      STV Construction, Inc.

    Project Date 6/6/2014Location Weekday Friday

    Client Report # 136

    Contract # Weather  

    Project # Temp. L/H

    STV Representative: Bill King Wind Speed

    Work hours 8:30-4:30 Precip.

    29 46 75 0.61 106 74 1.4

    53 0.87 106 106 100%

    73 33 41

    Pile Drilling (106 piles along Pacific St.): Complete.

    2114659

    Sidewalk/Curb/Street 2' wide section replacement: Not started.

      Slight

    Existing Wall Demo: Use of hoe ram on older SOE wall being removed in order to install new SOE wall behind it.

      0"

    New Fence:  Not started.

    Tiebacks (Ph2C - 75): Two tieback rigs working all day along Pacific Street, east of Carlton Ave. Bridge. Day 53 since the start of

    tiebacks. Waler installation continued in eastern half of wall on both top tieback row (Phase 3) and next lower (2nd) row in west end

    of block (Phase 2C). Drilling in some of the remaining 4 tiebacks to go on the lower row nearest Carlton Ave. Bridge (Phase 2C)

     Yard Excavation:  Excavation continued as needed along SOE wall.

    Summary of Construction Activities

    low 60's to mid/upper 70's

    DAILY CONSTRUCTION REPORT

    Atlantic YardsLIRR Phases 2C & 3

    ESD

    6717 Sunny, Beautiful Weather  

    New observations: Have 16 working days remaining from June 9 to and including June 30 to finish Phase 2C tiebacks.

    Previous observations: 4/1/14: Job is big enough for 2 tieback rigs working at the same time. Would be especially beneficial

    Information received:

    Manpower  15-20

    Posillico/Tully 15-20

     William King  6/6/2014 Date

    w en one e ac r g rea s own. s m ar r gs wor ng on sma er pro ec near .

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction given:

    Previous Information received: FCR reports that Atlantic Ave. median removal MPT setup will commence either the last week inJune or the first week in July.

    FCR confirmed that work on upper tieback row, east end, is change order to the current Phase 2C contract and represents early

    work on Phase 3.

    Major Equipment on site (I = Inactive)

    Prepared by William King

    Tieback Rig #1

    Materials Delivered (Observed)Equipment (Arrival / Departure)

    (Observed)

    Front End Loader/Excavator - Cat 300-series (tire)

    Manpower figure is a rough approximation by STV.

    Front End Loader/Excavator - Volvo

    Pile Rig (I - for Phase 3/4)

    Tieback Rig #2

    Cat forklift/hoe ram

    1 of 1

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    4/13

      STV Construction, Inc.

    Project Date 6/2/2014Location Weekday Monday

    Client Report # 328

    Contract # Weather  

    Project # Temp. L/H 60-79

    STV Representative: Bill King Wind Speed

    Work hours 8:30-5:00 Precip

    117 122 1.0

    930 0.126

    2114659

    Summary of Construction Activities

      Slight - 13-17 mph

      0"

    Other -  No Con Ed.

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Sunny, Perfect Weather  

    Tower Crane - Inactive.

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 122 workdays = 1 mod per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that

    mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the

    6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the

    Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced

    production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the

    week of 5/21 and that the 8th floor mods had begun production.

    MEP - Piping work at ground floor ceiling continued.

    Additional New Observations: Spray-on fireproofing (SOFP) continued on ground floor, west side, for 2nd day in a row after a 1-weekhiatus. Tarps hung around area.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep

    ahead of erection so there would be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Previous Information received:

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    5/13

      STV Construction, Inc.

    Manpower on Site 10-20

    Navillus 0

    Stearns 0-5

    J SuporTrucking 0

    MEP trades 0-5

    Other 5-10

     William Kin  6/2/2014 Date

    Potain Tower Crane (I)

    Prepared by William King

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    6/13

      STV Construction, Inc.

    Project Date 6/3/2014Location Weekday Tuesday

    Client Report # 329

    Contract # Weather  

    Project # Temp. L/H 67-87

    STV Representative: Bill King Wind Speed

    Work hours 8:30-5:00 Precip

    117 123 1.0

    930 0.126

    Tower Crane - Inactive.

