Site ReportMeasurement 1 (QSB 60104)-Sr. Ang Fuey Lin

Building Materials (BLD 62003) - Puan Hasmanira Mokhtar

Construction Technology I (BLD 60104)-Mr.Leong Boon

Tik

Sharon Chow Ci Yung (0313387)

1 | P a g e

Page 2: Site report

Table of Content

Cover Page Page 1

Table of Content Page 2

Introduction Page 3

Objectives Page 4

Content/Technical Observations Page 5

Photos and Descriptions Page 6 to 23

Learning Outcomes / Conclusion Page 24 to 25

2 | P a g e

Page 3: Site report

Introduction

On 20th June 2014, we had a site visit organized by our Measurement 1 lecturer,

Sr.Ang. The site is located at Jalan Kelang Lama, right beside Pearl International Hotel.

It is the construction of a 25-storey mixed-use building. The building is named as Pearl

Suria. Its main contractor is Encorp Construct Sdn Bhd, its quantity surveyor is PCM

Kos Perunding Sdn Bhd, its civil and structural engineer is Perunding Majujaya, its

architect is LT Leong Sekutu and last but not least its mechanical and electrical

engineer is Kew & Associates.

Before we started our site visit, we were given a brief talk about the safety on site

by the safety officer of the site. Then we kicked off our site visit. Our visit were

accompanied by Mr. John and Mr. Chong. First of all, they told us the brief information

of Pearl Suria. Pearl Suria consists of 2 levels of shopping mall and 18 levels of

residential condominium. There are 2 levels of basement car park for the customers of

the shopping mall and 4 levels of car park on the 3rd, 4th, 5th and 6th floor for the residents

of the condominium from the 7th to 24th floor.

We started our visit from the basement car park. Then, we went up to the car park

on the 3rd, 4th and 5th floor which are meant to be the car park for the residents.

3 | P a g e

Page 4: Site report

Objectives

1. Enable us to understand the sequences of constructing a building

2. Allow us to understand the building structures such as columns and beams well.

3. Expose ourselves to different types of building materials construction technologies

which we have learnt in class but have never seen in real life before.

4. Raise our awareness in the importance of taking care of our safety when we are in a

site.

5. Gain construction knowledge that we don’t get to learn in class such as the use of

continuous bore pile as a retaining wall.

6. Get a better grip when it comes to the understanding of construction machineries.

7. Allow us to get a vivid image of what we are actually learning in class especially

Measurement I by looking at the actual structures, for instance the formwork of a beam

where no deduction for the main beam even though there are secondary beams

penetrating it.

8. Allow us to get a sneak peek of the job scoop of a Quantity Surveyor.

4 | P a g e

Page 5: Site report

Content/ Technical Observations

When we got to the basement which is the car park of the building, we saw a

continuous row of cylindrical-shaped concrete. Mr. Chong explained to us that bore

pilling is commonly used for high-rise buildings especially in the Kuala Lumpur region,

replacing the conventional reinforced concrete pile (RC pile). The continuous bore piles

act as a retaining wall for the building.

When we around the site, there are actually plastic pipes lying around the site and

some of the pipe were installed upright and protruding the upper floor suspended slab.

Mr. Chong told us those are concrete pipes. Those pipes are connected to the concrete

pump in order to transfer the concrete from the ground floor to upper floors. The main

reason to use concrete pipe is to increase productivity as it is too slow and troublesome

to transfer the concrete from one floor to another using manpower and tower crane isn’t

fast enough either. Tower crane is usually used when transferring small amounts of

concrete. Concrete pipe is able to transfer a whopping 30m3 per hour. Mr.Chong also

told us that concreting works are forced to stop when it is raining as the concrete can be

diluted by the rainwater.

After we are done walking around the site, we went back to the ground floor of the

site. There are a cluster of concrete pieces at the corner of the ground floor. Sr.Ang told

us those are the concrete spacers. We even get to see one of the workers making the

concrete spacers on site by cutting a large slice of concrete slab into small pieces. The

thickness of the concrete spacer is either 25mm or 50mm.

Before we left the site, me and a few of my other classmates witnessed the bar

benders bending the bars. Sr. Ang had told us before that the bar benders had their

own ways in calculating the amount of steel bars needed. We got to see them bending

the bars with the bar bending machine.

5 | P a g e

Page 6: Site report

Photos and Descriptions

Figure 1.0 The Overview of The Site (Pearl Suria at Jalan Kelang Lama).

Figure 1.2 Temporary Toilets on Site.

6 | P a g e

Page 7: Site report

Figure 1.3 Temporary Accommodations for the Workers on Site.

Figure 1.4 Putlog Scaffolding from the 1st Floor to the 5th Floor

7 | P a g e

Page 8: Site report

Figure 1.5 Independent Scaffolding

Figure1.6 Mobile Access Towers

8 | P a g e

Page 9: Site report

Figure 1.7 One of the Two Tower Cranes on Site.

