View
220
Download
0
Category
Tags:
Preview:
Citation preview
1
Risk Management
2
Road Ahead
• Risk Management Process
• Cost and Schedule Risk
• Estimating Likelihood
• Mitigation
• Utility and Consequences
• Sensitivity Analysis
3
Reference Material
• Risk Management Guide for DOD Acquisition, 6th Ed, Ver 1.0, August 2006 http://www.dau.mil/pubs/gdbks/docs/RMG%206Ed%20Aug06.pdf.
• INCOSE Systems Engineering Handbook, Ver 3, INCOSE-TP-2003-002-03, June, 2006, Chapter 7.3
4
Why Do We Care?
• Every change from a current state to a future state occurs as a result of a process.
• The future behavior of any process is affected by uncertainties.
• Management of the process requires consideration of these uncertainties to minimize their influence on the desired final outcome of the process.
5
Elementary ProcessElementary Process
TransformationInput Output
Unknowns Uncertainty
6
Risk vs. Issues
• Risk refers to a future uncertain event.
• If an event has occurred it is no longer uncertain. It becomes an issue or a problem.
• Management of either requires expenditure of resources.
7
Risk Definitions
• Statistics: P[Undesirable Event]
• Risk Management: P[Undesirable Event] Plus the Consequences of the Event
• INCOSE considers both Undesirable and Desirable events
8
Consequences Can Impact:
• Technical Performance– Key Performance Parameters– Operational capability– Supportability
• Schedule
• Cost
• The above are not mutually independent
9
Risk Categories
• Technical Risk – A technical requirement may not be satisfied during the life cycle
• Cost Risk – Available budget may be exceeded
• Schedule Risk – May fail to reach Scheduled Milestones
• Programmatic Risk – Events beyond the control of the Program Manager
10
A Risk Reporting Matrix
1
2
3
4
5L
ikel
ihoo
d L
evel
1 2 3 4 5
Consequence Level
Low Risk
Moderate Risk
High Risk
11
Possible Risk Likelihood Criteria
Level Likelihood P[Occur]
1 Not Likely p< 0.10
2 Low Likelihood 0.10<=p<0.30
3 Likely 0.30<=p<0.70
4 Highly Likely 0.70<=p<0.90
5 Near Certainty 0.90<=p
12
Possible Consequence Level Criteria
Level Technical Performance
Schedule Cost
1 None to Minimal None to Minimal None to Minimal
2 Can be tolerated
Little program impact
Slip< ? mo C< 1% of Budget
3 Moderate, Limited program impact
Slip<? mo
Subsys slip>? Mo
1%<=C<5% of Budget
4 Significant degradation,
May jeopardize program
Critical path affected
5%<=C<10% of Budget
5 Severe degradation, Will jeopardize program success
Cannot meet key program milestones
10% of Budget
<= C
13
Risk Criteria Depend on Program
Risk Level Criteria
1 P<0.0001
2 P<0.02
3 P<0.05
4 P<0.25
5 P>0.25
14
Risk Reporting Illustration
1
2
3
4
5L
ikel
ihoo
d L
evel
1 2 3 4 5
Consequence Level
Risk Title (Category)CauseMitigation Approach
15
Risk Management
• A process to minimize the adverse effects of uncertain future events on the achievement of end state objectives.
• Basic Tasks:– Identify and characterize process properties.
– Decide on a course of action to minimize adverse affects of events on program objectives.
– Implement and control the course of action.
16
Risk Management Functions
• Planning
• Resourcing
• Staffing
• Controlling
17
Planning
• Define the strategy and process to be used• Establish a Risk Management Plan (RMP)
– Tasks– Schedules– Reviews– Reporting
• Define the resources required– People– Funds– Space and support resources
18
An Example RMP Format Summary
1. Introduction
2. Program Summary
3. Risk Management Strategy and Process
4. Responsible/Executing Organization
5. Risk Management Process and Procedures
6. Risk Identification
7. Risk Analysis
8. Risk Mitigation Planning
9. Risk Mitigation Implementation
10. Risk Tracking
19
Events May Cause RMP Update
• A change in acquisition strategy, • Preparation for a milestone decision, • Results and findings from event–based
technical reviews, • An update of other program plans, • Preparation for a Program Objective
Memorandum submission, or • A change in support strategy.
20
Identify Uncertain Events
EstimateP[Occur]
EstimateConsequences
Formulate AlternativeCourses of Action
EvaluateAlternatives
Choose Approach Execute andTrack
Working? OR
Continueor Stop
Yes
No
Risk Management Process
Planning
21
Risk (Uncertain Event) Identification
• What can go wrong?
