoon season i.e., Oct 2013-
Dec 2013 subject to the condition that baseline data should not be more than three years
old and also minimum one month study shall be carried out in core Zone.
Reply: EIA/EMP report has been prepared on the basis of baseline data of Knowledge Park at
Sector 66-B, 82-A & 101-A, Mohali by GMADA during Oct to Dec, 2013 which is not more
than three years old and additional one month baseline study (12th May to 12th June, 2016) on
project site. The copy of test reports is enclosed as Annexure-6 in EIA/EMP report.
3. Examine and submit the details of the environmental impacts due to change of land use and
land cover including aspects such as hydrological characteristics, imperviousness of land
and drainage pattern being altered.
Reply:. The copy of allotment letter is enclosed as Annexure-3 of EIA/EMP Report. Copy of
Master Plan is referred as Annexure 2(a). Impact and mitigation measures are mentioned in
Chapter 4 Pg No. 91 of EIA/EMP report.
4. Examine and submit the details of the environmental impacts at the stage of construction of
boundaries & fencing including its impact on the pattern of natural drainage and flooding
pattern and barriers being constructed for restricting wildlife movement into project area.
Reply: The project is not likely to alter or obstruct any drainage courses. There is a Choi Nala
and Choa Nala passing at the distance of 1.35 km and 2.64 km respectively from the project site.
2
The 5km buffer map showing location of nalas is enclosed as Annexure-2(b). Impact and
mitigation measures are mentioned in Chapter 4 Pg No. 91 of EIA/EMP report.
5. Examine and submit the details of the environmental impacts due to leveling and
landscaping including aspects such as excavation & filling of soil, clearing of vegetation,
change of topography, development of plantation, green belt, lawns & parks and
development of impervious areas.
Reply: Impact and mitigation measures are mentioned in Chapter 4 Pg No. 91 of EIA/EMP
report. Landscape plan is enclosed as Annexure 2(c ).
6. Examine and submit the details of the environmental impacts due to excavation,
transportation and filling of earth including aspects such as excavation, filling, sourcing,
transportation and disposal of soil.
Reply: Impact and mitigation measures are mentioned in Chapter 4 Pg No. 91 of EIA/EMP
report.
7. Examine and submit the details of the construction material to be used at the construction
stage including aspects such as quarries and transportation, stone crushing and screening,
mining & transportation of sand, soil excavation, transportation and filling.
Reply: Details of Construction material and machinery to be used is mentioned in Chapter 2 Pg
No. 38 of EIA/EMP report.
8. Examine and submit the impacts being caused due to transportation of construction
materials and men such as increase in traffic and load on public transportation facility,
destruction and damage of transportation infrastructure, increase of risk due to road
accident, pollution caused due to dust and tail pipe emissions and consumption of fuel by
transport vehicles.
Reply: The project site is well connected to NH-64 anticipating a good transportation viability
and connectivity.
3
Vehicular emissions will be the major source of air pollution from building construction projects.
During the post construction phase, cars, scooter/motorcycle will be owned by the population of
the project. PM, NO2, SO2 and CO will be the main pollutants of primary concern released from
traffic movement. It is also proposed to make use of Pollution under Control (PUC) certified
vehicles and make operated vehicle with low sulphur diesel.
9. Examine and submit the details-of the temporary housing and amenities to be created and
used by the work force including aspects such as water supply, electrical energy and fuel
supply.
Reply: Details are mentioned in Chapter 2 Pg No. 24 and 27 of EIA/EMP report.
10. Examine and submit the details of the environmental impacts at the stage of creation of
roads, transportation facility and other physical infrastructure including aspects such as
use of construction materials, excavation and /or filling of soil, generation of construction
waste, creation of impervious surfaces, noise & suspended dust pollution and accidental
risk.
Reply: Details are mentioned in Chapter 4 Pg No. 91 of EIA/EMP report
11. Examine and submit the details of noise pollution, air pollution, consumption of fuel and
generation of scrap being caused due to operation and maintenance of construction
machinery and equipment.