Figure 1.8 Safety Precaution Sign and The Name of Main Contractor

9 | P a g e

Page 10: Site report

Figure 1.9 Safety Precaution Signs Outside the Site.

Figure 2.0 Description Board of The Site. 10 | P a g e

Page 11: Site report

Figure 2.1 Safety Precaution Sign in the Site.

Figure 2.2 Safety Precaution Sign in the Site.

11 | P a g e

Page 12: Site report

Figure 2.3 The Working Schedule of The Site.

Figure 2.4 Mesh Fabric Reinforcement Kept on Site (BRC).

12 | P a g e

Page 13: Site report

Figure 2.5 The Bar Benders Bending The Steel Bars at the Bar Bending Yard.

Figure 2.6 Steel Rods That Were Bent Into Stirrups or Links.

13 | P a g e

Page 14: Site report

Figure 2.7 Steel Rods That Are Kept On Site.

Figure 2.8 Starter Bars of Column.

14 | P a g e

Page 15: Site report

Figure 2.9 Starter Bars.

Figure 3.0 Concrete Spacer for Mesh Fabric Reinforcement (BRC).

15 | P a g e

Page 16: Site report

Figure 3.1 Main Bars and Stirrups in Beam.

Figure 3.2 Formwork for Sides and Soffit of Staircase

16 | P a g e

Page 17: Site report

Figure 3.3 Strike-Off Formworks.

Figure 3.4 The Making of Concrete Spacers.

17 | P a g e

Page 18: Site report

Figure 3.5 Concrete Spacers.

Figure 3.6 Concrete Spacers.

18 | P a g e

Page 19: Site report

Figure 3.7 Concrete Pump.

Figure 3.8 Concrete Pipe.

19 | P a g e

Page 20: Site report

Figure 3.9 Concrete Pipe.

Figure 4.0 Joint of Two Concrete Pipes.

20 | P a g e

Page 21: Site report

Figure 4.1 Attached Beams and Suspended Slabs.

Figure 4.2 An Example of Column Can be found on Site.

21 | P a g e

Page 22: Site report

Figure 4.3 Slopping Slab at the Car Park.

Figure 4.4 Bore Pilling.

22 | P a g e

Page 23: Site report

Figure 4.5 Concrete Staircase Connecting The Ground Floor and the Basement Car Park.

Figure 4.6 Interior Acrylic Emulsion Paint.

23 | P a g e

Page 24: Site report

Learning Outcomes / Conclusion

After the site visit, I got a better grip with what I am actually learning in my

classes and gained some extra knowledge. For instance, there are a lot of scaffoldings

and mobile access towers that can be found on the site. By seeing them with my own

eyes, I get to easily tell apart the differences between independent scaffolding and

putlog scaffolding, previously I had difficulties telling them apart as to me, their

appearances are quite similar.

Besides that, the site visit raised my awareness when it comes to taking care of

my own safety on site. The brief given by the site safety officer highlighted the

importance of keeping our safety helmet on at all times when we are on site. Apart from

keeping our head safe by wearing a safety helmet, we should as be careful of the nails

on the floor of the site as mentioned by the safety officer. It is common to have nails

scattered around in a site thus I shall be extra careful when walking around the site.

Moreover, this site visit helps me to understand the principles of measurement

of reinforcement bars better after looking at the links and stirrups that were bent by the

bar benders. Apart from that, I also get to understand the concept of deducting concrete

cover when I am calculating steel reinforcement better now after Sr. Ang showed us the

concrete spacers on us and gave us a brief explanation.

In addition, I get to expose myself to construction machineries that I will hardly

get a chance to see in regular basis such as concrete pump, concrete pipe and bar

bending machines. Before the site visit, I have never heard of a concrete pipe. Concrete

pipes connected to a concrete pump actually transfer concrete from the one floor to

another with a whopping speed of 30m3 per hour, before this I thought that was the

function of tower crane. Mr. Chong told us that tower crane are only used to transfer

small amounts of concrete while for large quantity, concrete pump are used to transfer

large quantities of concrete which in return, save a lot of time. Time is crucial when it

comes to the construction industry.

24 | P a g e

Page 25: Site report

Lastly, through this site visit, I get to get a sneak peak of the life and job scoop

of a Quantity Surveyor. During the site, Mr. Chong actually brought us to walk down the

scaffolding from the fifth floor. It was quite terrifying. Mr. John told us we work as

professional quantity surveyors, we might have to walk up and down these scaffolding

on regular basis.

To conclude, I find this site visit very useful to me as a Semester 1 student who

is a total newbie to the construction industry. I get to gain a lot of useful construction

knowledge that some I might not be able to learn in class and experience what might be

like to work as a professional in the construction industry.