Riverbanks Zoo and Garden Phase II, Seals and Sea Lions

02.08-02.12

2016

RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:

EXHIBIT POOL, VIEWING & HOLDING BUILDINGS

Perspective of the New SSL Exhibit from the Main Entrance Plaza

Perspective of the North End Of the SSL Exhibit

Perspective of the Exhibit from the Stadium Seating

Perspective of the West Entrance to the Viewing Building

Finishes Within the Viewing Building Completed

Flooring Installation Completed for the Viewing Building

West End of the Upper Viewing Deck

South End of the Upper Viewing Deck

Perspective of the Southwest Corner of the Viewing Building

New Hard and Softscape completed behind the Viewing Building

Perspective of the South Entrance to the Viewing Building

Softscape complete between the Holding and Viewing Buildings

Eastern Perspective of the Holding Building

Caging at the Holding Building Completed

Northeastern Perspective of the Holding Building

Constructed Wetlands for the LSS Completed

View of the Holding Building from the Upper Viewing Deck

Final Finishes Around the Exhibit Pool Underway

The Submerged Curing Process for the WetEdge Pool Bottom

Aluminum Ships Ladder Installed at the Shipping Container

View of the Exhibit Pool from the Holding Building Swim Deck

Concrete Apron Above the Underground Tanks Completed

SSL Life Support Systems Completed

SSL Life Support Systems Completed

SSL Life Support Systems Completed

Riverbanks Zoo and Garden Phase III, Pedestrian Bridge

02.08-02.12

2016

RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT

Clearing for the Pedestrian Bridge Phase of the Zoo Completed

Erosion Protection Installation Nearly Completed

One Week Look Ahead With the Rodgers Punch Work nearly

completed; the interiors of the Holding and

Viewing Buildings are ready for the

Architectural, Engineering and Owner

Punch, to begin next week. Mike Nardella

and Ted Maranda to be on site starting

Tuesday of next week. Hard and Softscape

to continue to progress; as the Structural

Steel Support for the Shade System, is

installed next week.

With the Clearing for the Pedestrian Bridge

Phase of the Project completed; Grading

and Proof Rolling may begin next week for

the North Tower side of the Site, while the

Temporary Road begins for the South

Tower side.

YOUR NEW SEAL AND SEA LION EXHIBIT COMING SOON