Upload
dpcoe
View
0
Download
0
Embed Size (px)
Citation preview
ARCHITECTURAL PROJECT
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Dissertation Report Prepared By Bhagyashree Patil | BNCA Fourth Yr. General |
2015
Guided by Prof. Sujata Karve | HOD M.arch (Environmental Architecture )
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
2
Title :
Adaptive Use of Construction Waste To Reduce Material Cost In Architecture
Abstract :
As architects , we are responsible to make a judicious decision when it comes to the
materials of our buildings. Construction materials pool out a major chunk of the
capital required to start a new project. Parallely , buildings generate a large amount
of material waste throughout their life cycles, from construction and building
operations to demolition. The amount of waste leaving the property can be reduced
by adaptively using the construction waste produced on site and creating an
alternative for the virgin material. This research paper intends to explore the
possibility of using construction waste generated around us as a tool to lower the
material costs in architecture. The study discusses the feasible alternatives to treat
waste or use it to replace certain conventional materials in a building. Comparisons
are drawn between both the approaches towards the use of materials to note the
differences and highlight the cost factor involved in it. Finally , to derive an approach
that would not only reduce the cost of materials in construction but also to reduce
the environmental impact of waste by eliminating the energy consumed in disposal
as well as reduce the generation of virgin material for construction.
Keywords :
Adaptive use , material, cost - reduction , construction waste , tiles , mosaic .
Introduction :
" Waste is not waste , but misplaced resources following manufacturing activities and
treatment processes. " ( Wang Jing-Yuan , 2012)
The rate of cycling of materials is a more important indicator in determining
productivity than the amount present at any one place at any one time. Material
cycles become more closed as a system matures (i.e., when fewer materials are
lost or wasted). Thus, the role of waste products in the overall health of the system
increases
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
3
This paper intends to transform the waste materials into art and seeks to address
the issue of adaptive use , by bold articulate use of waste in architecture for a dual
purpose of prolonging the life span of existing materials to reduce the requirement
of virgin material as reducing the cost of construction.
Since , building construction comes at a considerable expense and, in the case of
architecturally designed projects, usually comes the assumption of an even greater
expense, the promotion of Adaptive Use of waste to strengthen the building
resilience is the idea that has been highlighted in the overall study
Impacts of Construction Waste :
Current advancements in the construction industry in India project that it would
become world’s third largest construction market by 2025.The construction market is
also accounting for 11% of India’s GDP after agriculture. Construction waste is
produced in hefty quantities by infrastructure projects, renovation or demolition of
structures, etc.
Construction management plans are also adopted by few site managers in the
beginning of the construction work. But it is difficult to monitor and control effectively
throughout the process due to less awareness of the environmental impact of the
construction material waste and lack of interaction in between the working people on
the construction site. Hence , large amount of waste is generated on construction
site in conventional construction process.
Increasing quantity of construction material waste has become an issue of
environment concern as it causes carbon emissions, solid waste generation, and
water effluents. This waste consists mostly of non-biodegradable material such as
concrete, mortar, reinforcement / steel, brick, block, etc. which are heavy, having
high density and occupy considerable space on valuable land. These lands are
costly and construction material waste dumps particularly are unpleasant and are
sources of environmental hazard. These dumps pollute valuable lands as well as
ground water resources.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
4
Reducing the Cost of Construction through Choice of Materials :
For architects material selection is one of the most crucial choices faced when
designing. Materials clothe our creations, offering protection and shelter, ultimately
setting the tone and appearance of a building. Generic building materials such as
plaster, timber and concrete, clad and coat the majority of buildings within our cities:
but an alternative approach towards utilisation of the construction waste as a
resource needs to be developed over the period of time to cut down on the
generation of virgin material and the followed wastage of virgin material on site
during various construction stages.
