Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
1
6.25.05 mms
hm
ms
h
Introduction & Acknowledgements Developing the National Center for Community Renewal Preliminary thoughts to guide facility programming and design Interest in the success of Shreveport / Bossier Community Renewal has resulted in the need to establish a national center. The philosophy, programs and methodology of rebuilding communities on mutually enhancing relationships are working. Shreveport / Bossier, Louisiana is the laboratory to develop and implement programs. As word spreads support and interest are growing. The Robert Wood Johnson Foundation has provided the resources to help formalize the methodology for documenting success and replicating the processes of renewal in other communities. Community Renewal has established a national board for the purpose of building capacity to share these programs with communities around the world. Partnering initiatives with several Universities and interest from federal and state political leadership supports the need for establishing a National Center for Community Renewal (NCCR). The Center will serve two primary purposes:
The Community Renewal Learning Center will provide training and conference facilities. Training sessions will range in duration from several days up to six weeks. Participants in longer duration training will achieve Community Renewal Certification. The training and conference sessions are collaborative and experiential. Participants are exposed day and night to opportunities to learn the programs and develop strategies to apply to their communities. This teacher and peer learning process requires a building that functions as a complete conference center with training / meeting rooms; housing that encourages informal gatherings and small group peer collaboration; and food service. Flexibility is important for training rooms. Group sizes are anticipated to range from several groups of 10 – 15 to larger sessions of up to 300 participants. The market for training is broad and includes community activist, social service providers, community development professionals, planners, redevelopers, political leaders, and many others from communities all over the world.
The Community Renewal Institute will provide offices for faculty, researchers,
interns, guest lecturers, Community Renewal administration and other support staff (current projections for CR administrative staff of 35); research library that will include production facilities for developing training materials; and distance learning / web casting facilities. Activities of the Institute will include monitoring the progress of renewal communities, publishing research and partnership initiatives with higher education institutions.
The Center will be a demonstration of renewal, a symbol that reflects the purpose and spirit lifting qualities that inspire rebuilding quality communities. The NCCR will be designed and operated to stimulate renewal of the building context. A location at the heart of Shreveport /
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
2
6.25.05 mms
hm
ms
h
Introduction & Acknowledgements
Bossier was identified: a 16-story, 140,000 square foot high-rise office building. The owners agreed with the concept and donated the building for use as the NCCR. The 1960’s vintage, concrete frame, curtain wall building was abandoned in the late 1980’s due to local market conditions and cost of asbestos removal. It is a great building to target for renewal using appropriate urban design and renewal architecture principals to symbolize the mission of the NCCR. For example, the first floor uses of the building should contribute to the streetscape pedestrian experience. Storefront business with display windows and frequent entry doors add to the life and safety of the street. A mixed-use project adds to the viability of a 24-hour a day downtown. The act of renovating this building is a “green action” that reduces embodied energy required to manufacture and transport materials for construction. What are the additional opportunities to renew this building through “green building” principals? What is the appropriate LEED certification? The building as a symbol and an experience should inspire an architectural expression of the NCCR purpose to renew communities. The top of the building is an opportunity to distinguish this building and design a memorable addition to the skyline. The building entry should be inviting and encourage the feeling of mutually enhancing relationships. Ideas discussed include a 2-story lobby that conceptually resembles a neighborhood main street. The building design should encourage interaction. Public spaces should provide a variety of opportunities for participants and visitors to meet and places to sit, talk and collaborate. Dialogue areas or “living areas” should be included in residential, conferencing and any commercial areas of the building. Among the Center amenities include a small chapel that could be located on the top of the building or other appropriate location. The issue of food service should be explored carefully to determine the degree of on site food preparation or contract food service. In determining an exact program to guide design there are many issues to explore and understand. Among those issues are:
Descriptions of training and other activities in the building. Requirements for research and library facilities. Management and staffing requirements for the national center. Parking options for the facility. Facility management options and analysis. Operational budgets. Renovation and furnishings functional concepts and budgets. Residential floors requirements - room sizes, features and quantity. Code implications
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
3
6.25.05 mms
hm
ms
h
Introduction & Acknowledgements
Fundraising strategies and publications Technology requirements
Current challenges include identifying and organizing people resources to model the possibilities for NCCR. The current strategy is to bring diverse brainpower to the table in a “Charette” setting. Invitation possibilities for groups or individuals are:
Conference Center experts from Oklahoma University with applicable functional and operational knowledge.
Architecture and planning students and faculty from University of Texas, Oklahoma and Louisiana Tech to work in blended teams on design ideas. A program will be prepared prior to the Charette to guide teams. The Charette agenda will be structured to allow teams to incorporate ideas from parallel facilitations for other group discussions.
Academicians to discuss organization, certification and teaching techniques. Community Renewal Staff Facility managers to discuss operational structures and options. Economic developers from the state and representative(s) from the Governor’s
office. Fundraising strategists Professional architects, planners and board members Others?
Discussion and evaluation is also needed to determine the structure for project delivery and schedule. Funding for asbestos removal is under way and initial funds are committed to move forward with planning for abatement. Potential project funding sources include HUD, Brownfield grants, Kresge Foundation and donations.
