New X-band testing facility a.k.a. Xbox 2N. Catalan. Lasheras for the X-band testing areas (XTA) activity group
N. C
atal
an L
ashe
ras
What is Xbox2?
• A new test bench for testing RF structures at 12GHz above 100MV/m– One structure/three months testing
• CPI VKX-8311A, 50MW klystron – First of this model under construction– Based in SLAC XL5 tube
• Scandinova 50Hz, 450kV modulator• Full time operation expected from next year.• Possible extension in 2014-15 (Xbox3) when
Linac4 klystrons/waveguides are installed
N. C
atal
an L
ashe
ras
#2 50 MW klystron (XL-5, CPI) test stand will be able to deliver to the testing area up to 130 MW x 250 ns pulses at 50 Hz repetition rate. The overall power consumption is 43 kW.
From last collaboration meeting. (I. Syratchev)
Xbox1 in building 2013N
. Cat
alan
Las
hera
s
CTF3 klystron gallery CTF2
N. C
atal
an L
ashe
ras
Building 150. 352 MHz test stand
Proposed layout for Xbox2 in buidling 150N
. Cat
alan
Las
hera
s
Dmitry Gudkov. RF-PM. See also EDMS 1238874
Proposed layout for Xbox2 in buidling 150
Dmitry Gudkov. RF-PM
• Bunker to be reused as such with small modifications– Chicane modified to minimize
waveguide length– Radiation measurements done
in Xbox1 indicate shielding shall be reinforced on axis
• Modulator uses existing water/electricity distribution
• Top-left area used by the EBIS source tests at least until the end of 2013 (TBC)
N. C
atal
an L
ashe
ras
Test bunker
Modulator
Working area
LLRF
Vacuum/TWT
N. C
atal
an L
ashe
ras
Modular design (from EDMS 1238874)
N. C
atal
an L
ashe
ras
Modular design (from EDMS 1238874)
Bunker areaN
. Cat
alan
Las
hera
s
• Vacuum sectors for fast turn around– Loads an waveguide
network baked-out– Bake-out of the DUT
after installation
• Adjustable length for DUT– Single and double
structures
• Additional capacity for extra diagnostics
Dmitry Gudkov. RF-PM
• First piece of Xbox2!!• Compact SLED type pulse compressor.• RF measurements and final tuning next week!!• Four more units required
– Review of the concept, fabrication, mechanic support etc., by the end of February.
Pulse compressor
‘’Simple” -60 dB directional coupler.
RF components procurement• Range of components
developed for X band• Design and prototyping ready
end 2012• First orders expected by the
end of May• New x-band flanges for Xbox3
N. C
atal
an L
ashe
ras
LLRF• No beam. No synchronizing timing required.• Signal generation, diagnostics and control can be done within a NT PXI rack• Frequency multiplication and down conversion
– Successful tests in the lab• Temperature regulated rack (BI)
N. C
atal
an L
ashe
ras
Status of the Xbox• Preparation of the site
– Final layout of the test stand. January 2013.– Cleaning-up the area.– Safety file preparation. RP shielding estimations done.– Shielding reinforcement .– Water system modification.– Electricity modification.– Cabling, Ethernet, compressed air.
• Installation– Modulator procurement. End of March 2013.– Klystron delivery. Delayed by 4 months!!– RF network and components. End of May 2013.– Vacuum network, pumps and valves. LLRF and controls.
• Commissioning– Modulator/klystron unit. – Conditioning of RF network surely 2014.
• Constrains– LS1 resources availability.– Water cut due to LS1 from mid-may until beginning 2014.
PlanningN
. Cat
alan
Las
hera
s
Schedule adjusted
• Yesterday
• Today
N. C
atal
an L
ashe
ras
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb MarKlystron procurement
RF components
System tests
No water
LS1
2012 2013 2014
Commissioning
Modulator procurement
Pulse compressor prototypeSite preparation
Network procurementNetwork installation
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
No water
LS1
Network installationCommissioning
Klystron procurementModulator procurement
RF componentsPulse compressor prototype
Site preparationNetwork procurement
2012 2013 2014
Future:Xbox3. Cluster of small power units• Market survey for klystron-
modulator units out– Call for tender in the next weeks
• Components procurement under way – Waiting for new flanges
• Plan to start installation in2015
Xbox2
Xbox 3
In summary
• New test facility preparation on-going– Site identified– Klystron and modulator under construction– RF components under procurement– Site preparation starting
• Still learning from Xbox1 and dog-leg experiences
• Preparing the way for Xbox3• X-band test capacity multiplied by 3!!
N. C
atal
an L
ashe
ras
Thanks for your attention!!