STV Construction, Inc.
Project Date 6/6/2014Location Weekday Friday
Client Report # 136
Contract # Weather
Project # Temp. L/H
STV Representative: Bill King Wind Speed
Work hours 8:30-4:30 Precip.
29 46 75 0.61 106 74 1.4
53 0.87 106 106 100%
73 33 41
Pile Drilling (106 piles along Pacific St.): Complete.
2114659
Sidewalk/Curb/Street 2' wide section replacement: Not started.
Slight
Existing Wall Demo: Use of hoe ram on older SOE wall being removed in order to install new SOE wall behind it.
0"
New Fence: Not started.
Tiebacks (Ph2C - 75): Two tieback rigs working all day along Pacific Street, east of Carlton Ave. Bridge. Day 53 since the start of
tiebacks. Waler installation continued in eastern half of wall on both top tieback row (Phase 3) and next lower (2nd) row in west end
of block (Phase 2C). Drilling in some of the remaining 4 tiebacks to go on the lower row nearest Carlton Ave. Bridge (Phase 2C)
Yard Excavation: Excavation continued as needed along SOE wall.
Summary of Construction Activities
low 60's to mid/upper 70's
DAILY CONSTRUCTION REPORT
Atlantic YardsLIRR Phases 2C & 3
ESD
6717 Sunny, Beautiful Weather
New observations: Have 16 working days remaining from June 9 to and including June 30 to finish Phase 2C tiebacks.
Previous observations: 4/1/14: Job is big enough for 2 tieback rigs working at the same time. Would be especially beneficial
Information received:
Manpower 15-20
Posillico/Tully 15-20
William King 6/6/2014 Date
w en one e ac r g rea s own. s m ar r gs wor ng on sma er pro ec near .
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction given:
Previous Information received: FCR reports that Atlantic Ave. median removal MPT setup will commence either the last week inJune or the first week in July.
FCR confirmed that work on upper tieback row, east end, is change order to the current Phase 2C contract and represents early
work on Phase 3.
Major Equipment on site (I = Inactive)
Prepared by William King
Tieback Rig #1
Materials Delivered (Observed)Equipment (Arrival / Departure)
(Observed)
Front End Loader/Excavator - Cat 300-series (tire)
Manpower figure is a rough approximation by STV.
Front End Loader/Excavator - Volvo
Pile Rig (I - for Phase 3/4)
Tieback Rig #2
Cat forklift/hoe ram
1 of 1
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
4/13
STV Construction, Inc.
Project Date 6/2/2014Location Weekday Monday
Client Report # 328
Contract # Weather
Project # Temp. L/H 60-79
STV Representative: Bill King Wind Speed
Work hours 8:30-5:00 Precip
117 122 1.0
930 0.126
2114659
Summary of Construction Activities
Slight - 13-17 mph
0"
Other - No Con Ed.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny, Perfect Weather
Tower Crane - Inactive.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 122 workdays = 1 mod per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that
mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the
6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured.
Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the
Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced
production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the
week of 5/21 and that the 8th floor mods had begun production.
MEP - Piping work at ground floor ceiling continued.
Additional New Observations: Spray-on fireproofing (SOFP) continued on ground floor, west side, for 2nd day in a row after a 1-weekhiatus. Tarps hung around area.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.
1/20/14
Information previously requested: 5/1/14 -
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
New Information received:
New Information requested:
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Previous Information received:
1 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
5/13
STV Construction, Inc.
Manpower on Site 10-20
Navillus 0
Stearns 0-5
J SuporTrucking 0
MEP trades 0-5
Other 5-10
William Kin 6/2/2014 Date
Potain Tower Crane (I)
Prepared by William King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
2 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
6/13
STV Construction, Inc.
Project Date 6/3/2014Location Weekday Tuesday
Client Report # 329
Contract # Weather
Project # Temp. L/H 67-87
STV Representative: Bill King Wind Speed
Work hours 8:30-5:00 Precip
117 123 1.0
930 0.126
Tower Crane - Inactive.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 123 workdays = 1 mod per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that
mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the
6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that
mod installation starting on 6/9 will definitely be through 9th Floor.
Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the
Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced
production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the
week of 5/21 and that the 8th floor mods had begun production. FCR adds that 9th floor mod fab completion is scheduled for 7/3 and that
Navy Yard plant headcount is now in the high 140's.
MEP - Piping work at ground floor ceiling continued.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Very Warm & More Humid, Sunny, Rain Late
2114659
Summary of Construction Activities
Slight gusting up to 24 mph
1/5"
Other - No Con Ed.
New Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount is nowin the high 140's.
New Information requested: From FCR, update on production progress at Navy Yard.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
hiatus. Tarps hung around area. Progress slow.
