15
1 Rauch & Hackenberg Project Earned Value Management X 443.17 Class 2 The Basics of Earned Value Copyright © 2012 Bill Hackenberg. All rights reserved. Dilbert on progress reports… 2

Evm class 02 1to15 by upad

  • Upload
    hvostik

  • View
    290

  • Download
    0

Embed Size (px)

DESCRIPTION

Earned value

Citation preview

Page 1: Evm   class 02  1to15 by upad

1

Rauch & Hackenberg

Project Earned Value Management X 443.17 Class 2 The Basics of Earned Value

Copyright © 2012 Bill Hackenberg. All rights reserved.

Dilbert on progress reports…

2

Page 2: Evm   class 02  1to15 by upad

2

Rauch & Hackenberg

Class 1, Introduction Review Questions

Q. What is the difference between projects and operations:

a. Projects are ongoing activities b. Projects are performed by people, while operations are performed by machines

c. Projects are temporary and create a unique product or service

d. Projects and operations are the same

3 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Class 1, Introduction Review Questions

Q. The triple constraint is: a. Scope, Cost, Time b. Resources, Cost, Budget c. Schedule, Duration, Time d. Scope, Requirements, Quality

4 Copyright © 2012 Bill Hackenberg. All rights reserved.

Page 3: Evm   class 02  1to15 by upad

3

Rauch & Hackenberg

Class 1, Introduction Review Questions

Q. Which phase-to-phase relationship in a Project Life Cycle can have decision gates that the project must pass through before proceeding?

a. Sequential Relationship (Waterfall) b. Overlapping Relationship (Fast Tracking) c. Iterative Relationship (Iterative) d. Any of the above

5 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Class 1, Introduction Review Questions

Q. The Project Charter is used to do all the following except:

a. Establish measurable project objectives and related success criteria for the project

b. Communicate Project purpose or justification to project stakeholders

c. Document high-level risks d. Provide a baseline for progress measurements and project control

6 Copyright © 2012 Bill Hackenberg. All rights reserved.

Page 4: Evm   class 02  1to15 by upad

4

Rauch & Hackenberg

Class 1, Introduction Review Questions

Q. How does the Project Management Maturity Model OPM3 define process maturity for organizations?

a. As soon as all processes have been formalized into documentation

b. When projects are completed quickly (cost overruns are ok)

c. When projects are complete cheaply (schedule overruns are ok)

d. When they adopt Program & Portfolio process

7 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Earned Value Primitives, or Primary Metrics •  Planned Value (PV)

–  Budgeted Cost of Work Scheduled –  How much work should be done? –  What is the budget for the work scheduled (according to the original

estimate)?

•  Earned Value (EV) –  Budgeted Cost of Work Performed –  How much work is done? –  What was the budget for work accomplished? –  Interpretation of EV: “Task A, which I was supposed to complete today, is

scheduled to cost $1,000. I am only 85 percent done on this task. Thus I have done $850 worth of work—which is my earned value (EV).”

–  EV = PV x % Complete

•  Actual Cost (AC) –  Actual Cost of Work Performed –  How much did the “is done” work cost? –  What are the actual costs for the Earned Value

8 Copyright © 2012 Bill Hackenberg. All rights reserved.

has to be $$$ Ex: Task A 10 hrs, $10/ per hr PV=$100

Page 5: Evm   class 02  1to15 by upad

5

Rauch & Hackenberg

Schedule Variance (SV)

•  SV = EV – PV

•  Interpretation of SV: “As of today, I was supposed to have done $1,000 worth of work on Task A (PV). I have actually done $850 worth of work (EV). Thus, I am behind in my schedule by $150 worth of work (SV).”

•  Note: Schedule variance is valued in dollars!

9 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Cost Variance (CV)

•  CV = EV – AC

•  Interpretation of CV: “I have done $850 worth of work (EV), but it actually cost me $900 to do this (AC). It has cost me $50 more to do what I have done than I originally thought (CV).”

