Training Workshop on Business Process Analysis in International Trade
Joint Workshop on Trade Facilitation and the Single Window23-25 September 2015, Moscow
Module 1: Preliminary stage. Preparation for the BPA.
1.1. Organization and Management of the BPA
Somnuk Keretho, PhDDirector, Institute of IT Innovation
Kasetsart University, Bangkok
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Objectives of this session
To understand the basic concept about “what is a project?” and “how to manage a project?” e.g. basic project management
To understand the overall 3 main phaseson how to conduct a BPA project.
To understand basic roles & responsibilities of those who should involve in the BPA project.
2
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
What is a Project?
Definition of a “Project” (* ISO/DIS 21500:2011 Standard)
A project is a unique set of processes consisting of coordinated and controlled activities with start and finish dates, undertaken to achieve an objective.
Achievement of the project objective requires deliverables conforming to specific requirements, including multiple constrains such as time, cost and resources.
3
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
What do we need to manage in a project?[Basic Project Management]
4
Time
Cost Resources
Requirements StartDate
FinishDate
Deliverables
Tasks
Managing Risks & Issues
Team & StakeholdersCollaboration
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Project Management in general: 4 phases
1. Preliminary (Initiation)
2. Planning (Detailed Design)
3. Implementation 4. Closing
5
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Project Management Example: Electronic Single Window for Swiss Border Control*
* EA PM Course in Cybernetic Approach to Project Management Bangkok 2015. Prof. Dr. Bogdan Lent (2015)
6
BPAis conducted
here.
BPAis needed here.
BPAis needed here.
BPAis needed here.
BPAis needed here.
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
What is a BPA Project?
7
A Business Process Analysis (BPA) is a project to understand, then capture and analyze business processes and their attributes such that improvement recommendations can be provided.
BPA is an important and necessary analysis normally conducted before and during Single Window initiation, planning/design & implementation.
Who involved
Proceduresand Documents
required
Related Rulesand Regulations
Some quantitative
indicators
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Why conducting a BPA Project?(Benefits of BPA)
8
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Three (3) main phases to conduct a BPA Project
1. Defining Scope of and Planning a BPA Project
2. Capturing and Modelling the As-Is Process
3. Analyzing Findings of the BPA andProposing Recommendations for Improvement(Proposing the To-Be Process)
9
Ref: Business Process Analysis Guide to Simplify Trade Procedures, Updated 2012, UNESCAP/UNECE. http://unnext.unescap.org
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
3 Phases (6 steps) & Deliverables of a BPA Project
Step Deliverable
Step 1: Define project scope
Use case diagram illustrating business domain, process areas, process participants, and key business processes
Step 2: Develop a detailed plan and secure resources
Detailed project plan including an estimation of human resources required, schedules, and software supported tools A list of potential interviewees and their contact information
Step 3: Acquire background information
A folder of background information about the business processes under the investigation A list of guiding questions for the interview
Step4: Conduct interview and document captured data
A set of activity diagrams illustrating activities that come in a specific order and decision points, actors who perform those activities, defined inputs and outputs of each activity, criteria for entering and exiting the business process, relationships among actors, and information flow A set of business process descriptions that describes activity diagram and lists all related rules and regulations Activity diagram illustrating integrated processes in the business domain Time-Procedure chart displaying time required to complete each business process
Step 5: Analyze the “as-is” processes and identify bottlenecks
A set of observations of the as-is business processes that have the potential for improvement
Step 6: Develop and propose recommendations
Final report with recommendations which may include diagrams of “to-be” business processes
Phas
e I
Phas
e II
Phas
e III
10
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Several roles & responsibilities are neededfor conducting a BPA project plan.
Project Sponsor (PS): an authorized person(s)/organizations (who has the authority) who can
grant the necessary resources and takes the ownership of the deliverables
of the BPA project, e.g. by escalating it for actual implementation. Project Manager (PM):
A person who is assigned to manage the BPA project, e.g. planning, staffing and controlling this BPA project.
