Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
CDL Land NZ Ltd – 7-11 Christian Road, Swanson– Engineering Report
October 2017
15
APPENDIX B
USLE Calculations
ESTIMATION OF SEDIMENT YIELD
BY THE UNIVERSAL SOIL LOSS EQUATION
PROJECT NO.: 1167
SITE LOCATION: 7-11 Christian Road, Swanson
CLIENT: CDL Land NZ Limited
DATE: 20/10/2017
CALCULATED: D. Morris
CHECKED: V. Crang
ANALYSIS PERIOD: PRE-EARTHWORKS 6 MONTH PERIOD
FILE LOCATION:
CATCHMENT:
Total: Site 1 Site 2
DURATION (years): 0.5 0.5
AREA (Ha): 4.1 0 1.6 2.5
A = R x K x LS x C x P (Goldman et al (1986))
where:
A = soil loss (tonnes/ha/year)
Rainfall erosion index (R ):
R = 0.00828 * (P)^2.2 *1.70
Where P = the rainfall figure from 6 hours duration 2 years storm event
For Auckland Region, refer to ARC TP108, Fig A.1, and multipply the 2 year depth by 0.628
TP108 2 year depth = 88 mm (From Graph in TP108)
P = 55 mm
R = 96
Soil erodibility index (K): (from triangular nomograph)
Wischmeier et al. Nomograph (1971)
Kfact
= (1.292) [2.1e-6
x fp
1.14
(12 - Pom
)+ 0.0325 (Sstruc
- 2)+ 0.025 (fperm
-3)]
where fp = P
silt (100 - P
clay)
fp = particle size parameter (unitless)
Pclay = the percent clay (unitless).
Pclay = 44 %
Psilt = the percent silt (unitless).
Psilt = 56 %
fp = 3136
Pom = percentage organic matter (unitless)
Pom = 2 % (estimate)
Sstruc = the soil structure index (unitless)
= 1 very fine granular soils
= 2 fine granular soil
= 3 medium or coarse granular soil
= 4 blocky, platy or massive soil
Sstruc = 2 fine granular soil
fperm = the profile-permeability class factor (unitless)
= 1 very slow infiltration
= 2 slow infiltration
= 3 slow to moderate infiltration
= 4 moderate infiltration
= 5 moderate to rapid infiltration
= 6 rapid infiltration
fperm = 3 slow to moderate infiltration
K = 0.26 (nomograph)
P:\1167 - 10 Tram Valley 7 Christian Rd\6.0 Reports\Engineering Report\[USLE Calculations.xlsx]Pre
ANALYSIS DETAILS
WORKING FORMULA (USLE)
Page 1 of 6
K Factor Data ( Organic Matter Content)
Average Less than 2 % More than 2 %
Clay 0.22 0.24 0.21
Clay Loam 0.3 0.33 0.28
Coarse Sandy Loam 0.07 -- 0.07
Fine Sand 0.08 0.09 0.06
Fine Sandy Loam 0.18 0.22 0.17
Heavy Clay 0.17 0.19 0.15
Loam 0.3 0.34 0.26
Loamy Fine Sand 0.11 0.15 0.09
Loamy Sand 0.04 0.05 0.04
Loamy Very Fine Sand 0.39 0.44 0.25
Sand 0.02 0.03 0.01
Sandy Clay Loam 0.2 -- 0.2
Sandy Loam 0.13 0.14 0.12
Silt Loam 0.38 0.41 0.37
Silty Clay 0.26 0.27 0.26
Silty Clay Loam 0.32 0.35 0.3
Very Fine Sand 0.43 0.46 0.37
Very Fine Sandy Loam 0.35 0.41 0.33
Select Design K for Each Area
Upstream Site 1 Site 2
K = 0 0.5 0.5
Conversion to metric multiply K by 1.32
K = 0 0.66 0.66
Slope length and steepness factor (LS):
Goldman et al (1986) have expressed LS factor as :
where:
Sslope
= the slope gradient, %
a = a factor in the LS equation, unitless
a = (Sslope
2
+10,000)0.5
Lslope
= slope length (cm)
mLS
= the exponent in the LS factor equation, unitless
Sslope < 1% 1% - 3% 3.5% - 4.5% > 5%
mLS
0.2 0.3 0.4 0.5
Upstream Site 1 Site 2 Site 3 Site 4 Site 5
Slope Length (m) = 200 240
Avg Change in Slope Elevation = 12 20
Slope (%) = 0.0% 6.0% 8.3%
a = 100.0 100.2 100.3
mLS
= 0.2 0.5 0.5
LS = 0.00 1.72 2.95
Ground Cover Factor (C):
(after Kay (1983), USDA (1975), Wischmeier and Smith (1978), as reported by Goldman (1986)
Type of Cover C Soil Loss
Reduction, %
None 1.0 0
Native vegetation (undisturbed) 0.01 99
Temporary Seedings:
