EVM Basics

  • Upload
    orjuan

  • View
    235

  • Download
    0

Embed Size (px)

Citation preview

  • 8/9/2019 EVM Basics

    1/43

    12/25/06 EVM Introduction 1

    12/25/06 EVM Introduction 1

    Brief Introduction toEarned Value Management (EVM)

  • 8/9/2019 EVM Basics

    2/43

    12/25/06 EVM Introduction 2

    12/25/06 EVM Introduction 2

    Outline

    Introduction to the basic rationale and elements of EVM

    Issues of actually implementing an EVM tracking scheme

    Background materials

  • 8/9/2019 EVM Basics

    3/43

    12/25/06 EVM Introduction 3

    12/25/06 EVM Introduction 3

    The Problem

    A successful program manager says: We completed the projectwe promised to deliver in the time we promised and with the

    budget we asked for. The standard source of information about the status of the

    project is the status of the budget, which only tells you howquickly and how completely you are spending the money youhave.

    What you really want to track is how quickly and howcompletely you are accomplishing the work you promised to do.

    The coupling of money spent to work done

    or schedule consumed is loose and nonlinear. Also, the expenditure track is a

    one-dimensional projection of a

    two-dimensional problem.

    ScheduleVariance

    BudgetVariance

    (under)

    (over)

    (ahead)(behind)

  • 8/9/2019 EVM Basics

    4/43

    12/25/06 EVM Introduction 4

    12/25/06 EVM Introduction 4

    Why You Need to Know Both

    Cost and Schedule Variances

    Project A is in good shape, under budget and ahead of schedule.

    Project B is over budget, but if we realize

    it is ahead of schedule, we can

    slow the effort to save money.

    Project Ds cost variance looks

    better than As, but if we

    realize it is behind schedule,

    we can spend more to catch up.

    Project C looks just like B if we

    only look at the cost variance, butwe cant slow down to save money.

    And it looks just like D if we only look at

    schedule, but we cant spend more to catch up. Its time to rescope!

    ScheduleVariance

    Budget

    Variance(under)

    (over)

    (ahead)(behind)

    A

    BC

    D

  • 8/9/2019 EVM Basics

    5/43

    12/25/06 EVM Introduction 5

    12/25/06 EVM Introduction 5

    1. DEFINE THE WORK AND ORGANIZE TEAMS

    100

    40

    60

    15

    25

    30

    30

    2. SCHEDULE THE WORK

    3. ALLOCATE BUDGETS

    $

    CONTRACT BUDGET BASE

    TIME

    BASELINE

    So What Do We Have to Work With?

    MANAGEMENT RESERVE (MR)

    Each chunk of workcorresponds to a

    chunk of budget anda chunk of schedule.

  • 8/9/2019 EVM Basics

    6/43

    12/25/06 EVM Introduction 6

    12/25/06 EVM Introduction 6

    For each chunk of work, define its value as the budgetassigned to it.

    When you complete that chunk of work, you have earned itsvalue.

    The total earned value to date gives you a point on the ($,time)graph the Budgeted Cost of Work Performed (BCWP).

    You could compare this to the actual amount of work that youwere supposed to have completed by this point in the schedule,as measured by its budgeted cost the Budgeted Cost of WorkScheduled (BCWS), another point on the ($,time) graph.

    You could also compare it to the actual amount spent to

    complete the chunks of work done to date theActual Cost ofWork Performed (ACWP), a third point on the ($,time) graph.

    Look at what information these comparisons give about thestatus of the project.

    The Basic Idea

  • 8/9/2019 EVM Basics

    7/43

    12/25/06 EVM Introduction 7

    12/25/06 EVM Introduction 7

    Budgeted Cost of Work Scheduled

    (BCWS)

    Total Budget = $5,000to be spent over 5 months

    We plan to deploy 1 standeach month at an estimatedcost of $1,000.BCWS each month = $1,000Month 1

    BCWS = $1,000

    Month 4BCWS = $1,000

    Month 3BCWS = $1,000

    Month 5BCWS = $1,000

    Month 2BCWS = $1,000

    Each dollar of BCWS represents a specific dollar of workscope. BCWS is aggregated and summed as the performancemeasurement baseline.