Reply: Details are mentioned in Chapter 4 Pg No. 91 of EIA/EMP report
12. Examine and submit the details of the Source and supply of water for Construction
activity.
Reply: The water requirement will be supplied from private water suppliers during construction
phase. The copy of agreement is enclosed as Annexure- 2(e).
13. Examine and submit the details of the source and quantity of power for Construction
activity.
Reply: The source of the power supply will be Punjab State Power Corporation Ltd. Demand
load during construction phase is estimated to be around 25 kW for which permission has been
obtained, further if demand rises same will be obtained.
4
14. Examine, and submit the details of the fuel consumption, noise pollution, emissions of the
exhaust gas, engine & coolant oil and batteries being discarded due to captive and
emergency power generation.
Reply: Details are mentioned in Chapter 4 Pg No. 91 of EIA/EMP report
15. Examine and submit the details of the handling of wastewater during construction
including the domestic wastewater being generated from amenities.
Reply: Total nos. of local labors working during construction phase will be 150-200 hired from
nearby areas. Details mentioned in Chapter 2 Pg No. 27
16. Examine and submit the details of the environmental impacts at the stage of development
of residential building, commercial, Institutional and Industrial infrastructure Including
aspects such as Construction materials to be used, earth work (excavation and/or soil
filling), generator of construction waste, lighting and ventilation system, air Conditioning
and air handling units, waste generation from packaging, residual paints and chemicals
and their cans, Generation of wooden, glass, metal and other Scrap I materials, plumbing
and sanitary waste generation , creation of Impervious surfaces, noise pollution Suspended
dust pollution and risk of accidents.
Reply:
Risk assessment has been submitted in the EIA/EMP report in chapter 7.
17. Examine and submit the details of the environmental Impacts due to the laying of the water
supply system including aspects such as use of piping, fittings ad pumps, water pumping
stations, earth work-and water treatment - plant.
Reply: Details of Environment Impact mentioned in Chapter 4 Pg No. 91. All the details have
been given in the EIA/EMP report in chapter 5.
18. Examine and submit the details of the environmental impacts due to the lying of the
sewerage and sewage treatment and disposal system including aspects such as use of
5
construction material, piping, fittings ad pumps, earth work, laying of sewers & manholes,
sewage pumping stations and sewage treatment plant.
Reply: Details mentioned in Chapter 2 Pg No. 27. Details of material to be used are given in
Chapter 5 Pg no. 145.
19. Examine and submit the details of the environmental impacts due to the laying of the
storm water drainage system including aspects such as use of construction material, piping,
fittings and pumps, earth work, storm drains, storm water inlets and catch basins and
storm water outfalls.
Reply: Details of Environment Impact mentioned in Chapter 4 Pg No. 91. Details of material to
be used are given in Chapter 5 Pg no. 145.
20. Examine and submit the details of the environmental Impacts due to the electrical power
system and street lighting to be provided including aspects such as Construction materials
to be used, distribution lines, cables, Control panels, transformers and meters.
Reply: Details of Environment Impact mentioned in Chapter 4 Pg No. 91. Details of material to
be used are given in Chapter 5 Pg no. 143.
B. Operation Stage:
1. Examine and submit the details of the environmental impacts due to the residential,
commercial, Institutional, industrial, recreational, social, cultural & religious activities
to be carried out.
Reply: This is a commercial project which includes office, service apartment, retail etc.
Impact matrix due to project activity is summarized in Table 4.1 of Chapter 4.
2. Examine and submit the details of the environmental impacts due to the facilities to be
provided such as Water supply, electrical power supply, Fuel supply & consumption
including LPG, transportation and communication.
Reply: Refer Chapter 2, Section 2.12, 2.8, 2.11.
6
3. Examine and submit the details of the environmental impacts due to the coming up of
the activities such as urban agriculture and animal husbandry.
