MSME PARKS : APPLICATIONS RECEIVED UNDER SAIP LOCATION OF THE PROPOSED PARKS P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K DISTRICT LOCATION DEVELOPER Bardhhama n Andal Bengal Aerotropolis Projects Ltd. Shaktigarh Shaktigarh Textiles & Industries Ltd. Hooghly Chanditala Vashist Infracon Pvt. Ltd. Howrah Domjur SD Infrastructure & Real Estate Pvt. Ltd. Lilluah South City Anmol Infra Park LLP PROPOSED PARKS: Lilluah South City Anmol Infra Park LLP Uluberia Patton International Ltd. Jalpaiguri Baikunthapur North Bengal Industrial Park Development Pvt. Ltd. Fulbarihat Amrit Vyapaar Pvt. Ltd. Binnagari North Bengal Industrial Park Infrastructures Pvt.Ltd. South 24 Paraganas BudgBudge Petrofarms Limited & Hindusthan Storage and Distribution Co. Ltd. Amtala Bengal Salarpuria Eden Infrastructure Development Company limited Location of Proposed Parks Map Courtesy: Maps of India

MSME PARKS : APPLICATIONS RECEIVED UNDER SAIP

Embed Size (px)

Citation preview

MSME PARKS : APPLICATIONS RECEIVED UNDER SAIPLOCATION OF THE PROPOSED PARKS

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

DISTRICT LOCATION DEVELOPER

Bardhhaman Andal Bengal Aerotropolis Projects Ltd.

Shaktigarh Shaktigarh Textiles & Industries Ltd.

Hooghly Chanditala Vashist Infracon Pvt. Ltd.

Howrah Domjur SD Infrastructure & Real Estate Pvt. Ltd.

Lilluah South City Anmol Infra Park LLP

PROPOSED PARKS:

Lilluah South City Anmol Infra Park LLP

Uluberia Patton International Ltd.

Jalpaiguri Baikunthapur North Bengal Industrial Park Development Pvt. Ltd.

Fulbarihat Amrit Vyapaar Pvt. Ltd.

Binnagari North Bengal Industrial Park Infrastructures Pvt.Ltd.

South 24 Paraganas BudgBudge Petrofarms Limited & Hindusthan Storage and

Distribution Co. Ltd.

Amtala Bengal Salarpuria Eden Infrastructure Development Company limited

Location of Proposed Parks

Map Courtesy: Maps of India

STATE-OF-THE-ART INFRASTRUCTURE• Connectivity- Advantageous location

and Connectivity• Integrated Transport Network

INDUSTRIAL PARK FOR MSME AT GOLDEN CITY INDUSTRIAL TOWNSHIP

PROJECT FEATURES• Connectivity- Located along NH 2 and

Andal- Ukhra Road; Durgapur,Asansol and Bardhhaman Town is 10km, 18 km and 65 km respectively

• Project Area- 66 .03 acre• MSME Units proposed– 72 nos• Project Cost- Rs.54.13 Cr• Proposed Investment- Rs 250 Cr• Expected Employment- 23,000

DEVELOPED BY: BENGAL AEROTROPOLIS PROJECTS LIMITEDANDAL, BARDDHAMAN

PROPOSED MSME PARK

PROPOSED MSME PARK

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

• Integrated Transport Network• Stable and low cost power• 24x 7 water supply• Integrated sewerage network with

ETP, STP• Integrated solid management system• Rainwater Harvesting and Renewable

energy• IT & telecom Supports; Call Centre• Dedicated infrastructure for MSME• Easy Registration and Trade Facilitation

Centre• Central Marketing for SME & Micro

Sector• Banking Support• Training & tool room,• Centralised Security & Infrastructure

Maintenance , etc.