• If EVENT happens then CONSEQUENCE results
• Find everywhere Mr. Murphy can rear his ugly head!
22
What to Look At
• Current and proposed staffing, process, design, suppliers, concept of operation, resources, interfaces, interactions, etc.
• Test results and failures (especially readiness results)
• Potential Shortfalls• Trends• External Influences (programmatic, political)
23
Potential Root Causes of Risk Events
• Need (Threat)• Requirements• Technical Baseline• Test & Evaluation• Modeling & Simulation• Technology• Logistics• Production/Facilities
• Concurrency• Industrial Capability• Cost• Management• Schedule• External Factors• Budget• Earned Value Realism
24
Possible Risk Management Actions
• Avoid– Redesign– Change requirements
• Accept• Control
– Expand resources– Reduce likelihood and/or consequences
• Transfer– By mutual agreement to party more qualified to
mitigate
25
Interactions and Consequences
• Schedule affects costC = A +BT
• Budget constrains costForces B vs T tradeoff
• Schedule constraint affects costCauses B increase
• Technology maturity and workforce skills affect all terms
26
Example:Program to modify an existing guided submunition
Current CharacteristicsWeight 20 kg
Length 50 cm
Diameter 15 cm
Required CharacteristicsWeight 15 kg
Length 40 cm
Diameter 10 cm
27
1 2 3 4 5 6 7 8 9 10 11 12Weight Reduction
Length Reduction
Diameter Reduction
Month
Example Schedule
28
Uncertain Events?
If ---------------- Then ---------------------
29
ExampleGuided Antitank Submunition
• Effectiveness:– Dictates minimum number/carrier
• Carrier Vehicle– Constrains length, diameter, and weight
30
Technical Performance Vector
Element Required Current
Length (L) 40 cm 50 cm
Diameter (D) 10 cm 15 cm
Weight (W) 15 kg 20 kg
31
Actions to Meet RequirementsElement Discrepancy
Cause
Corrective
Action
LengthUse of discrete components
Special chips
Diameter Seeker antenna New detector
WeightDiscrete components,
battery
Reduce power requirements, use integrated circuits
32
Activities Required to Reduce LengthID Description Time
(Mo)Preceded by Expected
Length
A1 Analysis & Design 1 --- 50
A2 Breadboard Fabrication 2 A1 50
A3 Test 1 A2 50
A4 Modify Breadboard 0.5 A3 50
A5 Retest 0.5 A4 43
A6 Admin Lead Time 1.5 A1 ---
A7 Develop Chips 3 A5, A6, C5 43
A8 Test Chips 1 A7 40
33
A1 A2 A3 A4 A5
A6
A7 A8
1 2 1 0.5 0.5 3 1
1.5
From C5
1 3 4 4.5 5
2.5
8 9
Length Reduction Program
34
Length Reduction, No Interaction
0
10
20
30
40
50
60
0 1 2 3 4 5 6 7 8 9 10
Time, Months
Le
ng
th, c
m
35
Activities to Reduce Diameter
ID Description Time (Mo
Preceded By Expected Diameter
B1 Trade Offs 2 --- 15
B2 Subcontractor Lead Time 2.5 --- 15
B3 Prototype design & Fab 5 B1, B2 13
B4 Prototype Test 1 B3 13
B5 Redesign 3 B4, C5 13
B6 Retest 0.5 B5 10
36
B1
B2
B3 B4 B5 B6
2
2.5
5 1 3 0.5
2
2.5
7.5 8.5 11.5 12
From C5
Diameter Reduction Program
37
Diameter Reduction, No Interaction
0
2
4
6
8
10
12
14
16
0 2 4 6 8 10 12 14
Time, Months
dia
me
ter,
cm
38
Activities Required to Reduce WeightID Description Time (Mo) Preceded By Expected
Weight
C1 Trade Offs 2.5 --- 20
C2 Administrative Lead Time 1 C1, A1, B1, B2 20
C3 Design 1 C2 20
C4 Refine & Deliver 1 C3, A3, B4 20
C5 Integrate & Test 1.5 C4 17
C6 Administrative Lead Time 1 C5 17
C7 Delivery 2 C6 17
C8 Integrate & Test 2 C7 15
39
C1 C2 C3 C4 C5 C6 C7
2.5 1 1 1 1.5 1 2
2.53.5
4.55.5 7 8 10
C82 12
Weight Reduction Program
From A1From A3
From B1 From B2 From B4
40
Weight Reduction, No Interaction
0
5
10
15
20
25
0 2 4 6 8 10 12
Time, Months
