11
Page 1 Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only O P E N A C C E S S Vol. XXVI October 2012 www.reconnectenergy.com Dear Readers, REC prices remained at floor price due to the large gap in supply and demand. This trend has persisted for the last several months now. Even with recent pronouncements by the Ra- jasthan High Court (covered in September newsletter) and some action by state ERCs, demand fell this month compared to last month. At the same time, supply is continuing to in- creasing with over 5 lakh RECs being issued every month. After the end of the trade ses- sion, close to 13 lakh RECs remain unsold – this is more than 5 month supply at current demand levels. In October, CERC came out with the order on UP Co-gen plants. The order lays down several principles which further clarify the eligibility of RE generators for REC mechanism. However, several questions still remain before RECs can be issued to UP Co-gen plants. Our main arti- cle provides a detailed analysis. Several states have also been coming out with their solar policies. This month we analyze the TN solar policy. As always, detailed trading statistics, analysis and regulatory updates are available in this newsletter. Happy reading and we look forward to hear- ing feedback from you. Team REConnect REConnect Energy India’s Largest Green Credits Trading Company The verdict by CERC on eligibility for REC of UP Sugar Co-Gen From Management’s Desk Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen The CERC recently gave its order in the long standing issue on RECs issuances to UP sugar plants. The order is important as it sheds light on eligibility of RECs, particu- larly in the case of self-consumption, and is also likely to have a significant impact on the RECs markets (over 650 MW capacity of sugar mills is registered in the RECs mechanism from UP alone). The important points that CERC considered were: Eligibility of UP Co-gen plants for RECs for the self-consumption portion Roles and responsibility of SLDC Various other miscellaneous clarifications on points raised by UP SLDC. The key outcome of the order is that in case a RE generator does not consume 51% or more of the power generated, such a generator cannot be classified as a captive power plant (CPP). Such a generator will be considered as any other RE generator supplying electricity to a consumer. The self-consumption portion of the power will be eligible for RECs provided no benefits that are available to CPPs are claimed. In case such benefits are availed, they will have to be foregone. In UP, electricity duty is waived on all CPPs since 1998. Eligibility for RECs based on the order can be summarized as below (specifically in the case of UP): 2200 MW+ 2200 MW+ 2200 MW+ 2200 MW+ Portfolio under REC 16 States 16 States 16 States 16 States Projects under REC Over 50% Over 50% Over 50% Over 50% Market Share in REC Trade 7 States 7 States 7 States 7 States Physical Presence 51% or more power is consumed in-house Avails Electricity duty waiver Not eligible 51% or more power is consumed in-house Does not avail Elec- tricity duty waiver or other concessional benefits Eligible for RECs This is unlikely in UP as ED waiver has been available to all CPPs since 1998 Less than 51% of power is consumed in -house Avails Electricity duty waiver Eligible for RECs only after foregoing ED waiver See ‘open ques- tions’ section be- low Less than 51% of power is consumed in -house Does not avail Elec- tricity duty waiver or other concessional benefits Eligible for RECs

Re connect newsletter xxvi

Embed Size (px)

Citation preview

Page 1: Re connect newsletter xxvi

Page 1

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

OOOO

PPPP

EEEE

NNNN

AAAA

CCCC

CCCC

EEEE

SSSS

SSSS

Vol. XXVI October 2012

www.reconnectenergy.com

Dear Readers,

REC prices remained at floor price due to the

large gap in supply and demand. This trend

has persisted for the last several months now.

Even with recent pronouncements by the Ra-

jasthan High Court (covered in September

newsletter) and some action by state ERCs,

demand fell this month compared to last month.

At the same time, supply is continuing to in-

creasing with over 5 lakh RECs being issued

every month. After the end of the trade ses-

sion, close to 13 lakh RECs remain unsold – this

is more than 5 month supply at current demand

levels.

In October, CERC came out with the order on

UP Co-gen plants. The order lays down several

principles which further clarify the eligibility of

RE generators for REC mechanism. However,

several questions still remain before RECs can

be issued to UP Co-gen plants. Our main arti-

cle provides a detailed analysis.

