49
Mashhad Urban Railway Operation Company

MUROC, Mashhad Urban Railway Operation Company

Embed Size (px)

Citation preview

Page 1: MUROC, Mashhad Urban Railway Operation Company

Mashhad Urban Railway Operation Company

Page 2: MUROC, Mashhad Urban Railway Operation Company

In the name Of God, The Compassionate, The Merciful

Page 3: MUROC, Mashhad Urban Railway Operation Company

Planning & Development Department

July 2016

MUROC Company Presentation

Page 4: MUROC, Mashhad Urban Railway Operation Company

Mashhad: spiritual Capital of Iran

Mashhad Transport Plan

Mashhad Urban Railway Operation Company(MUROC)

1

2

3

Contents

Presenter
Presentation Notes
Hello Everyone. First of all let me thank you all for coming here today. Let me Introduce myself. I am Abdullah Sarkhosh from Planning & Development Department. As you can see on the screen, our topic today is an MUROC company presentation and I am going to introduce our company. If you would like to know MUROC stands for Mashhad Urban Railway Operation Company.
Page 5: MUROC, Mashhad Urban Railway Operation Company

Chapter1:Mashhad: spiritual Capital of Iran

Page 6: MUROC, Mashhad Urban Railway Operation Company

Mashhad is located in northeast (NE) of Iran in Khorasan Razavi Province. Area :285 km2

Population: More than 3,134,408 Mashhad is second biggest city and spiritual capital of Iran.

Area = 285 Km2

Imam-Reza Holy Shrine

International Airport

Mashhad: Spiritual Capital of Iran

Mashhad

Ashgabat

Herat

Tehran

Page 7: MUROC, Mashhad Urban Railway Operation Company

Strategic Location Second largest religious city in the world

Historical background of 1200 years

Welcomes about 25 million domestic tourists

as well as 3 million international tourists per

year

Mashhad-Sanabad-Toos

818 AD (Martyrdom Of Imam Reza)

Location North-East of Iran

Altitude from sea level 985 m (3,232 ft.)

Temperature range -25C to +40C

Mashhad: Spiritual Capital of Iran

Presenter
Presentation Notes
Mashhad is the second most populous city in Iran. Its population is more than 3 million. The city is most famous and revered for housing the tomb of Imam Reza. Because of existence of the holy shrine of Imam Reza , the eight Imam of Shiites & other tourist attractions of this city , about 25 million domestic tourists as well as 3 million international tourists per year travel to Mashhad pay their tributes to Imam Reza..
Page 8: MUROC, Mashhad Urban Railway Operation Company

Chapter 2:Mashhad Transport Plan

Page 9: MUROC, Mashhad Urban Railway Operation Company

Long Term Population Estimation of Mashhad(2031)

Estimated population in Mashhad 253 traffic regions in 2026S Shaped logistic Growth curve

Mashhad has 13 municipal zones

Page 10: MUROC, Mashhad Urban Railway Operation Company

Demography & Transportation Statistics

3.5Million daily trips in 2004 Million Population

3.13 6.25 1.2% Annual GrowthMillion Daily Trips(2015)

7.5Million in 10 years

(By 2025)

Presenter
Presentation Notes
I would like to proceed with more detailed statistics on transportation in Mashhad. The metropolitan area falling under the responsibility of the Metropolitan Municipality is 285 km2, with a population of 3.13 million. Annual population growth is approximately 1.2%. This population generates near 6.25 million trips everyday in the area in question (this figure was 3.5 million in 2004). Number of daily trip is estimated to increase to 7.5 million trips a day in 10 year.
Page 11: MUROC, Mashhad Urban Railway Operation Company

Transportation Statistics

Cars per 1000 residents96 in 2006

247

Vehicles(cars, vans and taxis)230,000 in 2006

126 New vehiclesAdded to the roads everyday

735,000

705.2km Network

QuantityIndex

6,245, 396Number of Daily Motorized Trip

765,739Number of Daily Motorized Trip in Morning Peak hours

2797Number of Bus Fleet

2202 kilometerBus Network length(urban, suburban and night shift)