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 123 workdays = 1 mod per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that

    mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the

    6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that

    mod installation starting on 6/9 will definitely be through 9th Floor.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the

    Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced

    production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the

    week of 5/21 and that the 8th floor mods had begun production. FCR adds that 9th floor mod fab completion is scheduled for 7/3 and that

    Navy Yard plant headcount is now in the high 140's.

    MEP - Piping work at ground floor ceiling continued.

     

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Very Warm & More Humid, Sunny, Rain Late

    2114659

    Summary of Construction Activities

      Slight gusting up to 24 mph

      1/5"

    Other -  No Con Ed.

    New Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount is nowin the high 140's.

    New Information requested: From FCR, update on production progress at Navy Yard.

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep

    ahead of erection so there would be no downtime during mod erection at the B2 site.

     hiatus. Tarps hung around area. Progress slow.

    Previous Information received:

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

    FCR states that mods installed from 6/9 on will be floors 6-9.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.

    Final mold report due from Skanska's environmental consultant on 6/6.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    7/13

      STV Construction, Inc.

    Manpower on Site 10-20

    Navillus 0

    Stearns 0-5

    J SuporTrucking 0

    MEP trades 0-5

    Other 5-10

     William King 6/3/2014 Date

    Manpower figure is rough approximation by STV.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by William King

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    8/13

      STV Construction, Inc.

    Project Date 6/4/2014Location Weekday Wednesday

    Client Report # 330

    Contract # Weather  

    Project # Temp. L/H 63/83

    STV Representative: Bill King Wind Speed

    Work hours 8:30-5:00 Precip

    117 124 0.9

    930 0.126

    Tower Crane - Inactive.

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 124 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that

    mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the

    6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that

    mod installation starting on 6/9 will definitely be through the 9th Floor.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the

    Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced

    production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the

    week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that 9th floor mod fab completion is scheduled for 7/3

    and that Navy Yard plant headcount is now in the high 140's.

    MEP -

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Warm & Humid, Sunny to High Overcast

    2114659

    Summary of Construction Activities

    Slight gusting up to 17 mph

      0"

    Other -  No Con Ed.

    Very low activity day. Trades not on site: masons, SOFP, plumbing. A few ironworkers on site but work uncertain.

    New Information received:

    New Information requested:

    Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

    FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.

    Final mold report due from Skanska's environmental consultant on 6/6.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    9/13

      STV Construction, Inc.

    Manpower on Site 10

    Navillus 0

    Stearns 2

    J SuporTrucking 0

    MEP trades 0-5

    Other 5-10

     William Kin  6/4/2014 Date

    Manpower figure is rough approximation by STV.

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep

    ahead of erection so there would be no downtime during mod erection at the B2 site.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by William King

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    10/13

      STV Construction, Inc.

    Project Date 6/5/2014Location Weekday Thursday

    Client Report # 331

    Contract # Weather  

    Project # Temp. L/H 62/76

    STV Representative: Bill King Wind Speed

    Work hours 8:30-4:30 Precip

    117 125 0.9

    930 0.126

    2114659

    Summary of Construction Activities

    Slight gusting up to 25 mph

      3/4"

    Other -  No Con Ed.

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Rainy in a.m., Sunny p.m.

    Tower Crane - Inactive.

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 125 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that

    mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the

    6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that

    mod installation starting on 6/9 will definitely be through the 9th Floor.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the

    Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced

    production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the

    week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that mods for floors 6-8 have been completed and 9th

    floor mod fab completion is scheduled for 7/3; also Navy Yard plant headcount is now in the high 140's.

    MEP -

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

    FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches tothe façade; interior: lack of completeness of mods.

    1/20/14 -

    Information previously requested: 5/1/14 - Inquired.

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.

    Final mold report due from Skanska's environmental consultant on 6/6.

    New Information received:

    New Information requested:

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep

    ahead of erection so there would be no downtime during mod erection at the B2 site.