    Each dollar of BCWS represents a specif ic dollar of workscope. BCWS is aggregated and summed as the performancemeasurement baseline.

  • 8/9/2019 EVM Basics

    8/43

    12/25/06 EVM Introduction 8

    12/25/06 EVM Introduction 8

    Budgeted Cost of Work Performed

    (BCWP)

    Were at the end of thesecond month, but only1 stand is complete.Value of work performed= $1,000

    You earn value the same wayas it was budgeted in the baseline.

    You earn value the same wayas it was budgeted in the baseline.

  • 8/9/2019 EVM Basics

    9/43

    12/25/06 EVM Introduction 9

    12/25/06 EVM Introduction 9

    Schedule Variance

    (SV)

    BC WSBC WP

    Of the work we scheduled to have done,

    how much did we budget for it to cost?

    Of the work we actually performed,how much did we budget for it to cost?

    SCHEDULE VARIANCE is the difference between work scheduledand work performed (expressed in terms of budget dollars)

    formula: SV $ = BCWP - BCWS

    example: SV = BCWP - BCWS = $1,000 - $2,000

    SV= -$1,000 (negative = behind schedule)

    SCHEDULE VARIANCE is the difference between work scheduledand work performed (expressed in terms of budget dollars)

    formula: SV $ = BCWP - BCWS

    example: SV = BCWP - BCWS = $1,000 - $2,000

    SV= -$1,000 (negative = behind schedule)

    BUDGETBASED

  • 8/9/2019 EVM Basics

    10/43

    12/25/06 EVM Introduction 10

    12/25/06 EVM Introduction 10

    Schedule Variance

    (SV)

    $

    5 months

    BCWSthe baseline

    BCWPearned value

    TIME

    5,000

    sv

  • 8/9/2019 EVM Basics

    11/43

    12/25/06 EVM Introduction 11

    12/25/06 EVM Introduction 11

    Actual Cost of Work Performed

    (ACWP)

    Labor came to $1,300,and materials cost$1,100. That first standcost $2,400!

    actual expenditures vs. budgetactual expenditures vs. budget

  • 8/9/2019 EVM Basics

    12/43

    12/25/06 EVM Introduction 12

    12/25/06 EVM Introduction 12

    Cost Variance

    (CV)

    BC WPAC WP

    Of the work we actually performed,

    how much did we budget for it to cost?

    Of the work we actually performed,how much did it actually cost?

    COST VARIANCE is the difference between budgeted costand actual cost

    formula: CV $ = BCWP - ACWP

    example: CV = BCWP - ACWP = $1,000 - $2,400

    CV= -$1,400 (negative = cost overrun)

    COST VARIANCE is the difference between budgeted costand actual cost

    formula: CV $ = BCWP - ACWP

    example: CV = BCWP - ACWP = $1,000 - $2,400

    CV= -$1,400 (negative = cost overrun)

    PERFORMANCE

    BASED

  • 8/9/2019 EVM Basics

    13/43

    12/25/06 EVM Introduction 13

    12/25/06 EVM Introduction 13

    Cost Variance

    (CV)

    $

    TIME 5 months

    BCWPearned value

    ACWPactual cost

    5,000

    cv

  • 8/9/2019 EVM Basics

    14/43

    12/25/06 EVM Introduction 14

    12/25/06 EVM Introduction 14

    Note That We Can Isolate

    Schedule and Cost Variances

    schedule variance = BCWP - BCWS = negative numbercost variance = BCWP - ACWP = negative number

    behind schedule,over cost

    behind schedule,over cost

    5 months

    BCWS

    BCWP

    ACWP

    TIME

    5,000

    sv

    cv$

  • 8/9/2019 EVM Basics

    15/43

    12/25/06 EVM Introduction 15

    12/25/06 EVM Introduction 15

    Where are the significant problems?

    WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC

    1 3600 PCC Zepka 28.99 34.09 0.850 -296.2 -17.62 -187.2

    2 3200 COMMUNICATIONS Tideman 34.63 41.03 0.844 -130.8 -18.49 -87.0

    3 G&A GEN & ADMIN 33.67 36.11 0.932 -45.2 -7.26 -36.8

    4 2200 SYS ENGINEERING Price 85.04 94.35 0.901 -26.4 -10.95 0.0

    5 3800 I & A Troop 35.40 37.08 0.955 -24.2 -4.75 -24.8

    6 2100 PROJ MANAGEMENT Brown 45.70 48.51 0.942 -17.4 -6.16 -3.2

    7 2300 FUNC INTEGRA Price 71.62 75.23 0.952 -17.4 -5.03 -30.8

    8 5200 MANAGEMENT DATA Simmons 84.18 98.10 0.858 -13.2 -16.54 -16.0

    9 3100 SENSORS Smith 20.87 21.49 0.971 -10.6 -2.94 -21.6

    10 4000 SPARES Blair 17.87 18.90 0.945 -7.8 -5.78 -6.2

    11 6200 SYSTEM TEST Hall 60.82 61.66 0.986 -5.6 -1.38 -2.0

    12 5100 ENG DATA Novak 38.51 52.80 0.729 -4.6 -37.10 0.0

    13 MR MGT RESERVE 0.00 0.00 0.0 439.2

    14 UB UNDIST BUDGET 0.0 0.0

    15 COM COST OF MONEY 0.0 0.0

    16 3700 DATA DISPLAY Troop 41.13 41.13 1.000 0.0 0.00 0.017 OV OVERHEAD 0.0 0.0

    18 6100 TEST FACILITIES Smart 100.00 98.02 1.020 2.0 1.98 0.0

    19 3500 COMP PROGRAMS Pino 46.46 44.66 1.040 3.4 3.87 -1.4

    20 6300 PCC TEST Bond 23.13 22.64 1.021 4.2 2.10 0.0

    21 3400 ADPE Zepka 41.89 39.79 1.053 12.6 5.02 4.6

    22 3300 AUX EQUIP Tideman 27.57 24.33 1.133 78.2 11.73 8.4

    sorted by CV ($)By tracking and sorting on variances, wecan isolate the troublesome WBSelements.

  • 8/9/2019 EVM Basics

    16/43

    12/25/06 EVM Introduction 16

    12/25/06 EVM Introduction 16

    COST PERF INDEX (CPI) = BCWPACWP

    SCHED PERF INDEX (SPI) = BCWPBCWS

    COST PERF INDEX (CPI) = BCWPACWP

    SCHED PERF INDEX (SPI) = BCWPBCWS

    1.0

    .9

    1.1

    G

    OOD

    BAD

    1.2

    .8

    CPI

    SPI

    TIME

    Performance Indices

    We can also get a sense of the overall performanceof the project by tracking performance indices.

  • 8/9/2019 EVM Basics

    17/43

    12/25/06 EVM Introduction 17

    12/25/06 EVM Introduction 17

    Budget at Completion

    (BAC)

    $

    time

    BACsum of all BCWS =

    $

    $

    $$

    $

    $

    $

    When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000

    When all work has been phased, the cumulative BCWS = BACe.g., $5,000 = $5,000

    $5,000$5,000

    The most important markers of the overallperformance of the project look atpredictions of the variances at the end.These require several quantities, the firstbeing the Budget at Completion.

  • 8/9/2019 EVM Basics

    18/43

    12/25/06 EVM Introduction 18

    12/25/06 EVM Introduction 18

    Estimate at Completion (EAC)

    defined as actual cost to date + estimated cost of work remaining usually develop comprehensive EAC at least annually

    reported by WBS in cost performance report

    should examine on monthly basis

    consider the following in EAC generation:

    performance to date

    impact of approved corrective action plans

    known/anticipated downstream problems

    best estimate of the cost to complete remaining work

    also called latest revised estimate (LRE), indicated final cost, etc.

