BIOGAS UPGRADING
Jevnaker Norway
Carborex®MS 400
Membrane Biogas Upgrading
BIO LNG Production
BIO LNG Production
Upgrading Polishing Liquefaction
• Pressure Swing Adsorption• Temperature Swing Adsorption• Membranes• Membrane Contactors• Amine scrubbing• Cryogenic upgrading
Lelystad PILOT (2013-2015)
• Max. 50 Nm3/h raw biogas
• Fluctuating biogas compositions
• Upgrading of biogas to LNG Quality (100 ppm)
• Liquefaction with Sterling Cryogenerators.
• 100-300 ppm CO2 in outlet gas
• Innovative and one-of-a kind solution
• Reduction of footprint
• Benefits of membrane technology
History DMT with BIOLNG
Temperature Swing Adsorption
• Regeneration by increasing Temperature (90 C)• Reduces CO2 very selective from 1,5-2 % to <50 ppm• Robust system, longer cycles, less fluctuations• No methane loss
Total system
Compact and containerizedFully integratedEasy to operateFast startup of system24/7 service
Capacity: 5 – 10 tons per day
Flexible solutions
The possibility to change from Gas2Grid to BIO-LNG
Concept
Gas to Grid• Business case based on Gas2Grid• Standardized Carborex MS:• Carborex MS can be used for both options• Carborex MS + LNG:
• Dry processes, no chemicals or water• Energy consumption < 1,5 kWh/kg
biomethane• Modelar build up
• Business case with ROI of 3-4 years is possible• Raw biogas price has significant effect: Increase €0,235 per kg when increase of €0,10 per Nm3
• Electricity price has significiant effect: €0,02 p.kg / €0,01 p kWh
0
0.5
1
1.5
2
0 0.1 0.2 0.3 0.4 0.5 0.6
Pri
ce B
ioLN
G (
euro
/kg)
Price raw Biogas (Euro/Nm3)
Biogas vs LNG price
0
20
40
60
80
100
0 0.2 0.4 0.6
RO
I (%
)
Raw biogas price (Euro/Nm3)
ROI vs. Raw biogas price at different LNG price
LNG price 1,30LNG price 1,40LNG price 1,60Lineair (LNG price 1,30)Lineair (LNG price 1,40)Lineair (LNG price 1,60)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
0 0.2 0.4 0.6
BIO
LNG
pri
ce (
Euro
/kg)
Raw biogas price (Euro/Nm3)
Raw biogas vs. BIOLNG price
Electricity (0,085 euro)
Electricity price 0,00(euro)
Electricity price 0,05(euro)
Electricity price 0,10(euro)
Electricity price 0,15(euro)
Electricity price 0,20(euro)
Business Case
Investment routes
1.Sale of Biogas or Biomethane to DMT
➢ Long term contracts on Sales of Biogas or Biomethane to DMT
➢ BOOM concept➢ Necessary permits for Bio-LNG to be arranged by DMT➢ Free access for Bio-LNG producer on site➢ Site works on cost of DMT➢ LNG installation remains part of DMT➢ Annual escalations depending on type off-take contract
DMT
2.Full CAPEX investment route
➢ Rough investment Euro 0,16 per Kg LNG➢ Necessary permits to be arranged by DMT➢ Up-time guarantee DMT on Bio-LNG➢ Various off-take contracts possible to be facilitated by
DMT➢ Possible subsidy in joint request and facilitated by DMT
Conclusions
• Proven and robust concept
• Standardized and scalable
• Flexibility in cooperation
WE ARE READY!
Harmen DekkerBusiness Development Manager
+31 6 54331782hdekker@dmt-et.nlwww.dmt-et.nl
Please visit our Youtube channel for latest animations and product video’s
DMT Environmental Technology
Or follow us on Social Media
DMTenvironmentaltechnology
DMT_ET
DMT Environmental Technology
Recommended