We
igh
t, k
g
41
C1 C2 C3 C4 C5 C6 C7
2.5 1 1 1 1.5 1 2
2.53.5
4.59.5 11 12 14
C82 16
B1
B2
B3 B4 B5 B62
2.5
5 1 3 0.5
2
2.5
7.5 8.5 14 14.5
D2 D4 D5
8.52.5
11
15 13 10
20 17
15
A1 A2 A3 A4 A5
A6
A7 A8
1 2 1 0.5 0.5 3 1
1.5
1 3 4 4.5 5
2.5
14 15
D1 D3D6
1 4
11
50 43 40
Development Program
42
Length Reduction Comparison
0
10
20
30
40
50
60
0 2 4 6 8 10 12 14 16
Time, Months
Le
ng
th, c
m
43
Diameter Reduction, With Interaction
0
2
4
6
8
10
12
14
16
0 2 4 6 8 10 12 14 16
Time, Months
Dia
me
ter,
cm
44
Weight Reduction, with Interaction
0
5
10
15
20
25
0 2 4 6 8 10 12 14 16 18
Time, Months
We
igh
t, k
g
45
Effect of Variability on Schedule
• For the length reduction program:– Average time to achieve 43 cm = 5 months– 95% confidence band: 4.49 –5.51 months
• Assumes Normal Distribution of activity time and 10% coefficient of variation
• Activity time distributions are usually triangular (a,a,c)– Moves mean and right tail to the right
46
Time
Tech Parameter
95 % Confidence Regions
Parameter – Time Relationship
47
Cost
C = A + B*T
C = Activity cost
A = Fixed Cost
B = Expenditure RateT = Elapsed Time
48
1 2 3 4 5 6 7 8 9 10 11 12Activity RN Tbar Std dev T A B ES T LF Sum T C Sum C
1 A1 -0.10534 1 0.1 5 12 0 0.989466 0.989466 0.989466 16.87359 16.873592 A2 1.623725 2 0.2 5 12 0.989466 2.324745 3.314211 3.314211 32.89694 49.770533 A3 -0.64564 1 0.1 5 12 3.314211 0.935436 4.249646 4.249646 16.22523 65.995764 B1 -2.33173 2 0.2 5 12 0 1.533655 1.5336556 B2 -1.16468 2.5 0.25 5 12 0 2.20883 2.20883 2.20883 63.01192 63.011925 B3 1.512863 5 0.5 5 12 2.20883 5.756431 7.965261 7.965261 74.07718 137.08917 B4 0.928476 1 0.1 5 12 7.965261 1.092848 9.058109 9.058109 18.11417 155.20338 C1 -0.37803 2.5 0.25 5 12 0 2.405491 2.405491 2.405491 33.8659 33.86599 C2 -1.02047 1 0.1 5 12 2.405491 0.897953 3.303444 3.303444 15.77543 49.6413310 C3 -0.98917 1 0.1 5 12 3.303444 0.901083 4.204527 4.204527 63.24298 112.884311 C4 0.450058 1 0.1 5 12 9.058109 1.045006 10.10311 10.10311 17.54007 130.424412 C5 0.614575 1.5 0.15 5 12 10.10311 1.592186 11.6953 11.6953 24.10624 154.530613 C6 0.471922 1 0.1 5 12 11.6953 1.047192 12.74249 12.74249 17.56631 172.096914 C7 -0.66776 2 0.2 5 12 12.74249 1.866448 14.60894 14.60894 27.39738 199.494315 C8 -0.24237 2 0.2 5 12 14.60894 1.951527 16.56047 16.56047 28.41832 227.912616 B5 -0.11804 3 0.3 5 12 11.6953 2.964587 14.65989 14.65989 40.57504 195.778317 B6 3.841706 0.5 0.05 5 12 14.65989 0.692085 15.35197 15.35197 13.30502 209.083318 A4 -1.01906 0.5 0.05 5 12 4.249646 0.449047 4.698694 4.698694 10.38857 76.3843219 A5 -0.90231 0.5 0.05 5 12 4.698694 0.454885 5.153578 5.153578 10.45862 86.8429420 A6 -0.02406 1.5 0.15 5 12 0 1.496391 1.49639121 A7 -0.6049 3 0.3 5 12 11.6953 2.818529 14.51383 14.51383 38.82235 125.665322 A8 0.391379 1 0.1 5 12 14.51383 1.039138 15.55297 15.55297 17.46966 143.1349
Max time A Time B Time C Time A Cost B Cost C Cost Total Cost16.56047 15.55297 15.35197 16.56047 143.1349 209.0833 227.9126 580.1309
49
Max time A Time B Time C Time A Cost B Cost C Cost Total CostAVG 15.97062 15.01999 14.49016 15.97062 143.1657 204.0246 223.8933 571.0836SD 0.565504 0.629229 0.547394 0.565504 5.05307 7.084639 4.971504 12.03786
Estimated 16 15 14.5 16 143 204 220 567F(Est) 0.52072 0.487328 0.507168 0.52072 0.486923 0.498614 0.216778 0.36722Risk 0.47928 0.512672 0.492832 0.47928 0.513077 0.501386 0.783222 0.63278
Schedule and Cost Risk
50
Summary
• All activities affecting the desired end result and their interactions must be considered.