90% Cover, annual grasses, no mulch 0.1 90
Wood fiber mulch, 1.7 t/Ha, with seed* 0.5 50
Excelsior mat, jute* 0.3 70
Straw mulch*:
3.4 t/Ha, tacked down 0.2 80
9 t/Ha, tacked down 0.05 95
* For slopes up to 2:1
Textural Class
LSm
slope
slopeslopeL
a
S
a
SS 4
2
2
1053.4065.056.441.65
Page 2 of 6
Upstream Site 1 Site 2
C = 0.00 0.15 0.15
Erosion Control Practice Factor (P):
(after Ports (1973))
Erosion Control Practice P
Surface Condition with No Cover
Compact, smooth, scraped with buldozer or scraped up and downhill 1.30
Same as above, except raked with bulldozer and root-raked up and downhill 1.20
Compact, smooth, scraped with buldozer or scraped across the slope 1.20
Same as above, raked with bulldozer and root-raked across slope 0.90
Loose, as a disked plow layer 1.00
Rough irregular surface, equipment tracks in all directions 0.90
Loose with rough surface 0.3m depth 0.80
Loose with smooth surface 0.3m depth 0.90
Structures
Small Sediment Basins:
0.09 basins /Ha 0.50
0.13 basins /Ha 0.30
Downstream Sediment Basins:
With chemical flocculants 0.10
Without chemical flocculants 0.20
Erosion Control Structures:
Normal rate usage 0.50
High rate usage 0.40
Strip building 0.75
Upstream Site 1 Site 2
P = 0 1 1
Sediment Delivery Ration (SDR)
SDR = 0 (range 0 - 1)
Typically 0.5 is an accepted value. However if slopes are steep, and /or immediately adjacent to the receiving
environment, the sediment ratio may be considerably higher, eg 0.7 for slopes > 10°. For concave slopes
the sediment delivery may be somewhat lower.
Sediment Control Efficiency (SCE):**
SCE = 0%
50% is considered conservativel appropriate for most measures. 75% wiould be considered an upper limit in
Auckland soils. Flocculation or coarse grained soils may give a somewhat higher efficiency.
** The USLE predicts the total yield of sediment generated but makes no allowance for that retained
on site. A Sediment Delivery Ratio (SDR) must be selected. American sources state that SDR
rates range mostly from 10% to 70% (N.Y. Guidelines for Urban Erosion and Sediment Control)
R K LS C P
UPSTREAM 96 0 0 0.00 0
Site 1 96 0.66 1.72 0.15 1
Site 2 96 0.66 2.95 0.15 1
AREA TIME
(Ha) (yr)
UPSTREAM 0 0
Site 1 1.6 0.5
Site 2 2.5 0.5
TOTAL GROSS YIELD FOR SITE (t) 48.11
0.00
EST.GROSS SEDIMENT
YIELD FOR SITE (t)
16.4
28.0
SECTION
ESTIMATION OF SEDIMENT
SECTIONUSLE PARAMETERS Avg annual soil loss
A (t/Ha/yr)
0.0
13.09
35.02
Page 3 of 6
ESTIMATION OF SEDIMENT YIELD
BY THE UNIVERSAL SOIL LOSS EQUATION
PROJECT NO.: 1167
SITE LOCATION: 7-11 Christian Road, Swanson
CLIENT: CDL Land NZ Limited
DATE: 20/10/2017
CALCULATED: D. Morris
CHECKED: V. Crang
ANALYSIS PERIOD: DURING EARTHWORKS 6 MONTH PERIOD
FILE LOCATION:
CATCHMENT:
Upstream Area 1 Area 2
DURATION (years): 0 0.5 0.5
AREA (ha): 0 1.6 2.5
A = R x K x LS x C x P (Goldman et al (1986))
where:
A = soil loss (tonnes/ha/year)
Rainfall erosion index (R ):
R = 0.00828 * (P)^2.2 *1.70
Where P = the rainfall figure from 6 hours duration 2 years storm event
For Auckland Region, refer to ARC TP108, Fig A.1, and multipply the 2 year depth by 0.628
TP108 2 year depth = 88 mm (From Graph in TP108)
P = 55 mm
R = 96
Soil erodibility index (K): (from triangular nomograph)
Wischmeier et al. Nomograph (1971)
Kfact
= (1.292) [2.1e-6
x fp
1.14
(12 - Pom
)+ 0.0325 (Sstruc
- 2)+ 0.025 (fperm
-3)]
where fp = P
silt (100 - P
clay)
fp = particle size parameter (unitless)
Pclay = the percent clay (unitless).