INDUSTRIAL UNITS COMING UP• Polyfibre based manufacturing, cotton

spinning, auto parts manufacturing, small machine & equipment manufacturing , solar panel manufacturing, aluminum pre-cast channels, etc. (in large plots)

• Cable manufacturing, electric fans manufacturing, LED Manufacturing, Industrial fastener manufacturing, plastic sheet & plastic films manufacturing, UPS manufacturing, Ayurvedic Pharmaceutical, etc. (in medium plots)

• Garment, toys manufacturing, costume jewelry, agro food packaging, surgical products,, etc. (in multi-use floors)

K E Y M A P

PRESENT STATUSApproved in-principle under SAIP P R O P O S E D L A Y O U T

SHILPANGAN INDUSTRIAL PARK

PROJECT FEATURES• Spread over Mouza

Malanchaberia, Maheshpurand Routa

• Site 1000 m from NH 31; closeto SH 12 connecting Siliguriand Jalpaiguri;

• 14 km from Siliguri, 10 km from NJP Railway Station, 30 km from Bagdogra Airport

• Project Area- 107.61 acre• MSME Units proposed– 122

Nos• Project Cost- 134.08 Cr• Proposed Investment- Rs 580

DEVELOPED BY: NORTH BENGAL INDUSTRIAL PARK DEVELOPMENT PRIVATE LIMITEDBAIKUNTHAPUR, JALPAIGURI.

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

• Project Components- industrial plots of different sizes• Standard Design Factory of 1 Lakh sq. ft.; units ranging from 100 - 3000 sq. ft.• Common Amenities- Fabrication Unit, Clinic, Bank, Grocery , hardware, etc. • Water supply – integrated water supply network; Provision for 1000 KLD demand• Power supply- 33 KVA Substation already constructed by NIDPL; Demand- 7500

KVA; Ready HT/LT power at the door step of every plot• Integrated Road Network-Well lit internal road network; 3000 rm of 12 m wide

concrete road; 2200 rm of 24 m concrete road

• Drainage & sewerage- Properly designed drainage & Sewerage system coupled with rainwater harvesting system; CETP

• Common Facilities Building - telephone exchange, bank, conference room, room for service providers, etc.; over 60,000 sqft

• Employee Housing- Low Cost housing for Staff; Workers’ Colony of 3lakh sq. ft.

• Proposed Investment- Rs 580Cr

• Expected Employment- 23,000

K E Y M A P

PRESENT STATUS• Approved in-principle under SAIP

P R O P O S E D L A Y O U TSTATE-OF-THE-ART INFRASTRUCTURE

SOUTH CITY ANMOL INFRAPARK

PROJECT FEATURES• Located on NH 6 ; Kolkata 25 km; Liluah, Bally and

Santragachi Railway Stations at 1km, 4 km and 10 km;respectively.; Howrah Rail terminal -15 km

• Infra-park for micro, medium & small enterprises withlogistics cum warehousing facilities

• Industrial plots ranging from 500 sq. m to 2600 sq. m• Project Area- 24.31 acre• MSME Units proposed– 45 Nos• Project Cost- Rs. 54.63 Cr• Proposed Investment- Rs 155 Cr• Expected Employment- 3,000

DEVELOPED BY: SOUTH CITY ANMOL INFRA PARK LLPLILUAH, HOWRAH

PRESENT STATUS• Application submitted under SAIP

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

• Integrated Road network with three levels of road of 28.4 m, 20 m and 15m; each category designed with proper carriageway, medians and footpaths

• Water supply network – 200 m dia bore well; filtration plant; 2 lakh litre OHR; supply to plots through under PPR pipes; Stand- by system vide 2 lakh litre UGR

• Power Supply Network- Envisaged power supply to the park- 8000 KV. Provision of power for each plot -125 KW and for infrastructure & services 50 KW. 6300 KVA sub station; Buried cables under footpath through hume pipe with draw pits at interval; LT cables will be drawn to pillar boxes from where cables will be drawn to individual plots; Stand by power for street light and social infrastructure, estimated to be 75 KVA

• Drainage -Storm water drainage network with RCC drains on both sides of road with pre cast RCC slabs and catch-pits; each plot to be provided with master pit for storm water and waste water

• Sewerage – Either underground sewerage network of HDPE pipelines and inspection pit; Connection from plots to inspection pit through master trap within plots; STP capacity 1600 cu m/ day; or FRP STP’s for individual plots,