    What will be the final cost?

    ACWP + ETC = EAC

  • 8/9/2019 EVM Basics

    19/43

    12/25/06 EVM Introduction 19

    12/25/06 EVM Introduction 19

    Getting the Estimate at Completion

    Just a few little glitches.

    We should be able to dothe complete job.ack

    lets see, for about $7,500

  • 8/9/2019 EVM Basics

    20/43

    12/25/06 EVM Introduction 20

    12/25/06 EVM Introduction 20

    Common EAC Formulae:

    EAC = BAC/CPI

    = ACWPcum + Budgeted Cost of Work Remaining

    CPI3

    = ACWPcum + Budgeted Cost of Work Remaining

    .8(CPI) +.2(SPI)

    = ACWPcum + Budgeted Cost of Work Remaining

    CPI * SPI

    Determining EAC via Statistics

  • 8/9/2019 EVM Basics

    21/43

    12/25/06 EVM Introduction 21

    12/25/06 EVM Introduction 21

    Other methods of EAC calculation

    Grass Roots or formal EAC

    detailed build-up from the lowest level detail

    hours, rates, bill of material, etc.

    Average of statistical formulae

    Show range of EACs (optimistic, most probable,pessimistic)

    Complete schedule risk analysis for remaining work,

    estimate work remaining

  • 8/9/2019 EVM Basics

    22/43

    12/25/06 EVM Introduction 22

    12/25/06 EVM Introduction 22

    Variance at Completion(VAC)

    VARIANCE AT COMPLETION is the difference between what the totaljob is supposed to cost and what the total job is now expected to cost.

    FORMULA: VAC = BAC - EAC

    Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

    VARIANCE AT COMPLETION is the difference between what the totaljob is supposed to cost and what the total job is now expected to cost.

    FORMULA: VAC = BAC - EAC

    Example: VAC = $5,000 - $7,500VAC = - $2,500 (negative = overrun)

    B AC

    E AC

    what the totaljob is supposedto cost

    what the totaljob is expectedto cost

  • 8/9/2019 EVM Basics

    23/43

    12/25/06 EVM Introduction 23

    12/25/06 EVM Introduction 23

    Variance at Completion

    (VAC)

    VAC = Budget at Completion - Estimate at Completion

    = BAC - EAC

    $

    BAC

    EACVAC

    TIME

  • 8/9/2019 EVM Basics

    24/43

    12/25/06 EVM Introduction 24

    12/25/06 EVM Introduction 24

    Variance at Completion vs. Contractor Loss

    Positive VAC: EAC < BAC underrun contractor gain

    Negative VAC:

    EAC > BAC share area contractor partial loss

    EAC > ceiling overrun contractor loss (100%)

    Government develops top level EAC for comparison

    Government will limit progress payments if EAC is greater thanceiling

    Government needs forecast of fund requirements

    May still have time to change the final outcome

    VAC is Particularly Importantfor Government Contracts

  • 8/9/2019 EVM Basics

    25/43

    12/25/06 EVM Introduction 25

    12/25/06 EVM Introduction 25

    A survey of over 800 military programs showed that no programever improved performance better than the following EACcalculation:

    EAC = BAC/CPI,

    at the 15%-complete point in the program.

    Thus, there is strong empirical evidence that EVM translates earlyinformation into essential guidance for program re-baselining.

    Probably the BiggestSelling Point for EVM

  • 8/9/2019 EVM Basics

    26/43

    12/25/06 EVM Introduction 26

    12/25/06 EVM Introduction 26

    EVM Analyses

    PCUM

    Term Formula

    Percent Complete

    Cost Performance Indexor Performance Factor

    Checklist Actions

    Ratio of work accomplished in terms of the total amount of work to do.