Pclay = 44 %
Psilt = the percent silt (unitless).
Psilt = 56 %
fp = 3136
Pom = percentage organic matter (unitless)
Pom = 2 % (estimate)
Sstruc = the soil structure index (unitless)
= 1 very fine granular soils
= 2 fine granular soil
= 3 medium or coarse granular soil
= 4 blocky, platy or massive soil
Sstruc = 2 fine granular soil
fperm = the profile-permeability class factor (unitless)
= 1 very slow infiltration
= 2 slow infiltration
= 3 slow to moderate infiltration
= 4 moderate infiltration
= 5 moderate to rapid infiltration
= 6 rapid infiltration
fperm = 3 slow to moderate infiltration
K = 0.26 (nomograph)
ANALYSIS DETAILS
WORKING FORMULA (USLE)
P:\1167 - 10 Tram Valley 7 Christian Rd\6.0 Reports\Engineering Report\[USLE
Calculations.xlsx]During
Page 4 of 6
K Factor Data ( Organic Matter Content)
Average Less than 2 % More than 2 %
Clay 0.22 0.24 0.21
Clay Loam 0.3 0.33 0.28
Coarse Sandy Loam 0.07 -- 0.07
Fine Sand 0.08 0.09 0.06
Fine Sandy Loam 0.18 0.22 0.17
Heavy Clay 0.17 0.19 0.15
Loam 0.3 0.34 0.26
Loamy Fine Sand 0.11 0.15 0.09
Loamy Sand 0.04 0.05 0.04
Loamy Very Fine Sand 0.39 0.44 0.25
Sand 0.02 0.03 0.01
Sandy Clay Loam 0.2 -- 0.2
Sandy Loam 0.13 0.14 0.12
Silt Loam 0.38 0.41 0.37
Silty Clay 0.26 0.27 0.26
Silty Clay Loam 0.32 0.35 0.3
Very Fine Sand 0.43 0.46 0.37
Very Fine Sandy Loam 0.35 0.41 0.33
Select Design K for Each Area
Upstream Area 1 Area 2
K = 0 0.26 0.26
Conversion to metric multiply K by 1.32
K = 0 0.3432 0.3432
Slope length and steepness factor (LS):
Goldman et al (1986) have expressed LS factor as :
where:
Sslope
= the slope gradient, %
a = a factor in the LS equation, unitless
a = (Sslope
2
+10,000)0.5
Lslope
= slope length (cm)
mLS
= the exponent in the LS factor equation, unitless
Sslope < 1% 1% - 3% 3.5% - 4.5% > 5%
mLS
0.2 0.3 0.4 0.5
Upstream Area 1 Area 2
Slope Length (m) = 200 240
Avg Change in Slope Elevation = 12 20
Slope (%) = 0.0% 6.0% 8.3%
a = 100.0 100.2 100.3
mLS
= 0.2 0.5 0.5
LS = 0.00 1.72 2.95
Ground Cover Factor (C):
(after Kay (1983), USDA (1975), Wischmeier and Smith (1978), as reported by Goldman (1986)
Type of Cover C Soil Loss
Reduction, %
None 1.0 0
Native vegetation (undisturbed) 0.01 99
Temporary Seedings:
90% Cover, annual grasses, no mulch 0.1 90
Wood fiber mulch, 1.7 t/Ha, with seed* 0.5 50
Excelsior mat, jute* 0.3 70
Straw mulch*:
3.4 t/Ha, tacked down 0.2 80
9 t/Ha, tacked down 0.05 95
* For slopes up to 2:1
Textural Class
LSm
slope
slopeslopeL
a
S
a
SS 4
2
2
1053.4065.056.441.65
Page 5 of 6
Upstream Area 1 Area 2
C = 0.0 1.0 1.0
Erosion Control Practice Factor (P):
