Future Improvements of

Bayview Street Bridge and US 1

Bridge over I-295

Preliminary Public Meeting

Yarmouth Town Office

February 5, 2018

2

Presentation Outline

• Introduction and Meeting Goals

• US Route 1 Bridge followed by Bayview Street

Bridge

o About the bridges (age, condition, widths)

o Programmed scope of work at each bridge

o Concepts for maintaining traffic during construction

• Schedule for Bridge Projects

• Public Input, Questions, Answers

3

Introduction and Goals

Joel Kittredge – MaineDOT Project Manager

Steve Hodgdon – Hoyle, Tanner Project Manager

o Make Public Aware of the Project Early in Design

o Share Project Information, Development Process and

Preliminary Schedule

o Listen to Concerns and Gather Public Input Prior to

Design

o Answer Questions

4

Presented to:

Presented by:

US Route 1 Bridge over I-295

CUMBERLAND

YARMOUTH

Graphic Source:

Bing Maps

5

About the US 1 Bridge over I-295

• Constructed 1958 (age 60 years). 242’ long.

• Past Rehabilitation Work includes:

o 1991 – new bridge railing, new pavement, deck joints,

steel painting, concrete repairs. Roadway width

increased 16” (to 41.3’).

o 2013 – exit 15 NB off-ramp relocated under southern

span. Top layer of bridge pavement replaced for new

pavement markings.

• Deck, abutments, and piers are in “fair” condition.

The steel beams are in “satisfactory” condition.

6

DECK

PIER

COLUM

DECK

JOINT

7

Looking northerly along US 1 bridge

8

Deck Replacement

Increase roadway 2’ ± for wider shoulders

43’ ± curb-to-curb

New, wider deck

New bridge railing not shown

9

Maintain 2 lanes of two-way traffic

New bridge railing not shown

Work Area

Work Area

Work Area

Stage 1

Stage 2

Stage 3

10

Presented to:

Presented by:

Bayview Street Bridge over I-295

Exit 17

Graphic Source:

Bing Maps

11

About Bayview Street Bridge over I-295

• Constructed 1962 (age 56 years). 227’ long.

• Past Rehabilitation Work includes:

o Routine preservation and maintenance activities

o No substantial rehabilitation work

• Deck is in “fair” condition, steel beams are in “good”

condition, and abutments and piers are in

“satisfactory” condition.

12

DECK

PIER

COLUM

DECK

JOINT

13

Looking westerly along Bayview Street

14

Deck Replacement with new Sidewalk

New bridge railing not shown

24’5’

sidewalk curb-to-curb

Looking westerly

New, wider deck

15

Maintain 1 lane of reversible two-way traffic

New bridge railing not shown

Work Area

Work Area

Work Area

Work Area – Stage 4

Sidewalk construction

trafficpedestrians

Stage 1

Stage 2

Stage 3

16

Est. Project Schedule (Both Bridges)

• Preliminary Design – now to September 2018

• Informational Meeting – late Spring 2018

• Formal Public Meeting – July/August 2018

• Final Design and Permitting – 2019

• Construction – 2020/2021 (may change depending on

conflicts with other capital, maintenance, and

preservation projects scheduled in the next 3 years)

17

Public Input & Questions

• Ground Rules:

o Use the Microphone if available

o Introduce Yourself for the

Public Record