Pump Centre - BIM Awareness Day

BIM for Consultants

Presenter : Mr Kevin Williamson

Assistant Information Manager TEAM2100

2

Key enabling documents

2007 BS 1192 2007

2011 BIM Working Party Strategy Paper

2012 Gov BIM strategy Paper

2013 PAS 1192-2

2013 CIC BIM Protocol

2014 PAS 1192-3

2014 BS 1192-4

2015 Uniclass 2015

2015 Digital Plan of Works

2015 BS 1192-5

2015 GSL

2015 PLQ’s

2007 BS 1192 2007 (2016)

Pump Centre - BIM Awareness Day

Responding to the Employers Information Request

4

PAS-1192-2:2013

This image is taken from PAS 1192-2:2013

5

A compliant BEP will demonstrate how the requirements outlined in the EIRs will be met.

The content of the BEP covers three main areas:

Technical – details of• Software Platforms• Data Exchange Format• Co-ordinates• Level of Detail• Training

Management – details of• Standards• Roles and Responsibilities• Planning the Work and Data Segregation• Security • Coordination and Clash Detection Process• Collaboration Process• Health and Safety and Construction Design Management• Systems Performance• Compliance Plan• Delivery Strategy for Asset Information

Commercial – details of BIM Model deliverables, timing of data drops and definitions of information purposes• Data drops and project deliverables• Clients Strategic Purpose• Defined BIM/Project Deliverables• BIM-specific competence assessment

6

These images are taken from http://www.cpic.org.uk/

Information on the production of the pre-contract execution plan is given in PAS 1192-2 clause 6.2

7

The client develops the EIRThe supply chain further develops the pre tender BIM Execution Plan to meet the post tender requirements of the EIR

8

Digital Plan of Works (DPoW)

Captures project specific information requirements

At project stages

Integrates project deliverables

The Environment Agency have developed a web based tool to capture what we want, when and the format

These images courtesy of

Pump Centre - BIM Awareness Day

The Role of the Information Manager

10

10

Information ManagerPAS 1192-2: 3.26 information management

tasks and procedures applied to inputting, processing

and generation activities to ensure accuracy andintegrity of information

NOTE 3 On projects led with the CIC BIM Protocol

(2013), a key role is the information manager. The

information manager has a role in facilitating the

management of the federated model and the

production of project outputs. The information

manager is also responsible for managing the

operation, standards and culture of the common data

environment. The information manager is not a

standalone role and is expected to shift from design

team to contractor prior to start on site. Under the BIM

Protocol, a client is obliged to appoint an information

manager at all project stages.

Info

rmat

ion

Man

ager

Documents

Data

Geometric models

11

BIM Execution Plan

• This is a plan which outlines the entire BIM from inception to post-completion

• This is produced at the start of the project and controls all aspects of BIM

• There are various versions of the plan; CH2M use the Penn State BIM Execution Plan

• Within the BEP are:

– Information exchange requirements

– Level of Detail at each information exchange

– Software and hardware requirements

– Defined roles, including Information Manager

Pump Centre - BIM Awareness Day

The Importance of CAD and Model Standards

13

TEAM2100 2D CAD

14

Field Role Classification Presentation Status Description

Reference TEAM2100 - Uniclass 2015 - BS 1192-2007 TEAM2100 - Uniclass 2015

Structure [XX] - [XX_00_00_00] - [X] [X] - [X…]

Each layer name is comprised of five partsfrom four predefined sources

IM-ZZ_10_20_95-PZ-Viewports

TEAM2100 2D CAD

15

TEAM2100 3D models

BS 8541-3:2012 Library objects for architecture, engineering and

construction. Shape and measurement - code of practice

16

Federated models

Benefits include clash detection, improved design coordination / collaboration

It will usually mean a file type such as IFC will need to be output. As this is a common file type that contains all the non geometric data too.

Federated models

Allow all parties involved in the design or supply chain to work on one information model. Referencing only published data via the Common Data Environment.

All files names will be to the project standards

This approach will allow discipline based models. Civil, structural etc.. This will ensure all relevant health & safety, design standards and codes are met.

Also allow the control of sensitive data.

Pump Centre - BIM Awareness Day

Exporting Asset Information

18

19

“Construction Operations Building Information Exchange (COBie) is a non-proprietary data format for the publication of a subset of building information models (BIM) focused on delivering asset data as distinct from geometric information. ”

COBie spreadsheet tabs

COBie FLOOR tab

COBie SPACE tab

COBie cell colordefinitions

20

Practical example – Federated model

21

Practical example – Takeoffs

22

COBie Floor and space information from Revit

23

Project Example – FM System integration

• Assets tagged and full manufacturer data sets available in (or linked to) the model

24

Delivering dataUsing a standardised structure we can deliver better quality data on EA elements aligned to AIMS and further granularity of data specific to TEAM2100.

This is example of our Part A assessments delivered from GIS into the COBie data structure

25

COBie can be used to transfer health & safety data

“Issues” can cover:• Environmental• Functional• Quality• RFI• Safety• And anything else!

Pump Centre - BIM Awareness Day

The supply chain and

the supplier side Common Data Environment

27

Common Data Environment (CDE)Over view

28

29

Practical example –Structural Discipline model

30

Practical example –Architectural Discipline model

31

Practical example –Mechanical (plant) Discipline model

32

Practical example –Mechanical (HVAC) Discipline model

33

Practical example – Federated model

34

Practical example – linkages

35

ProjectWise(doc. / CAD / model

mgnt.)

Civil 3D(model)

Revit(model)

Civil:-site

Building:-architectural-structural-building mech.-building elec.

AutoCAD(2D deliverables including PDFs)

Deliverables:-AutoCAD-NWD, -PDF

Standard EA BIM project

Navisworks (Design Review)

36

Data needs

• To fully realise and maximise the potential of the data model some view on the following are required, working backwards from final handover:

– Asset management information needs

– Construction information needs

– Estimator information needs

– Design information needs

– Inspection information needs

– Other: cost/programme/HSE/quality/contractual etc

• View on that above will maximise the development, use and re-use of information and enrich the quality of information we have

Thank You