13274Number of Taxis

133 LineNumber of Taxi Lines

4 lines(85 Km)Number of Approved Railway Lines

1 line(24 Km)Number of Railway Lines in Operation

Presenter
Presentation Notes
There are 735,000 vehicles throughout the metropolitan area which circulate on the roads. We’ve got around 126 new cars joining the traffic everyday, and this figure tends to increase day by day because it’s becoming increasingly easyier to buy an automobile. The transportation network length currently amounts to 705.2 kilometers. Car ownership per 1.000 residents is 247 automobiles, which is growing as more and more people are better off in Iran. This figure is still quite low when compared to other countries such as USA (812/1.000), Italy (656/1.000), Japan (599/1.000) France (576/1.000), Spain (564/1.000) Germany (586/1.000), UK (515/1.000) (figures for the year 2002). But here we should note that the figure was only 96 in the year 2006. So, this is the time to solve this traffic problem, and past experience as well as the case of huge metropolises show that, no matter how large and long are the roads you build, you’l not be able to solve the traffic congestion problem, unless you create a backbone transport network which is based on railways. That’s why the Municipality’s strategy is to build high-capacity lines throughout the city.
Page 12: MUROC, Mashhad Urban Railway Operation Company

Mashhad Urban Road Network in 2015

Type of Road Length

Highways 65.1 Km

Ramps and Loops 35.2 Km

Principal(major) Arterial 134.6 Km

Minor Arterial 252.4 Km

Collector 217.9 Km

Page 13: MUROC, Mashhad Urban Railway Operation Company

Trip Objectives Share in Residents’ Daily Trips in an Ordinary Day in 2015

Work29%

Education20%

Shopping13%

Leisure13%

Personal10%

Pilgrimage5%

Way Back Home10%

Work Education Shopping Leisure Personal Pilgrimage Way Back Home

Trip Objective Number of Trip

Work 1,795,889

Education 1,216,315

Shopping 835,938

Leisure 837,659

Personal 616,700

Pilgrimage 307,859

Way Back Home 635,034

Overall 6,245,396

Page 14: MUROC, Mashhad Urban Railway Operation Company

Personal Vehicles(55.85%)Taxis(22.04)

Buses(including BRT system),Privately-owned public buses, Minibuses(20.46)

Road System 98.35 %

MUROCRail System 1.65 %

Rail, 1.65

Bus & Mini Bus, 20.46

Taxi, 22.04

Personal vehicles,

55.85

Transportation Modes (2015)

Public transportation share: 44.15%Commuting Rate: 1.99 per person

Presenter
Presentation Notes
Statistical figures about transportation in Mashhad in general are as follows: The road system currently accounts for about 98.35 percent of overall transport in Mashhad. This includes the elements of private cars, buses(including the BRT system), privately-owned public buses, minibuses, taxis, bicycles and pedestrians. The share of rail-based transportationion is currently about 1.65 percent. In line with Mashhad’s Transport Master Plan for 2021, the future vision of the Municipality consists in changing the balance in favor of the second one—increasing the share of rail-based modes up to more than 10 percent, in order to have a sustainable, liveable city. As for Mashhad’s future vision in railways: As I explained before, Mashhad urgently needs high-capacity railway systems to meet the increasing mobility needs within the city. Mashhad Municipality has dedicated an important section of its investment budget to transport projects. Thanks to that, only for the time being, we have about 35 kilometers of new railways under construction.
Page 15: MUROC, Mashhad Urban Railway Operation Company

The use of public transportation should be raised up to 75% in 2020 based on the Master Plan within the city

Expected Use (2020)Current UseType of Transportation

40 %20.46%Bus

25 %22.04%Taxi

10 %1.65%Rail based transport

Master Transportation Plan of Mashhad - 2021

Page 16: MUROC, Mashhad Urban Railway Operation Company

Goals of Mashhad Transportation Development

Mission: planning, monitoring and management of transportation and traffic in Mashhad Improving Mobility Comfort

Improving Reliability of Transportations

Creating a link for further opportunities

Improving Safety and Security

Reducing Environmental Threats

Reducing the costs of Transportation Systems

Adaptation of Transportation System to Culture

Page 17: MUROC, Mashhad Urban Railway Operation Company

Traffic Decision Procedures in Iran & Mashhad

Khorasan RazaviPolice

MashhadMunicipality

High Council of Traffic Coordination

Khorasan Razavi Council of Traffic

Coordination(Strategy)

Khorasan Razavi Traffic Police Enforcement Transportation & Traffic

Deputy of Mayor

Interior Ministry

Presenter
Presentation Notes
High Council of Traffic Coordination Approval is necessary before implementation: Traffic management policies Plans and measures developed by Traffic & Transportation Organizations Transportation & Traffic Deputy of Mayor Similar to other high populated Iranian cities, Mashhad has a Deputy Mayor responsible for traffic and transportation policies and measures. �
Page 18: MUROC, Mashhad Urban Railway Operation Company