Several states have also been coming out with

their solar policies. This month we analyze the

TN solar policy.

As always, detailed trading statistics, analysis

and regulatory updates are available in this

newsletter.

Happy reading and we look forward to hear-

ing feedback from you.

• Team REConnect

REConnect Energy India’s Largest Green Credits Trading Company

The verdict by CERC on eligibility for REC of UP Sugar Co-Gen

From Management’s Desk

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

The CERC recently gave its order in the long standing issue on RECs issuances to UP

sugar plants. The order is important as it sheds light on eligibility of RECs, particu-

larly in the case of self-consumption, and is also likely to have a significant impact

on the RECs markets (over 650 MW capacity of sugar mills is registered in the RECs

mechanism from UP alone).

The important points that CERC considered were:

•Eligibility of UP Co-gen plants for RECs for the self-consumption portion

•Roles and responsibility of SLDC

•Various other miscellaneous clarifications on points raised by UP SLDC.

The key outcome of the order is that in case a RE generator does not consume 51%

or more of the power generated, such a generator cannot be classified as a captive

power plant (CPP). Such a generator will be considered as any other RE generator

supplying electricity to a consumer. The self-consumption portion of the power will

be eligible for RECs provided no benefits that are available to CPPs are claimed. In

case such benefits are availed, they will have to be foregone.

In UP, electricity duty is waived on all CPPs since 1998.

Eligibility for RECs based on the order can be summarized as below (specifically in

the case of UP):

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

51% or more power is

consumed in-house

Avails Electricity duty

waiver

Not eligible

51% or more power is

consumed in-house

Does not avail Elec-

tricity duty waiver or

other concessional

benefits

Eligible for RECs This is unlikely in

UP as ED waiver

has been available

to all CPPs since

1998

Less than 51% of

power is consumed in

-house

Avails Electricity duty

waiver

Eligible for RECs

only after foregoing

ED waiver

See ‘open ques-

tions’ section be-

low

Less than 51% of

power is consumed in

-house

Does not avail Elec-

tricity duty waiver or

other concessional

benefits

Eligible for RECs

Page 2: Re connect newsletter xxvi

Page 2

www.reconnectenergy.com

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

This order leaves some questions unanswered:

• If a RE generator is determined to be not a CPP and foregoes the benefits available to CPP, will they be immediately eli-

gible for RECs or will the 3 year restriction apply?

A simple reading of the order does not provide any answer to this. In our opinion the 3 year restriction may not apply as in

the CERC regulations pertaining to eligibility, the 3 year restriction is a clause specific to CPPs.

• Determination of CPP - Electricity Rules provides that

“no power plant shall qualify as a ‘Captive Generating Plant’ unless 26% of the ownership is held by the captive user

(s) and not less than 51% of the aggregate capacity generated in such plant, determined on annual basis, is

consumed for the captive use.” (emphasis supplied)

According to this definition, the status of a power plant as CPP or otherwise needs to be determined on the basis of its an-

nual power generation/ consumption. In such a case, applying for RECs may be a challenge as such an application has to be

made within 3 months of generation. In that duration, the status of a plant as CPP may be unclear. Moreover, the status

may change from year to year based on the consumption pattern.

Given these issues, in our opinion, it will be some more time before any capacity from UP sugar plants access the RECs mar-

kets.

The CERC order also alludes to further clarity on this through an amendment in the REC mechanism.

Impact of the order in other states

Andhra Pradesh: E-Duty is still applicable for self-consumption as per CERC order. Since the case against E-Duty is pending at

HC AP, it can't be determined whether E-Duty is exempted or not. If only E-Duty is concerned, as per CERC order, a co-gen

unit can forgo the benefit of E-Duty exemption and avail RECs.

Note: its important to highlight that only E-duty will not make project eligible or ineligible for REC. There is a statement by

CERC in its order which says "any other benefits applicable to CPP" which needs to be looked into more carefully.