• Discharge to drainage lines through master pits• Fire Fighting- natural water bodies and UGR act as fire fighting storage; MS pipes

run under footpaths with fire hydrants • Solid Waste Management- One garbage Vat with one garbage compactor;

compacted garbage to be removed periodically; Alternatively a mobile garbage compactor and disposal vehicle will be operated by Park Authority

• Social Infrastructure- Trucker’s Amenity centre cum canteen, parking; ICT – fibre optic cable network

• Green Design-Rain water harvesting provisions through recharge of ground aquifers, harvesting of rain water in natural water bodies and rain water recharge pits; Waste Water Recycling; Re Use of the discharge of ETP; Landscaping of Medians and other green areas

K E Y M A P• Application submitted under SAIP

P R O P O S E D L A Y O U T

STATE-OF-THE-ART INFRASTRUCTURE

REGENT SME PARK DEVELOPED BY: SD INFRASTRUCTURE & REAL ESTATE PRIVATE LIMITED

DOMJUR, HOWRAH

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

PROJECT FEATURES• Located on Bombay Road

(NH 6) , Near SaraswatiBridge, Howrah

• MSME Units proposed– 644nos

• Project Area- 21.236 acre• Project Cost- Rs.371.10 Cr• Proposed Investment- Rs

371 Cr• Expected Employment-

15,000

K E Y M A P

PRESENT STATUS• Approved in-principle under SAIP

STATE-OF-THE-ART INFRASTRUCTURE

• Integrated Road Network; 18m and 10m wide Roads• Integrated Water Supply network own; total supply of 5 MLD; Source- bore well ;

Underground water reservoir and water treatment plant• Power supply through dedicated substation; 1 acre land earmarked fro

substation; Power supply of 11 MW• Underground Sewerage Network with STP, etc. (STP Capacity-4.2 MLD) • Storm Water Drainage network with suitable drain sections and

intermittent infiltration trenches

• Building for Common Facilities • Common amenities like rest houses, service areas, first aid centre, training &

testing lab, admin block, ATM, product display centre, warehouse, etc.• Education and Training Centre• Banking and Financial Institution• Residential Units for Staff and Workers hostel in separate zone

INDUSTRIAL UNITS COMING UP• MSME Units- Manufacturing and processing Units• Warehousing Facilities for the manufacturing Units

P R O P O S E D L A Y O U T

SHILPABROTO INDUSTRIAL PARKDEVELOPED BY: NORTH BENGAL INDUSTRIAL PARK INFRASTRUCTURES PRIVATE LIMITED

BINNAGARI, JALPAIGURI.

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

STATE-OF-THE-ART INFRASTRUCTURE• Standard design factory of 1 Lakh sq. ft.; units ranging from 100 sq. ft. to 3000 sq. ft.;

industrial Plots• Road Network- Well lit internal road network; 3500 rm of 12 m wide concrete road; Over

1000 rm of 24 m concrete road; Water supply – Provision of 1000 KLD • Drainage & Sewerage disposal system ; each unit with connection for discharge of storm

water; Common Effluent Treatment Plant• Power Supply- Ready HT/LT power will be available at the door step of every plot;

Dedicated 33 KVA Substation will be set up by NIIPL; Power demand- 7500 KVA• Common Facilities Building ( telephone exchange, bank, conference room, service

providers, etc.) -62600 sqft ; Workers’ Colony- 2.3 lakh sq. ft.

PROJECT FEATURES• Located in Sanyasikata, Binnagari; Site 1000 m from NH 31; close to SH 12

connecting Siliguri and Jalpaiguri;• 14 km from Siliguri, 10 km from NJP Railway Station, 30 km from Bagdogra

Airport• Project Area- 105.80 acre; MSME Units proposed– 145 Nos• Project Cost- 110.31 Cr• Proposed Investment- Rs 600 Cr; Expected Employment- 26,000

K E Y M A P

P R O P O S E D L A Y O U T

PRESENT STATUS• Approved in-principle under SAIP

FULBARI INDUSTRIAL PARK

PROJECT FEATURES•Located in Village Chhowa Vita,•Post: Fulbarihat.•Located on State Highway•9 km from heart of Siliguri town,