Process Analysts (PA): A person(s) who collects data related to the processes, documents/models
those processes, identify bottlenecks, and propose improvement recommendations.
Domain Experts (DE) - Stakeholder Organizations: Those who are knowledgeable about some specific processes,
documentation requirements, practices and laws/regulations related to the scope of the BPA project – providing information, verify and validate the findings as captured and proposed by PA.
11
BPA
core
team
Sta
keh
old
ers
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 12
Activities for Planning a BPA Project
Project Sponsor
Process Analysts
1.2) Develop a detailedplan and secure
resourcesProject Manager/Project Leader
Objective – To develop a detailed work plan that helps guide and manage the implementation of a BPA project
(WBS – Work Breakdown Structure Approach for planning by breaking the works down into several tasks, and several work products (deliverables).
Project Manager/ Project Leader Project Sponsor
Identify tasks and their sequence
Estimate efforts
ProjectDetailed Plan
Process Analysts
Develop projectschedule
Assign processanalysts
Derive thedetailed plan
Review and provide feedback
Review and provide feedback
Unacceptable
Approve
Acceptable
Unacceptable
Use Case Diagram
Acceptable
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 13
WBS 5 – Administrative/Project Tracking Work-Monthly progress report
WBS 1 – Refine the scope of the project- Develop the detailed plan
Project Start Date
Project End Date
WBS 2– Collect information- Capture & Document
the process
An example: a BPA Project Plan
Month 1 Month 2 Month 4Month 3
WBS 3– Analyze and identify bottlenecks- Provide recommendation for improvement
WBS 4– Wrap-up &
submit the final report
Several iterations of verification & validation
(refinement)
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Identifying BPA Project Tasks Develop a work breakdown
structure for a BPA project A work breakdown structure is
an output-oriented description of project tasks. It typically starts with outputs.
The work components of outputs are then broken down into tasks necessary to achieve them.
14
Ref: Business Process Analysis Guide to Simplify Trade Procedures, Updated 2012, UNESCAP/UNECE. http://unnext.unescap.org
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Identifying BPA Project Tasks
Use the Business Process Analysis Guide to Capture and Simplify Trade Procedures, as an input for identifying BPA tasks for each output Activity 3.1 – 3.3 and Activity 4.1 – 4.7 for the
modeling of activity diagrams describing core business processes represented by use cases in the use case diagram
Activity 4.8 – 4.10 for the development of process description for all activity diagrams
Activity 4.11 – 4.14 for the development of an integrated activity diagram
Activity 4.12 – 4.14 for the development of time-procedure chart
Activity 4.15 – 4.16 for the consolidation and submission of output no. 1 – 4 to project sponsor for perusal
Activity 5.1 – 5.4 for the identification of bottlenecks
Activity 6.1 – 6.4 for the development of recommendations and/or new business processes
15
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 16
Small activities may be grouped into one prior to the estimation of efforts for a BPA project.
The number of key business processes and stakeholders involved in each business process must be taken into account when estimate time required for elaborating them into activity diagrams.