(after Ports (1973))
Erosion Control Practice P
Surface Condition with No Cover
Compact, smooth, scraped with buldozer or scraped up and downhill 1.30
Same as above, except raked with bulldozer and root-raked up and downhill 1.20
Compact, smooth, scraped with buldozer or scraped across the slope 1.20
Same as above, raked with bulldozer and root-raked across slope 0.90
Loose, as a disked plow layer 1.00
Rough irregular surface, equipment tracks in all directions 0.90
Loose with rough surface 0.3m depth 0.80
Loose with smooth surface 0.3m depth 0.90
Structures
Small Sediment Basins:
0.09 basins /Ha 0.50
0.13 basins /Ha 0.30
Downstream Sediment Basins:
With chemical flocculants 0.10
Without chemical flocculants 0.20
Erosion Control Structures:
Normal rate usage 0.50
High rate usage 0.40
Strip building 0.75
Upstream Area 1 Area 2
P = 0 1.3 1.3
Sediment Delivery Ration (SDR)
SDR = 0.5 (range 0 - 1)
Typically 0.5 is an accepted value. However if slopes are steep, and /or immediately adjacent to the receiving
environment, the sediment ratio may be considerably higher, eg 0.7 for slopes > 10°. For concave slopes
the sediment delivery may be somewhat lower.
Sediment Control Efficiency (SCE):**
SCE = 75%
50% is considered conservativel appropriate for most measures. 75% wiould be considered an upper limit in
Auckland soils. Flocculation or coarse grained soils may give a somewhat higher efficiency.
** The USLE predicts the total yield of sediment generated but makes no allowance for that retained
on site. A Sediment Delivery Ratio (SDR) must be selected. American sources state that SDR
rates range mostly from 10% to 70% (N.Y. Guidelines for Urban Erosion and Sediment Control)
R K LS C P
UPSTREAM 96 0 0 0.0 0
Area 1 96 0.34 1.72 1.00 1.3
Area 2 96 0.34 2.95 1.00 1.3
AREA TIME SDR SCE
(Ha) (yr) %
UPSTREAM 0 0 0.5 75%
Area 1 1.6 0.5 0.5 75%
Area 2 2.5 0.5 0.5 75%
TOTAL GROSS YIELD FOR SITE (t) 216.8
27.1
ESTIMATION OF SEDIMENT
SECTIONUSLE PARAMETERS Avg annual soil loss
A (t/Ha/yr)
0.0
73.8
126.2
59.01 7.4
157.81 19.7
SECTIONEST.GROSS SEDIMENT NET SEDIMENT
YIELD FOR SITE (t) LOSS (t)
0.00 0.0
ESTIMATED TOTAL NET SEDIMENT LOSS (t)
Page 6 of 6
CDL Land NZ Ltd – 7-11 Christian Road, Swanson– Engineering Report
October 2017
16
APPENDIX C
STORMWATER CALCULATIONS
STORMWATER CALCULATIONS
Project
Job No. 1167 Calculations By: DAVID DATE 17/10/17
Storm Frequency 10 year Duration=10min VC DATE
To Catchment Run off Equiv. Total This Design Pipe Comments
MH MH Area (m2) Coef. Area Eqiv. Rainfall Int line Q S % Pipe D V(m/s) Pipe D Capacity