• Network representation takes care of this
• Activities must be considered at a low enough level to permit reasonable accurate time estimates
51
Summary (cont’d)
• Cost for development programs is a function of time
• There is variability in everything
• Variability can cause the critical path to change
• Plan for the occurrence of bad outcomes
52
Decision Environments
• Certainty
• Uncertainty
• Risk
53
Probability Refresher
54
Classical Interpretation
• N possibilities– Equally likely– One must occur– S of N possibilities = event “success”
• P[success] =S/N
55
Frequency Interpretation
• P[event] = proportion of the time event occurs over the long run
• Not very practical for situations that result in only one trial
56
Probability Axioms
Consider sample space S for events A, B, C … in S.
0 ≤ P[A] ≤ 1 for all A in S
P[S] = 1
If A and B are mutually exclusive,
P[A B] = P[A or B or both] = P[A] + P[B]
57
Theorem
If A is an event in finite S, and Ei, i = 1, 2, …n are events comprising A, then
nn EPEPEPEEEPAP ...... 2121
58
Theorem
If A and B are two events in S then
where is the common part of A and B
BAPBPABAP
BA
59
Total Probability
If Bi , i = 1, 2, …n, are mutually exclusive events, then
][][][1
n
i ii BPBAPAP
60
Conditional Probability
BPBAP
BAP
61
Bayes’ Theorem
• If Bi , i = 1, 2, …n, are mutually exclusive events, then
• P[Bi] are prior, or “a priori” probabilities and must be determined prior to some experiment that results in event A based on the nature of the problem, data, experience, or subjectively based on experience.
n
i ii
rrr
BPBAP
BPBAPABP
1
62
Expected Value
ni
i ii xpxxEV1
)()(
Discrete Distribution
dxxxfxEV )()(
Continuous Distribution
63
Subjective Probability
• Consider the following Events– Flip a coin and let it hit the floor. Before looking at the
coin, what is the probability it is “heads”?
– What is the probability that the coin flip before the 2009 Auburn/Alabama football game resulted in “tails”?
• Both events have occurred.The outcome is certain. The only uncertainty is in your mind; i.e., in your “degree of belief”
64
Subjective Probability Problems
• Same phrase has different connotations with different people
• Interpretation is context dependent
• People are uncomfortable doing it
• There is no “correct” value
65
Example
• You and a friend disagree on P[Your team will win its next game]. Discussion of factors, home advantage, injuries, weather, etc., does not result in agreement.
• How do you resolve the disagreement?
66
Assessing Subjective Probabilities
• Direct Inquiry– Just make an estimate based on knowledge and
perception– May not be able to come up with a value– May not have much confidence in the result
• Analysis of bets
• Comparison of Lotteries
67
Analysis of Bets
• Compare two bets• Look for indifference point• Example
– LA Lakers vs Boston Celtics– What do you think is P[Lakers Win]
• Bets– Win X$ if LA wins, lose Y$ if LA loses– Lose X$ if LA wins, win Y$ if LA loses
68
Analysis of Bets (Cont’d)
Bet for LA
Bet Against LA
LA wins
LA loses
LA loses
LA wins
X
-Y
-X
Y
Procedure:
Change X and Y until willing to take either bet.
69
Analysis of Bets (Cont’d)
• Expected Value
• At indifference EV should be the same
i ii ZPZZEV
YX
Yp
YpXpYpXp
YpXpAgainstLAEV
YpXpForLAEV
w
wwww
ww
ww
))(1())(1(
))(1()(
))(1()(
70
Example
10$,1$
1$,10$
YX
YX
8$,2$
2$,8$
YX
YX
5$,4$
4$,5$
YX
YX
9
4
45
4
wp
For LA
Against LA
For LA
Against LA
Indifferent
Round 1
Round 2
Round n
.
.
.