     

    Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    11/13

      STV Construction, Inc.

    Manpower on Site 10-15

    Navillus 0

    Stearns 2

    J SuporTrucking 0

    MEP trades 0-5

    Other 5-10

     William King 6/5/2014 Date

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by William King

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

    2 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    12/13

      STV Construction, Inc.

    Project Date 6/6/2014Location Weekday Friday

    Client Report # 332

    Contract # Weather  

    Project # Temp. L/H

    STV Representative: Bill King Wind Speed

    Work hours 8:30-4:30 Precip

    117 126 0.9

    930 0.126

     

    Tower Crane - Inactive.

    Module Transportation - 0 mods delivered to site.

    Module Installation - 0 new mods installed. Mod completion stands at 12.6%, 117 of 930 installed. Installation Rate = 117 in 126 workdays = .9 mods per day so far. Last mod installed 4/14. Skanska confirmed mod installation will restart 6/9. FCR had informed on 5/13 that

    mod installation restart was to be pushed back to June 9 from June 2 and that it is expected installation will halt again after installation of the

    6th-8th floors, poss bly the 9th floor, as there will be another wait for another 3-floor backlog to be manufactured. FCR updated on 6/3 that

    mod installation starting on 6/9 will definitely be through the 9th Floor.

    Module Fabrication - Ongoing at Navy Yard, presumably, working on 8th floor mods with 142-man workforce. FCR reported on 5/2 that6th floor mods were all done, per schedule. On 5/30, as well as on 5/13, a number of mods were observed sitting outside Bldg 293 at the

    Navy Yard along with a host of frames (largest quantity seen sitting outside). Schedule received 4/28 states 7th Floor mods commenced

    production on 4/18 and will be finished by 5/14 but FCR informed on 5/13 that were running late and on 5/14 reported they will be finished the

    week of 5/21 and that the 8th floor mods had begun production. FCR added on 6/3/14 that mods for floors 6-8 have been completed and 9th

    floor mod fab completion is scheduled for 7/3; also Navy Yard plant headcount is now in the high 140's.

    MEP -

    DAILY CONSTRUCTION REPORT

    Atlantic YardsB2ESD

    6717 Sunny, Beautiful Weather  

    low 60's to mid/upper 70's2114659

    Summary of Construction Activities

      Slight

      0"

    Other -  No Con Ed.

     

    Previous Information received: FCR states that 9th floor mod fab completion is scheduled for 7/3 and that Navy Yard plant headcount isnow in the high 140's.

    New Information received: Received safety harness training from STV CM Northeast Safety Director, Phil Taylor. Will use harness next

    week during the week and be checked for fit next Friday, 6/13 by PT who will also do a safety audit of the project.

    New Information requested: Sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may besuspected.

    Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.

    FCR stated on 6/3/14 that mods installed from 6/9 on will be floors 6-9.

    Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to

    the façade; interior: lack of completeness of mods.

    1/20/14 -

    of .

    Information previously requested: 5/1/14 -

    2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.

    4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.

    Broadway Stack received its TCO on 5/15, about 10-11 months after all of its mods were installed.

    Final mold report due from Skanska's environmental consultant on 6/6.

    1 of 2

  • 8/20/2019 Atlantic Yards B2 FOIL, AY STV Report - 6-6-14 - Proposed Redactions_Redacted

    13/13

      STV Construction, Inc.

    Manpower on Site 10-15

    Navillus 0

    Stearns 2

    J SuporTrucking 0

    MEP trades 0-5

    Other 5-10

     William Kin  6/6/2014 Date

    Previous observations: Front façade is 33-35' from the ped walkway. Flatbush façade is 12' from the edge of the sidewalk shed. Heightexceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.

     At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog

    of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep

    ahead of erection so there would be no downtime during mod erection at the B2 site.

    Potain Tower Crane (I)

    Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None

    Special instruction(s) given:

    Prepared by William King

    Materials Delivered other than Mods (Observed)Equip. Arr./ Departure-Observed

    Major Equipment on site (I = Inactive)

    Manpower figure is rough approximation by STV.