Reply: These impacts have not been anticipated due to this project.
4. Examine and submit the details of the environmental impacts due to the
sewerage & sewage treatment and its disposal systems and storm water & it drainage
system.
Reply: Refer EIA/EMP report, chapter 2, section 2.12. The permission for sewerage
disposal, storm water disposal, solid waste and water supply is enclosed as Annexure- 2(f).
5. Examine and submit the details of the environmental impacts caused due to the
generation of captive power & emergency power.
Reply: Refer EIA/EMP report, chapter 2, section 2.8.
6. Submit the details of the management & handing of municipal solid waste, e-waste,
hazardous waste, scrap, estate management, construction and demolition waste
management. The proposal of MSW should include the bio-composting of the organic
waste.
Reply: Refer EIA/EMP report, chapter 4, Section 4.6.1. The copy of permission of solid
waste management is enclosed as Annexure-2(f).
7. Submit the details of the socio economic impact due to the employment to be generated
from the household activities.
Reply: Once the development and construction of World Trade Centre will complete, there
will be some long-term positive impact on the economic structure of the area. People in the
area will get direct and indirect employment opportunities and other benefits from this
Project.
Therefore, overall positive impact is anticipated on economy of the area due to development
and construction activity of the World Trade Centre. Refer EIA/EMP report, Chapter 3,
Section 3.4.7.
7
General
1. Other details as indicated In Appendix III of EIA Notification 2006 and the manual titled
as “EIA guidance Manual-Building, Construction, Township and area Development
projects” published by the Ministry of Environment & Forests, New Delhi, should also be
attended.
Reply: Agreed
2. Environmental aspects identified under some of the project activities may not be
comprehensive and some of the significant aspects under some of the activities of the
project in question might not have been identified. All such environmental aspects may be
added to the list.
Reply: Project activities have been identified and all the Environmental aspects such as Air,
Water, Noise and Soil have been collected and baseline data of Knowledge Park at Sector 66-B,
82-A & 101-A, Mohali by GMADA during Oct to Dec, 2013 and additional one month baseline
study (12th May to 12th June, 2016) on project site is incorporated in the EIA/EMP report. Refer
Chapter 3.
3. Some of the activities with their associated environmental aspects of the project in question
might be of significant magnitude and not included in the list project activities. All such
activities may be added to the list of project activities.
Reply: Refer EIA/EMP report, Chapter 3
4. The project proponent may add additional project activities and environmental aspects, if
any, fill the Impact matrix (copy attached) and carryout significance analysis for
identifying the significant environmental aspects. Scale, sensitivity and duration of
Impacts; type, size and frequency of environmental aspects; applicable legal requirements;
and concerns of interested parties and local public may be used as the basis for the
significance analysis of the environmental aspects.
Reply: These activities have been studied and incorporated in EIA/EMP report, Refer chapter 4.
8
5. In the EIA study each of the environmental aspects listed In the ToR should be quantified,
their positive and negative impacts on different areas of impacts should be identified and
assessed and the results of such assessment should be reported in the EIA report.
Reply: Refer EIA/EMP report, Chapter 4.
6. In the environment Management Plan, management of each of the significant
environmental aspects (with identified and assessed significant environmental impacts) for
mitigating the impacts should be objectively stated.
Reply: Refer EIA/EMP report, Chapter 9.
7. Environment Management Plan should include technical and institutional aspects for pre-
treatment by constituent units.
Reply: Environment Management Plan has been included technical and institutional aspects.
Refer EIA/EMP report, Chapter 9.
8. Environmental Management Plan should be accompanied with Environmental Monitoring
Plan and environmental cost and benefit assessment.
Reply: Refer EIA/EMP report, Chapter 9, Table no 9.1
9. Examine separately the details for construction and operation phases both for
Environmental Management Plan and Environmental Monitoring Plan.
