UBCAP introduction and work progress

Stove testing process and outcome

Page 3: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

3

3

Government of Mongolia, Municipality of UB

city, World Bank, Clean Air Fund.

TO FACILITATE

DEVELOPMENT OF A

SECOND

GENERATION OF

INVESTMENT

TO ACHIEVE GOOD PERFORMANCE IN A

SHORT PERIOD

TO FILL ABATEMENT

PROGRAM GAPS

Page 4: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Ulaanbaatar Clean Air Project

Component 2

Central Ulaanbaatar

particulate matter

mitigation

Component 3

Public awareness

raising. Program

coordination and

project management.

Component 1

Ger area particulate

matter mitigation

Page 5: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Ger area particulate matter mitigation

• Less 2.5 µmPM2.5

• 2.5-10 µm

PM10

Page 6: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Stove replacement program

Market study of water heating small stove,

standard and technical advice

Page 7: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Central Ulaanbaatar particulate matter mitigation

Mitigation of

fugitive dust

from lack of

city greening

PP emission

and ash pond Affordable housing

policy technical

assistance

District heating

feasibility study and

knowledge building

Page 8: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Public awareness raising – Coordination – Training –

Monitoring

Project coordination

Testing equipment training

Information dissemination program

Project monitoring and evaluation

Page 9: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

◦ MUB

◦ National Committee on Air Pollution Reduction

◦ Clean Air Fund

◦ Ministry of Energy –Department of strategy and policy

planning

◦ Air Quality Agency (MUB)

◦ Scientific and research organizations – MUST

◦ National stove producers

◦ Media

◦ Other programs - MCA, JICA, ADB, EBRD

Page 10: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

To

2017

from

2013

Page 11: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

UBCAP OUTCOMES

Main output

• Ger area stove emission will be reduced ;

• To be prepared air pollution reduction long and medium-term

investment plan, feasibility study and strategy document;

• To be improved coordination and correspondence between

Ulaanbaatar city air pollution reduction programs;

Page 12: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

UBCAP present activities

PP emission and ash pond

feasibility studyAffordable housing

policy feasibility

study

District heating feasibility study

and knowledge building

City greening feasibility

study

Public awareness raising

program EE stove program

Page 13: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

Stove testing process in laboratory

The stove testing laboratory was operationalized on May 2013. There

was tested 15 type of stoves in 10 manufacturers and 4 type of stoves was

selected according to requirement.

Page 14: 18.09.2013, Ulaanbaatar clean air project, Ariuntuya Tserendorj

New stoves in the market

“Selenge

construction” LLC

ULZII stove

“Royal Ocean” LLC

BIG DUL

stove “Elmeco” LLC

ТALST

stove

“Ikh tengeriin khuch”

LLC

BEKAS-107

stove