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
4
6.25.05 mms
hm
ms
h
Project Goals & Overview
Operation
Existing Site & Building Context
Site Improvements, Analysis & Concepts
Area Summary
Program Spaces & Descriptions
Program Adjacency Diagrams & Concepts
Code Provisions
Space Description Worksheets
Facility M.E.P. Systems
Product Information & Web Sites
Budget
Schedule
Summary
Index
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
5
6.25.05 mms
hm
ms
h
Goals & Overview Form: The goal is to apply reasonable energy conversation measures to enhance the projects status as ‘green architecture”, “sustainable design” and “smart growth”. Function: Economy: Time:
Shreveport, La.
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
6
6.25.05 mms
hm
ms
h
Goals & Overview Vision Our vision is to develop, support, and nurture the Center for Community Renewal located in downtown Shreveport where learning to restore the foundation of safe and caring communities by rebuilding the system of caring relationships is demonstrated and taught to other communities, national and international. Major Goal We envision building this National Center to aid in stopping the disintegration of cities and neighborhoods where families and individuals can have hope and live in productive and healthy communities. To understand that by re-establishing a systemic way of building relationships, we will restore our ability to build healthy and productive communities in our cities. To develop and implement the development of a new industry of social technology to renew neighborhoods and cities. Major Action To remediate, renovate, and develop a sustainable environmentally sound “green” building using cutting edge technology and techniques in partnership with the University of Texas School of Architecture and the University of California at Berkeley for the purpose of housing the National Center of Community Renewal.. What Is the Need? It is apparent that communities and cities are experiencing rising criminal activity, drug and alcohol abuse, children being abused and neglected, domestic violence, school dropouts, and increasing number of uneducated individuals living in poverty. Billions of dollars and effort goes into addressing these problems through our federal, state, and city budgets each year. An individual or organization alone will not solve these problems. Solving these problems will take all of us. We realize that our cities rest on the foundation of relationships. If these relationships disintegrate we will continue to see these difficult problems face our individuals, communities, and cities. By establishing a systemic process to rebuild these relationships, which has been established in Shreveport, Louisiana, this process can then be shared with others through our National Center of Community Renewal. Expected Outcomes of Training of National Center
Develop a new industry of “social technology” to enhance growth capital Dissemination of a systematic working model to neighborhoods and cities who wish to
stop disintegration of cities through an established training and demonstration program
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
7
6.25.05 mms
hm
ms
h
Goals & Overview
An established on-going training program and support for all levels of individual and organizations through the National Training Center Program
Replication of model in partnering cities through training and technical assistance Increased involvement of individuals in impoverished neighborhoods in changing their
culture Established academic certification through partnership with existing universities Established a curriculum for interns with partnership with existing college and
universities Develop curriculum to deliver training in all three aspects of model by on-site and
through distance learning Increase in quality of life in neighborhoods and cities Develop a fee structure for national center to become a profit center to support
activities Seek grants/contracts to aid participation by others interested in studying at the
National Center and the concept of Community Renewal Major Components of Modal of Renewal— Our model will provide the principles and knowledge to implement the major efforts. Renewal Team: The Renewal Team acts as a coordinator and facilitator of many individuals and groups including businesses, civic organizations, churches, and professional organizations that support our mission of connecting and serving the community. The We Care Team helps caring people visible to one another throughout the community. Haven House Plan: Caring relationships among neighbors are developed “block by block” across the city by enlisting and training persons willing to build friendships and neighbors on their street. These dedicated volunteers are committed to remaking “their neighborhoods”. Volunteer Haven House Leaders learn to reach out their neighborhood through a systematic, yet very simple approach. SBCR offers training sessions to equip these volunteers. The Internal Care Unit – Friendship Houses: The Internal Care Unit “Friendship Houses” are homes established in high crime/low-income neighborhoods to help bring hope and support to children and adults. A local missionary family moves into these homes to build trust and relationships within these communities and through after-school, and mentoring programs, lives are changed and hope is restored. Various educational, spiritual, and healthcare initiatives are provided to help families become productive citizens of our community.
Renewal Team Haven House
Internal Care Unit
Community Renewal International Paradigm
Social TechnologySocial Technology
Renewal TeamRenewal Team Haven HouseHaven House Internal Care UnitInternal Care Unit
Caring alone does not stop collapse…
Connect Caring People:1. Visible2. Connected3. Committed
Caring alone does not stop collapse…
Connect Caring People:1. Visible2. Connected3. Committed
Relational Foundation = Social Capital = Mutually connected togetherSBCR produces MER by doing 3 things: RT, HH & ICU
Relational Foundation = Social Capital = Mutually connected togetherSBCR produces MER by doing 3 things: RT, HH & ICU
We are disconnected / isolated on our streets & in our neighborhoods…
Take city back, systematically:1. Rebuild relational foundation2. Build social networks3. Block leaders form connected
nurturing structure
We are disconnected / isolated on our streets & in our neighborhoods…
Take city back, systematically:1. Rebuild relational foundation2. Build social networks3. Block leaders form connected
nurturing structure
There is the reality of decay & problems of oppression, race & poverty…
Renew whole persons:1. Build trust by serving2. Friendship Houses3. Model the family unit4. Paid staff
There is the reality of decay & problems of oppression, race & poverty…
Renew whole persons:1. Build trust by serving2. Friendship Houses3. Model the family unit4. Paid staff
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
8
6.25.05 mms
hm
ms
h
Goals & Overview
Why Shreveport? The SBCR model was developed and exists in Shreveport and is changing lives. By locating the “National Center” in Shreveport those who come to learn will be able to participate in a “living laboratory” as well as experiencing their own renewal. Who will come to the National Center?
