Pump Centre - BIM Awareness Day
BIM for Consultants
Presenter : Mr Kevin Williamson
Assistant Information Manager TEAM2100
2
Key enabling documents
2007 BS 1192 2007
2011 BIM Working Party Strategy Paper
2012 Gov BIM strategy Paper
2013 PAS 1192-2
2013 CIC BIM Protocol
2014 PAS 1192-3
2014 BS 1192-4
2015 Uniclass 2015
2015 Digital Plan of Works
2015 BS 1192-5
2015 GSL
2015 PLQ’s
2007 BS 1192 2007 (2016)
Pump Centre - BIM Awareness Day
Responding to the Employers Information Request
4
PAS-1192-2:2013
This image is taken from PAS 1192-2:2013
5
A compliant BEP will demonstrate how the requirements outlined in the EIRs will be met.
The content of the BEP covers three main areas:
Technical – details of• Software Platforms• Data Exchange Format• Co-ordinates• Level of Detail• Training
Management – details of• Standards• Roles and Responsibilities• Planning the Work and Data Segregation• Security • Coordination and Clash Detection Process• Collaboration Process• Health and Safety and Construction Design Management• Systems Performance• Compliance Plan• Delivery Strategy for Asset Information
Commercial – details of BIM Model deliverables, timing of data drops and definitions of information purposes• Data drops and project deliverables• Clients Strategic Purpose• Defined BIM/Project Deliverables• BIM-specific competence assessment
6
These images are taken from http://www.cpic.org.uk/
Information on the production of the pre-contract execution plan is given in PAS 1192-2 clause 6.2
7
The client develops the EIRThe supply chain further develops the pre tender BIM Execution Plan to meet the post tender requirements of the EIR
8
Digital Plan of Works (DPoW)
Captures project specific information requirements
At project stages
Integrates project deliverables
The Environment Agency have developed a web based tool to capture what we want, when and the format
These images courtesy of
Pump Centre - BIM Awareness Day
The Role of the Information Manager
10
10
Information ManagerPAS 1192-2: 3.26 information management
tasks and procedures applied to inputting, processing
and generation activities to ensure accuracy andintegrity of information
NOTE 3 On projects led with the CIC BIM Protocol
(2013), a key role is the information manager. The
information manager has a role in facilitating the
management of the federated model and the
production of project outputs. The information
manager is also responsible for managing the
operation, standards and culture of the common data
environment. The information manager is not a
standalone role and is expected to shift from design
team to contractor prior to start on site. Under the BIM
Protocol, a client is obliged to appoint an information
manager at all project stages.
Info
rmat
ion
Man
ager
Documents
Data
Geometric models
11
BIM Execution Plan
• This is a plan which outlines the entire BIM from inception to post-completion
• This is produced at the start of the project and controls all aspects of BIM
• There are various versions of the plan; CH2M use the Penn State BIM Execution Plan
• Within the BEP are:
– Information exchange requirements
– Level of Detail at each information exchange
– Software and hardware requirements
– Defined roles, including Information Manager
Pump Centre - BIM Awareness Day
The Importance of CAD and Model Standards
13
TEAM2100 2D CAD
14
Field Role Classification Presentation Status Description
Reference TEAM2100 - Uniclass 2015 - BS 1192-2007 TEAM2100 - Uniclass 2015
Structure [XX] - [XX_00_00_00] - [X] [X] - [X…]
Each layer name is comprised of five partsfrom four predefined sources
IM-ZZ_10_20_95-PZ-Viewports
TEAM2100 2D CAD
15
TEAM2100 3D models
BS 8541-3:2012 Library objects for architecture, engineering and
construction. Shape and measurement - code of practice
16
Federated models
Benefits include clash detection, improved design coordination / collaboration
It will usually mean a file type such as IFC will need to be output. As this is a common file type that contains all the non geometric data too.
Federated models
Allow all parties involved in the design or supply chain to work on one information model. Referencing only published data via the Common Data Environment.
All files names will be to the project standards
This approach will allow discipline based models. Civil, structural etc.. This will ensure all relevant health & safety, design standards and codes are met.
Also allow the control of sensitive data.
Pump Centre - BIM Awareness Day
Exporting Asset Information
18
19
“Construction Operations Building Information Exchange (COBie) is a non-proprietary data format for the publication of a subset of building information models (BIM) focused on delivering asset data as distinct from geometric information. ”
COBie spreadsheet tabs
COBie FLOOR tab
COBie SPACE tab
COBie cell colordefinitions
20
Practical example – Federated model
21
Practical example – Takeoffs
22
COBie Floor and space information from Revit
23
Project Example – FM System integration
• Assets tagged and full manufacturer data sets available in (or linked to) the model
24
Delivering dataUsing a standardised structure we can deliver better quality data on EA elements aligned to AIMS and further granularity of data specific to TEAM2100.
This is example of our Part A assessments delivered from GIS into the COBie data structure
25
COBie can be used to transfer health & safety data
“Issues” can cover:• Environmental• Functional• Quality• RFI• Safety• And anything else!
Pump Centre - BIM Awareness Day
The supply chain and
the supplier side Common Data Environment
27
Common Data Environment (CDE)Over view
28
29
Practical example –Structural Discipline model
30
Practical example –Architectural Discipline model
31
Practical example –Mechanical (plant) Discipline model
32
Practical example –Mechanical (HVAC) Discipline model
33
Practical example – Federated model
34
Practical example – linkages
35
ProjectWise(doc. / CAD / model
mgnt.)
Civil 3D(model)
Revit(model)
Civil:-site
Building:-architectural-structural-building mech.-building elec.
AutoCAD(2D deliverables including PDFs)
Deliverables:-AutoCAD-NWD, -PDF
Standard EA BIM project
Navisworks (Design Review)
36
Data needs
• To fully realise and maximise the potential of the data model some view on the following are required, working backwards from final handover:
– Asset management information needs
– Construction information needs
– Estimator information needs
– Design information needs
– Inspection information needs
– Other: cost/programme/HSE/quality/contractual etc
• View on that above will maximise the development, use and re-use of information and enrich the quality of information we have
Thank You