No No Incr. C (C*A) Area I (mm/sec) only(l/s) (mm) (mm) (l/s)
LINE 2
2/3 2/2 4040 0.70 2828 2828 0.0302 85 0.70 300ф 1.17 300ф 180 Lot 7 & 8
2/2 2/1 0 0.70 0 2828 0.0302 85 0.70 300ф 1.17 300ф 290
2/1 1/8 4001 0.70 2801 5629 0.0302 170 0.86 375ф 1.5 375ф 274 Lot 5 & 6
LINE 1
1/9 1/8 832 0.85 707 707 0.0302 21 Road 1 & Accessway 2 CP
1246 0.70 872 1579 0.0302 48 1.05 225ф 1.19 225ф 80.8 Lot 3
1/8 1/7 1244 0.70 871 2450 0.0302 74 Lot 2
457 0.85 388 2839 0.0302 86 Accessway 1 CP
0 0.70 0 8467 0.0302 256 1.95 375ф 2.26 375ф 392 Added Line 2
1/7 1/6 1200 0.70 840 9307 0.0302 281 0.90 450ф 1.73 450ф 299 Lot 1
1/6 1/5 1205 0.70 844 10151 0.0302 307 1.91 Lot 20 & 21
1610 0.85 1369 11519 0.0302 348 1.40 450ф 2.16 450ф 583 Road 1 CP
1/5 1/4 2385 0.70 1670 13189 0.0302 398 0.64 525ф 1.8 525ф 639 Lot 22 to 25
1/4 1/3 0 0.70 0 13189 0.0302 398 0.32 600ф 1.38 600ф 556
1/3 1/2 703 0.70 492 13681 0.0302 413 0.34 600ф 1.43 600ф 507 Lot 26
1/2 1/1 615 0.70 431 14111 0.0302 426 0.36 600ф 1.47 675ф 616 Lot 27
LINE 4
4/1 3/3 601 0.70 421 421 0.0302 13 0.10 225ф 0.36 225ф 67 Lot 30
LINE 3
3/6 3/5 600 0.70 420 420 0.0302 13 0.10 225ф 225ф 40.5 Lot 33
3/5 3/4 600 0.70 420 840 0.0302 25 0.28 225ф 0.61 225ф 53.5 Lot 32
3/4 3/3 1205 0.70 844 1684 0.0302 51 Lot 29 & 31
617 0.85 524 2208 0.0302 67 0.43 225ф 0.92 300ф 220 Road 2 CP
3/3 3/2 635 0.70 445 2652 0.0302 80 Lot 28
49 0.85 42 2694 0.0302 81 Accessway CP
3115 0.0302 94 0.88 300ф 1.3 375ф 315 Added Line 4
3/2 3/1 1190 0.85 1012 4126 0.0302 125 0.47 375ф 1.11 450ф 211 Road 2 CP
LINE 5
5/2 5/1 580 0.85 493 493 0.0302 15 0.11 225ф 0.38 225ф 141 Christian Road CP
CDL - CHRISTIAN ROAD
1 24/10/2017
LINE 6
6/2 6/1 600 0.70 420 420 0.0302 13 0.10 225ф 0.36 225ф 67.7 Lot 47
LINE 7
7/3 7/2 840 0.85 714 714 0.0302 22 0.22 225ф 0.54 225ф 152 Lot 48
7/2 7/1 640 0.70 448 1162 0.0302 35 0.56 225ф 0.87 300ф 102 Christian Road
LINE 8
8/2 8/1 610 0.70 427 427 0.0302 13 0.10 225ф 0.36 225ф 33.4 Lot 46
LINE 12
12/2 12/1 705 0.70 494 494 0.0302 15 0.88 150ф 0.86 150ф 33.3 Lot 36
LINE 11
11/2 11/1 620 0.70 434 434 0.0302 13 Lot 38
95 0.85 81 515 0.0302 16 0.12 225ф 0.4 225ф 152 Accessway 5 CP
11/1 10/5 745 0.70 522 1036 0.0302 31 Lot 37
1530 0.0302 46 0.96 225ф 1.14 225ф 152 Added Line 12
LINE 10c
10c/1 10/2 710 0.85 604 604 0.0302 18 0.15 225ф 4.78 225ф 104 Road 3
LINE 10b
10b/1 10/8 2002 0.70 1401 1401 0.0302 42 6.80 150ф 2.31 150ф 49 Lot 19
LINE 10a
10a/7 10a/6 2000 0.70 1400 1400 0.0302 42 0.78 225ф 1.02 225ф 152 Lot 18
10a/6 10a/5 2513 0.70 1759 3159 0.0302 95 0.88 300ф 1.31 300ф 247 Lot 14 & 15
10a/5 10a/4 1257 0.70 880 4039 0.0302 122 Lot 16