Karnataka: KERC regulation mandates that a project must be a captive power project to qualify for REC. Co-Gen units by na-

ture in Karnataka, would not fall under the category of CPP and hence as per KERC regulation, sugar Co-Gen units will not be

eligible. Since the KERC regulation itself is radically different than CERC regulation, the CERC order will have no impact unless

KERC regulation falls in-line with central regulation.

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

55%55%55%55%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 3: Re connect newsletter xxvi

Page 3

www.reconnectenergy.com

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

Tamil Nadu recently announced its Solar Policy. The policy

aims to achieve an ambitious target of 3000 MW by 2015

in phased manner with capacity addition of

• 1500 MW from utility scale projects

• 350 MW from roof top installations

• 1150 MW under REC mechanism.

Key Differentiator: The policy unlike any other state pol-

icy, highlights the NET METERING ARRANGEMENTS for

feeding excess power back to grid for Rooftop Solar. Pro-

jects to evacuate power at following voltages .

What does it mean: The current REC policy recognises

only grid connected RE projects under REC. With Net Me-

tering, even small scale roof-top solar projects can partici-

pate into REC.

1000 MW out of 1500 MW utility scale capacity to be

funded by Solar Purchase Obligation (SPO) and balance

500 MW through Generation based incentive (GBI) by the

govt. The utility scale projects are also expected to be de-

veloped through competitive bidding process.

Solar Purchase Obligation: The SPO to be administered by

TANGEDCO has been mandated as 3% till Dec’13 and

scaled up to 6% from Jan’14 ,is applicable on all HT Con-

sumers (HT Tariff I to V) & LT Commercial (LT Tariff V).

Domestic consumers, huts, cottage & tiny industries,

power looms, LT industrial consumers and Agricultural

Consumers are exempted from SPO.

What does it mean: As per TANGEDCO, HT Consumers

(Cat I to V) and LT Commercial consumers, would collec-

tively consume about 25 BUs annually (FY 12-13).

This means, at 3% SPO, Tamil Nadu will require about 500 MW

of Solar power to meet SPO of 3%. To meet 6% of SPO, the to-

tal Solar power required will be about 1000MW.

Two RPO Structures? – TNERC also has specified 0.05% of Solar

RPO. With state policy in effect, there will be dual RPO imposed

on HT and LT Commercial consumers. The state commission

might have to realign the Solar RPO to align the RPO structure

to meet the policy objective.

Promotion of Solar Rooftops:

GBI for Solar Roof top : All domestic solar & solar-wind hybrid

rooftops to be installed before 31st

march’14 will be provided

with GBIs at Rs. 2/kWh for first two years, Rs. 1/kWh for the

next two years and Rs. 0.5/kWh for the subsequent two years.

All new government/local buildings shall necessarily install so-

lar rooftop.

Other initiatives and exemptions:

• Solar water heating systems mandatory for Public Buildings

and Industries using hot water boiler/steam boiler using

fossil fuels.

• Wheeling & Banking Charges applicable as per TNERC or-

ders.

• Exemption of Electricity Duty for 5 years for using solar

power from projects of self consumption/sale to utility.

• Tax Concessions as per TN Industrial policy.

• TEDA designated as single window clearance agency who

would be coordinating power evacuation approval, approv-

als related with connectivity to substation, approvals from

pollution control board etc.

• Empowered committee to accord project clearances.

Even though the policy looks quite ambitious, overall its quite

encouraging for the investors.

Regulatory Updates: Tamil Nadu Solar Policy

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Solar PV System size Grid Connected

<10 kWp 240 V

10 kWp to 15 kWp 240 V/415V

15 kWp to 50 kWp 415 V

50 kWp to 100 kWp 415 V

>100 kWp 11 kV

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 4: Re connect newsletter xxvi

Page 4

www.reconnectenergy.com

Non-solar RECs

The prices remained at floor price this month (Rs.1500/REC at IEX and PXIL; this is the same in September) as supply has remained far in

excess of demand. The total RECs available this month was 15 lakh out of which only 2.22 lakh RECs were redeemed leaving an inven-

tory of 12.8 lakh RECs .

10 lakh RECs were bid for sale ( up by 42 % from last month) while demand was for only 2.22 lakh RECs (down 16 %).