71
Reference Lottery
• Lottery 1– Win A if LA wins– Win B if LA loses
• Lottery 2 (Reference)– Win A with probability p– Win B with probability 1-p
72
Reference Lottery (Cont’d)
Lottery 1
Lottery 2Reference
LA wins
LA loses
1-p
p
A
B
A
B
Procedure:
Change p until willing to take either bet.
Outcome of lottery 2 is determined by a random process.
Choose p, generate a random variate, x, from U(0,1) distribution.
If x p then win A; otherwize, win B
73
Example
1.0
9.0
p
p
2.0
8.0
p
p
3.0
7.0
p
p
Round 1
Round 2
Round 3
Prefer lottery 2
Prefer lottery 19.01.0 p}
Prefer lottery 2
Prefer lottery 2
Prefer lottery 2
Prefer lottery 1 }
}
08.2.0 p
3.02.0 p
Home in slowly.Check for consistency with probability axioms and theorems.
74
Continuous Probability Distributions
• Strategies– Direct assessment of p– Fractile assessment of X
ix
ii dxxfxxPxF )()()(
Probability Distribution Function(Cumulative probability)
75
Direct Assessment
• Estimate range of values for x, xmin, xmax
• Pick value xi : xmin < xi < xmax
• Estimate • Repeat for a number of points (for 3 points pick
mid range, then mid range of the two segments unless distribution is strongly skewed)
• Use Reference lottery approach to find indifference
][ ixxP
76
Reference Lottery
Lottery 1
Lottery 2Reference
x<xi
x>xi
1-F(x)
F(x)
$1000
$0
$1000
$0
77
Example
Estimate time to get home from work
Min 20 min F(t)=0.00 25 F(t)=0.50 30 F(t)=0.70 35 F(t)=0.85Max 40 F(t)=0.95
Distribution Function
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
0 5 10 15 20 25 30 35 40 45
Time, Min
F(t
)
78
Fractile Method
• Pick range values for x: xmin, xmax
• Pick a number of fractiles– F(x)=0.05 Min– F(x)=0.95 Max– F(x)=0.50– F(x)=0.25– F(x) =0.75
• Note order• Use Reference lottery to find indifference
79
Reference Lottery
Lottery 1
Lottery 2Reference
x<xi
x>xi
1-p
p
$1000
$0
$1000
$0
80
Heuristics and Biases
• Representativeness
• Availability
• Anchoring and adjusting
• Motivational bias
81
Representativeness
• Judge that something or someone belongs to a particular category– Stereotyping– Insensitive to base rates and prior probabilities– Unreliable information– Failure to account for inherent uncertainty
• Misunderstanding random processes– Regression to the mean– Extreme outcomes likely to be followed by one closer
to the mean
82
Availability
• Judge P[event] according to ease of recalling similar events
• Influenced by unbalanced reporting
• Illusory correlation – pair of events perceived as happening together frequently
83
Anchoring and Adjusting
• Choose initial point then adjust about it• Affects continuous distributions more that
discrete probabilities• If initially estimate median will tend to
underestimate extremes so distribution is too narrow
• Estimate extremes first- the “worst” extreme before the other
84
Motivational Bias
Incentives often exist that motivate person to report forecasts or probabilities that do not reflect their true beliefs– Salesman forecasting sales– Weather forecasters forecasting rain– Program managers predicting lower cost,
shorter schedule, and low risk
85
Decomposition
• Break problem down to make probability assessment easier– Permits using people with subject matter knowledge
– More likely to get a realistic estimate
• Look at fault tree analysis and hazard analysis• Use laws of probability to reconstruct the problem• Very important concept for planning and
constructing mitigation efforts
86
Coherence
All assessed probabilities MUST obey the laws of probability
87
Using Test Results
• Requirements are often placed on characteristics that are stochastic– Reliability
– Accuracy
• Can use probability to estimate probability of not satisfying the requirement if test data exist
• Example: Impact accuracy of a projectile specified by the standard deviation of miss distance
88
Example• Requirement:• Data yield sample estimate S, sample size n where
• Recall
• Then
• Look up alpha in a table or use the chidist(chi,dof) function in Excel to find Alpha=0.067
• Alpha is the risk probability
3Re q
2
22
,1
)1(
Snn
10,4 nS
169
16*92,9
89
Chi Squared Probability Distribution Function9 DOF
0
0.2
0.4
0.6
0.8
1
1.2
0 5 10 15 20 25
X
1-al
pha
90
Value of Information
• Information reduces uncertainty– Toss a pair of dice and do not look at result– Estimate the probability that it is 7– If told it is not 5, does this change your
estimate?