Governmental Agencies Community Leaders Urban Planners Faith-Based Groups Neighborhood Associations National Organizations College and Universities Non-Profit Groups Individuals Committed to Renewal International Organizations Foundations Continuing Education
What Will the National Center Offer?
Academic Certifications Seminars/Awareness Conferences Major Conferences Internships Intensive Training for Replication of Model Support and Technical Assistance Continuing Education
Think Tanks On-going systemic research on defining renewal process Publishing efforts for renewal effort Developing success indicators Evaluation and monitoring the impact with Shreveport-Bossier and cities who
plan replication
Safe Environments Mutually Enhancing Relationships
Adequate HousingEducation Meaningful Work
Common Culture Leadership Health Care
Key Elements of Renewal
Community Renewal International Paradigm
Mutually Enhancing RelationshipsThe Relational Foundation of Community
Mutually Enhancing RelationshipsThe Relational Foundation of Community
SafetySafety
Adequate HousingAdequate Housing
Meaningful WorkMeaningful Work
HealthcareHealthcare
Culture of CaringCulture of Caring
Servant LeadershipServant Leadership
EducationEducation
Village StructureVillage StructureCommunity Renewal International Paradigm
Whole Person = competent & compassionateWhole Person = competent & compassionate
Competent- willingness & ability to access & appropriate resources to continually grow :
Spiritually, Socially, Skillfully, Physically, Intellectually & Emotionally
Compassionate- lifestyle devoted to seeking the good of others while seeking their own good
Competent- willingness & ability to access & appropriate resources to continually grow :
Spiritually, Socially, Skillfully, Physically, Intellectually & Emotionally
Compassionate- lifestyle devoted to seeking the good of others while seeking their own good
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
10
6.25.05 mms
hm
ms
h
Location and Existing Building Description National Center for Community Renewal The National Center for Community Renewal (NCCR) will be located in a vacated existing fifteen-story high-rise office building in the central business district of Shreveport, Louisiana. The site is at the Northeast (North by compass) corner of Texas and Edwards Streets. The west side of the building is 150 feet along Edwards Street. Lobby entry to the high-rise is near the center of this side. The south side is 60 feet along Texas Street. Along the north side is a service alley that divides the city block. The east side of the building is on the property line adjoining an adjacent two story building. The orientations described are for ease of describing the building, as compass north is diagonal to the city block grid. The building, constructed as the Petroleum Tower in 1958, is located in a downtown historic district. There are approximately 10 other high-rise buildings of 10-24 floors within one block of this building. There are also a number of locally important buildings that add to the historic fabric within one block (e.g., The Chamber of Commerce that was the old library, the old Post Office that was renovated for use as the central library and the Parish Courthouse). There remain a number of 2 – 5 story commercial buildings that also contribute to the “toute ensemble” of the historic district. Over the past 20 years approximately 80 of these structures have been demolished and primarily used as surface parking. The National Center building is in the center of this area of downtown that is the business and financial center of Shreveport and the Ark-La-Tex. Texas Street is the historic main street and is the widest street in downtown. Zoning for the property is B-4 (Central Business District). Parking is not required for office use. Petroleum Tower does not have parking associated with the building, which was a likely contributing factor to the decision to vacate the building. There are a number of parking structures and surface lots within a short walk. One nearby parking facility is structured for additional floors. Petroleum Tower is a concrete frame building with aluminum curtainwall exterior cladding on the north, west and south facades. The party wall on the east façade is black modular brick masonry. Structural bays are nominally 20’ x 25’. Building core functions (i.e., traction elevators, stairs and toilets) are located along the east side of the building. In addition to the 15 floors of tenant space are a basement and mechanical penthouse. Induction heating units are located on the perimeter of each floor. Space above the ceilings of each floor is used as a return air plenum. Concrete beam and floor construction provides a 3-hour fire separation. Stairwells are enclosed in 2-hour construction of 2.5” thick solid plaster walls. Stair widths are approximately 3’-8” with an exit capacity of 140 (.3” per person) for each stair. Separation of
Site & Context
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
11
6.25.05 mms
hm
ms
h
Site & Context stairs is approximately 1/3 the diagonal distance of the building which will require that the building be sprinkled in any reuse configuration. Floor to floor heights are relatively shallow ranging from 14’ on the first floor to 11’6” for upper floors. The aluminum curtainwall components are no longer made and air infiltration is evident. Several asbestos containing materials have been identified in acoustic plaster ceilings and piping that will be abated prior to renovation.
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
19
6.25.05 mms
hm
ms
h
Site Utilities
summer winds
winter winds
N
S
EW
June 22 sun path
December 22sun path
60°
120°
33º North LatitudeSun Path diagram
N
S
EW
June 22 sun path
December 22sun path
60°
120°
33º North LatitudeSun Path diagram
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
20
6.25.05 mms
hm
ms
h
Program Summary Department Net Area (s.f.) Department
Efficiency (%) Department Total (s.f.)