Materials are the easiest way for architects to begin incorporating sustainable design
principles in buildings. Price has been the foremost consideration when comparing
similar materials or materials designated for the same function. Further analysis of
building products, from the gathering of raw materials to their ultimate disposal,
provides a better understanding of the long-term costs of materials. These costs are
paid not only by the client, but also by the owner, the occupants, and the
environment. Each step of the manufacturing process, from gathering raw materials,
manufacturing, distribution, and installation, to ultimate reuse or disposal, is
examined for its environmental impact. Consideration for materials and resources
focuses on the health and productivity consequences of material selections for
building occupants, plus the long term social, economic, and environmental impacts
of materials used in the design and construction of the building.
This paper investigates how waste can form architectural design with construction
waste obtained from sites .It is a sustainable method of work as the provider of the
material saves time and money in disposal/recycling costs and the purchaser is
provided with materials at a lower rate.
Adaptation of Construction Waste as a Building Material :
The Reduce , Reuse and Recycling of building material is a growing area of interest
and concern in many parts of the world due to massive procreation of dissipate on
construction sites and the difficulties faced in its disposal . Current practices and
trends in the building material waste management area are examined from a building
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
5
life cycle standpoint or cradle to reincarnation concept. Strategies include optimisation
of energy through reuse and recycle, minimisation of construction waste through
efficient planning , integrated recycling and adaptive use of waste material.
It is pointed out that experience plays a major role in waste adaptation. Professional
working for many years seems to be implementing the on-site practices and
procedures to use waste and cost effectiveness of the specific materials. But the
scenario is not same in all construction processes and their material waste
generation stages.
As architects have the ability to change how materials are used , gives them an
opportunity to re-use the waste materials efficiently and expressively through
building design. Waste materials create waste landscapes: landfills, massive
incinerator systems, and multi-square-mile floating plastic garbage islands in the
world's oceans. The disposal of waste consumes a lot of energy and it also creates a
need for new virgin material to be harvested as feedstock for new generations of
product. If this waste is integrated within architectural construction practices , it
would help not only lower the impact on the environment but may also help cut down
the costs of construction .
In her paper , Ar. Dharti Sote suggests certain alternatives to adaptively use the
dissipate within the given project for site development purposes , further eliminating
the transportation and procurement cost of the waste in the markets. Certain general
practices to be followed on site to train the labourers to segregate the construction
waste at the source have been included in the research carried out by her.
Materials whose waste can be reduced and used but not recycled from construction
waste form a larger chunk that needs to be focused through this approach of
adaptive use.
Following are certain materials which cannot be recycled but reused :
(as inferred from the interview of Mr. Swapnil Raikar
1. Soil
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
6
2. Sand
3. Aggregate
4. Wood
5. Tiles
The final material order placed for any construction project is inclusive of certain
wastage / losses caused as mentioned earlier. These are generally percentages
assumed of the actual quantity required.
The estimated material waste percentage differs as per construction material. The
total amount of material purchased on the project site is as per this ´estimated
quantity. Since these materials cannot be recycled , the approach of adaptive use
can be followed in such cases . Hence it is important to determine the exact quantity
of waste estimated and the actual waste generated on the site
Estimated wastage of these materials :
. Table 1: Estimated wastage of construction material
Sr.
No.
Type of material ´Estimated
wastage
1 Sand 10 %
2 Aggregate 5 %
3 Wood for shutters , frames 7 %
4 Wood for flooring / walling 5%
5 Tiles 10 %
´By K.K. Chitkara, Construction project management - Planning, scheduling and
controlling, Page no. 330-331
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
7
Actual Waste of Construction Material :
Table 2: Actual wastage of construction material :
´By K.K. Chitkara, Construction project management - Planning, scheduling and
controlling, Page no. 330-331
From the above data , tiles are clearly identified as a construction waste that is
generated in large amounts and also contribute to the elevation of the capital for
construction as they are an comparatively expensive material . Hence the scope of
further studies has been limited to tiles as a construction waste material that can be
adaptively used to reduce the material cost in architecture.