• Information has a cost and a worth• Should never pay more than it is worth
91
Example*
A new manufacturing process has been developed. It will cost $0.5M to implement. It will save $0.5M over investment if implemented by your current vender. There are two other vendors willing to implement the process, but both require some relief from EPA regulations in order to provide savings, which could be least double those offered by the current vendor. No relief offers savings, but not as great as keeping the current vendor. It is known the EPA is re-examining these regulations and could either provide relief, make no change, or increase the requirements. The current vendor is not impacted regardless of any changes. An increase will cause a loss by both of the other vendors which you must reimburse.
* Based on an example in Making Hard Decisions, An introduction to Decision Analysis; PWS Kent, 1991; Robert T. Clemen
92
Payoffs
EPA Action
Vendor
Relief
P= 0.5
Same
P= 0.3
Increase
P=0.2
V1 $0.5 $0.5 $0.5
V2 $1.0 $0.2 -$0.1
V3 $1.5 $0.1 -$1.0
93
Decision Tree Structure
V1
V2
V3Relief
Relief
Same
Same
Increase
Increase
0.5
0.5
0.3
0.3
0.2
0.2
$0.5M
$1.0M
$0.2M
-$0.1M
$1.5M
$0.1M
-$1.0M
(0.5M)
($0.54M)
($0.58M)
(xxx)=EMV
94
Dilema
• Highest expected saving is obtained by choosing Vendor 3
• This choice also involves the highest potential loss– Risk probability is 0.2– Risk consequence is -$1.0 M– High Yellow
• How to mitigate?
95
96
Possible Actions
• Obtain Information– Re-estimate probabilities– Hire knowledgeable consultant
• Knows for sure
• Probably knows
• Questions:– What is information worth?– How reliable is the consultant’s result?
97
Perfect Information
(xxx)=EMV
$0.5
$1.0
$1.5
$0.5
$0.2
$0.1
$0.5
-$0.1
-$1.0
Relief0.5
Same0.3
Increase0.2
Perfect Information
NoInformation
($
($0.58MFrom previous analysis)
($1.0M)
EMVPI = $1.0M - $0.58M = $0.42M
V1
V1
V1
V2
V2
V2
V3
V3
V3
98
Imperfect InformationRelief
Same
Increase
Relief
Same
Increase
ReliefSame
Increase
Relief
Same
Increase
Same
Increase
Relief
Same
Increase
No Consultant
HireConsultant
“Relief”
“Same”
“Increase”
V3
V3
V3
V2
V2
V2
V1
V1
V1
$1.5M
$1.5M
$1.5M
$0.1M
$0.1M
$0.1M
-$1.0M
-$1.0M
-$1.0M
$1.0M
$0.2M
-$0.1M
$1.0M
$0.2M
-$0.1M
$1.0M
$0.2M
-$0.1M
$0.5M
$0.5M
$0.5M
($0.58M)
(xxx)=EMV
]Re"Re[ liefliefP ?
Relief
99
Problem
• Need to find conditional probabilities for chance events
• Solution– Total probability law– Bayes’ theorem
100
Solution
Total Probability
Where:R=ReliefS=SameI=Increase“R” denotes predict Relief, etc.
