32
Earned Value Management Drexel University, Goodwin College CT431-120 Project Management R. Gottardi, Instructor/Author May 31, 2009

Earned value management lecture 2009e my31

Embed Size (px)

DESCRIPTION

project cost management, earned value management, performance measurement, schedule variance, cost variance, budget

Citation preview

Page 1: Earned value management lecture 2009e my31

Earned Value ManagementDrexel University, Goodwin College CT431-120 Project ManagementR. Gottardi, Instructor/Author May 31, 2009

Page 2: Earned value management lecture 2009e my31

2

Some Definitions

• Planned Value, PV (BCWS): the portion of the approved total cost estimate during a given period

• Actual Cost, AC: the total of the direct & indirect costs incurred in accomplishing work on a task or project during a given period

Page 3: Earned value management lecture 2009e my31

3

Project Tracking without Earned ValueProject Performance

0

20

40

60

80

100

120

140

160

180

200

Weeks

$000

BCWS Actual Cost

BCWS 10 20 25 40 62 80 98 125 137 149 160 175

Actual Cost 30 48 52 55 60 65 70 72

1 2 3 4 5 6 7 8 9 10 11 12

Conclusion: It looks like we are under budget. What’s missing?

Page 4: Earned value management lecture 2009e my31

4

What’s Missing

• Any measure of how much work has been accomplished

• Earned Value: an estimate of the value of the physical work actually completed

• Can be – currency, e.g., $– Quantities, e.g., tons, yds3, SF, etc.– Any agreed upon value for the tasks

Page 5: Earned value management lecture 2009e my31

5

How Can We Measure Progress?

• % complete of the tasks’ durations• Rate of performance (RP): % complete actual/%

compete planned• Physical quantities (works for some tasks but not others)

– Tons of earth moved– Cubic yards of cement poured– Floors completed– Sq ft completed

• Let’s use RP because it is common to many tasks & gives us a schedule related measure

Page 6: Earned value management lecture 2009e my31

6

Establish Earning Rules

Rule Credit at Start Credit at End

0/100 0% 100%

50/50 50% 50%

25/75 25% 75%

20/80 20% 80%

Credit means the budgeted cost of work performed is included in the earned value calculation to the extent of the % indicated.

Page 7: Earned value management lecture 2009e my31

7

Earned Value Vs. Planned ValueProject Performance

0

20

40

60

80

100

120

140

160

180

200

Weeks

$000

PV(BCWS) EV(BCWP)

PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175

EV(BCWP) 28 60 62 70 72 80 82 92

1 2 3 4 5 6 7 8 9 10 11 12

Schedule VarianceBehind Schedule

Page 8: Earned value management lecture 2009e my31

8

Earned Value vs. Actual CostProject Performance

0

10

20

30

40

50

60

70

80

90

100

Weeks

$000

Actual Cost EV(BCWP)

Actual Cost 30 48 52 55 60 65 70 72

EV(BCWP) 28 60 62 70 72 80 82 92

1 2 3 4 5 6 7 8 9 10 11 12

Cost Variance ($)Under Budget

Page 9: Earned value management lecture 2009e my31

9

Combine All VariablesProject Performance

0

20

40

60

80

100

120

140

160

180

200

Weeks

$000

PV(BCWS) AC(Actual Cost) EV(BCWP)

PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175

AC(Actual Cost) 30 48 52 55 60 65 70 72

EV(BCWP) 28 60 62 70 72 80 82 92

1 2 3 4 5 6 7 8 9 10 11 12

PV

AC

EV

Page 10: Earned value management lecture 2009e my31

10

Variance Computations

• Cost Variance (CV)=EV-AC

• Schedule Variance (SV)=EV-PV

• Negative values are unfavorable

• Positive values are favorable

Page 11: Earned value management lecture 2009e my31

11

Performance Indices

• Cost Performance Index (CPI)=EV/AC

• Schedule Performance Index (SPI)=EV/PV

• <1= unfavorable

• >1=favorable

Page 12: Earned value management lecture 2009e my31

12

Earned Value

• Integrates schedule & cost data

• Explains causes of variances

• Encourages objective measurement of progress

• Measures performance

Page 13: Earned value management lecture 2009e my31

13

Problem

• Given:• EV = $5,000• PV = $10,000• AC = $15,000

• Solve:• CV =• SV =• CPI =• SPI =

Page 14: Earned value management lecture 2009e my31

14

Problem

• Given:• EV = $5,000 = Earned Value• PV = $10,000 • AC = $15,000

• Solve:• CV =• SV =• CPI =• SPI

Page 15: Earned value management lecture 2009e my31

15

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000• AC = $15,000

• Solve:• CV = • SV = • CPI =• SPI =

Page 16: Earned value management lecture 2009e my31

16

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value• AC = $15,000

• Solve:• CV =• SV =• CPI =• SPI =

Page 17: Earned value management lecture 2009e my31

17

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BCWS• AC = $15,000

• Solve:• CV = • SV =• CPI =• SPI =

Page 18: Earned value management lecture 2009e my31

18

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BCWS• AC = $15,000 = Actual Cost

• Solve:• CV =• SV =• CPI =• SPI =

Page 19: Earned value management lecture 2009e my31

19

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC• SV = • CPI =• SPI =

Page 20: Earned value management lecture 2009e my31

20

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 • SV = • CPI = • SPI =

Page 21: Earned value management lecture 2009e my31

21

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = • CPI = • SPI =

Page 22: Earned value management lecture 2009e my31

22

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV• CPI =• SPI =

Page 23: Earned value management lecture 2009e my31

23

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000• CPI = • SPI =

Page 24: Earned value management lecture 2009e my31

24

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = • SPI =

Page 25: Earned value management lecture 2009e my31

25

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC• SPI =

Page 26: Earned value management lecture 2009e my31

26

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC = 5,000/15,000• SPI =

Page 27: Earned value management lecture 2009e my31

27

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC = 5,000/15,000 = .33• SPI =

Page 28: Earned value management lecture 2009e my31

28

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC = 5,000/15,000 = .33• SPI = EV/PV

Page 29: Earned value management lecture 2009e my31

29

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BSWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC = 5,000/15,000 = .33• SPI = EV/PV = 5,000/10,000

Page 30: Earned value management lecture 2009e my31

30

Problem

• Given:• EV = $5,000 = Earned Value = BCWP• PV = $10,000 = Planned Value =BCWS• AC = $15,000 = Actual Cost

• Solve:• CV = EV-AC = 5,000-15,000 = -10,000• SV = EV-PV = 5,000-10,000 = -5,000• CPI = EV/AC = 5,000/15,000 = .33• SPI = EV/PV = 5,000/10,000 = .5

Page 31: Earned value management lecture 2009e my31

31

Other Terms & Computations

• BAC: Budget at Completion: The original total budget for a project

• EAC: Estimate at Completion = BAC/CPI (CPI = Cost Performance Index)

• ETC: Estimate to Complete: EAC-AC

• Variance at Completion: BAC-EAC

Page 32: Earned value management lecture 2009e my31

32

Earned Value

• Title: Earned Value Management• Filename: Earned Value Management Lecture 2009eMY31• Author: Ron Gottardi• Author Affiliation: Drexel University, Goodwin College of

Professional Studies• Course: CT431-120 Project management• Date: May 31, 2009• Copyright 2009 Ron Gottardi