ViewPoint - Why Your Projects Are Late
Preview:
Citation preview
- 1. Why Your Projects are Late (and How to Prevent Them from
Being So) ViewPoint CCPM 1
- 2. Projects True? Its hard to get a project team to work
together Projects will be better if our resources are fully
utilized Start the project sooner, youll finish it sooner Planning
is the key to project success 2
- 3. What I Want to Share Successful projects are rare The core
reasons why A path forward 3
- 4. Project Failures are Commonplace 4 A staggering 39% of
projects with budgets over $10 million USD failed.
- 5. 5 PricewaterhouseCoopers reviewed 10,640 projects from 200
companies in 30 countries and across various industries Only 2.5%
of the companies successfully completed 100% of their projects
- 6. 6 Harvard Business Review Study of 1.471 IT projects The
average overrun was 27%, but one in six projects had a cost overrun
of 200% on average and a schedule overrun of almost 70%
- 7. 7 Projects often fail because organizations put more
emphasis on rational factors than on employees' psychological
engagement -- and the cost to organizations is enormous
- 8. When the emphasis is on procedures, compliance becomes a
substitute for results. 8
- 9. Dont Forget 9
- 10. 10
- 11. You are the new Director of Engineering - What is the
status of the project work? 11
- 12. Project Teams Cannot See 12 Where are we? Where is the
path?
- 13. Three Keys 13
- 14. Project teams dont work together. Is this collaboration?
Protecting reputations Defending original delivery promises Giving
reasons for why things havent quite worked out Talking about the
past 14
- 15. Project Team Members have Different Goals Resource
utilization? Earned hours? Budget compliance? Get promoted? Avoid
punishment? 15
- 16. It Doesnt Have to be Lose-Lose Resource utilization? Earned
hours? Budget compliance? Get promoted? Avoid punishment? 16
- 17. 17
- 18. To finish early, one should start early. 18
- 19. But, everyone starts early! 19 Heres the project
manager
- 20. Too much work creates confusion and loss of capacity.
20
- 21. Confusion Breeds Multitasking 21
- 22. Lets Play a Game! Well play two rounds. You just need a
piece of paper and a pen. First round: Write MULTITASKING Then
write 1234567890 Note the time Second round: Switch between letters
and numbers: Letter number letter number Note the time Check
quality 22
- 23. Multitasking Adds Excess Time 23 Day 42 Day 28 Task 1 Task
2 Task 3 12 days 12 days 12 days Setup Setup Setup Task 2 Task 3
Task 1 7 days 7 days 7 days 7 days Setup Task 1 Setup Setup Setup
Task 2 7 days Setup Task 3 7 days Setup Day 35
- 24. Conventional Approach to Projects 24 Make a Good Plan
Execute the Plan Success
- 25. Youre taking a trip. Which comes first? 25
- 26. Heres your car! 26
- 27. Build the Vehicle First Get control of the work Focus on
execution behaviors Use the team (or structure) that already exists
to make room for proper planning 27 Get Control Execute Well
Release Capacity Success
- 28. 3 Keys 28
- 29. Improve Visibility 1. Improve Teamwork and Collaboration
during execution 29
- 30. Align the Team 2. Establish a common goal for the team
30
- 31. Manage the Flow 3. Control the amount of work in the system
31
- 32. The First Step 32
- 33. Collaboration During Execution Provide visibility Focus on
the future Stop blaming and get moving Focus on the right things
Bust the bottlenecks Establish common goals Solving the teams
problems 33
- 34. Building Collaboration Accurate / shared assessment of the
situation The right people in the room Acting to achieve the goal
34
- 35. The Situation Must Be Obvious Accuracy Where are we now?
Shared Do we agree on it? 35
- 36. 36 Make it Visible Like This
- 37. OrLike This. 37
- 38. Focus on the Future 38
- 39. 39 Accelerate Flow Project X Project YY Project XX Project
Z Project Y Estimate Select Engineering Procurement Stopped!
- 40. The Second Step 40
- 41. Completing Projects is Behavior How to create the right
behavior to drive the project in the right direction? 41
- 42. Behavior is a Function of Consequences You have everything
you need to understand people What is the behavior? What are the
consequences of that behavior? 42
- 43. Show me how you measure me, Ill show you how Ill behave
("If you measure me in an irrational way, don't complain about
irrational behavior.") 43 Eli Goldratt
- 44. People do what they do because of what happens to them when
they do it Aubrey Daniels 44
- 45. What do we want our people to do? Move the project to
completion (as fast as possible) 45
- 46. Match Behaviors To Metrics 46
- 47. Metrics Tied to Governance 47 0 2 4 6 8 10 12 14 Jan Total
Feb Total March Total April Total May Total TPCounts Throughput
T4-T6-T8 by Month Higher is be er More Projects Completed Should I
act? Escalation of Work Stoppages Where to act? Getting More Done
in LessTime Should I act?
- 48. The Third Step 48
- 49. The Objective of the System? 49
- 50. Control the work in the system The Constraint sets the rate
for the entire system. 50
- 51. To Increase the Rate, Eliminate the Bottlenecks 51 Create
process momentum during execution Focused efforts to increase
velocity
- 52. Making a difference 52
- 53. Youre taking a trip. Which comes first? 53
- 54. Project Execution Maturity Model 54 Date Mgmnt. Schedule
Risk Delivery Promising Managing Bottleneck s Remote Collaboration
Priority Control Collaborative Execution Control WIP Functional
Alignment Probabilistic Planning Subcontractor Management Capacity
Management More Mature Less Mature
- 55. Basic Collaboration The work before you Near term The team
before you The process you own 55 Priority Control Collaborative
Execution Control WIP Functional Alignment More Mature Less
Mature
- 56. Improved Coordination Other teams Emphasize Velocity
Deliver on Time Medium Term 56 Date Mgmnt. Schedule Risk Delivery
Promising Managing Bottleneck s Remote Collaboration More Mature
Less Mature
- 57. Integrated Planning & Execution CCPM / Buffer
Management Detailed task management Finite resource planning Life
of project, full portfolio 57 Probabilistic Planning Subcontractor
Management Capacity Management More Mature Less Mature
- 58. Business Value by Maturity 58 Delivery Excellence
Developing Average Performance Basic Collaboration Improved
Coordination Integrated Planning & Execution
- 59. ViewPoint Critical Chain Results 433% increase in effective
capacity 326% increase in units shipped Lead-time reduced from 31
to 8 days Revenue increased $47MM 59
- 60. Datu Case - Collaboration 60
- 61. BP Case - Savings Project throughput increased 24% in 6
months $12,000,000 cost reduction 61
- 62. Why does project performance suffer? Lack of Collaboration
Too Much Work in Process Conflicting Goals 62
- 63. 3 Steps to Deliver More Projects On Time 1. Visual
Execution to facilitate collaboration 2. Common Purpose / Alignment
on the team 3. Control the amount of work in the system to maximize
flow 63 Were not driving cars, were managing traffic
- 64. Next Execution Maturity Benchmarking 64
- 65. Horace Wilcox 65
- 66. 66