705 0.85 599 4638 0.0302 140 Road 1 CP
1070 0.85 910 5548 0.0302 168 Christian Road CP
6949 0.0302 210 0.50 450ф 1.29 375ф 292 Added Line 10b
10a/4 10a/3 1300 0.70 910 7859 0.0302 237 Lot 39 & 40
658 0.85 559 8418 0.0302 254 0.74 450ф 1.57 375ф 461 Christian Road CP
10a/3 10a/2 1300 0.70 910 9328 0.0302 282 Lot 41 & 42
606 0.85 515 9844 0.0302 297 1.00 450ф 1.82 450ф 535 Christian Road CP
10a/2 10a/1 660 0.70 462 10306 0.0302 311 Lot 43
LINE 10 11835 0.0302 357 0.25 600ф 1.22 600ф 507 Added Line 11
10/4 10/3 601 0.70 421 421 0.0302 13 Lot 35
546 0.85 464 885 0.0302 27 0.33 225ф 0.66 225ф 117 Road 3 CP
10/3 10/2 2150 0.70 1505 2390 0.0302 72 0.50 300ф 0.99 300ф 247 Lot 34,44 & 45
10/2 10/1 1410 0.85 1199 3588 0.0302 108 0.35 375ф 1.26 375ф 143 Road 3 CP
LINE 14
14/1 13/2 1261 0.70 883 883 0.0302 27 Lot 4
222 0.85 189 1071 0.0302 32 0.47 225ф 0.5 225ф 33.7 Accessway 3 CP
LINE 13
13/3 13/1 27785 1.00 27785 27785 0.051 1417 0.47 900ф 1.68 900ф 1605 Stream Flood Catchment
LINE 15
15/3 15/2 2061 0.70 1443 1443 0.0302 44 0.86 225ф 1.08 225ф 117 Lot 9
15/2 15/1 4166 0.70 2916 4359 0.0302 132 0.52 375ф 1.17 375ф 185 Lot 10 & 112 24/10/2017
LINE 17
17/4 17/3 1203 0.70 842 842 0.0302 25 Lot 13
170 0.85 145 987 0.0302 30 0.40 225ф 0.73 225ф 120 Accessway 4 CP
17/3 17/2 815 0.85 693 1679 0.0302 51 0.25 300ф 0.7 300ф 210 Road 1 CP
17/2 17/1 1229 0.70 860 2540 0.0302 77 0.18 375ф 0.68 375ф 130 Lot 12
LINE 18
18/2 18/1 2020 0.70 1414 1414 0.0302 43 0.18 300ф 0.59 225ф 107 Lot 17
3 24/10/2017
CDL Land NZ Ltd – 7-11 Christian Road, Swanson– Engineering Report
October 2017
17
APPENDIX D
WASTEWATER CALCULATIONS/
WATERCARE SERVICES
F
F
F
F
F
F
F
F
P
P
P
P
P
P
P
W
W
2
0
0
P
E
1
0
0
P
E
2
0
0
P
E
2
0
0
P
E
1
0
0
A
C
(
A
b
d
)
1
0
0
P
E
1
5
P
E
1
5
P
E
1
5
P
E
1
8
0
P
E
1
5
0
C
L
S
5
0
A
C
1
8
0
P
E
1
5
0
A
C
(
A
b
a
n
d
o
n
e
d
)
1
0
0
A
C
(
A
b
d
)
1
0
0
A
C
1
0
0
A
C
5
5
0
C
L
S
O
O
S
4
7
0
1
5
0
P
V
C
1
5
0
P
V
C
1
5
0
P
V
C
1
5
0
P
V
C
2
2
5
C
O
N
C
2
2
5
C
O
N
C
3
7
5
C
O
N
C
2
2
5
C
O
N
C
3
0
0
C
O
N
C
2
2
5
C
O
N
C
4
0
0
C
O
N
C
3
0
0
C
O
N
C
2
2
5
C
O
N
C
1
5
0
P
V
C
1
5
0
P
V
C
2
2
5
C
O
N
C
SA
VE
D: P
:\1
16
7 - 1
0 T
ra
m V
alle
y 7
C
hristia
n R
d\5
.0
D
ra
win
gs\C
41
0 S
EW
ER
C
AT
CH
ME
NT
P
LA
N.d
wg
- A
ug
ust 1
8, 2
01
7. P
RIN
TE
D: A
ug
ust 1
8, 2
01
7
DRAWING No REVISION
TITLE
PROJECT
CLIENT
SCALE
This document and the copyright in this document remain the property of Crang Consulting Ltd. The contents of this documentmay not be reproduced either in whole or in part by any means whatsoever without the prior written consent of Crang Consulting.