1.5 km from the Ghoshpukurbypass on SH 12A and 2.5 kmfrom Uttarkanya

• Industrial plots of different sizesranging from 14 to 60 Katha

•Project Area- 32.37 acre•MSME Units proposed– 38 Nos•Project Cost- Rs.23 Cr•Proposed Investment- Rs 150 Cr•Expected Employment- 6,500

K E Y M A P

DEVELOPED BY: AMRIT VYAPAAR PRIVATE LIMITEDFULBARIHAT, JALPAIGURI.

PRESENT STATUS

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

STATE-OF-THE-ART INFRASTRUCTURE• Integrated Road Network with 12 m wide metaled trunk road; and 10 m wide

internal metaled road with single/both side RCC drains; Navigation Map on each island

• Drainage and Sewerage Network- Integrated network with CETP & STP• Water supply Network with boring, 7.5 HP submersible pump, water treatment

plant and OHR• Power Supply- Dedicated Substation; 11 KV transmission lines; step down

transformer; Provision for 5000 KVA power supply for the whole park; 0.537 acre land earmarked

• Adequate Green Patches; Plantation along boundary wall; community parks• Common fire fighting arrangement with network of live water hydrant along each

unit; 200 KL dedicated UGR for fire fighting; 125 KVA dedicated DG for fire fighting• Common Amenities like canteen, guest house, Sulabh, 60 MT weigh bridge, 6000

sq. m car & truck parking, separate community hall for industrial and residential, etc.

• Space for Staff and workers flats

•Expected Employment- 6,500PRESENT STATUS• Approved in-principle under SAIP

P R O P O S E D L A Y O U T

ULUBERIA INDUSTRIAL PARKDEVELOPED BY: PATTON INTERNATIONAL LIMITED

ULUBERIA, HOWRAH

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

STATE-OF-THE-ART INFRASTRUCTURE• Industrial Units, Warehouses and Common/

ancillary facilities• Support Facilities like loading & Unloading Bay,

Weigh Bridge, Truck & car parking, Food Stalls. • Integrated network of All utilities

UNITS COMING UP• Serviced plots for small and medium scale

industries and multi-level standard design factory

• Big units of Howrah and Kolkata will act as the catchment area of the MSME Park

PROJECT FEATURES• NH 6 is the main approach to the site• Location close to Uluberia Growth

Centre• Easy and fast access to Mumbai and

Central India (via NH 6)• Santragachi Railway Station, Jalan

Industrial Complex, Vidya Sagar Setuat 9km, 2 km and 12 km respectively

• Proposed MSME Unit- 24 Nos• Project Area- 56.12 acre• Project Cost- Rs. 235.57 Cr• Proposed Investment- Rs 1180 Cr• Expected Employment- 8000.

K E Y M A P

PRESENT STATUS• Approved in-principle

under SAIP

P R O P O S E D L A Y O U T

STATE-OF-THE-ART INFRASTRUCTURE• Integrated Road network- 30m and 24 m wide main arterial road; 18m & 15 m wide main

internal road• Voice and data network connectivity- WBIDC is providing the facility; local network

connectivity already available

INDUSTRIAL PARK OF BAJRANGBALI COMMERCIAL HUB (PHASE I)

PROJECT FEATURES• Connectivity- Located along NH 2 and Andal- Ukhra Road; Durgapur, Asansol and

Bardhhaman Town is 10 km, 18 km and 65 km respectively• Project Area- 20 acre• MSME Units proposed– 23 Nos• Project Cost- Rs.14.03 Cr• Proposed Investment- Rs 55 Cr; Expected Employment- 1,200

K E Y M A P

DEVELOPED BY: VASHIST INFRACON PRIVATE LIMITEDCHANDITALA, HOOGHLY

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

PRESENT STATUS• Application Submitted under SAIP• Application Submitted under SAIP