Connecting Efficiency (%)
Total Area (s.f.)
Community Renewal Training Center 119,910 80 149,000
Community Renewal Resource Center 17,850 75 23,800
Community Renewal Institute 4,740 75 6,300
Administration 2,855 80 3,570
Common Areas 15,020 75 20,000
Mechanical / Electrical Spaces 11,000 11,000
Totals 213,670 85 251,000
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
21
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
General Building Considerations 1. The National Center for Community Renewal will be composed of 3 components: The Community Renewal Training Center, The Community Renewal
Institute and The Community Renewal Resource Center. 2. Reinforce the concepts of “renewal” and “community" in the building design. Symbolism should reflect ideals such as “Inclusion, Community, Neighborliness,
World Community and Togetherness” . 3. The building ground floor should function as a welcome center and registration area. It should also provide activities that enhance the downtown
neighborhood such as storefront shops (coffee shop, food court and other retail for downtown) and possibly a “Community Renewal Museum with exhibits that document the growth and success of the Renewal Movement.
4. Classes at the National Center will be revenue generating to cover some of operations. 5. One suggestion was offered that the National Center could be like a “Friendship House” that includes downtown human resources for teaching low income in
the downtown area as a demonstration of community building by the National Center. This concept would have full time residents to resemble a Friendship House—possibly one role as facility manager and one role for downtown neighborhood coordinator.
Community Renewal Training Center 1. The Community Renewal Training Center is a conference center that includes housing and meeting / training rooms. 2. Learning will occur in large groups of up to 300 for “information sharing” such as orientation and in small groups of 7 to 20 (15 is ideal) for “interaction
learning”. 3. One concept discussed is small groups symbolized as neighborhoods with small group participants residing in a cluster of bedrooms around a common area
for social and learning gatherings. This could become a co-op type environment where participants share responsibilities (some examples mentioned that are similar include new dorm concepts & senior centers). Questions discussed included: Will internet access in bedrooms limit interaction? Will we include provisions for children? Should some double rooms (2 beds) be included to allow for cultural considerations or choice?
4. Large group meetings could symbolize the gathering of many neighborhoods to share ideas, resources and work. Consider the possibility of moveable walls to subdivide larger meeting rooms to allow experimenting with group size and learning.
5. Training will take place in sessions from as few as 3 days to as long as 6 weeks. Learning activities will take place in The Center and out in area neighborhoods that are the laboratory for Community Renewal. A summary of the renewal process is included in the Project Goals and Overview section of the program. Staff is developing the training programs and considering issues such as: How do we create learning programs and environments that maximize benefit to various learning styles? How will we build community in 3 days? How much interaction time and how much quiet time for individual reflection?
6. Learning activities should include behavior pattern development that occurs during meals and community meetings that are scheduled in a disciplined process. (could include gatherings after normal hours?)
7. Ancillary spaces for residential areas include: laundry room, exercise room, small place for reflection or worship (could be a chapel, place on each floor or individual bedrooms)
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
22
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Training Center (continued) Reception & Lobby Inviting space with informal seating areas for
approximately 30. Access to elevators and registration desk. Consider 2 story spaces to connect to functions on 2nd
and possibly 3rd floors Connection to ground floor storefront retail and museum
from lobby Counter area for refreshments for guests
2,000
Registration Desk & Information / Transportation Center
Counter space for approximately 4 employees to handle registration, issuing and receiving keys, holding messages / mail, etc. (Could be located at 2nd floor)
Space for cueing guests for registration Information display and interactive computer access
(could be kiosk in lobby)
250
Storage Storage area for holding luggage, carts, etc. 120
Housing Manager Office Desk, credenza, 2 side chairs, shelving and lateral file Near registration desk
150
Work/ Copy & Files Supply for storage for administration Copy machine, fax, postage, computer and printer
150
Offices Additional staff offices 2 120 240
Community Renewal Museum, Gift Shop & Welcome Center
Display area / exhibits of the Community Renewal message and progress and locations. (1000 s.f.)
Museum receiving, exhibit prep, curator office and storage (1,500 s.f.) could be in basement.
Gift Shop of tapes, books, shirts etc. (500 s.f.) Gift shop storage could be in basement (500 s.f.) Welcome Center area for orientation to the National
Center & Community Renewal principles—audiovisual presentation room (500 s.f.)
4,000
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
23
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Training Center (continued) Common Area Rooms Common areas will be used for social gatherings &
training sessions for the participants housed in a bedroom cluster
One room in each cluster of bedrooms Conference / dining table(s) for ± 14 Kitchenette unit with microwave, coffee, double sink, ice
maker and refrigerator TV / lounge seating area Computer area with 5 computers with internet access Window view if possible Laundry room with 2 washers and 2 dryers (100 s.f.)
20 800 16,000
Bedroom Clusters Bedrooms will also serve as places for personal reflection of dailey activities
± 14 bedrooms with queen size beds (250 s.f. each) Rooms to be small to encourage time in the common
area and nicely appointed with simple elegance. Furnishings should include a desk , small refrigerator
unit, chair, clothes storage in furniture unit and bed tables.
Bathroom with tub / shower, water closet and lavatory for each bedroom (50 s.f.)