][]""[][]""[][]"["]"[" IPIRPSPSRPRPRRPRP
101
Bayes’ Theorem
]"["
][]""[]""[
RP
RPRRPRRP
102
Prior Conditional Probabilities
True EPA ActionPrediction Relief Same Increase P[prediction]"Relief" 0.80 0.15 0.20 0.485"Same" 0.10 0.70 0.20 0.300"Increase" 0.10 0.15 0.60 0.215Sum 1.00 1.00 1.00 1.00P[Action] 0.50 0.30 0.20
Posterior Conditional Probabilities
True EPA ActionPrediction Relief Same Increase P[prediction]"Relief" 0.8247 0.0928 0.0825 1.0000"Same" 0.1667 0.7000 0.1333 1.0000"Increase" 0.2326 0.2093 0.5581 1.0000
103
Imperfect InformationRelief
Same
Increase
Relief
Same
Increase
ReliefSame
Increase
Relief
Same
Increase
Same
Increase
Relief
Same
Increase
No Consultant
HireConsultant
“Relief”
“Same”
“Increase”
V3
V3
V3
V2
V2
V2
V1
V1
V1
$1.5M
$1.5M
$1.5M
$0.1M
$0.1M
$0.1M
-$1.0M
-$1.0M
-$1.0M
$1.0M
$0.2M
-$0.1M
$1.0M
$0.2M
-$0.1M
$1.0M
$0.2M
-$0.1M
$0.5M
$0.5M
$0.5M
($0.58M)
(xxx)=EMV
0.8247
0.1667
0.2326
0.485
0.300
0.215
0.8247
0.1667
0.2326
0.0928
0.0928
0.700
0.700
0.2093
0.2093Relief
0.0825
0.0825
0.1333
0.1333
0.5581
0.5581
($1.164M)
($0.835M)
($0.187M)
($0.293M)
-($0.188)
($0.219M)
($0.822M)
EMVI=$0.822M-$0.580M=$0.242M
104
Impact on Risk
• Probability of $1M loss reduced from 0.2 to 0.0825
• Risk changed from high yellow to low level
• Can pay consultant up to $0.242M
105
Problem• Using EMV may lead to solutions that may not be intuitively appealing• Example:
– A1 Win $30, p=0.5 EMV = $14.50
Lose $1, p=0.5– A2 Win $2000, p=0.5 EMV = $500
Lose $1000, p=0.5
• Choose A2 based on EMV
• What about Risk and Consequence?– Would probably rather have A1
106
Reason
• EMV is valid for the long run; i.e., multiple occurrences of the chance event
• This is a one time event
• Ignores the range of possible outcomes
• Play 10 times– Max loss A1 = $10– Max loss A2 = $20000
107
Solution
• Find a transformation of consequence into a utility measure, U
• Must accommodate attitude toward the risk/consequence combination– Risk averse– Risk taking– Risk neutral
108
Utility Functions
• Tabular
• Math functions
• Graph
)()(
1)(
)log()(
5.0xXU
exU
xxU
R
x
109
Risk AttitudesUtility Functions
0
0.2
0.4
0.6
0.8
1
1.2
0 20 40 60 80 100 120
Consequence, $
Uti
lity
Averse
NeutralSeeking
110
Scenario
• Forced gamble– Win $500, p=0.5– Lose $500, p=0.5
• Would you pay $x to get out of this gamble?– If so, you are risk averse
• Examples– Insurance– Ransom
111
Comment
• Not everyone is risk averse
• Many people are risk seeking over some range and risk averse over others
• Depends on wealth level (range of consequences)
• Risk attitudes are important in analyzing mitigation alternatives
112
Mixed Risk Attitude
0
0.2
0.4
0.6
0.8
1
1.2
0 10 20 30 40 50 60 70 80 90 100
Consequence, $
Uti
lity
Risk Seeking
Risk Averse
113
Transformation• Utility function transforms wealth (consequence) into a
measure that accounts for risk attitude• Certainty equivalent (CE)
– Gamble: Win $2000, p=0.5 EMV=$990 Lose $20, p=0.5
– Offered $300 for the gamble. Ask $301, won’t accept $299
• Then CE=$300 for this gamble• If CE ~ EMV then
– U(CE)=EMV($)– Can substitute U(x) for $x
• EMV – CE = Risk Premium
114
Utility Function AssessmentCE Method
1. Fix min and max values of wealth
2. Set U(min)=0, U(max)=1
3. Structure a lotterymin
max
CE1
0.5
0.5
4. Find CE1. Then
5.0)10(5.0(max)05.(min)5.0)( 1 UUCEUExample:
5.0)30($
30$,100$max,10$min
U
CE
115
CE Method (Cont’d)
5. Pick another range, say CE1 – max
6. Structure a new lottery
CE1
max
CE2
0.5
0.5
75.0)15(.5.0(max)5.0)(5.0)( 12 UCEUCEU
7. Set range 0 –CE1
8. Repeat 6. To obtain U(CE3) = 0.25
9. Stop or further subdivide the intervals
10. Either draw the curve or fit a function
116
Probability Equivalent (PE) Method1. Fix max and min of wealth2. Set U(min) = 0, U(max) = 13. Pick CE: min < CE < max4. Structure lottery
min
max
CE
1-p
p
5. Find p: CE ~ p(min) + (1-p)(max)
Then:
pppppUCEU )1)(1()0()(max)1((min))(
6. Repeat steps 3. – 5. For other values of CE
117
Risk Tolerance
Consider the utility function
max
1)(
011)0(
1)(
xx
as
xU
U
exU R
x
R determines shape
Larger R -> Flatter function
Smaller R -> more concave (risk averse)
Hence, R depends on risk attitude
118
Determination of R
Consider a lottery
Y
Y/2
0
0.5
0.5A1
A2
Find largest value of Y for which A1 > A2
R = YY
x
exU
1)(
R
x
eUE
1)(
To find CE, Find E(U) for the decision. Solve
For x = CE
119
Caveats
• Utilities do not add U(A+B) = U(A)+U(B)• Utilities do not express strength of preference.
