Projects
under
JnNURM Scheme
• Construction of traffic transit management centres
• Procurement of buses
Procurement of buses under JnNURM
Procurement of buses under JnNURMDetails of Funding – GoI, GoK and BMTC
3
ParticularsTotal
GrantsGoI share
(35%)GoK share
(15%)BMTC share
(50%)
Purchase of 1000 buses 303.07 106.07 45.46 151.53
Total No. of buses approved
No. of buses
received
Approved cost(Rs. in crore)
GoI share (35%) (Rs. in crore)
GoK share (15%) (Rs. in crore)
Released Amount
(Rs. in crore)
Balance Amount (Rs.
in crore)
GoI GoK GoI GoK
1000 1000 303.07 106.07 45.46 83.33 35.71 22.74 9.75
(Amount in Rs.Crores)
(Amount in Rs.Crores)
• Construction of 10 Traffic and Transit Management centers was taken up. 9 out of 10 TTMC’s have been
commissioned and 10th TTMC will be commissioned shortly .
Traffic and Transit Management Centres (TTMCs) Under JNNURM Scheme
BMTC is the first urban transport organization to get JNNURM funding for a national pilot project for an
innovative idea called TTMC
To meet some of the objectives of the national urban transport policy. To Provide an integrated transportation facility with adequate facilities and
amenities to cater to the requirements of all user groups. To minimize/ reduce congestion on main road through efficient traffic
movement. Smooth flow of all types of traffic to and from the terminal such that there is
no congestion/disturbance caused to traffic along the main road. Minimum /no conflict between various traffic types-Passengers, buses and
private vehicles and to achieve minimum passenger and vehicle processing time.
To encourage use of public transport and provide first-mile connectivity through provision of park and ride facilities in the proposed bus terminal.
Concept of TTMC
Facilities at T T M Cs Bus terminal
• Bus bays• Platforms• Seating & lighting• Public conveniences• Information systems• Safety and security
Bus maintenance depot• Maintenance bays, • washing platform• Bus parking• Services and Utilities• Fuel filling station• Amenities for crew
Passenger amenities• Bangalore One centers• Other citizen amenity
centers• ATMs• Daily needs shopping
Park and Ride facilities
• Park and Ride Facilities
Traffic and Transit Management Centre
– First and last mile connectivity
– Aim to provide at least 500 4W and 2W
parking space
– Integrated with main bus terminal building
JNNURM PROJECT FINANCIAL SHARING DETAILS
Sl No Name of Project Sanctioned Cost at CSMC Delhi
Project Cost as awarded to Contractor
Share of GOI & GOK
Share of BMTC
1 Shanthinagar 8468.00 10722.00 4234.00 6488.002 Koramangala 5058.00 7065.00 2529.00 4536.003 Whitefield 2656.00 3710.00 1327.00 2383.004 Vijaynagar 3812.00 5332.00 1906.00 3426.005 Kengeri 2113.00 2956.00 1057.00 1899.006 Banashankari 2224.00 3111.00 1112.00 1999.007 Yeshwanthpur 6132.00 7950.00 3066.00 4884.008 Jayanagar 890.00 1290.00 445.00 845.009 Domlur 1750.00 2200.00 875.00 1325.0010 Bannerghatta 500.00 600.00 250.00 350.00
Total (In Lakhs) 33603.00 44936.00 16801.00 28135.00
JNNURM PROJECT FINANCIAL SHARING DETAILSRs in Lakh
JNNURM PROJECT –Progress Review
Sl No
Name of TTMC
Approved Cost (Rs. in
crores)
Ampount spent (Rs. In crores)
% Achievement
Targetted date of
completionTarget Action
taken
1 Shantinagar 107.22 34.10 34.10 100 Jul-2010
2 ITPL Whitefield 37.10 9.40 8.00 85 Jul-2010
3 Koramanagala 70.65 19.15 19.00 99 Jul-2010
4 Kengeri 29.57 20.00 20.00 100 Jul-2010
5 Vijayanagar 53.31 15.89 15.90 100 Jul-2010
6 Banashankari 31.11 5.80 6.10 105 Jul-2010
7 Yeshwanthpura 79.50 23.37 24.00 103 Jul-2010
8 Jayanagara 12.90 12.90 9.50 74 Jun-2009
9 Domlur 17.55 1.00 0.00 0 Jul-2010
10 Bannerughatta 5.49 0.50 0.00 0 Jul-2010
Total 444.40 142.11 136.60 96
TTMC Jayanagar 4th Block
Project Cost : Rs. 12.90 CroreDate of Commission:31.8.2009.
Recommended