Future Improvements of
Bayview Street Bridge and US 1
Bridge over I-295
Preliminary Public Meeting
Yarmouth Town Office
February 5, 2018
2
Presentation Outline
• Introduction and Meeting Goals
• US Route 1 Bridge followed by Bayview Street
Bridge
o About the bridges (age, condition, widths)
o Programmed scope of work at each bridge
o Concepts for maintaining traffic during construction
• Schedule for Bridge Projects
• Public Input, Questions, Answers
3
Introduction and Goals
Joel Kittredge – MaineDOT Project Manager
Steve Hodgdon – Hoyle, Tanner Project Manager
o Make Public Aware of the Project Early in Design
o Share Project Information, Development Process and
Preliminary Schedule
o Listen to Concerns and Gather Public Input Prior to
Design
o Answer Questions
4
Presented to:
Presented by:
US Route 1 Bridge over I-295
CUMBERLAND
YARMOUTH
Graphic Source:
Bing Maps
5
About the US 1 Bridge over I-295
• Constructed 1958 (age 60 years). 242’ long.
• Past Rehabilitation Work includes:
o 1991 – new bridge railing, new pavement, deck joints,
steel painting, concrete repairs. Roadway width
increased 16” (to 41.3’).
o 2013 – exit 15 NB off-ramp relocated under southern
span. Top layer of bridge pavement replaced for new
pavement markings.
• Deck, abutments, and piers are in “fair” condition.
The steel beams are in “satisfactory” condition.
6
DECK
PIER
COLUM
DECK
JOINT
7
Looking northerly along US 1 bridge
8
Deck Replacement
Increase roadway 2’ ± for wider shoulders
43’ ± curb-to-curb
New, wider deck
New bridge railing not shown
9
Maintain 2 lanes of two-way traffic
New bridge railing not shown
Work Area
Work Area
Work Area
Stage 1
Stage 2
Stage 3
10
Presented to:
Presented by:
Bayview Street Bridge over I-295
Exit 17
Graphic Source:
Bing Maps
11
About Bayview Street Bridge over I-295
• Constructed 1962 (age 56 years). 227’ long.
• Past Rehabilitation Work includes:
o Routine preservation and maintenance activities
o No substantial rehabilitation work
• Deck is in “fair” condition, steel beams are in “good”
condition, and abutments and piers are in
“satisfactory” condition.
12
DECK
PIER
COLUM
DECK
JOINT
13
Looking westerly along Bayview Street
14
Deck Replacement with new Sidewalk
New bridge railing not shown
24’5’
sidewalk curb-to-curb
Looking westerly
New, wider deck
15
Maintain 1 lane of reversible two-way traffic
New bridge railing not shown
Work Area
Work Area
Work Area
Work Area – Stage 4
Sidewalk construction
trafficpedestrians
Stage 1
Stage 2
Stage 3
16
Est. Project Schedule (Both Bridges)
• Preliminary Design – now to September 2018
• Informational Meeting – late Spring 2018
• Formal Public Meeting – July/August 2018
• Final Design and Permitting – 2019
• Construction – 2020/2021 (may change depending on
conflicts with other capital, maintenance, and
preservation projects scheduled in the next 3 years)
17
Public Input & Questions
• Ground Rules:
o Use the Microphone if available
o Introduce Yourself for the
Public Record
Joel Kittredge,
MaineDOT Project Manger
Phone: (207) 624-3550