10 Copyright © 2012 Bill Hackenberg. All rights reserved.

difference between Planned & spent

Page 6: Evm   class 02  1to15 by upad

6

Rauch & Hackenberg

Schedule Performance Index (SPI)

•  SPI = EV/PV

•  Interpretation: “I have done $1,500 worth of work (EV). The value of work scheduled is $1,000. Each dollar of scheduled work generated $1.50 worth of work (schedule performance index).”

11 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Cost Performance Index (CPI)

•  CPI = EV/AC

•  Interpretation: “I have done $850 worth of work (EV). It has cost me $900 to do so (AC). Each dollar I actually spent generated 94.4 cents worth of work (cost performance factor).”

12 Copyright © 2012 Bill Hackenberg. All rights reserved.

Ratio of planned and spent

SV= - bad, + good (under budget)SPI= <1 bad, >1 good (ahead of schedule)

CV= $100000 (bad)CPI= .94 ok

1.5 times

CV= $100000CPI= .94 ok

CVCPI: 1.1SVSPI: 1.1under budget, ahead of schedule

Page 7: Evm   class 02  1to15 by upad

7

• The Project Baseline Plan

• 3 months • status

• Actual Costs = $300K

• Planned Costs = $300K

• Thousands (000)

• $1,000

• 500

• 750

• 250

• Authorized Budget $1,000,000

• 12 months duration

• Quentin W. Fleming 13

• Earned Value is three dimensional: • As we perform our projects, we need to determine:

• 1. What work has been scheduled? (from PMS)

• 2. What is the budget for the work scheduled?

• The Planned Value

• 3. What work has been accomplished? (from PMS)

• 4. What was the budget for work accomplished?

• The Earned Value

• 5. What are the actual costs for the Earned Value?

• The Actual Costs

• Quentin W. Fleming 14

Page 8: Evm   class 02  1to15 by upad

8

• Quentin W. Fleming

• EVM Measures 3 Dimensions

• Cost Actuals = $300K

• Thousands (000)

• Planned Value = $300

• $1,000

• 500

• 750

• 250

• Authorized Budget $1,000,000

• Earned Value = $200K

• 3 months • status

• 12 months duration

15

• Quentin W. Fleming

• The Fundamental Difference:

• Earned Value Project Management

• Earned value = $200K

• Actual costs = $300K

• Planned value = $300K • Variance from the planned schedule = (-$100K)

• The "true" cost variance = (-$100K)

• Traditional Project Cost Management

• Actual costs = $300K

• Planned costs = $300K • Variance from the expenditure plan • (everything is 0K)

16

PV= $300KAC= $300KEV= $200K% = 200K/1000K(BAC)= 20%

CV= EV - AC =200K-300K=-100KCPI= 200/300= .67SV= EV-PV= 200K-300K=-100KSPI= EV/PV = 200K/300K= .67

over-budget, behind schedule

Page 9: Evm   class 02  1to15 by upad

9

Rauch & Hackenberg

EVM Metrics, or Reporting and Comparison Metrics

•  Earned Value Formulas: – Schedule Variance:

SV = EV - PV – Schedule Performance Index:

SPI = EV / PV – Cost Variance:

CV = EV - AC – Cost Performance Index:

CPI = EV / AC

17 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

•  The way to remember this is to write down the first part of the four earned value calculations:

•  CV=... •  CPI=... •  SPI=... •  SV=...

18 Copyright © 2012 Bill Hackenberg. All rights reserved.

EVM Metrics, or Reporting and Comparison Metrics

Page 10: Evm   class 02  1to15 by upad

10

Rauch & Hackenberg

•  In each case EV is the first variable:

•  CV=EV... •  CPI=EV... •  SPI=EV... •  SV=EV...

19 Copyright © 2012 Bill Hackenberg. All rights reserved.

EVM Metrics, or Reporting and Comparison Metrics

Rauch & Hackenberg

•  Then add the operator: •  CV and SV (variance) use - •  CPI and SPI (Index) use /

•  CV=EV-... •  CPI=EV/... •  SPI=EV/... •  SV=EV-...