Reply: Refer EIA/EMP report, Chapter 9, Table no 9.1 & Chapter 10, Section 10.5
10. Does the company have a well laid down Environment Policy approved by its Board of
Directors? If so, it may be detailed in the EIA report.
Reply: Agreed. Refer Chapter 10, section 10.5
11. Does the Environment policy prescribe for standard operating process / procedures to
bring into focus any infringement / deviation / violation of the environmental or forest
norms / conditions? If so, it may be detailed In the EIA.
Reply: Not Applicable
9
12. What is the hierarchical system or Administrative order of the company to deal with the
environmental issues and for ensuring compliance with the EC conditions, Details of this
system may be given.
Reply: M/s. WTC NOIDA Development Company Pvt. Ltd manages the environmental
condition/ compliance through an in house team.
13. Does the company have a system of reporting of non compliances / violations of
environmental norms to the Board of Directors of the Company and / or shareholders or
stakeholders at large? This reporting mechanism should be detailed in the EIA report.
Reply: The details will be submitted at the time of SEAC meeting. Refer Chapter 10, section
10.5
14. Delineate the concrete proposal regarding activities to be undertaken under Corporate
Social Responsibility programme, which should be long lasting in nature and should be as
per the needs of a particular Village/area to be adopted by the promoter company, which
can be done by involving a person having knowledge and experience of socio-economic
activities.
Reply: CSR plan is enclosed as Annexure- 2(g) .
SANELAC CONSULTANTS PVT LTD
7-Apr-16I. ENERGY SAVING SUMMARY
II.Use of 15 watt LED Fixture as against 18 W CFL lamps for Guest rooms
0.10%
III. Use of 20 watt LED Fixture as against 36 W T5 lamps for Office 15.65%
IV. Use of 15 watt LED Fixture as against 18 W CFL lamps for common Area0.39%
V. Use of 20 watt LED Fixture instead of 28 W T5 lamps in Basements area0.39%
VI. Use of Solar backed LED landscape lights 0.02%
Total Saving (I + II + III + IV + V + VI) 16.56%
Note:
The following assumptions are made for Energy Saving calculations.
1)
2) Basement lamps are of 20 watt LED Fixture.
3) Common area lights are assumed as LED Fixture.
4)
PROJECT: WORLD TRADE CENTRE CHANDIGARH AT AEROCITY, MOHALI
ENERGY SAVING CALCULATION
ENERGY SAVING CAN BE ACHIEVED DUE TO FOLLOWING :
Guest room lights are of 15 watt LED Fixture.
External Lights are based on our proposal, which may change as per landscape details.
\\dataserver\DOCUMENTATION\MY DOC\MD 2016\WTC\EIA DATA\ELE\Energy Saving Calculation.xls Page-1