Certain practices for waste segregation should me made mandatory at the site level
if this waste needs to be further used for other activities on site. A strict check should
be kept on the segregation so as to avoid damage to the material and its quality.
Parallely , Dr. M.F. Hussein discusses the use of waste materials to replace
conventional materials in the interior and exterior spaces. His literature highlights the
reuse of building materials through salvage or refurbishment . The intent is to reuse
the resources to reduces the extraction of materials from virgin resources, saving
landfill space and saving money , thus pronouncing the reuse of waste material as a
sustainable alternative for the construction sector.
Sr.
No.
Construction stage *Types of waste generated *Percentage
of actual
waste
material
1 Site preparation / clearing Soil 20 %
3 Hard landscape Tiles / blocks 2
4 Floor finishing (Tiling) Tiles 7
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
8
It is understood from his study that in order to enable comparative analysis of
sustainability implications, life cycle analysis of building materials is necessary. In
addition to the local economic benefits of the use of waste building materials, less
overall embodied energy, and therefore less overall energy, is spent due to shorter
distances travelled in transport as the material procurement and implementation can
be directly on site.
Recommended practices for Adaptive Use of Waste Tiles :
Table 3 : Recommended Practices
Sr.
no.
Waste
material
Recommended practices for
reuse of waste material on
site
Tiles
Use to treat the facade :
Interesting patterns created
on the facade using mosaic
technique(Figure 1) . This
eliminates the use of plaster
and paint on the wall and thus
saves the cost required for
painting.
Figure(1)
www.mexicantiles.com/artman2/upl
oads/exterior-fence-walls
(11.03.2015)
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
9
Mosaic pattern can be
created by reusing the pieces
of ceramic tiles in front of
entrance door.
Figure (2)
Blenstone.blogspot.com
(11.03.2015)
Large and small pieces can
be used to create path and
walkway in the garden
Figure (3)
www.pintrest..com/waste-
tiles/pathway/flowerbeds
(10.03.2015)
Tiles pieces can be placed
around flower bed to create
beautiful colorful fences.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
10
(*Sote , 2012)
Methodology :
Two cases of residential projects in Pune have been studied to draw comparisons
between the conventional practices and the adaptive use of waste . A study was
made of the availability of the quantity of tile waste generated on site and
opportunities for its adaptation as a material instead of virgin material in a
construction work. On site observations and interviews of site engineers , tile
contractors and developers culminated in a series of calculations considering the
cost factor , the labour involved , the time consumed and the total difference in cost
achieved with the use of waste tiles.
.
Large ceramic pieces can be
used in kitchen countertop
Figure (4)
www.biomes-
solutions.com/wastematerial-
reclaimed (11.03.2015)
Top finish for sitout in the
open space and entrance
lobby
Parapet top
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
11
Case study 1 :
A residential project is studied in Pune to study the quantity of tile waste generated
on site and its possible adaptive uses to reduce the material cost in construction.
The availability of tiles as a waste material on site and the scope for its use is
established through this case study.
Project details
Project Name - Avanish Regency
Developer : Ajay Raikar , Swapnil Raikar
Project type – Residential project
Location – Navale Bridge , Sinhagad Road
Plot area – 17200.00 Sq. Ft.
B/up area – 15020.00 Sq. Ft
No: of buildings - 2
Number of Floors per building – Parking + 5 floors + Terrace
Use of virgin tiles in the project at different areas :
Table 4 :
Spaces / Type of work Materials used :
Flooring 600 x 600 vitrified tiles
Kitchen Dado 300 x 300 ceramic wall tiles
Toilet Dado 300 x 300 antiskid ceramic tiles
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
12
Skirting 10 mm High cut pieces of floor vitrified
tiles
Terrace 300 x 300 anti skid ceramic tiles
Total expenses on tile purchase are approximately 8 % of the total cost of project.