20 Copyright © 2012 Bill Hackenberg. All rights reserved.

EVM Metrics, or Reporting and Comparison Metrics

Page 11: Evm   class 02  1to15 by upad

11

Rauch & Hackenberg

EVM Metrics, or Reporting and Comparison Metrics

•  Then add the second variable: •  C(ost)V and C(ost)PI use AC(ost) •  S(hedule)PI and S(hedule)V use P(lan)V

•  CV=EV-AC •  CPI=EV/AC •  SPI=EV/PV •  SV=EV-PV

21 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Forecasting Metrics •  Three Estimate to Complete (ETC) Forecasting

formulas mentioned in PMBOK

•  EAC forecast for ETC work performed at budgeted rate: EAC = AC + BAC – EV Where: EAC = Estimate at Completion (forecast)

BAC = Budget at Completion (original baseline)

•  EAC forecast for ETC work performed at the present CPI: EAC = BAC / cumulative CPI

•  EAC forecast for ETC work considering both SPI and CPI: AC + [(BAC – EV) / (cumulative CPI x cumulative SPI)]

22 Copyright © 2012 Bill Hackenberg. All rights reserved.

PMBOK Pg. 184-185EAC Formula

Page 12: Evm   class 02  1to15 by upad

12

•  Cumulative CPI stabilizes at 20% point

•  At 20% point variances only +/- 12%

•  At 30% point variances only +/- 11%

•  At 40% point variances only +/- 09%

•  At 50%point variances only +/- 08% • Quentin W. Fleming 23

• Estimate at Completion

• AC • $300,000 = Actual Cost

• EV • $200,000 = Earned Value

• Cost Performance Index CPI = EV/AC = .67

• Schedule Performance Index SPI = EV/PV = .67

• PV • $300,000 = Planned Value

• Quentin W. Fleming

• Estimate At Completion =(AC+(BAC-EV)/CPI) = $1,500,000

• $1,000,000 = Budget • At Completion

• ($500K projected overrun)

• BAC

• EAC

24

BAC = original planned valueEAC = PM project the project will cost

Page 13: Evm   class 02  1to15 by upad

13

Rauch & Hackenberg

Break

•  10 minute break

25 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Learning Team Project

•  Each learning team can pick their own project. •  The project should be a medium scale:

–  at least 50 tasks –  at least 5 resources

•  The project must come from a business situation. •  Learning team members will contribute background

details to define the project •  The team will work together to create a project

deliverables for its execution. •  Make sure projects are appropriately sized.

26 Copyright © 2012 Bill Hackenberg. All rights reserved.

Page 14: Evm   class 02  1to15 by upad

14

Rauch & Hackenberg

Learning Team Project Objectives

•  Demonstrate a working knowledge of project earned value.

•  The team can split up the work anyway they choose

•  Final deliverable must be a single document for which the team will receive a single grade.

•  This will count 30% towards your individual grade.

27 Copyright © 2012 Bill Hackenberg. All rights reserved.

Rauch & Hackenberg

Learning Team Project Roadmap

•  Using earned value tools, learning teams will create and present a project charter, WBS, schedule, EVM metrics, and EVM implementation to demonstrate that the group members have command of the project earned value.

•  Draft deliverables will be required several times during the course, with a final presentation of the project due in the final week.

•  Interim deliverables will receive feedback from the instructor as the work proceeds and modifications may be made before turning in the final paper.

28 Copyright © 2012 Bill Hackenberg. All rights reserved.

Page 15: Evm   class 02  1to15 by upad

15

Rauch & Hackenberg

Learning Team Class Exercise, Project Charter

•  Project Charter: – Project purpose or justification – Measurable project objectives and related

success criteria – High-level risks

29 Copyright © 2012 Bill Hackenberg. All rights reserved.