20 3,920 (14 bedrms. @ 280 s.f.
each)
78,400
Exercise Room 3 tread mills, 3 stationary bicycles, 3 weight machines Floor area for stretching or aerobics with mirror 2 Toilet and dressing rooms with showers (400 s.f. each).
Include 10 lockers in each. One location for all residents
2,100
Chapel Small inspirational worship space Accessible to all facility users and guests Accommodate approximately 20 Incorporate art, special lighting and possibly water
400
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
24
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Training Center (continued) Auditorium / Meeting Room
Flat floor flexible gathering place for 300 in a dining configuration
Small raised platform for speakers or panel Great audio visual & video equipment capability Consider moveable wall to subdivide into 2 or 3 spaces
5,600
Small Group Rooms Break out rooms for smaller group training sessions Rooms of up to 30 people Liquid marker boards and possibly smart boards with
LCD projectors
10 500 5,000
Training Center Lobby Space for refreshment tables and seminar registration tables
Gathering space during seminar breaks
300 7 2100
General Storage & Staging Storage room for chairs and tables (400 s.f.) Staging area for serving meals (400 s.f.)
800
Warming Kitchen Meals will be catered for banquets Warming Kitchen should be located near loading dock
service areas and acoustically separated from seminar / banquet areas
Kitchen should include a small walk-in cooler and freezer; a storage area for dishes and condiments; warmers and coolers; ice maker; ovens; sinks and other equipment to be determined
500
119,910 80 149,000 Community Renewal Training Center
Toilets Locate near Training Center Lobby 2 300 600
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
25
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Resource Center 1. The Resource Center will provide “technical” & “foundation” support to individuals & groups involved in developing social technology to renew
communities. This support will include building a community of people renewing communities. 2. Technical support will include a staff of specialists that form “technical support teams” that specialize in: general knowledge of renewal, volunteer
recruitment, Community Coordinators, Haven Houses, Renewal Teams & CEO development. Over a ten year period these specialist areas will grow to 5 staff for each area of specialty. Some of these staff will travel to communities to provide on site assistance. Tech Teams will convene monthly virtual town hall meetings to share progress as a means of developing a support system for community renewers across the country. This will require a media department with a small television studio for recording & broadcast. The work of Technical Support will be supported by Renewal Publishing Company that will be housed in the Community Renewal Resource Center Media Department.
3. The Community Renewal Foundation will offer memberships nationwide thru the internet. The foundation will make seed grants of approximately $50,000 per year per group to get started. A portion of foundation funds will go to SBCR to support development work as the laboratory organization. Staffing for the foundation will include a director, assistant with conference room and support areas.
4. The Resource Center will also include a Library, Technology Department and Media Department. 5.
Technical Support Team Directors
One enclosed office for each of the six specialists categories mentioned above
Desk, Credenza and 2 side chairs
6 150 900
Toilets 2 250 500
Copy, Files & Supplies Work Counter, copier, mail & postage, lateral files 300
Technical Support Team Work Stations
Four open office cubicles for each of the six specialists categories (approximately 90 s.f. per work station
Evaluate a hoteling office concept for shared work stations to gain space efficiency
24 112.5 2700
Conference Rooms Accommodate 6 around a table White board on one wall and
6 200 1200
Clerical work stations Open office cubicles for secretarial & interns (60 s.f. per work station)
12 75 900
Department Reception & Waiting
Seating for 6 adjacent to Clerical area 150
Coffee Bar Counter area with sink, under counter refrigerator 80
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
26
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Resource Center (continued) Foundation Director Office Desk, credenza & 3 side chairs 200
Foundation Assistant Office with desk, credenza & side chair 120
Foundation Secretary / Reception
Secretarial work station Waiting for 4
200
Foundation Work / File Room
Work Counter, copier, lateral files 250
Foundation Conference Room
Accommodate 12 around table AVV capability
350
Library Book stack area for ? Volumes Reading area for 20 Circulation desk 5 computer stations 2 project rooms Librarian work area and storage Archive storage display
5,000
Technology Department Closed circuit production Access to satellite feed T-3 connections / fiber throughout / wireless hubs Web site design and updates
2,000
Media Department Video tape, filming & broadcast capability Video editing room (250 s.f.) Small television studio (500 s.f.) Renewal Publishing Company (500 s.f.)
3,000
17,850 75 23,800 Community Renewal Resource Center
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
27
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Community Renewal Institute 1. The Institute will develop state-of-the-art thinking for Community Renewal. The Institute will work with academic and institutional partners on research
projects such as conceptual models, methodologies, research techniques and information tracking. The analogy for the institute is the “Manhattan Project” as a model for how to bring together brainpower to design solutions to a complex problem.
2. The Institute will operate a “Think Tank” and will periodically assemble “thinkers” that understand principles that lead to renewal. Topics for think tank sessions could include diagnostics and solutions that affect change.
3. The Institute will produce and distribute “white papers” and a journal. Much of the research will be contracted with academic researchers. 4. The staff will plan and conduct conferences with targeted small groups.
Director Office Desk , credenza and 2 side chairs 200
Staff Researcher Office Researchers and conference planners Desk , credenza and 2 side chairs
3 180 540
Secretarial / Reception Secretarial work station and waiting for 6
Large Conference Room State of the art conferencing room for 20 with small kitchen and break out room for 4 people
Room should be designed to accommodate intense brainstorming activities by thinkers invited to explore and develop specific issues.