The total quantity of tiles that are ordered are inclusive of any wastage that might
happen on site during storing , installation and post installation when lighting ,
electrical fixtures are being put up. This is considered to be 7 % of the quantity of
tiles required actually.
On Site Conditions :
Table 5 :
Issues with tile work causing wastage : As Observed on the site
Wastage of tiles due to demolition of an
improper installation work.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
13
Wastage of tiles due to cutting of pieces
of end tiles in order to match the room
dimensions.
Small uneven pieces of tiles generated
due to fine adjustments while laying or
due to mishandling and breakage.
Waste tiles just dumped on site . No
segregation of the waste followed .
No proper storing/ stacking space
provided for the tiles which further
causes wastage due to breakage.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
14
Estimated Wastage of Tiles on Site :
Table 6:
Sr.
no. Waste material
Estimated
material quantity
Waste
percentage
Total waste
quantity
1 Tiles 19000 sq ft. 7% 1330 sq ft
This wastage is further defined as follows : Table 7
Sr. No Waste Type Causes Possible Uses on
Site
1. Intact Pieces of
Tiles
Ordered extra
considering the
wastage , but not
used on site
Can be used for
Site office ,
Workers' Toilets
or sold out at
subsidized rates.
(50-60 % cheaper)
2. Clean Cut Pieces
Of Tiles
Left over due to
cutting in flooring ,
dado work .
Used for Skirting ,
Cladding the
treads ,etc
3. Small Uneven
Pieces of Tiles
Mostly due to
breakage , improper
handling ,
demolition due to
wrong installation
Mosaic work for
terrace floor,
pathways , top
finishes for
benches , feature
wall in the lobby
area.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
15
Analysis : The actual consumption of tiles on site is generally less compared to the
estimated quantity. Hence the actual wastage ranged between 9-12 % ( approx
2200 sq ft) by the completion of the project ( as specified by the tile contractor Mr.
Hanuman Somonshi) . This is a large enough amount which can be effectively
channelized to reduce the material cost of floor finishes in any other project.
Case Study 2 :
The terrace flooring done with waste tile mosaic for a residential project in Warje is
compared with the conventional flooring methods to determine the overall savings in
the cost of materials , thus reducing the total cost on construction .
Project details :
Project type – Residential project
Location – Warje , Pune
Plot area – 16200.00 Sq. Ft.
B/up area – 14000.32 Sq. Ft
Number of Floors per building – Parking + 5 floors + Terrace
Total terrace area - 1850 sq ft
The broken tiles were obtained from another construction site being executed by the
same developer . The waste from one site , instead of being dumped , is used as an
alternative flooring material for another project.
In this case the material cost for the tiles is almost non - existent. The only cost
changing parameter was the labourer required as the no: of days to complete each
project were kept constant.
From further interviews with the tile contractore , we are able to establish a
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
16
substantial difference in the cost of construction due to use of waste material.
Mosaic Work :
Table 8:
Area of Terrace Days
required to
complete the
work
No: Of
Masons
@ Rs.
600 /
person
perday
No: Of
Helpers @
Rs. 300 /
person
perday
Amt. Spent on the
Material
1850 Sq ft 3 Days 6 8 Only for preparing
the structural floor
for laying the
finishing material.
No expenditure in
buying the
finishing material
Total Expenses on
Labour
3600 2400 -
Rs. 6000
Conventional Tiling : ( Assumed as per the details given by tile contractor)
Table 9 :
Area of Terrace Days
required to
complete the
No: Of
Masons
@ Rs.
No: Of
Helpers @
Rs. 300 /
Amt. Spent on the
Material
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
17
work 600 /
person
perday
person
perday
1850 Sq ft 3 Days 3 4 For preparing the
structural floor for
laying the
finishing material.
( This amount is
same for both)
Purchasing of
Tiles :
Considering 7%
wastage , approx
2000 sq ft of
finishing material
would be ordered.