    Symbol

    % Done

    CPI or PF

    TCPI or VF

    BCWPBAC

    Average Per formanceBCWPcum

    Duration (wks or mos)Since ACWP Began

    BCWPcum

    Duration (wks or mos)From Time Now toManager's StatedCompletion Date

    SC or S/CSchedule Correlation

    BCWPACWP

    Ratio of work accomplis hed against money spent (an effici ency rating: WorkDone for Resources Expended)

    To CompletePerformance Index

    or Verification Factor

    BAC - BCWPEAC - ACWP

    Ratio of work remaining against money remaining (Efficiency which must beachieved to complete the remaining work with the expected remaining money)

    Schedule Performance Index SPIRatio of work accomplished against what should have been done (Efficiency

    Rating: Work done as compared to what should have been done)

    BCWP

    BCWS

    SV

    Ratio of Schedule Variance (SV) in terms o f average amount of workaccompli shed (in weeks or months). It indicates a correlation to prog ram trueschedule condition

    IEACIndependent EstimateAt Completion

    BACPF

    Calculation of a projected Estimate At Completion to compare with the CAM'sEstimate At Completion:1) Ration of total work to be done against experienced cost effici ency2) Sunk costs added to a ratio of remaining work against weighted cost andschedule efficiencies

    1)

    2)BAC - BCWP.8CPI + .2SPI

    ACWP +

    Average ExpectedPerformance To Finish

    Average rate at wh ich work has been accompli shed s ince work began

    Average rate at wh ich work must be accompl ished in the fu ture to fi nish on thedate the CAM has forecasted for completion of the work.

    PTO GO

    PCUM

    There are a wide variety of indicators to play with in EVM.

  • 8/9/2019 EVM Basics

    27/43

    12/25/06 EVM Introduction 27

    12/25/06 EVM Introduction 27

    EVM Analyses

    Sort on significant variances

    eliminate almost complete, just starting, etc. Graph and analyze trends

    Look at comparative data

    e.g. cumulative performance vs. projected performance

    Examine written analysis by contractor

    does it answer why?

    adequacy of corrective action plans

    Analysis of schedule trends, critical path Analysis of EAC realism

    what are the drivers?what can we do about them?

    what are the drivers?what can we do about them?

    There are a wide variety of analytic techniques to play with in EVM.

  • 8/9/2019 EVM Basics

    28/43

    12/25/06 EVM Introduction 28

    12/25/06 EVM Introduction 28

    Graphical EVM Analyses

    Dollar

    sInMillions

    Estimates at CompletionMEGA HERZ ELEC & VEN F04695-86-C-0050 RDPR FPI

    Element: 3600 Name: PCC

    BACLRECUM CPI

    1992APR MAY JUN JUL AUG SEP OCT NOV DEC

    1993JAN

    5.0

    6.0

    7.0

    8.0

    5.1 5.4 5.1

    5.1 5.4 5.7

    5.1 5.4 5.9

    5.1 5.4 6.0

    5.1 5.5 6.3

    5.1 5.5 5.8

    5.1 5.5 6.5

    5.5 5.7 7.6

    5.5 5.7 6.8

    5.8 6.0 6.8

    MEGA HERZ ELEC & VEN Cost/Schedule VarianceF04695-86-C-0050 MOH-2 RDPR FPI POP: 01 MAR 1992 - 15 SEP 1993