2,000
Small Conference Room Staff conference & work room 300
File & Work Room Work counter, files , copier 200
Expansion Space Space allowance for additional growth and intern work areas
1,500
4,740 75 6,300 Community Renewal Institute
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
28
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Administration 1. The administrative department will house the National Center CEO and support staff for managing the National Center. It will also house the staff that
oversees the local model SBCR that includes trainers and 4 community coordinators. Directors offices will include building manager, training, Marketing & Development.
CEO Office 280
Administrative Assistant 120
Reception / Waiting Secretarial Work Station Waiting for 8
200
Files, Work & Storage 150
Building Director Office 180
Training Director Office 180
Marketing / Development Office
180
Support Staff Work Stations
Cubicle work stations for additional staff and interns (70 s.f. per work station)
6 87.5 525
Conference / Board Room 500
Conference Room 300
Small Kitchen Area 80
Toilets 2 80 160
2,855 80 3,570 Administration
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
29
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Common Areas Outdoor / Indoor Plaza Connecting entry area that links Training Center,
Resource Center, Institute and retail tenant spaces This could be an atrium type space with stairs and
elevators serving the existing tower if existing stairs and elevators are abandoned due to code related issues.
Welcoming space from street / sidewalk This concept will require acquisition of adjacent 2 story
building(s) and surface parking Provide variety of indoor and outdoor seating
arrangements and landscaping
4,000
Retail Lease Areas Locate on Ground Floor with entries from sidewalks and from building lobby areas.
4 to 6 spaces at approximately 1200 s.f. average
6 1,200 7,200
Loading Dock Provide loading dock area for 2 delivery vehicles from alley that will not block the alley
Locate a trash compactor / dumpster at the dock area
2,500
Receiving Area Area for uncrating and temporary storage Accessible to serve the entire complex
400
Building Security Office to monitor cameras and facility 120
Facility Maintenance Office space & shop for maintenance engineer and support
400
Janitorial and Central Supplies
A laundry service will be used for cleaning linens etc for the housing and food service operations
Storage of cleaning supplies, linens etc.
400
15,020 75 20,000 Common Areas
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
30
6.25.05 mms
hm
ms
h
Program Spaces Space Space Description Quantity Area /
Space (s.f.) Net Area (s.f.)
Efficiency (%)
Total Area (s.f.)
Mechanical / Electrical Spaces 1. Refer to section on mechanical and electrical design requirements.
Mechanical Equipment Allow 5% of sum of net department area Based on 202,000 net s.f.
10,000
Electrical and Communications
Allow .5% of sum of net department area Based on 202,000 net s.f.
1,000
Mechanical / Electrical Spaces 11,000 11,000
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
38
6.25.05 mms
hm
ms
h
Code Category N.F.P.A.. 101 (2003 Edition) International Building Code (2000 Edition)
General Building Description: Approximately 144,000 s.f.; Existing 16 floor high rise (basement, 14 tenant floors & mechanical penthouse) ; original use as multi-tenant office building Proposed use: Renovate as a mixed use conference center with hotel type housing for participants, assembly areas for approximately 300, limited retail and
offices for administration / resource center Where discrepancies in the codes occur the NFPA 101 shall be used. Louisiana law
Occupancy Classification :
High Rise (chapter 11, section 11.8) Multiple occupancy separates uses with fire rated construction
(6.14.2.3 & table 6.1.14.4.1); or Mixed occupancies intermingle uses w/ more stringent requirements (6.1.14.3)
Business (chapter 38), Assembly (chapter 12) and Residential / Hotel (chapter 28)
Mixed use (each portion of the building classified based on occupancy): Group R-1 hotel, Group B business, Group A-2,3 Assembly
Occupancy separations of 2 hours per table 302.3.3 can be reduced 1 hour in sprinkled buildings
Construction Type : Type I (332) Note: a less stringent classification could be used if additional property is acquired for some uses by separating the high rise with rated construction. (table A.8.2.1.2)
Columns: 3 hours Beams, girders, trusses & arches: 3 hours Floors: 2 hours Roof: 1 1/2 hours
Type 1A sprinkled (table 601) note: if site area expanded use of less stringent construction could be considered for solutions under 4 stories by separating the high rise with 2 hour construction.
Structural frame (columns / trusses / girders) : 3 hours Floor construction (includes beams & joists) : 2 hours Roof construction : 1.5 hours except no rating when roof 20’
above floor below.