Here the cost of
tile per sq. ft is
considered Rs. 10
/ Sqft
( For average
quality work )
Total Expenses on
Labour
1800 1200 Total - Rs. 20000
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
18
Total Expenditure Rs. 23000
Analysis : Thus the total difference in that is achieved is of Rs. 17000 . So
approximately 70 % reduction in construction cost is indicated through this study.
Further variations in this cost may occur with the choice of brand , sizes of tiles and
other specifications asked by the user for the conventional flooring method.
Conclusion :
The monetary as well as environmental impacts of the material waste generation are
large in construction process . Thus if conventional materials are replaced with
alternative materials bought at subsidised price , the total cost of material purchase
would be drastically reduced and hence the further project cost can be brought
down.
The above studies show that Adaptive use of waste materials is mostly considered
from resource-saving (green) perspective , but an combined approach of
environmental awareness and cost effectiveness in construction can be achieved
this way. With material costs almost being nonexistent, time is the only expense with
selecting suitable waste materials fitting for each area and then forming them into
weather tight surfaces and structurally safe frames.
Acknowledgements :
I wish to express my sincere thanks to Prof. Anurag Kashyap, Principle and Prof.
Sujata Karve, HOD of M. Arch. (Environmental department) of Dr. B. N. College of
Architecture for providing me with an opportunity to conduct this research.
This research was put-up with the support of many people . I would like to thank Ar.
Dharti Sote , Mr. Swapnil Raikar , Ar. Pankaj Sanghvi and Tile contractor Hanuman
Somonshi who added value to this study with their time and expertise. I would also
like to thank Spandan Developers for co-operating and providing needful assistance
during the site visits.
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
19
References :
1. Dharati Sote – Wankhade ,Dinesh Bhonde, Rahul Nawle, Vaishali Anagal
Optimizing energy through on-site reuse and recycle construction waste in
residential project – A Case Study of Pune , 2014
2. Dharti Sote Wankhede , Approach to on site construction material waste
reuse in residential projects
3. M.F Hussein , The ideal usage of sustainable materials and local resources of
the interior space design in Jordan
4. Simon Emett. "Waste to Worth " Adaptive reuse of recycled waste in existing
structures 2013 ; 1- 66
5. United States Environmental Protection Agency Using recycled industrial
materials in buildings 2008; 1-4
6. “Techno economic feasibility report on mosaic tiles using wastes”
7. ´By K.K. Chitkara, Construction project management - Planning, scheduling
and controlling, Page no. 330-33
Bibliography :
1. Dharati Sote – Wankhade ,Dinesh Bhonde, Rahul Nawle, Vaishali Anagal
Optimizing energy through on-site reuse and recycle construction waste in
residential project – A Case Study of Pune , 2014
2. Dharti Sote Wankhede , Approach to on site construction material waste
reuse in residential projects
3. M.F Hussein , The ideal usage of sustainable materials and local resources of
the interior space design in Jordan
4. John May Buildings without architects 2010 ; 35-40
5. Simon Emett. "Waste to Worth " Adaptive reuse of recycled waste in existing
structures 2013 ; 1- 66
6. Parviz Soroushin Towards broad use of recycled glass on MSU Campus ; 1-
49
Adaptive Use Of Construction Waste To Reduce Material Cost In Architecture
Bhagyashree Patil | Fourth Yr. General | BNCA
20
7. United States Environmental Protection Agency Using recycled industrial
materials in buildings 2008; 1-4
8. American Society Of Landscape Architects Sustainable Residential Design -
Using low Impact Materials 2014 ;
9. Govt . Of India BMTPC ( Building Materials and Technology Promotion
Council ) Region wise Recommended choice of construction materials
10. David Pearson Designing Your Natural Home 2005 ;
11. Fly Ash and Recycled Coarse Aggregate in Concrete: New Era for
Construction Industries - Prof. Chetna M.Vyas1, Prof. Jayeshkumar Pitroda2
12. “Techno economic feasibility report on mosaic tiles using wastes”