Hierarchy of Policy-Making Members of Public Transportation in Mashhad

Mashhad Urban Railway

Operation Company (MUROC)

Municipal organization & companies responsible for traffic and public transportation under

Transport & Traffic Deputy Mayor

Bus TerminalOrganization

(BTO)

Taxi Management Organization

(TMO)

Public Buses Organization

(PBO)

Mashhad Transportation

and Traffic Organization

(MTTO)

Municipal companies responsible for construction of railway projects under

Technical & Civil Deputy Mayor

Mashhad Urban

Railway Corporation

(MURCO)

Inter-urban Freight

Transportation Management

Elite Intelligent Traffic Company

Coordination, Planning and Supervision

Management

Studies and Planning of

Transportation System

Management

Transport and Traffic

administrative department in

each of 13 municipality

zone

Presenter
Presentation Notes
The MTTO under the Deputy Mayor Coordinates Institutional arrangements for: Traffic management strategy Planning & Modeling Design Implementation Plans will be prepared by followings: Key policies for traffic and transportation which are approved by the High Council of Traffic in Coordination with: Transport vision for Mashhad in 2021 6th Five Year Development Plan (SFYDP)(2016-2020) Mashhad Traffic Control Center(MTCC) Established in 2000 as the agency responsible for Mashhad Traffic Management with following objectives: To improve the flow of traffic and reduce delays, To minimize congestion while maximizing the movement of people and goods, To reduce air pollution, To reduce fuel consumption, To maximize the safety and efficiency, To provide users with useful information, To provide a means of aiding users who encounter problems Taxi management organization responsibilities: Management and supervision Issuance of taxi licenses Training and education for taxi drivers Supervision of taxi drivers Monitoring costs & revenue, and defining taxi fare
Page 19: MUROC, Mashhad Urban Railway Operation Company

Mashhad Transport Master Plan 2021 Mashhad’s Master Plan of Transportation 2021 Trip Attraction Diagrams

Mashhad’s Master Plan of Transportation in 2021

Page 20: MUROC, Mashhad Urban Railway Operation Company

Master Plan- Mashhad Transport In 2021c

Results of Studies Conducted By Sharif University

Page 21: MUROC, Mashhad Urban Railway Operation Company

Urban Transit Study

Comprehensive Public Transportation Plan Developed by Sharif University of Technology Mashhad Transportation: 1994 to 1996 Complementary research of Railway Transportation : 2002 to

2004

Presenter
Presentation Notes
Mashhad Comprehensive Public Transport Plan Urban train systems spread all over the world. In the holy city of Mashhad in Iran, municipal authorities provided preliminary design studies in 1991 which led to the preparation of Mashhad Transportation Services in early 1994 by the Transportation Studies Center of Sharif University of Technology. Comprehensive studies of Mashhad transportation between 1994 and 1999 and Complementary research of railway transport between 2002 and 2004 was conducted by the Institute of Transportation, Sharif University of Technology. Based on researches approved by the Traffic Council of State and stated in Traffic Supreme of Iran cities, Mashhad needs 4 metro lines. According to existence of new cities such as Golbahar in the north and Binalud in south, after some researches, the development of subway lines in these cities was also expected and its ratification process has been done. After analyzing various options and studies, the best route got a priority which was from the end of the Fadayian Islam street (Nakhrisi) to the end of Vakil Abad Boulevard; because, based on estimates for the year 2016, Demand for travel by public transport on this route is so large that the number of passengers in each direction during peak hours is over 17,000 and to respond to this demand, a rail system of LRT train urban style with adequate capacity which meets the technical specifications, is required.
Page 22: MUROC, Mashhad Urban Railway Operation Company

Line 1Line 3

Line 2Line 4

Mashhad Urban Railway Networks

Total: 4 Lines 85 Km 76 Stations

Line 1: 24 Km length / 24 station

Line 2: 15 Km length / 13 station

Line 3: 28.5 Km length / 24 station

Line 4: 17.5 Km length / 15 station

Line 5: (Monorail Ring belt) 46 km - study phase

Presenter
Presentation Notes
Line 1: South-East to West: From Airport to Vakil Abad 24 km Line 2: North to South: Kouhsangi to North Tabarsi 15 Km Line 3: North to East: Amiriyeh to Abouzar town 28.5 Km Line 4: South to North-West: Shahid Rajaee district to tomb of Khajehrabi 15 Km Line 5: Monorail ring around Mashhad City 46 Km
Page 23: MUROC, Mashhad Urban Railway Operation Company