    PercentofDollars

    COST VARIANCESCHEDULE VARIANCE

    1992MAY JUN JUL AUG SEP OCT NOV DEC

    1993JAN

    -30.0

    -20.0

    -10.0

    0.0

    10.0

    20.0

    30.0

    Cost Drivers, Cause

    Dollars In MillionsBCWSBCWPACWP

    CVSV

    0.3 0.2 0.2

    0.0 -0.1

    0.6 0.5 0.5

    -0.0 -0.1

    1.0 0.9 0.9

    -0.0 -0.1

    1.4 1.4 1.5

    -0.1 -0.0

    2.2 2.2 2.2

    0.0 -0.0

    2.5 2.7 3.0

    -0.3 0.2

    4.2 3.8 4.2

    -0.5 -0.4

    5.6 5.3 5.6

    -0.3 -0.3

    7.3 6.9 7.3

    -0.5 -0.4

    At CompletionKTR PO

    20.8 20.8

    20.8 20.8 20.8 23.0

    0.0 -2.2

    PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0

    CURRENT FUNDING: 10.0PO EPC: 24.0

    PROJ FUNDING: 23.0

    AS OF: JAN 93OPR: MR B. TECH

    PROGRAM: Mohawk Vehicle

    0%

    -11%-7%-6%

    Overall cost and schedule trend

    EAC realism

    graphs show overall trend...are you getting better,

    or worse?

    graphs show overall trend...are you getting better,or worse?

  • 8/9/2019 EVM Basics

    29/43

    12/25/06 EVM Introduction 29

    12/25/06 EVM Introduction 29

    Will the contractor come in on budget?

    COST PERFORMANCE INDEX:

    CPI = cost efficiency for work performed to date(The value of work accomplished for each dollar spent)

    $1000

    = = = $2400 = .42

    Compare the CPI to the TCPI-BAC:

    TCPI(BAC) = Effic iency necessary to complete on budget

    = = = $5000 - $1000$5000 - $2400

    Example: Using Performance Efficiencies (1)

    BCWP

    ACWP

    WORKACCOMPLISHED

    ACTUALS

    BAC-BCWPBAC-ACWP

    WORKREMAINING

    BUDGETREMAINING

    = $4000$2600 = 1.54

    HISTORY

    FUTURE

  • 8/9/2019 EVM Basics

    30/43

    12/25/06 EVM Introduction 30

    12/25/06 EVM Introduction 30

    Example: Using Performance Efficiencies (2)

    SCHEDULE PERFORMANCE INDEX:

    SPI = schedule effic iency with which work has been accomplished(The rate at which work is being accomplished)

    WORK= BCWP = ACCOMPLISHED = $1000 = .50

    BCWS WORK $2000SCHEDULED

  • 8/9/2019 EVM Basics

    31/43

    12/25/06 EVM Introduction 31

    12/25/06 EVM Introduction 31

    IS THE CONTRACTOR'S EAC (LRE) REASONABLE?

    Compare the CPI to the TCPI-LRE

    TCPI(LRE) = Effic iency necessary to complete at the contractors estimate

    WORKBAC-BCWP REMAINING $5000 - $1000 $4000 1.00

    LRE-ACWP ESTIMATE $6400 - $2400 $4000REMAINING

    Cumulative performance to date (CPI) = .42

    Contractor has been performing at 42% efficiency, but expects tocomplete remaining work at 100% efficiency!

    Example: Using Performance Efficiencies (3)

    reasonable?