Allowable Height & Area UL stories, UL height (table 503) Multi-story maximum = UL s.f./ floor
Occupant Load (s.f./ occupant)
Hotel: 200 s.f. / person; Classrooms: 20 net; library reading: 50 net; assembly: 7 net for concentrated without fixed seats, 15 net less concentrated without fixed seats, actual number of fixed seats; kitchens, library stacks & offices: 100 (table 7.3.1.2)
Classrooms: 20 net; Assembly: 7 net for chair only, 5 for standing, 15 for tables & chairs, and actual number for fixed seating; library: reading areas 50 net and stacks 100 gross
Residential: 200 s.f. / occupant; exercise: 50 net s.f. / occupant Office areas: 100 s.f. gross / occupant
Exit Capacity .2” / person for doors and aisles .3” / person for stairs Minimum door width = 36” (32” clear) Street floor exits shall be calculated on the area of all floors
connected by openings (e.g. stairs or escalators) (38.2.3.3)
.2” / person or .15” with sprinkler .3” / person for stairs or .2” with sprinkler Minimum door width = 36” ( 34” clear)
Code Summary Provisions
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
39
6.25.05 mms
hm
ms
h
Code Category N.F.P.A.. 101 (2003 Edition) International Building Code (2000 Edition)
Exit Access Corridors Business occupancy: 1 hour rating except no rating is required in (1) open plan configurations, (2) single tenant spaces and (3) buildings protected by automatic sprinkler (38.3.6)
Minimum width of 44” (38.2.3.2) Hotel: When sprinkled, 1/2 hour rating in hotel areas w/ 20
minute self-closing doors (28.3.6). Spaces can be open to the corridor provided they are not hazardous and do not obstruct access.
1 hour rated; No rating when sprinkled (table 1004.3.2.1)
Number of exits 2 Minimum (38.2.4.1) Exits located no closer than 1/2 diagonal distance of room or
building, 1/3 diagonal distance for sprinkled buildings. (7.5.1.3.2—.4)
2 Minimum for 1-500(1 for spaces with less than 50 occupants) 3 for 501-1,000 and 4 for over 1,000 Exterior stairs permitted (1005.3.6.5)
Dead End Limit 35’ increased to 50’ when sprinkled (28.2.5.6) 20’ (1004.3.2.3)
Common Path of Travel 35’ increased to 50’ when sprinkled measured from the door to the hotel room (28.2.5.4)
Office: 75’, 100’ when sprinkled (38.2.5.3.2)
75’ (1004.2.5)
Exit Stairs & Shaft Enclosures & exit passageways
2 hour separation for high rise 48” minimum clear between handrails per 7.2.12.2.3 where
stairwell used as area of refuge
Shaft enclosure of 2 hours when connecting 4 or more floors (707.5) with 1.5 hour opening protection
1/2 of exits can be horizontal exits thru 2 hour walls (1005.3.5)
Travel Distance Office: 200’ increased to 300’ when sprinkled (38.2.6) Travel distance within a hotel room to a corridor shall not
exceed 75’; 125’ in sprinkled building (28.2.6.2) Travel distance from the corridor door of a hotel room in a
sprinkled building to the nearest exit shall not exceed 200’ (28.2.6.3.3.1)
200’ (250’ for R & A, 300’ for B when sprinkled) table 1004.2.4 1/2 diagonal distance (1/3 when sprinkled) from rooms with 2
exits (1004.2.2)
Exit discharge 50 % of exits may discharge through a lobby to reach the outside of the building provided the travel distance does not exceed 100’ from the exit enclosure. Open stairs can be part of the exit access path per section 7.6.2. (28.2.7)
Code Summary Provisions
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
40
6.25.05 mms
hm
ms
h
Code Category N.F.P.A.. 101 (2003 Edition) International Building Code (2000 Edition)
Elevators & Escalators Comply with the provisions of section 9.4. Elevators shall be available for fire department use. Under some circumstances elevators may be used as a means of egress. (28.5.3)
If less than 4 elevators, no more than 2 elevators per shaft. If more than 4 elevators, no more than 4 elevators per shaft.
Exit Signs Not required at main exterior exit doors (7.10.1.2) Not required at main entries obvious as exits or in rooms with one exit (1003.2.10.1 exceptions 1& 2)
Protection from Hazards One hour or sprinkler protection for: employee locker rooms, retail shops, guest laundries 100 s.f. and storage rooms
1 hour & sprinkler for laundries 100s.f., boiler & fuel fired heater rooms, maintenance shops, trash rooms and rooms for combustibles (table 28.3.22.2)
Furnace rooms over 400,000 Btuh, boilers over 15 psi, and refrigerant rms.—1 hour separation or sprinkler (table 302.1.1)
Hazard Classification Ordinary Hazard operations
Compartmentation & Tenant Separation
1 hour smoke partitions required to separate areas exceeding 30,000 s.f. or dimensions exceeding 300’ (?.4)
Floors serve as smoke barriers in type II(000) const. Horizontal exits permitted per 7.2.4 Hotel rooms separated by 1/2 hour rated walls in sprinkled
building (283.7)
Tenant separations within the same occupancy require no separation
Incidental Use areas such as laundry rooms over 100 s.f. and storage over 100 s.f. require 1 hour separation or sprinkler protection (table 302.1.1)
Assembly areas ≤ 10% area are not separate occupancies (table 302.3.3.e)
Atrium / Vertical Opening When connecting up to 3 floors as a communicating space for egress use the provisions of 8.6.6 and the building shall be fully sprinkled (28.3.1.1.1)
2 adjacent stories can be connected when not used as a required means of egress using the convenience openings provisions of 8.6.8
Laundry & rubbish chutes per section 9.5
Sprinkler protection required for entire building except atrium ceiling above 55’
Shaft enclosure is not required when connecting 2 stories when criteria of section 707.2 are followed
One half of the exit stairways can be unenclosed when serving one adjacent floor (1005.3.2 exception 8)
Interior finish Wall & Ceiling: Class A in exits, Class A , B or C in other areas
Artwork wall coverage: 20% max, 50% for sprinkled (?.7.4)
Exits– class A; exit access corridors—class B; rooms—class C Sprinkler reduces finishes to classes B,C,C for above list
Code Summary Provisions
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
41
6.25.05 mms
hm
ms
h
Code Category N.F.P.A.. 101 (2003 Edition) International Building Code (2000 Edition)
Extinguishing Requirements
Automatic sprinklers per section 9.7 & NFPA 13 required for high rise buildings (11.8.1)
Class I standpipes required for high rise (11.8.2.1) Portable fire extinguishers per NFPA 10 Buildings with assembly occupancies greater than 300 shall
be sprinkled (12.3.5) Quick response / residential sprinklers used in guest rooms
(28.3.5.5)
Required for each fire area exceeding 20,000 s.f. & areas below level of exit discharge (903.2)
Auditorium with fixed seating for 300
Type II (000) construction permitted for any assembly at level of exit discharge
Smoke protected assembly seating
Sprinkler protection of seating areas & smoke ventilation of egress areas serving seating (12.4.2). Smoke protection provides for increases in travel distance and increases in capacity for stairs & other means of egress components.