Previous Information received:
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
FCR states that mods installed from 6/9 on will be floors 6-9.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.
1/20/14 -
Information previously requested: 5/1/14 -
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.
Final mold report due from Skanska's environmental consultant on 6/6.
1 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
7/13
STV Construction, Inc.
Manpower on Site 10-20
Navillus 0
Stearns 0-5
J SuporTrucking 0
MEP trades 0-5
Other 5-10
William King 6/3/2014 Date
Manpower figure is rough approximation by STV.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by William King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
2 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
8/13
STV Construction, Inc.
Project Date 6/4/2014Location Weekday Wednesday
Client Report # 330
Contract # Weather
Project # Temp. L/H 63/83
STV Representative: Bill King Wind Speed
Work hours 8:30-5:00 Precip
117 124 0.9
930 0.126
Tower Crane - Inactive.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 124 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that
mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the
6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that
mod installation starting on 6/9 will definitely be through the 9th Floor.
Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the
Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced
production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the
week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that 9th floor mod fab completion is scheduled for 7/3
and that Navy Yard plant headcount is now in the high 140's.
MEP -
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Warm & Humid, Sunny to High Overcast
2114659
Summary of Construction Activities
Slight gusting up to 17 mph
0"
Other - No Con Ed.
Very low activity day. Trades not on site: masons, SOFP, plumbing. A few ironworkers on site but work uncertain.
New Information received:
New Information requested:
Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.
1/20/14 -
Information previously requested: 5/1/14 -
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.
Final mold report due from Skanska's environmental consultant on 6/6.
1 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
9/13
STV Construction, Inc.
Manpower on Site 10
Navillus 0
Stearns 2
J SuporTrucking 0
MEP trades 0-5
Other 5-10
William Kin 6/4/2014 Date
Manpower figure is rough approximation by STV.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by William King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
2 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
10/13
STV Construction, Inc.
Project Date 6/5/2014Location Weekday Thursday
Client Report # 331
Contract # Weather
Project # Temp. L/H 62/76
STV Representative: Bill King Wind Speed
Work hours 8:30-4:30 Precip
117 125 0.9
930 0.126
2114659
Summary of Construction Activities
Slight gusting up to 25 mph
3/4"
Other - No Con Ed.
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Rainy in a.m., Sunny p.m.
Tower Crane - Inactive.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 125 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that
mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the
6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that
mod installation starting on 6/9 will definitely be through the 9th Floor.
Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the
Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced
production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the
week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that mods for floors 6-8 have been completed and 9th
floor mod fab completion is scheduled for 7/3; also Navy Yard plant headcount is now in the high 140's.
MEP -
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.
1/20/14 -
Information previously requested: 5/1/14 - Inquired.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.
Final mold report due from Skanska's environmental consultant on 6/6.
New Information received:
New Information requested:
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.
1 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
11/13
STV Construction, Inc.
Manpower on Site 10-15
Navillus 0
Stearns 2
J SuporTrucking 0
MEP trades 0-5
Other 5-10
William King 6/5/2014 Date
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by William King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
2 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
12/13
STV Construction, Inc.
Project Date 6/6/2014Location Weekday Friday
Client Report # 332
Contract # Weather
Project # Temp. L/H
STV Representative: Bill King Wind Speed
Work hours 8:30-4:30 Precip
117 126 0.9
930 0.126
Tower Crane - Inactive.
Module Transportation - 0 mods delivered to site.
Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 126 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that
mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the
6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that
mod installation starting on 6/9 will definitely be through the 9th Floor.
Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the
Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced
production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the
week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that mods for floors 6-8 have been completed and 9th
floor mod fab completion is scheduled for 7/3; also Navy Yard plant headcount is now in the high 140's.
MEP -
DAILY CONSTRUCTION REPORT
Atlantic YardsB2ESD
6717 Sunny, Beautiful Weather
low 60's to mid/upper 70's2114659
Summary of Construction Activities
Slight
0"
Other - No Con Ed.
Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.
New Information received: Received safety harness training from STV CM Northeast Safety Director, Phil Taylor. Will use harness next
week during the week and be checked for fit next Friday, 6/13 by PT who will also do a safety audit of the project.
New Information requested: Sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may besuspected.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the façade; interior: lack of completeness of mods.
1/20/14 -
of .
Information previously requested: 5/1/14 -
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.
Final mold report due from Skanska's environmental consultant on 6/6.
1 of 2
8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted
13/13
STV Construction, Inc.
Manpower on Site 10-15
Navillus 0
Stearns 2
J SuporTrucking 0
MEP trades 0-5
Other 5-10
William Kin 6/6/2014 Date
Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
Potain Tower Crane (I)
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Special instruction(s) given:
Prepared by William King
Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed
Major Equipment on site (I = Inactive)
Manpower figure is rough approximation by STV.
Recommended