P R O P O S E D L A Y O U T

SHAKTIGARH JUTE PARK

INDUSTRIAL UNITS COMING UP• Spinning, wet processing,

Mackloom Unit, stitching, fine hessian finishing , auxiliary unis like raw jute & jute products warehousing, packaging units

K E Y M A P

DEVELOPED BY: SHAKTIGARH TEXTILES & INDUSTRIES LIMITEDSHAKTIGARH, BARDDHAMAN

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

PRESENT STATUS• Application submitted

under SAIP

PROJECT SITE

• Integrated Road network ; 2500 rft of 20 feet wide road • Water Supply- Provision for Daily Water Supply of 80000 L • Drainage and Sewerage- rectangular drains of length 9000 ft.; underground

sewerage network and STP; ETP of Capacity 40000 liter per day; raw effluent to be taken through SW pipes followed by plain sedimentation, primary settling & clarification, FAB reactor, Secondary settling and clarification, chlorination, filtration by multi-grade filters, activated carbon filters.

• Power Supply-Total connected load 2800 KVA; peak demand- 2.8 MW; 1 33KV/415 V substation within area; 4 nos 700 KVA transformer; captive DG set

• Fire Fighting system- Centralised fire station; storage for 2 hours of flow demand• Common facilities- Quality testing lab, design and product development centre,

training centre, common tool room& workshop facilities, market Information & Business Centre, Conference Hall, 5000MT capacity warehouse for raw and finished goods, admin block, canteen, guesthouse

PROJECT FEATURES

• 90 km from Kolkata; well connected with NH 2• Jute growing areas in the surrounding;• well connected through a network of highways and

railways• Reduction of fixed cost of assets for participating units• Better operational efficiency and supply- chain

management• Expected Employment- 9,000• Proposed Investment- Rs 95 Cr

• Presence of an Anchor unit; it will ensure strongmarket linkages for local entrepreneurs; develop bettermarket penetration

• Estimated Volume of finished product- 160 MT;Combined turnover of all units- 130 Cr; export around8750 MT per annum valuing Rs 27 Cr

• Project Area- 23.86 acre• MSME Units proposed– 20 Nos• Project Cost- Rs 24.46 Cr

K E Y M A P

P R O P O S E D L A Y O U T( s c a n n e d i m a g e )STATE-OF-THE-ART INFRASTRUCTURE

BUDGE BUDGE INDUSTRIAL PARK

PROJECT FEATURES• Connectivity- Short distance

from Kolkata; upcoming flyoverfrom Taratala to Batanagarenroute the site

• Existing significant volume ofcargo movement from BudgeBudge port

• Project Area- 80 acre• MSME Units proposed– 20 nos• Project Cost- Rs. 50.59 Cr• Proposed Investment- Rs 100 Cr• Expected Employment- 10,000

DEVELOPED BY: PETROFARMS LIMITED & HINDUSTHAN STORAGE AND DISTRIBUTION CO. LTD.BUDGE BUDGE, SOUTH 24 PARGANAS

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

PROJECT SITE

STATE-OF-THE-ART INFRASTRUCTURE• 750 MW thermal power station of CESC at 2 km ; 24 x7 quality power supply• Common facilities- logistics facilities like weigh bridge; admin building, training

centre, canteen, workers hostel, trade/ display centre, ATM counter, recreation centre

• Water supply – approx. 2 MLD; Deep tube wells, OHR; pipeline connection of Ganges water to the site; water treatment plant ; RCC pipe

• Workers’ C& employees housing- 4.35 lakh sq. ft.; on 4 acre• Common Effluent Treatment Plant• Area earmarked for substation- 0.3 acre; Power demand 12000 KVA• Street lighting poles @ 10 m interval• Storm Water Drainage & Sewerage system- Hume pipes; STP • Common fire fighting system with pumps, hoses & nozzle, Alarm system and

extinguishers

• Solid waste disposal (no detail)• Internal road network of 4.6 km; mainly of 10 m wide road network; entrance of

