LARP Magnet R&D Summary

Preview:

DESCRIPTION

LARP Magnet R&D Summary. S. Gourlay for the LARP Magnet Collaboration. US LARP Magnet Program. Large aperture, Nb 3 Sn Quadrupoles for LHC Upgrade. Length Scale-up. High Performance Conductor Development. 90 mm > 250 T/m. Collaboration established - PowerPoint PPT Presentation

Citation preview

LARP DOE Review June 13, 2006 S. Gourlay

LARP Magnet R&DSummary

S. Gourlay for the LARP Magnet Collaboration

LARP DOE Review June 13, 2006 S. Gourlay

US LARP Magnet Program

0.5 mm

Large aperture, Nb3Sn Quadrupoles for LHC Upgrade

90 mm> 250 T/m

High PerformanceConductor Development

LengthScale-up

LARP DOE Review June 13, 2006 S. Gourlay

Status and Achievements

• Collaboration established

• Excellent progress on all major activities

— Technology Quads (TQ)— Length Scale-up— Materials

• Model Magnet R&D

— TQS01 (Test in progress)— TQC01 (August)— TQC02 Fab and test by end of CY06

• Supporting R&D

— SQ-01 completed in FY04 and retested in FY05

— SQ-02 recently retested at FNAL @ 1.8K— Long Racetrack (LR) underway

• Materials— Characterization of strand, cable and

procurement

• Design Studies— Relevant studies underway

LARP DOE Review June 13, 2006 S. Gourlay

Materials

• Workhorse strand established— RRP 54/61 (successful industrial and lab use)

— Vigilant monitoring and evaluation required• Still an R&D material

— Conservative acceptance criteria established (Is > 2 X op)

• Parallel development of ultimate material (important)— Core programs

— SBIR

— Conductor Development Program

• Continued R&D— Measurement techniques (extracted strands)

— Cabling studies/parameters

— Cable testing (Ic and strain degradation)

LARP DOE Review June 13, 2006 S. Gourlay

Technology Quads

• Excellent first result— World’s highest gradient/bore (field) quad

— Truly collaborative effort

— Analysis and data unprecedented

• Some deviation from original plan – but we expected that— Evaluate next step in TQ

• Long Quad (LQ) start in FY07

• High Gradient Quad (HQ)— Phase in as resources allow

— Important to determine limits of technology

LARP DOE Review June 13, 2006 S. Gourlay

Length Scale-up

• Long Racetrack (LR)— Key to early start

— Focus on coil fabrication issues and tooling design

— Approach shell structure scale-up

— Lab integration

— Incurred delays not critical (yet)

— Design nearly complete

LARP DOE Review June 13, 2006 S. Gourlay

Proposed New Tasks and Scope

• New Tasks for FY07

— Long Quadrupole (LQ)

— High Gradient Quadrupole (HQ)• Engineering design

— Additional Long Racetrack coil

— SQ-03

— Rad-hard insulation

— Cable evaluation

• Performance expectation– “short sample”– Strain degradation

» Small racetracks (SRK), NHMFL, FRESCA

• Proposed new scope

— Rapid-cycling Nb3Sn dipole – TAMU

— Fast-Ramp - BNL• Measurement system• Design study

LARP DOE Review June 13, 2006 S. Gourlay

Risk and Risk Management

• LARP Magnet Program is very

ambitious, but . . .— Based on success of core programs— Focus on the goals— Effective use of resources

• Technical— Materials

• Extensive materials evaluation program

• Priority on delivery of “workhorse” material

— Parametric studies• Sub-scale magnets for early start on technical

issues

• Increase number of tests

• Schedule— Program planning takes into account

some unforeseen delays and difficulties

• Multiple targets

• Early schedule for completion

• Can recover additional schedule slip by accepting additional risk

• Reassess in mid-FY06— Modify as necessary

LARP DOE Review June 13, 2006 S. Gourlay

Milestones

TQ Prelim

LRS-01 LRS-

02Structure decision

LQ-01

HQ-01

LARP DOE Review June 13, 2006 S. Gourlay

Assessment Metric

In the bank!

Discuss, understand, review

Understand, try again.

180 T/m

200 T/m Success

LARP DOE Review June 13, 2006 S. Gourlay

Summary

• An excellent program has evolved over the past couple of years

• We have the tools and resources for success

• Off to a great start!

Recommended