Specification Line 1 Line 2 Line 3 Line 4 TotalTotal length(km) 24 15 28.5 17.5 84.9

Number of Stations 24 13 24 15 76Railway system type LRT Metro Metro Metro N.A

Number of fleet required 160 140 140 140 580

Current number of fleet 60 - - - 60

Passenger capacity(in 16 hours) 170,000 512,000 512,000 304,000 1,498,000

Designated headway 2.7 3 3 3 N.A

Mashhad Urban Railway Networks

0

5

10

15

20

25

30

Line 1Line 2Line 3Line 4

24

14.9

28.5

17.5

One Metro line will be lunched approximately every 5 years over a 15 year period

Page 24: MUROC, Mashhad Urban Railway Operation Company

1992 • start of invistigation about Comprehensive Public Transport Plan of Mashhhad

1994 • Institute of Transportation, Sharif University of Technology started studies

1995 • Establishment of MURCO

1998 • Studies of Institute of Transportation, Sharif University of Technology finished

2000 • Commencement of Construction of Line 1

2002 • Development research of Railway Transport started by Institute of Transporation

2004 • Institute of Transporation finished Development research of Railway Transport

2005 • Selection of Project Management & Detailed design of other lines

2005 • Establishment of MUROC

2009 • Basic Design of lines 2,3 & 4 was finished

2009 • Construction of line 2 started

2011 • Operation of line 1 started

2012 • Construction of line 1 extension to the Airport with 5 kilometers length started

2015 • Construction of line 3 started

2016 • Operation of line 1 Extension started

Key Events in Mashhad urban rail

Page 25: MUROC, Mashhad Urban Railway Operation Company

Chapter3: Mashhad Urban Railway Operation Company(MUROC)

Page 26: MUROC, Mashhad Urban Railway Operation Company

MURCO and MUROC

MUROCMURCO

Presenter
Presentation Notes
MURCO(Mashhad Urban Railway Corporation) is the authority that tenders, constructs and commissions the new railway lines in the city. MUROC takes over new lines once they are commissioned by the MURCO.
Page 27: MUROC, Mashhad Urban Railway Operation Company

z

Earnings per Passenger

% Metro's share of total urban travel

Safety

% Passenger Satisfaction

% Revenues from annual

budget

Line Productivity % Trip

Punctuality

Vision and Mission

Page 28: MUROC, Mashhad Urban Railway Operation Company

Thisproject includesadeeptunnel15-Km routewith13stationswhichextends fromtheendof Tabarsi Boulevard innorthtoFakouri Boulevard insouth ofMashhadasa MetroLine. Muchof the route isconstructed inundergroundanddrillingofthis section was done by 2 tunnel digging machine called the Tunnel Boring Machine (TBM) in one of the busiestcorridorsof thecity.The basic design studies for Mashhad metro line 2 was accomplished by joint effort of project's main local consultant"Pajoohesh" and French consultant "Systra". Twelve groups of qualified engineering consultants assisted the mainconsultant in preparation of basic studies such as topographical and geotechnical studies, civil design, traffic studies,urbanutility tracing, trackdesign,rollingstockfunctionalspecification,bio-ecoandvalueengineering.Thepreliminarydesignof line 2 hasbeen carriedout and acall for international tender (E.P.C) was launchedanda localGeneralContractor(GE)wasappointed.Currently tunnel construction by TBMs is finished. The contract for building rolling stock is signed and the first delivery ofrollingtockwillbedueearly2016.

Line 2

A2

B2

C2D2

E2F2

G2H2

I2J2

K2

L2

Page 29: MUROC, Mashhad Urban Railway Operation Company

Line 2 of Mashhad Urban Railway- Specifications

Length 15 KM (TBM Tunnel)

Number of Stations 13 Stations

System Capacity 24000 Passengers per Hour per Direction

Signaling Fixed Block

DepotOne depot near A2 Station

Overhaul capacity of Line 2 & 3400,000 m2

Operation Control Center One O.C.C. on M2 Station

Headway 180 Sec.(Can be decreased to 120 Sec.)