COPYRIGHT:
A1
A3DESIGNED
DRAWN
DATE
REVISION CHANGES CHECKED DATE
Unit 4, 517 Mount Wellington Highway, Auckland
PO Box 42-089, Orakei, Auckland 1745, NZ
+64 09 320 3325
www.crangcivil.co.nz
phone
web
address
post
PROJECT No DRAWING No REVISION
TITLE
PROJECT
CLIENT
SCALE
A1
A3DESIGNED
DRAWN
DATE
REVISION CHANGES CHECKED DATE
PROJECT No
CDL LAND NZ LTD
7-11 CHRISTIAN ROAD
SEWER CATCHMENT PLAN
ORIGINAL ISSUE VC 18/08/170
JUNE 2017
DW
1167 C410 0
NTS
A
D
C
E
CATCHMENT DWELLING NUMBERS:
1. SEWER LINE A TO C DWELLINGS: 54 (INCLUDINGPROPOSED 50 LOTS & 4 EXISTING).
2.SEWER LINE B TO C DWELLINGS: 36 (EXISTING)
3. SEWER LINE D TO E DWELLINGS: 49 (EXISTING)
4. SEWER LINE E TO F DWELLINGS: 139(TOTAL)
PROPOSEDSEWER LINE
PROPOSEDDEVELOPMENTSITE(48 DWELLINGS)
B
F
36 EXISTINGDWELLINGS
49 EXISTINGDWELLINGS
4 EXISTINGDWELLINGS
EXISTINGGOLFCOURSE
F
F
F
F
F
F
F
F
P
P
P
P
P
P
P
W
W
2
0
0
P
E
1
0
0
P
E
2
0
0
P
E
2
0
0
P
E
1
0
0
A
C
(
A
b
d
)
1
0
0
P
E
1
5
P
E
1
5
P
E
1
5
P
E
1
8
0
P
E
1
5
0
C
L
S
5
0
A
C
1
8
0
P
E
1
5
0
A
C
(
A
b
a
n
d
o
n
e
d
)
1
0
0
A
C
(
A
b
d
)
1
0
0
A
C
1
0
0
A
C
5
5
0
C
L
S
O
O
S
4
7
0
1
5
0
P
V
C
1
5
0
P
V
C
1
5
0
P
V
C
1
5
0
P
V
C
2
2
5
C
O
N
C
2
2
5
C
O
N
C
3
7
5
C
O
N
C
2
2
5
C
O
N
C
3
0
0
C
O
N
C
2
2
5
C
O
N
C
4
0
0
C
O
N
C
3
0
0
C
O
N
C
2
2
5
C
O
N
C
1
5
0
P
V
C
1
5
0
P
V
C
2
2
5
C
O
N
C
3.05
225Ø
P
W
SSMH 2LL = 33.73
SSMH 3LL = 32.25
SSMH 4LL = 30.49
SSMH 5LL = 28.32
SSMH 6LL = 26.60
SSMH 7LL = 26.90
SSMH 8LL = 25.97
SSMH 9LL = 25.98
SSMH 10LL = 25.20
SSMH 1LL = 35.35
IL = 34.13150Ø
IL = 34.11150Ø
IL = 32.25
IL = 32.14150Ø
IL = 3
2.27
150Ø
IL = 31.12
IL =
31.
0715
0ØIL
= 2
8.39
IL = 29.29150Ø
IL =28.29
IL =25.73
IL = 26.42150Ø
IL = 25.69150Ø
IL = 25.26
IL = 25.30
150ØIL = 25.24
150Ø IL = 23.93
IL = 23.79150Ø
IL = 23.75150Ø
IL = 23.31
IL = 23.40
150Ø IL =
23.2
4 IL =
23.1
4
300Ø
IL = 23.16300Ø
IL = 23.10 400ØIL = 22.69 IL = 22.60400Ø
IL =
22.9
215
0Ø
1
5
P
E
1
5
P
E
3
0
0
C
L
S
1
5
0
A
C
2
5
0
A
C
O
O
S
4
7
0
5
5
0
C
L
S
450Ø
450Ø
SWMHLL = 42.3941.24300Ø
40.94300Ø
SWMHLL = 42.8641.02
41.1
610
0Ø
41.12450Ø
41.41
225Ø225Ø41.22450Ø
GRADIENT
0.54 %
GRADIENT
1.50 %
GRADIENT
0.47 %GRADIEN
T10.0 %
GRAD
IEN
T2.
