Riverbanks Zoo and Garden Phase II, Seals and Sea Lions
02.08-02.12
2016
RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:
EXHIBIT POOL, VIEWING & HOLDING BUILDINGS
Perspective of the New SSL Exhibit from the Main Entrance Plaza
Perspective of the North End Of the SSL Exhibit
Perspective of the Exhibit from the Stadium Seating
Perspective of the West Entrance to the Viewing Building
Finishes Within the Viewing Building Completed
Flooring Installation Completed for the Viewing Building
West End of the Upper Viewing Deck
South End of the Upper Viewing Deck
Perspective of the Southwest Corner of the Viewing Building
New Hard and Softscape completed behind the Viewing Building
Perspective of the South Entrance to the Viewing Building
Softscape complete between the Holding and Viewing Buildings
Eastern Perspective of the Holding Building
Caging at the Holding Building Completed
Northeastern Perspective of the Holding Building
Constructed Wetlands for the LSS Completed
View of the Holding Building from the Upper Viewing Deck
Final Finishes Around the Exhibit Pool Underway
The Submerged Curing Process for the WetEdge Pool Bottom
Aluminum Ships Ladder Installed at the Shipping Container
View of the Exhibit Pool from the Holding Building Swim Deck
Concrete Apron Above the Underground Tanks Completed
SSL Life Support Systems Completed
SSL Life Support Systems Completed
SSL Life Support Systems Completed
Riverbanks Zoo and Garden Phase III, Pedestrian Bridge
02.08-02.12
2016
RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT
Clearing for the Pedestrian Bridge Phase of the Zoo Completed
Erosion Protection Installation Nearly Completed
One Week Look Ahead With the Rodgers Punch Work nearly
completed; the interiors of the Holding and
Viewing Buildings are ready for the
Architectural, Engineering and Owner
Punch, to begin next week. Mike Nardella
and Ted Maranda to be on site starting
Tuesday of next week. Hard and Softscape
to continue to progress; as the Structural
Steel Support for the Shade System, is
installed next week.
With the Clearing for the Pedestrian Bridge
Phase of the Project completed; Grading
and Proof Rolling may begin next week for
the North Tower side of the Site, while the
Temporary Road begins for the South
Tower side.