Rolling Stock

20 Train (100 Cars)DC 750 V 3rd Rail

Length of each car: 20 MCapacity of each train: 800 passengers

Power Supply 4 Passage Posts (132/20 KV AC)8 Traction Posts (750 V DC)

Page 30: MUROC, Mashhad Urban Railway Operation Company

Line 2 construction

Page 31: MUROC, Mashhad Urban Railway Operation Company

Total length of the route will be 28.5 kilometers fromend of Amirieh St. to Shahrak E Abouzar.Length of the route in Phase 1: 11.5 km from FerdowsiBlvd. to the Passenger Bus Terminal.Total number of stations: 24 stationsNumber of stations in Phase 1: 12 stations

Line 3

Presenter
Presentation Notes
The progress of operations : Agreement with Astan Ghods Razavi and start digging in the 40-hectar shaft ground with T.B.M in northeastern corner of Ferdowsi Square Building the walls of shaft area and then mobilization of construction sites and construction of the shaft, are in progress. Ongoing operations: Disassembling one of digger machines (TBM) of line 2, located in the Saadi Square and transfering it to the shaft of line 3 Mobilization of digger machine (TBM) shaft site and preparation of segmentation factory in order to manufacturing tunnel segments of line 3 In 4 phases
Page 32: MUROC, Mashhad Urban Railway Operation Company

Line 3 of Mashhad Urban Railway- Specifications

Length 28.5 KM

Number of Stations 24 Stations

System Capacity 24000 Passengers per Hour per Direction

Signaling Fixed Block

Depot One depot at the end of the line250,000 m2

Operation Control Center One O.C.C. at the end of the line

Headway 180 Sec.(Can be decreased to 120 Sec.)

Rolling Stock

35 Train (175 Cars)DC 750 V 3rd Rail

Length of each car: 20 MCapacity of each train: 800 passengers

Power Supply 5 Passage Posts (132/20 KV AC)13 Traction Posts (750 V DC)

Page 33: MUROC, Mashhad Urban Railway Operation Company

17.5 km from the end of the Khaje Rabi Street to Shahrak-e-Shahid RajayiTotal number of stations: 15 stations

Line 4

Presenter
Presentation Notes
Design operation improvements: Studies of phase 1 is in progress . Location of stations has been approved in the Supreme Council of Traffic on 2015/03/09. As depot of line 4 is next to the depot of line 2, increasing the route in northern part and establishment of a station in Shahrak-e-Shahid Rajayi in the western part of the line 4 have been proposed which is in investigation step.
Page 34: MUROC, Mashhad Urban Railway Operation Company

Length 14 KM

Number of Stations 15 Stations

Headway 180 Sec.(Can be decreased to 120 Sec.)

The first design phase is just beginning to develop

Line 4

Page 35: MUROC, Mashhad Urban Railway Operation Company

MUROC: Mashhad Urban Railway Operation Company

MUROC is an affiliated company of Mashhad Municipality established in 2005 The company currently operates 1 urban railway lines of 24 Km

After lunching Line 1, Mashhad became the second city of Iran which entered railway transportation system In February 2nd, The 4.5 Km extension of Line 1 with 2 stations (including HashemiNezhad international Airport) Was

lunched and Mashhad became the first Iranian city which connect it’s railway lines to it’s Airport.

Presenter
Presentation Notes
MUROC is an affiliate company of Mashhad Municipality and was established in 2005 for operating the urban railway network in the metropolitan area. The company currently operates 1 urban railway lines of 19 km. With inauguration of line 1, Mashhad became the second city of Iran which entered railway transportation system. It is a private company and is subject to the Iranian Commercial Laws. All managers including the Directing Manager as well as all employees are recruited under competitive private sector conditions. Only the members of the Board of Directors are appointed from among current bureaucrats of the Municipality. The Company’s purchases are subject to the Public Procurement Law. In February 2th, The 4.5 Km extension of line 1 with 2 station(including HashemiNezhad international airport) Was inaugurated and Mashhad Became the first Iranian city which connect it’s railway lines to it’s Airport.
Page 36: MUROC, Mashhad Urban Railway Operation Company

Mashhad won UITP regional Award for customer service in May 2013 only aftertwo and a half years of revenue service.