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 17
Use Case Diagram as an Input for Estimating Time Required to Complete Tasks to Product Output 1 and 2
Source: Case Study – Thailand’s Export of Frozen Shrimp
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 18
Estimating Efforts for a BPA Project
* Project Evaluation and Review Technique
Task/Activity(Shrimp Case)
Predecessor Optimistic Time (day)
Most-Likely Time (day)
Pessimistic Time (day)
Estimated Time (day)
A 3.1-3.3 None 5 8 10 7.83
A 4.1-4.2 A 3.1-3.3 2 4 5 3.83
A 4.3 A 3.1-3.3 2 3 5 3.16
A 4.4 A 4.1-4.2, A 4.3 3 5 10 5.5
A 4.5 A 4.4 3 4 10 4.83
A 4.6 A 4.5 5 8 10 7.83
A 4.7 A 4.6 1 1 2 1.16
A 4.8 A 4.7 3 4 10 4.83
A 4.9 A 4.8 5 8 10 7.83
A 4.10 A 4.9 1 1 2 1.16
A 4.11 A 4.10 2 4 5 3.83
A 4.12 A 4.10 1 1 2 1.16
A 4.13 A 4.11, A 4.12 5 8 10 7.83
A 4.14 A 4.11, A 4.12 1 1 2 1.16
A 4.15 A 4.7, A 4.10, A 4.14 1 1 2 1.16
A 4.16 A 4.15 1 1 5 1.66
Task Estimate = Optimistic Time + (4 * Most Likely Time) + Pessimistic Time 6(PERT*)
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 19
Developing Project ScheduleTask/Activity
(Shrimp Case)Predecessor Estimated
Time (day)Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7
M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F
A 3.1-3.3 None 7.83
A 4.1-4.2 A 3.1-3.3 3.83
A 4.3 A 3.1-3.3 3.16
A 4.4 A 4.1-4.2, A 4.3
5.5
A 4.5 A 4.4 4.83
A 4.6 A 4.5 7.83
A 4.7 A 4.6 1.16
A 4.8 A 4.7 4.83
A 4.9 A 4.8 7.83
A 4.10 A 4.9 1.16
A 4.11 A 4.10 3.83
A 4.12 A 4.10 1.16
A 4.13 A 4.11, A 4.12 7.83
A 4.14 A 4.11, A 4.12 1.16
A 4.15 A 4.7, A 4.10, A 4.14
1.16
A 4.16 A 4.15 1.66
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Managing risks
Identifying risks that could make some delay or some damages to the project (anything affecting badly on quality, time, and cost of the project).
Analyzing the possible likelihood of occurrence (1-5) and its negative impact (1-10) for each risk (if that risk occurs).
Mitigating those risks with the high value of likelihood multiplying with its impacts (say, more than 20) --> mitigation actions and plans for those risks should be developed.
20
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD 21
Skills needed for Process Analysts Technology skills: The basic knowledge of UML notations, especially in
use case diagrams and activity diagrams is desirable. Related work experience is complementary.
Business/ organization skills: It is important that the selected process analysts know or have an access to the individuals of the business domain under investigation. It is also very useful if they have knowledge of a particular organization or industry associated with the targeted business domain.
Interpersonal/ communication skills: Process analysts’ ability to effectively communicate and interact with other project members is mostly crucial to project success. They should have the ability to create and sustain reasonably good relationships with project stakeholders and especially Process Participants/Business Domain Experts.
Analytical skills: Process analysts should be able to capture relevant information from verbal expression and written documents, and then formalize them in various types of BPA output.
Training Workshop on Business Process Analysis in International Trade, 23-25 September 2015, Moscow @Somnuk Keretho, PhD
Practical Exercise 1 – Preparation for the BPA Project
Breaking out into small groups by countries, and in each group – please perform the following tasks:
[Suppose that each group is an initial core team to initiate and will actively involve in conducting a BPA project, as part of the Single Window initiative for international trade improvement in the country)
1. Discuss and propose the stakeholders/institutions who should be the authorized sponsor to officially create/endorse the BPA project, and take the ownership of the deliverables/outputs of the BPA project to escalate/push them further for actual implementation/realization.
2. Discuss and propose names/candidates of the BPA core team: Project Sponsor (SM):__________________________________ Project Manager (PM):__________________________________ Process Analysis (PA):__________________________________
3. Identify organizations both governments and business entities which should involve as the stakeholders (and provide/identify domain experts)
4. Identify main stages (phases/steps) for implementing the BPA project.
5. Discuss role of each participant on each stage of the project.
6. (if time permitted) Identify one significant risk in this project and how to mitigate its impact and/or its likelihood of occurrence.