Assembly seating access aisles
Where rows exceed 14 seats with aisles at both ends the aisle access clear width of 12” shall be increased .6” for each additional seat. Minimum aisle width is not required to exceed 22” (12.4.2.5) For single access rows the increase begins at 7 seats
Classroom aisles 30” wide minimum (?.2.5.6)
Windows for rescue 7.5 s.f. clear operable window required up to 3 stories & classrooms greater than 250 s.f. unless fully sprinkled (?.2.11.1)
Detection, Alarms and Communications
Fire Alarm system w/ voice/ alarm communications per 9.6 Emergency power (class 1, type 60) and central control
station for fire department are described in 11.8.4 Automatic initiation with sprinkler (?.3.4.2.2) Notification: Audible and visible per NFPA 72
Required for occupant load ≥ 50 (section 907) Manual fire alarm system connected to sprinkler and smoke
detection. Pull stations not required per 907.2.3 exceptions 2.1 thru 2.6 when all 6 requirements are met ( 1. Smoke detection 2. Heat detection in assembly areas 3. Heat detection in shops & labs 4. Off-premises monitoring 5. Activation from central point 6. Two-way communication)
Code Summary Provisions
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
42
6.25.05 mms
hm
ms
h
Code Category N.F.P.A.. 101 (2003 Edition) International Building Code (2000 Edition)
Emergency Lighting Required per 7.9 Required in spaces with 2 exits and components of egress (1003.2.11.2)
Equipment Access Minimum with for walkway, platform or stair is 22”, riser height up to 9”
Alternating tread stairs acceptable
2 exits are required from boiler rooms over 500 s.f. one of which may be a ladder or alternating tread device
Plumbing fixtures required per Louisiana Plumbing Code
Occupant load = Maximum daily population of Water Closets = ? male, ? female Lavatories = ? male, ? female Urinals = ? male ( can substitute for half of male WC’s) Drinking fountains = 1 pair / floor minimum Showers =
Zoning Classification B-4 Central Business District The zoning ordinances can be viewed at the MPC web site http://www.ci.shreveport.la.us/Code/Ords/CH106%20-%20Chapter%
20106%20%20ZONING.htm
Parking No parking required for uses in the B-4 classification. If parking is provided it must meet the requirements for the various uses prescribed in the zoning code: Hotel– 1 space per room, assembly— 1 space per 3 seats, office— 1 space per 200 s.f. with reductions applied when over certain area thresholds.
Parking can be developed on a demand basis and submitted to the MPC for approval.
Accessible Parking 5 accessible spaces required for 101-150 spaces One of the required accessible shall be van accessible for
every 8 accessible spaces
Raised or Roof mounted equipment
Clearance requirements when roofing extends beneath equipment ranges from 14” to 48” depending on size in table
Code Summary Provisions
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
43
6.25.05 mms
hm
ms
h
Activities:
Equipment:
Number of people:Hours of operation:Important adjacencies:Description of tasks / activities:
Equipment name: size: utility requirements: description:
Furnishings: (size & description)Desks:Tables:Chairs:
Lab casework:File Cabinet:Other:
Environmental Issues:Temperature Requirements:Lighting requirements:Exhaust requirements:Other:
Sinks:Deionized water:Compressed air:Vacuum:Power requirements:
Gas:Internet::Data/ Communications:Emergency Power:Other:
Utilities:
Activities:
Equipment:
Number of people:Hours of operation:Important adjacencies:Description of tasks / activities:
Equipment name: size: utility requirements: description:
Furnishings: (size & description)Desks:Tables:Chairs:
Lab casework:File Cabinet:Other:
Environmental Issues:Temperature Requirements:Lighting requirements:Exhaust requirements:Other:
Sinks:Deionized water:Compressed air:Vacuum:Power requirements:
Gas:Internet::Data/ Communications:Emergency Power:Other:
Utilities:
Classrooms
Room Worksheets
Center for Community Renewal Facility Design Program
Center for Community Renewal - Design Program Morgan Hill Sutton & Mitchell Architects LLC
46
6.25.05 mms
hm
ms
h
Room Worksheets