Preparing TPC Installation

Preview:

DESCRIPTION

Preparing TPC Installation. Preparations in SXL2. Remove clean room wall (towards Muon area) and roof Clear area for trailer Setup hydraulic station. DF + TPC. DF + TPC. Hydraulic station. Alternative: mobile crane. plan view. side view. Complete TPC/TRD heat screen - PowerPoint PPT Presentation

Citation preview

TB 14.9.06 Peter Glässel, Heidelberg 1

Preparing TPC Installation

TB 14.9.06 Peter Glässel, Heidelberg 2

Preparations in SXL2

Remove clean room wall (towards Muon area) and roof

Clear area for trailer

Setup hydraulic station

DF +

TPC

DF +

TPC

TB 14.9.06 Peter Glässel, Heidelberg 3

Hydraulic station

plan view side view

Alternative: mobile crane

TB 14.9.06 Peter Glässel, Heidelberg 4

Preparations in UX2

Complete TPC/TRD heat screen Platform under shaft: intermediate support for Delphi Frame (DF)Before L3 magnet

Support for DF (surveyed)Space Frame area

I-bars stored at BFConnection rails at BSFITS platform (used when moving TPC)

TB 14.9.06 Peter Glässel, Heidelberg 5

TB 14.9.06 Peter Glässel, Heidelberg 6

Special precautions

DF has 4 feet, but no deformation allowed

Lifting jig is 3-point

4-point floating hydraulic support

3-point support (on trailer)

TPC is a closed volume, safety bubbler with Δp < 1 mbar

Watch Δp, ΔT to avoid sucking air

CO2 bottle on DF for replenishing

TB 14.9.06 Peter Glässel, Heidelberg 7

TPC transport

Transport document is prepared DF + TPC: 24 t

1. On SX2 crane from clean room to hydraulic station2. Raise to allow trailer to pass under DF3. Lower onto trailer4. Transport on trailer to SX25. Pick-up with hydraulic station6. Lower to allow transfer to SX2 crane7. Lower into shaft onto intermediate support8. Transfer to UX2 crane9. Move to final support before L3 magnet

TB 14.9.06 Peter Glässel, Heidelberg 8

TB 14.9.06 Peter Glässel, Heidelberg 9

ITS platform

Any number of segments possible

TB 14.9.06 Peter Glässel, Heidelberg 10

Installation sequence

Based on previous experience in TPC-ITS integration test

1. Align, install connection rails

2. Move to IP under surveyNo adjustments of SF during moving foreseen, expected deformations < 2mm (cf. tolerance for beam pipe ±5 mm)

3. Align TPC at IP

4. Move back to ‘parking position’ under survey

5. ITS installation

TB 14.9.06 Peter Glässel, Heidelberg 11

Spares

TB 14.9.06 Peter Glässel, Heidelberg 12

TB 14.9.06 Peter Glässel, Heidelberg 13

TB 14.9.06 Peter Glässel, Heidelberg 14

TB 14.9.06 Peter Glässel, Heidelberg 15

TB 14.9.06 Peter Glässel, Heidelberg 16

Alignment of TPC with Beam Axis

Once the TPC is in the final position, the TPC axis is aligned with the beam axis.

Again, only the x,y,z, coordinates of the outer (and possibly inner) reference rods on the shaft side can be used to determine the position of the TPC.

TB 14.9.06 Peter Glässel, Heidelberg 17

Installation of 1st ITS rail section

Two 6m sections of the ITS rails are inserted through the TPC and fixed by the ITS rail fixation points on the frontabsorber.

Then, the fixations points are slightly opened to allow the ITS rails to move to the parking position together with the TPC.

Since we assume that after movement of TPC to parking position and back to the IP the TPC ends up in the same position, the above procedure will make sure that the ITS rails are well aligned with the TPC when it moves to the IP.

TB 14.9.06 Peter Glässel, Heidelberg 18

Heatscreen

TB 14.9.06 Peter Glässel, Heidelberg 19

TB 14.9.06 Peter Glässel, Heidelberg 20

TB 14.9.06 Peter Glässel, Heidelberg 21