Deliverables Project Plan Rev 1.5, 1.6 M7.2 (39 issues – 10% done), M7.3 (57 issues – 46% done) Discussion, Note and Messaging Software Product Manual o Done Project Demo based on New Scenario o On Live 3
Citation preview
Pink ElephantShowcase - 7.12.2015
1
Brief• What have we done last week?
o Deliverableso Estimations
• What are we going to do this week?o Deliverables of the Next Week
• Project Demo
2
Deliverables• Project Plan Rev 1.5, 1.6
• M7.2 (39 issues – 10% done), M7.3 (57 issues – 46% done)Discussion, Note and Messaging
• Software Product Manual - 1.0o Done
• Project Demo based on New Scenarioo On Live
3
Project Plan
4
• Trello Project Management Tool
Project Plan
5
• Ganttify Extension
Semantic Search
6
• Brief information gathered• Initial semantic search
implementationo getrecommendedGroups method
Estimations• Barış Özcanlı
7
Issue Estimation ActualCoding 3,5 hours 3,5 hours
Testing + Communication
1 hour 1 hour
Total 4,5 hours 4,5 hours
Estimations• Hayri Can Akyel
8
Issue Estimation Actual
Project Plan Rev 1.5 1 hour 1 hour
Semantic Search Analysis 2 hours 2 hours
Mobile - Create Discussion 2 hours 2 hours
Mobile - Create Discussion Revision
1 hour 1 hour
Transfer Project Plan to Trello
2 hours 5 hours
Project Plan Rev 1.6, Showcase Presentation Week 11, SPM Rev 1.0
3 hours 3 hours
GitHub Issue Tracking 1 hour 1 hour
Communication 2 hours 2 hours
Total 14 hours 17 hours
Estimations• Mehmet Çelikel
9
Issue Estimation Actual#206 Logout Service 0,5 hours 0,5 hours
#201, #178 Initial Semantic Search Implementation for Recommended Groups
4 hours 3 hours
#148 Messaging 4 hours 4 hours
#146 Search User 0,5 hours 0,5 hours
#204, #203, #200, #187, #186, #180 Refactoring
2 hours 4 hours
#202, #183 Bugfixing 2 hours 2 hours
Communication 2 hours 2 hours
Total 13 hours 14 hours
Estimations• Orkun Koçyiğit
10
Issue Estimation ActualImplementing Join Group, Leave Group, List Popular Groups
4 hours 3 hours
Developing Data Model 1 hour 1.5 hours
Communication 0.5 hours 1 hour
Code Refactoring 2 hours 2.5 hours
Bug Fixing 1 hour 0.5 hour
Total 8,5 hours 8,5 hours
Estimations• Recep Günay
11
Issue Estimation ActualCoding 8 hours 8 hours
Communication 1 hour 1 hour
Total 9 hours 9 hours
Estimations• Sinan Can Sürücü
12
Issue Estimation ActualBugfixes 2 hours 2 hours
Discussion Functions Development
4 hours 5 hours
Discussion Functions Testing 0,5 hours 0,5 hours
Note Functions Development 2 hours 2 hours
Note Functions Testing 0,5 hours 0,5 hours
Github issue tracking 1 hour 1 hour
Communication 2 hours 2 hours
Total 12 hours 13 hours
Estimations
13
Estimation ActualAnalysis & Coding 46,5 hours 48,5 hours
Documentation & Issue Tracking
8 hours 11 hours
Communication 8,5 hours 9 hours
Total 63 hours 68,5 hours
Deliverables of Next Week
• Project Plan Rev 1.7, 1.8• Software Product Manual Rev 1.1• M8.2 - Search and Bugfixes• M8.3 - Search and Bugfixes• Project Demo
14