15 m • 24 hours security surveillance system• Green and sustainable energy

K E Y M A P

PRESENT STATUS• Application submitted under SAIP

P R O P O S E D L A Y O U T

AMTALA INDUSTRIAL PARK

K E Y M A P

DEVELOPED BY: BENGAL SALARPURIA EDEN INFRASTRUCTURE DEVELOPMENT CO. PVT. LTD.AMTALA, SOUTH 24 PARAGANAS

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

PROJECT SITE

INDUSTRIAL UNITS COMING UP• Engineering, Machinery & Parts,

Electrical Items, Chemicals, Plastics and Polymers

PROJECT FEATURES• 400 m from Amtala Crossing• NH 117 on the east, Nibaran Dutta on the

North, Borhanpur Village Road on the West,Gotalahat Road on the south

• To be developed on cluster model; to enhancemarket linkages and anciliarisation

• Project Area- 116 acre• MSME Units proposed- 62• Project Cost- Rs 125.67 Cr• Proposed Investment- Rs 290 Cr• Expected Employment- 13,000 P R O P O S E D L A Y O U T

PRESENT STATUS• Application submitted under SAIP ST

ATE

OF

THE

ART

INFR

ASTR

UCT

URE

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

F O R E N Q U I R Y

SL. NO. LOCATION DEVELOPER NAME & ADDRESS

1 Andal Bengal AerotropolisProjects Ltd.

Mr. Partho Ghosh, Managing Director5 Gorky Terrace, Kolkata-700017Phone- 033-40201753; Email- [email protected]

2 Shaktigarh Shaktigarh Textiles & Industries Ltd.

Mr. Yuvraj Agarwal, General ManagerAddress: Rly Stn Shaktigarh Barshul , Burdwan, West [email protected]

3 Chanditala Vashist Infracon Pvt. Ltd.Mr. Nitesh Kumar Singh, DirectorAddress- 270/15, G.T. Road Liluah, Howrah - 7112043 Chanditala Vashist Infracon Pvt. Ltd. Address- 270/15, G.T. Road Liluah, Howrah - 711204Phone- 0342-3203637; Email- [email protected]

4 Domjur SD Infrastructure & Real Estate Pvt. Ltd.

Mr. SL Dugar, Director8/1, Lal Bazar Street, Kolkata-700001Phone-033-44500545; [email protected]

5 Lilluah South City Anmol Infra Park LLP

Mr. Sushil Mohta, Director375 Prince Anwar Shah Road. Kolkata-700068Phone- Email- [email protected]

6 Uluberia Patton International Ltd.Mr. Sanjay Budhia, Managing Director3C, Camac Street. Kolkata-700016Phone- 033-22294369; [email protected]

7 Baikunthapur North Bengal Industrial Park Development Pvt. Ltd.

Mr. Naresh Agarwal, DirectorUttarapan Market Complex, Hill Cart Road. Siliguri-734003Phone- 0353-2510040; Email- [email protected]

P R O J E C T S U N D E R S C H E M E F O R A P P R O V E D I N D U S T R I A L P A R K

FOR ENQUIRY

SL. NO. LOCATION DEVELOPER NAME & ADDRESS

8 Fulbarihat Amrit Vyapaar Pvt. Ltd.Mr. Ratan K. Bihani, Director327, Bidhan Road. Siliguri- 734001Phone- 0353-2430949; Email- [email protected]

9 BinnagariNorth Bengal Industrial Park Infrastructures

Mr. Naresh Agarwal, DirectorUttarapan Market Complex, Hill Cart Road. Siliguri-7340039 Binnagari Park Infrastructures

Pvt.Ltd.Uttarapan Market Complex, Hill Cart Road. Siliguri-734003Phone- 0353-2510040; Email- [email protected]

10 BudgBudge Petrofarms Limited & Hindusthan Storage and Distribution Co. Ltd.

Mr. Vedanta Saraf, Director53B, Chowringhee Lane, KolkataPhone- 033-22820915; Email- [email protected]

11 Amtala

Bengal Salarpuria Eden Infrastructure Development Company limited

Mr. S K Mohanty, Vice President (Legal)SS Chamber, 5 Chittaranjan Avenue; Kolkata-700072Telephone- 033-40306000; Email- [email protected]