Project ManagementCoordination & LiaisonConstruction Management Design (New, Seismic, Preliminary)Proposals and TenderConcepts and Ideas

L. Anders LoofC.Eng. MICE (UK)P.E. (California, USA)Chartered Architect RIBA (UK) loof_intl@hotmail.com

Second Penang Bridge, MalaysiaProject Management – DPM, ICE (Design) during construction

16.5 km Sea ViaductsPrecast SegmentalCable Stayed Bridge

Coordination – LiaisonICE Design – Client – D&B Construction

Second Penang Bridge, MalaysiaProject Management – DPM, ICE (Design) during construction

Stonecutters Bridge, Hong KongConstruction Management – RCTO for Stay Cable Installation

1018m Main Span CSB224 Stay CablesLongest over 540m

Stonecutters Bridge, Hong KongConstruction Management – RCTO for Stay Cable Installation

Machang Bridge, South KoreaConstruction Management – Responsible All of CSB

16.5 km Sea ViaductsPrecast SegmentalCable Stayed Bridge1.7 km Sea Crossing

ILM 8x 70m Spans170+400+170m CSB130+150+130m Steel Box Girders

Managed as “win-win;- to quality

- on programme- few claims.

Machang Bridge, South KoreaConstruction Management – Responsible All of CSB

16.5 km Sea ViaductsPrecast SegmentalCable Stayed Bridge

Chong Zun Expressway, ChinaConstruction Management / Bridge Expert Audits

> 120 Bridges in Constructionalong 117 km Expressway, RMB 6.7bn Tot, 24% ADB

17 Drill & Blast Tunnels into Carst Layered Rock, one > 2km2x Balanced Cantilver Turned After Construct 

“It is a very difficult project, possibly the most difficult inall of China. Some people doubted that we would ever

be able to build it.” – Xu Deyu of client, NCE 2005.06.16

Chong Zun Expressway, ChinaConstruction Management / Bridge Expert Audits

Chong Zun Expressway, ChinaConstruction Management / Bridge Expert Audits

Aswan Bridge, EgyptConstruction Management / Resident Engineer CSB

1km BridgeCable Stayed =125+250+125m

Aswan Bridge, EgyptConstruction Management / Resident Engineer CSB