MONTHLY STATUS REPORT– September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT

Oak Middle School Modernization Project

September 9, 2014

Los Alamitos, California

ACTIVITY SUMMARY

Progress 21

• Track • Grow-Out Period On-Going

Track and Field

Field Area

ACTIVITY SUMMARY

Progress 21

• Building N Entry • Demolition Complete

Southern View Building N Entry

Southern View Building N Entry

ACTIVITY SUMMARY

Progress 21

• Building N Entry • Demolition Complete

Plumbing Pipe Supporting Entry Doors

Entry Section Not Tied Into Building

ACTIVITY SUMMARY

Progress 21

• Classroom Building M • Complete

Building M Southern Facade

Building M Typical Classroom Interior

ACTIVITY SUMMARY

Progress 21

• Building N • Complete – Pending Multi-Purpose Room Turn-Over

New Kitchen Hood and Finishes

New Kitchen Pass Through and Railings

ACTIVITY SUMMARY

Progress 21

• Building N • Choir Room Complete

Choir Room View to Office Spaces

Choir Room View to Main Entry

ACTIVITY SUMMARY

Progress 21

• Buildings E and N • Complete

Building N, Multi-Purpose Room

New Classroom Building E

ACTIVITY SUMMARY

Progress 21

• Band Room and Outpost - Building L • Demolition Complete – Rough-Ins On-Going

Exterior Preparation - Ongoing

Rough Framing for New Offices

Schedule

Phase 7

• Buildings L & N

• Complete Multipurpose Room, Building N

• Complete Entry of Building N

• Complete Classroom Building L

• Continue Remediation of Track

• Continue Grow-Out Period

SCHEDULE

Recommended