    = == = =

  • 8/9/2019 EVM Basics

    32/43

    12/25/06 EVM Introduction 32

    12/25/06 EVM Introduction 32

    Outline

    Introduction to the basic rationale and elements of EVM

    Issues of actually implementing an EVM tracking scheme

    Background materials

  • 8/9/2019 EVM Basics

    33/43

    12/25/06 EVM Introduction 33

    12/25/06 EVM Introduction 33

    ControlAccount

    SoftwareEngineering

    Getting at the Value

    WorkPackages

    PlanningPackages

    OBS DATA SUMMARIZATION

    SOFTWAREINTEGRATION

    PROGRAM

    ProductDevelopment

    MasterPlanning

    AdaProducts

    SoftwareTools

    Standards

    CPCI #1MOS

    CPCI #2MOLE

    CPCI #3MAC

    AdaStudy

    AdaConversion

    AdaAppr oach

    AdaAppl icati ons

    SecureSystems

    LANAppl icati ons

    Marketing

    BCWSBCWPACWP

    BACEAC

    FUNCTIONAL

    ORGANIZATION

    CWBS

    EXTENSION

    SELECTED

    REPORTING

    ELEMENTS

    SELECTED

    PSWBS

    ELEMENTS

    HardwareEngineering

    Engineering

    Operations

    WBS

    DAT

    A

    SUM

    MARIZ

    ATION

    VP/GM

    Control

    Account

    ControlAccount

    Control

    Account

    Control

    Account

    ControlAccount

    Control Account

    Responsibility Matrix

  • 8/9/2019 EVM Basics

    34/43

  • 8/9/2019 EVM Basics

    35/43

    12/25/06 EVM Introduction 35

    12/25/06 EVM Introduction 35

    Development of Control Account Plans

    MAY break down the control account budget into smaller work

    packages

    Work Package

    subset of control account

    reasonably short in duration

    single element of cost (e.g., labor) single technique for earning value

    consistent with detail schedules

    has same characteristics as control account

    scope of work milestone completion criteria

    single performing organization

    start and end dates

    CONTROL ACCOUNT PLAN

    Work Pkg #1

    Work Pkg #2

    Work Pkg #3

    $$

    $ $

    $

    $

    $

    $$

    Work Packages

  • 8/9/2019 EVM Basics

    36/43

    12/25/06 EVM Introduction 36

    12/25/06 EVM Introduction 36

    Work packages are discrete and measurable.

    Work packages yield products or accomplishments, such as

    design drawing package

    conduct design review

    install stand

    Often done in rolling wave

    detailed plans made for near term work packages

    planning packages are for future work and are not detailed

    CAMs periodically plan another increment of work packages

    Work Package Characteristics

  • 8/9/2019 EVM Basics

    37/43

    12/25/06 EVM Introduction 37

    12/25/06 EVM Introduction 37

    Should be a quantitative and discrete way to measure the work

    Discrete

    physical, tangible end product Apportioned

    discrete, dependent on another discrete work package

    example: quality assurance

    planned as historical estimating factor (e.g., 7%)

    Level of Effort

    no tangible end product

    basis of measurement: time

    when clock starts ticking, you automatically accumulate earned value

    no schedule variance example: management personnel

    May tie in with success criteria or technical measure e.g., successful completion of a specific test, reliability growth curve

    Ways of Earning Value

  • 8/9/2019 EVM Basics

    38/43

    12/25/06 EVM Introduction 38

    12/25/06 EVM Introduction 38

    Method How Value is Earned

    0/100 no EV at opening, 100% EV at close of WP

    50/50 50% EV at opening, 50% EV at close of WP

    Units Completed same budget value for identical units

    Equivalent Units planned unit standards, allows partial credit

    Weighted Milestone each milestone weighted based on plannedresources

    ideal to have a milestone each month

    Percent Complete subjective (least desirable)

    Methods for Assigning Earned Value

  • 8/9/2019 EVM Basics

    39/43

    12/25/06 EVM Introduction 39

    12/25/06 EVM Introduction 39

    Suggested for LWA

    0/50/100 measurement

    Typical work package length is 80 hours.

    Work package status is reported at status meetings, held everytwo weeks. May just be that 50% of work packages are reported at weekly

    status meetings.

    EV is 0% (of budget for work package) if it has not yet been

    started, or is only now starting. EV is 50% if work is underway.

    EV is 100% if work is complete.

    If work package is at 50% two status meetings in a row, it is

    flagged as a potential issue. Avoids subjectivity of % done; compromises on granularity oftracking, frequency of reporting

    Puts the onus on doing the WPs right, up front.