Customer Service Award

Presenter
Presentation Notes
Winning the “high quality of consumer services” award: Alongside 80 cities from 30 countries of the 5 continents in the world, Mashhad, as the second largest city and the spiritual capital of Iran with population of over 3 million people, has joint the campaign “Grow with Public Transport” for developed transportation systems, and will continue to expand its contribution toward public transportation in Iran. With operation of line 1, Mashhad Urban Railway Operation Co. won the “costumer service award” in Biennial congress of UITP in 2013 Zurich, Switzerland.
Page 37: MUROC, Mashhad Urban Railway Operation Company

Human Resources

Employment~341 Employees

~ 675 outsource contract personnel

Qualified Engineers Skilled Labor90 Technical Staff

26%

55%

4% 15%

TechnicalOperationManagementSupport

Presenter
Presentation Notes
Currently, we have about three hundred forty employees and we outsourced maintenance, station cleaning and security. Our technical workforce consist of about 90 people which oversee maintenance contracts, new construction projects , …
Page 38: MUROC, Mashhad Urban Railway Operation Company

Certificates

Total Quality ManagementHealth and Safety Management

Environmental Management

European Foundation for Quality

Management

Information Security management system

Presenter
Presentation Notes
As for our approach to quality, we are adopting the Integrated Quality Management System of ISO 9001-2014, Health and Safety management OHSAS 18001 and Environmental Management ISO 14001. As for Information Security management system, we adopt our efforts with ISO 27001(ISMS).Also for about six month, we have the ongoing project of EFQM Excellence Model(similar Iranian Standard called Taali Sazmani), which will help us be more competitive and establish appropriate management systems to attain excellence.
Page 39: MUROC, Mashhad Urban Railway Operation Company

Annual Ridership Figures

110,000 Daily RidershipMore than 150 million passengers in total

0

5000000

10000000

15000000

20000000

25000000

30000000

35000000

40000000

2016 - Q120152014201320122011

9167765

37,047,714

32,641,77530,828,379

25,882,611

4,837,731

Annual Ridership Figures

Presenter
Presentation Notes
Under normal circumstances, we have approximately 8 percent increase in the ridership every year. Throughout the operation of line, we carried a total of more than 150 million passengers.
Page 40: MUROC, Mashhad Urban Railway Operation Company

Fare Collection System

Contactless ManCard

RFID TechnologyChargeable

Integrated Ticketing Systemfor all transportation modes

Contactless(LRT station only) Multi trip2,6,10 trips

Presenter
Presentation Notes
For the entire transport system of Mashhad, we have an integrated smart ticket called ManCard. It’s valid for all transport modes within the city.
Page 41: MUROC, Mashhad Urban Railway Operation Company

Number of Employees 343Approach Maximum OutsourcingLine length 24 Km

Limited revenue operation since 21st of February 2011Number of active vehicles 60

Present timing 06:00 am to 22:00 pmCurrent Headway in peak hours 4.5 min

Designed Headway(160 vehicles) 2.7 minComplete journey time 55 min

Number of stations 24 stationsDaily ridership 100,000 passenger/day

Line 1 Operation

Page 42: MUROC, Mashhad Urban Railway Operation Company

Track Gauge on a Straight Line 1435mm

Minimum Vertical Bending Radius 1000m(depot)

Lateral Bending Radius (ground) 300m

Lateral Bending Radius (depot) 25m

Maximum Slope 40‰

Traction Power Supply Voltage DC 750V

Length 29700mm

Material of Car body Carbon steel

New Wheel Diameter 660 mm

Maximum Operating Speed 80 km/h

Service Speed 34.5 km/h

Max. Acceleration 1.14m/s2(0-35km/h)

Rolling stock

Page 43: MUROC, Mashhad Urban Railway Operation Company

One vehicle is composed of two articulated modules, 60 cars Procured in total. Contract concluded on 11th September 2008.

First delivery: December, 2010.Last delivery: December, 2011.

Rolling stock

Page 44: MUROC, Mashhad Urban Railway Operation Company

Stations

Side platformsLength of platforms 90 m

Weather protection64 lifts of gearless type for 6 m

vertical travel

Page 45: MUROC, Mashhad Urban Railway Operation Company

Stations

Page 46: MUROC, Mashhad Urban Railway Operation Company

Stations Cultural Symbols

Page 47: MUROC, Mashhad Urban Railway Operation Company

Stations Cultural Symbols

Page 48: MUROC, Mashhad Urban Railway Operation Company

Summary

We Operate Traffic

Stations

We Maintain Facilities

Rolling Stock

On time, even before

We TrainTechnical staff

Drivers

Presenter
Presentation Notes
So, to summarize what we do: We can plan and start up any operations. We operate and maintain the system. Also we provide training services for divers & technical staff.
Page 49: MUROC, Mashhad Urban Railway Operation Company

Thank You For Your Attention

Ghadir boulevard, Mashhad, IranP.O.box: 91735-486

+98 915 525 8143+98 513 303 0629

+98513 342 33 11

[email protected]