Riverbanks Zoo and Garden Phase II, Seals and Sea Lions 02.08-02.12 2016 RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT: EXHIBIT POOL, VIEWING & HOLDING BUILDINGS

Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Riverbanks Zoo and Garden Phase II, Seals and Sea Lions

02.08-02.12

2016

RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:

EXHIBIT POOL, VIEWING & HOLDING BUILDINGS

Page 2: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the New SSL Exhibit from the Main Entrance Plaza

Page 3: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the North End Of the SSL Exhibit

Page 4: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the Exhibit from the Stadium Seating

Page 5: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the West Entrance to the Viewing Building

Page 6: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Finishes Within the Viewing Building Completed

Page 7: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Flooring Installation Completed for the Viewing Building

Page 8: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

West End of the Upper Viewing Deck

Page 9: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

South End of the Upper Viewing Deck

Page 10: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the Southwest Corner of the Viewing Building

Page 11: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

New Hard and Softscape completed behind the Viewing Building

Page 12: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Perspective of the South Entrance to the Viewing Building

Page 13: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Softscape complete between the Holding and Viewing Buildings

Page 14: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Eastern Perspective of the Holding Building

Page 15: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Caging at the Holding Building Completed

Page 16: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Northeastern Perspective of the Holding Building

Page 17: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Constructed Wetlands for the LSS Completed

Page 18: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

View of the Holding Building from the Upper Viewing Deck

Page 19: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Final Finishes Around the Exhibit Pool Underway

Page 20: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

The Submerged Curing Process for the WetEdge Pool Bottom

Page 21: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Aluminum Ships Ladder Installed at the Shipping Container

Page 22: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

View of the Exhibit Pool from the Holding Building Swim Deck

Page 23: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Concrete Apron Above the Underground Tanks Completed

Page 24: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

SSL Life Support Systems Completed

Page 25: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

SSL Life Support Systems Completed

Page 26: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

SSL Life Support Systems Completed

Page 27: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Riverbanks Zoo and Garden Phase III, Pedestrian Bridge

02.08-02.12

2016

RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT

Page 28: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Clearing for the Pedestrian Bridge Phase of the Zoo Completed

Page 29: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

Erosion Protection Installation Nearly Completed

Page 30: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing

One Week Look Ahead With the Rodgers Punch Work nearly

completed; the interiors of the Holding and

Viewing Buildings are ready for the

Architectural, Engineering and Owner

Punch, to begin next week. Mike Nardella

and Ted Maranda to be on site starting

Tuesday of next week. Hard and Softscape

to continue to progress; as the Structural

Steel Support for the Shade System, is

installed next week.

With the Clearing for the Pedestrian Bridge

Phase of the Project completed; Grading

and Proof Rolling may begin next week for

the North Tower side of the Site, while the

Temporary Road begins for the South

Tower side.

Page 31: Riverbanks Zoo and Garden · 2016. 2. 16. · Hard and Softscape to continue to progress; as the Structural Steel Support for the Shade System, is installed next week. With the Clearing