  • 8/9/2019 EVM Basics

    40/43

    12/25/06 EVM Introduction 40

    12/25/06 EVM Introduction 40

    Outline

    Introduction to the basic rationale and elements of EVM

    Issues of actually implementing an EVM tracking scheme

    Background materials

  • 8/9/2019 EVM Basics

    41/43

    12/25/06 EVM Introduction 41

    12/25/06 EVM Introduction 41

    A Spectrum of Implementation

    Where

    When

    Core EV PrinciplesANSI/EIA-748-1998

    (32 criteria)Tailored Applications

    SmallCompanies Larger Companies

    MajorDefense

    Contractors

    as desired

    Government

    Organic

    Reports

    ForeignCountries

    streamlined,no paper?

    corporatepolicy,

    enterprisewide

    DoD Non-MajorContracts

    (>12 months)

    $6M

    DoD MajorContracts

    >$70M RDT&E

    >$300M Prod

    tailored toneeds

    C/SSR CPR

    *with judgment

    FFPcontracts?

    Commercial or Defense

    Earned Value Management:

  • 8/9/2019 EVM Basics

    42/43

    12/25/06 EVM Introduction 42

    12/25/06 EVM Introduction 42

    Earned Value Management:History

    1959 PERT and PERT/Cost Milestone Charts And Rate-of-Expenditure

    Curves Dollars Spent Vs Estimates Of Percent

    Complete (DD 1097)

    1963 Earned Value Concept (MINUTEMAN)

    1964 Cost Accomplishment Concept (TITAN III)

    1966 AFCost/schedule Planning And ControlSpecification (C/SPCS)

    1967 DODCost/Schedule Control SystemsCriteria (C/SCSC) (DODI 7000.2)

    1972 DOD-Revised DODI 7000.2 and Issued theJoint Implementation Guide (JIG)

    1972 NASA Marshall Space Flight CenterC/SPC

    1975 DOEPerformance Measurement System(PMS)

    1976 DODRevised the C/SCSC JIG

    1980 DODRevised the C/SCSC JIG

    1982 National Security AgencyEarned Value

    1983 NASAGoddard Space Flight CenterPMS

    1984 FAA & NASA Lewis Research CenterPMS

    1985 NASA Johnson Space Flight CenterPMS

    1987 DODRevised DOD C/SCSC JIG

    1988 NASA Marshall SFCRevised PMS

    (MMI 8020.7C, 44 Criteria) 1989 Australian DODDODI 7000.2

    1990 Canadian DODPMS

    1991 DODI 5000.2 replaces DODI 7000.2

    1992 National Oceanic And AtmosphericAdministration (NOAA)PMS

    1993 Swedish FMVC/SCSC

    1994 Internal Revenue Service (IRS)C/SCSC

    1994 Federal Bureau Of Investigation (FBI)C/SCSC

    1996 DODR 5000.2-R replaces DODI 5000.2C/SCSC revised from 35 to 32 criteria

    1996 Revised JIGRenamed Earned Value

    Management Implementation Guide (EVMIG) 1997 EVMIG Revised

    1998 MIL-STD 881B replaced by MIL HDBK 881

  • 8/9/2019 EVM Basics

    43/43

    12/25/06 EVM Introduction 43

    12/25/06 EVM Introduction 43

    EVM Resources

    Books

    Earned ValueQuentin W. Fleming & Joel M. Koppleman

    Cost/Schedule Control Systems Criteria

    Quentin W. Fleming

    Project Performance MeasurementRobert R. Kemps

    Visualizing Project ManagementKevin Forsberg, Ph.D., Hal Mooz andHoward Cotterman

    Software

    Artemis ViewsArtemis Management SystemsContact: Patrick Perugini (303) 581-3102Web: http://www.artemispm.com

    CobraWelcom SoftwareContact: Diana Melton (281) 558-0514Web: http://www.wst.com

    Software [continued]

    Dekker TRAKKERDekker Ltd.Contact: Ron Barry (909) 384-9000

    Web: http://www.dtrakker.com

    MicroFrame Project Manager (MPM)MicroFrame Technologies, Inc.Contact: Carl Amacker (415) 616-4000Web: http://www.microframe.com

    Internet

    Project Management Institutehttp://www.pmi.org

    US DoD Earned Valuehttp://www.acq.osd.mil/pm

    Earned Value Bibliographyhttp://www.uwf.edu/~dchriste/ev-bib.html