– They only provide a numerical scale for ordering preferences
• Utility functions are not the same person to person– They are subjective and express personal preferences
120
Example Revisited
V1
V2
V3Relief
Relief
Same
Same
Increase
Increase
0.5
0.5
0.3
0.3
0.2
0.2
$0.5M
$1.0M
$0.2M
-$0.1M
$1.5M
$0.1M
-$1.0M
(0.5M)
($0.54M)
($0.58M)
$ U
1.5M 1.00
1.0M 0.86
0.5M 0.65
0.2M 0.52
0.1M 0.46
-0.1M 0.33
-1.0M 0.00
121
Utility Axioms
• Ordering and transitivityConsider events A1, A2, A3. Then
A1> A2, A2> A1, or A1~ A2
If A1> A2 and A2> A3, then A1> A3
• Reduction of compound uncertain eventsA DM is indifferent between compound uncertain events (a complicated mix of gambles and lotteries) and a simple uncertain event as determined using standard probability manipulations.
122
Example
A1
A2
E1
E2
E3
E4
E5
E6
E7
E8
E9
2
5
10.3
5
0
10.3
5
0
0.17
0.2
0.5
0.3
0.2
0.5
0.3
0.5
0.33
123
Example Continued
A1
A2
E1
E4
E5
E6
E7
E8
E9
2
5
10.3
5
0
10.3
5
0
0.17
0.15=0.5*0.3
0.066=0.33*0.2
0.165=0.33*0.5
0.099=0.33*0.3
0.1=0.5*0.2
0.25=0.5*0.5
124
Example Concluded
A1
A2
2
10.3
5
0
0.166=0.10+0.066
0.585=0.17+0.25+0.165
0.249=0.15+0.99
125
Axioms Continued
• ContinuityA DM is indifferent between outcome A and an uncertain event with outcomes A1 and A2 where A1>A>A2. Hence we can construct a reference gamble with p(A1) and (1-p)(A2) such that the DM is indifferent between A and the gamble
• SubstitutabilityA DM is indifferent between an uncertain event A and one found by substituting for A an equivalent uncertain event (gamble can be substituted for CE)
126
Axioms Continued
• MonotonicityGiven two reference gambles having the same possible outcomes, a DM will prefer the one with higher probability of winning the preferred outcome.
• InvarianceOnly outcome payoffs and probabilities are needed to determine DM’s preferences
• BoundednessNo outcomes are infinitely bad or infinitely bad
127
Comments
• There are some controversies and paradoxes regarding some of the axioms
• If you accept them then– There exist U1, U2, … , Un (utilities) with
associated payoffs such that the overall preference for uncertain events A and B can be determined by E(U)
– You should be using E(U) to make decisions (rational behavior)
128
Sensitivity Analysis
• To manage risk we need both probabilities and consequences
• Probabilities, utilities, and maybe consequences are likely subjective estimates
• Need to find out how much change will impact the decision
129
Example Problem Again
V1
V2
V3Relief
Relief
Same
Same
Increase
Increase
0.5
0.5
0.3
0.3
0.2
0.2
$0.5M
$1.0M
$0.2M
-$0.1M
$1.5M
$0.1M
-$1.0M
(0.5M)
($0.54M)
($0.58M)
$ U
1.5M 1.00
1.0M 0.86
0.5M 0.65
0.2M 0.52
0.1M 0.46
-0.1M 0.33
-1.0M 0.00
0.65
0.86
0.52
0.33
1.00
0.46
0.00
0.65
0.652
0.638
130
Change Utility for $1.0M
856.05.0
33.0*2.052.0*3.065.0
33.0*2.052.0*3.0*5.065.0
33.0*2.052.0*3.0*5.0)]2([
65.0)]1([
x
x
xVUE
VUE
131
Change in Probabilities
006.034.0
33.0*2.052.0*3.086.0*5.065.0
)52.086.0(33.0*2.052.0*3.086.0*5.065.0
33.0*2.0*52.052.0.*3.0*86.086.0*5.065.0
65.033.0*2.052.0*)3.0(86.0*)5.0()]2([
d
d
dd
ddVUE
132
Summary
• Risk management process• Cost and schedule risk
– Models– Monte carlo simulation
• Estimation of likelihoods• Analysis of mitigation alternatives• Value of information• Estimation of utility metrics• EMV vs Expected utility• Sensitivity analysis
Recommended