9 %
GRADIENT1.4 %
GRADIENT6.0 % A
C
E
F
B
D
PROPOSEDSEWER LINE
PROPOSEDDEVELOPMENT
SITE
SA
VE
D: P
:\1
16
7 - 1
0 T
ra
m V
alle
y 7
C
hristia
n R
d\5
.0
D
ra
win
gs\C
41
1 S
EW
ER
C
AP
AC
IT
Y C
AL
CU
LA
TIO
NS
.d
wg
- A
ug
ust 1
8, 2
01
7. P
RIN
TE
D: A
ug
ust 1
8, 2
01
7
DRAWING No REVISION
TITLE
PROJECT
CLIENT
SCALE
This document and the copyright in this document remain the property of Crang Consulting Ltd. The contents of this documentmay not be reproduced either in whole or in part by any means whatsoever without the prior written consent of Crang Consulting.
COPYRIGHT:
A1
A3DESIGNED
DRAWN
DATE
REVISION CHANGES CHECKED DATE
Unit 4, 517 Mount Wellington Highway, Auckland
PO Box 42-089, Orakei, Auckland 1745, NZ
+64 09 320 3325
www.crangcivil.co.nz
phone
web
address
post
PROJECT No DRAWING No REVISION
TITLE
PROJECT
CLIENT
SCALE
A1
A3DESIGNED
DRAWN
DATE
REVISION CHANGES CHECKED DATE
PROJECT No
CDL LAND NZ LTD
7-11 CHRISTIAN ROAD
SEWER CAPACITYCALCULATIONS
ORIGINAL ISSUE VC18/08/17
0
JUNE 2017
DW
1167 C411 0
1:2000
1:4000
SEWER CAPACITY CALCULATION:
BASED ON WATERCARE SERVICES LIMITED - WATER AND WASTEWATER CODEOF PRACTICE, VERSION MAY 2015 AND REFER ABOVE THE SURVEYEDEXISTING PIPEØ & GRADIENTS:
SEWER LINE A TO C: 54 DWELLINGS54 x 3 x 1500=2.81 l/s < EXISTING PIPE GRADIENT 0.47%, 150Ø, 11 l/s - OK
SEWER LINE E TO F: TOTAL DWELLINGS : 139139 x 3 x 1500=7.24 l/s< EXISTING PIPE GRADIENT 0.54%, 150Ø, 11.7 l/s - OK
1
Vaughan Crang
From: PJaggard (Phil) <[email protected]>
Sent: Wednesday, 15 May 2013 12:11 p.m.
To: Richard Osborne
Subject: RE: Tram Valley Road, Waitakere
Attachments: DOC150513-006.pdf
Hi Richard I note that the site is currently outside our area of service. It’s unlikely that there would be any trunk issues for this land alone, but needs to be considered as part of the whole picture and total future flows for the area and Swanson BS e.g what is the maximum catchment extents proposed under the Unitary plan. So without this I can only give some general comments. You don’t mention lots, but based single lots, the proposed connection shown on your attachment would probably not be adequate, but a new line to the main trunk sewer would be required unless the Penihana lines were designed for this area as part of their work. You’d have to discuss this with them now as they are in the process of designing it. Alternatively you could design a new line heading north to the other side of Swanson Road and on to the main trunk, but some of the small 150mm lines to the north may be adequate if it was a only a small development. You’d need to do some static calcs on options but there appears to be workable solutions with probably only minor local upgrades require that would be done by the developer. Hope this helps. Regards Phil
From: Richard Osborne [mailto:[email protected]]
Sent: Wednesday, 15 May 2013 11:32 a.m.
To: PJaggard (Phil) Subject: Tram Valley Road, Waitakere
Hi Phil
We have been asked to assist a client with a submission on the unitary plan which involves a block just outside the
MUL located at the intersection of Tram Valley and Christian roads in Waitakere, ( Plan Attached). This block is
directly opposite the Neil’s Penihana Block which is the process of being developed for residential development etc.
We need to provide comment on the feasibility of servicing the block with a reticulated wastewater connection, the
most likely being the extension of the council main from the east. Are you able to advise whom in your team we can
consult with on this. Principally need to receive feedback from Watercare on any capacity or other constraints
associated with this proposal etc.
Many Thanks in advance.
Regards
Richard Osborne Chartered Professional Engineer Director
Consultants Limited ● Consulting Engineers ● Resource Planners ● Project Managers
ATTACHMENT A