SANELAC CONSULTANTS PVT LTD
7-Apr-16I. ENERGY SAVING CALCULATION
1. Total energy consumption per annum
a. Load Demand : 6717.00 KW
b. Hours of operation : 16
c. Number of days : 365
d. Energy consumption per annum (6717 x 16 x 365) : 39,227,280 Units
1. CFL lamps (18 W) : 22 W
2. Lumen output : 1200
3. Lamp Life : 4000 Hrs.
4. LED Fixture : 15 W
5. Energy consumption with ballast : 15 W
6. Lumen output : 1200
7. Lamp Life : 10000 Hrs.
8. Saving in Energy (22 Watt – 15 Watt) : 7 Watt
9. Number of lights 15 Watt LED Fixture : 2190 Nos.
10. Electrical Load with CFL lamps (2190 Nos. x 22 W) : 48.18 KW
11. Electrical Load with 15 Watt LED Fixture (2190 Nos. x 15 W) : 32.85 KW
12. Saving in Electrical Load per unit (48.18 KW – 32.85 KW) : 15.33 KW
13. Considering diversity @ 70% : 10.73 KW
Say : 10.73 KW
14. Energy Saving / Annum
a. Hours of operation : 10
b. Number of days : 365
c. Energy saving / Annum (10.73 KW x 10 Hrs x 365 days) : 39,168 Units
d. % saving / Annum : 0.10%
PROJECT: WORLD TRADE CENTRE CHANDIGARH AT AEROCITY,
MOHALI
II. Energy Saving by 15 watt LED Fixture as against 18 W CFL lamps For Guest
rooms
PROJECT: WORLD TRADE CENTRE CHANDIGARH AT AEROCITY, MOHALI Page-2
SANELAC CONSULTANTS PVT LTD
III.
1. Fluorescent Lamps (36 watt) : 50 W
2. 20 watt LED Fixture : 20 W
3. Lamp Life : 10000 Hrs.
4. Saving in Energy (50 Watt – 20 Watt) per fitting to be used : 30 Watt
5. Total number of lights in Basement Area : 31155 Nos.
6. Saving in Electrical in Basement Area (30 W x 31155) ÷ 1000)
:934.65 KW
7. Considering diversity @ 90% : 841.19 KW
Say : 841.19 KW
8. Energy Saving / Annum
a. Hours of operation : 20
b. Number of days : 365
c. Energy saving / Annum (841.19 KW x 20 Hrs x 365 days) : 6,140,651 Units
d. % saving / Annum : 15.65%
1. CFL lamps : 22 W
2. 15 watt LED Fixture : 15 W
3. Lamp Life : 4000 Hrs.
4. Saving in Energy (22 Watt – 15 Watt) per fitting to be used : 7 Watt
5. Total number of lights in Basement Area : 10573 Nos.
6. Saving in Electrical in Basement Area (7 W x 10573) ÷ 1000)
:74.01 KW
7. Considering diversity @ 90% : 66.61 KW
8. Energy Saving / Annum
a. Hours of operation : 16
b. Number of days : 365
c. Energy saving / Annum (66.61 KW x 16 Hrs x 365 days) : 389,002 Units
d. % saving / Annum : 0.99%
1. T5 Lamps (28 watt) : 32 W
2. 20 watt LED Fixture : 20 W
3. Lamp Life : 10000 Hrs.
4. Saving in Energy (32 Watt – 20 Watt) per fitting to be used : 12 Watt
5. Total number of lights in Basement Area : 2435 Nos.
6. Saving in Electrical in Basement Area (12 W x 2435) ÷ 1000)
:29.22 KW
7. Considering diversity @ 90% : 26.30 KW
Energy Saving by 20 watt LED Fixture as against 36 W T5 lamps For Office.
IV.
V. Energy Saving by Using 20 watt LED Fixture as against 28 W T5 lamps in
Basement Area.
Energy Saving by Using 15 watt LED Fixture as against 18 W CFL lamps in
Common Area.
PROJECT: WORLD TRADE CENTRE CHANDIGARH AT AEROCITY, MOHALI Page-3
SANELAC CONSULTANTS PVT LTD
8. Energy Saving / Annum
a. Hours of operation : 16
b. Number of days : 365
c. Energy saving / Annum (26.3 KW x 16 Hrs x 365 days) : 153,580 Units
d. % saving / Annum : 0.39%
OUT DOOR LIGHTINGS
1. LED lamps : 70 W
2. Saving in Energy : 70 Watt
3. Number of lights : 30 Nos.
4. Saving in electrical Load with LED lights (30 Nos. x 70 W) : 2.10 KW
5. Energy Saving / Annum
a. Hours of operation : 12
b. Number of days (Excluding Rainy days) : 350
c. Energy saving / Annum (2.10 KW x 12 x 350) : 8,820 Units
d. % saving / Annum : 0.02%
VI. Energy Saving by Using 70 watt Solar backed LED fixture for Landscape Lighting
PROJECT: WORLD TRADE CENTRE CHANDIGARH AT AEROCITY, MOHALI Page-4