Demand has remained low in the last couple of months. The major reason slow progress on enforcement by SERCs. Clearing ratios were

approximately 30% on IEX and 70% on PXIL.

Solar RECs

Demand went up by 82% from last month whereas the supply also went up by 15%. The market clearing price on IEX was Rs 12,680 and

on PXIL was Rs 12,500 (last month it was Rs 12,900 on PXIL and Rs.12,500 on IEX). In total, 1,791 Solar RECs were sold (last month it was

1,160).

Review of REC Trading- October 2012

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 5: Re connect newsletter xxvi

Page 5

www.reconnectenergy.com

Status of projects in REC Mechanism

Accredited Capacity : 3556.451 MW

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

55%55%55%55%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 6: Re connect newsletter xxvi

Page 6

www.reconnectenergy.com

Status of projects in REC Mechanism

Registered Capacity : 3291.798 MW

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 7: Re connect newsletter xxvi

Page 7

www.reconnectenergy.com

• Clean Energy Fund headed nowhere

The clean energy fund is being used more to meet the budgetary shortfall of various ministries than to promote energy-

related research and projects. In the last few years, India has taken a number of concrete steps to propel its economy on a

greener, low-carbon pathway. The National Action Plan on Climate Change and National Clean Energy Fund (NCEF) are two

such ambitious endeavours.

http://www.thehindubusinessline.com/opinion/clean-energy-fund-headed-nowhere/article4051259.ece?homepage=true

• WInd energy industry seeks incentives

Wind energy equipment manufacturers hope the government would put policies for incentives to enable the wind energy

generation industry to reach its potential. Absence of proper incentives -- including the proposed generation-based incentive

(GBI) and accelerated depreciation benefits, which were earlier enjoyed by the industry -- had hit the industry hard, said

Ramesh Kymal, chairman, Indian Wind Turbine Manufacturers Association (IWTMA).

http://www.business-standard.com/india/news/wind-energy-industry-seeks-incentives-/490823/

• MNRE targets 45,000 sq m of solar collectors, identifies five user industries

The Ministry of New and Renewable Energy (MNRE) has said it would facilitate the installation of 45,000 square metres of so-

lar collectors — panels that generate heat from the sun’s rays — by March 2017. (Only last month the Ministry had indicated

a target of 15,000 sq m by 2016. Yet, the estimated reduction in carbon di-oxide reduction has been kept unchanged at

39,200 tonnes)

http://www.thehindubusinessline.com/industry-and-economy/economy/article3980957.ece

• Punjab Biomass Plans 96 Megawatts of Capacity by 2017

Punjab Biomass Power Ltd., a developer of clean-energy projects in India, plans to set up 96 megawatts of plants fueled by

rice straw by 2017. The company, backed by Infrastructure Leasing & Financial Services Ltd. and Bermaco Energy Ltd., expects

to raise 800 million rupees ($15.2 million) by February for its next plant in northern Punjab state, Bermaco Managing Director

Monish Ahuja said in a phone interview today from Mumbai. It has an existing 12-megawatt plant in Patiala district

http://www.bloomberg.com/news/2012-10-17/punjab-biomass-plans-96-megawatts-of-capacity-by-2017.html

Green News

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Meet us at

Vibhav Nuwal

[email protected]

+91 88006 79988

Vishal Pandya

[email protected]

+91 96202 21101

Page 8: Re connect newsletter xxvi

Page 8

www.reconnectenergy.com

Status of RPOs across various states in India - As on October 31, 2012

State

Status of Regulation

2012–13 RPO

Obligation

RPO on CPP?

RPO on OA

Users?

Penalty ?

Andhra Pradesh Final 4.75 % + 0.25 %

Yes

Yes

Not Specified

Assam Final

4.05 % + 0.15 %

Yes

Yes

Yes (RECmax)

Bihar

Final

3.25 % + 0..75 %

Yes

Yes

Yes (RECmax)

Chhattisgarh

Final

5.25 % + 0.50 %

Yes

Yes

Yes (RECmax)

Delhi Final

3.40 %+ 0.15 %

Yes

Yes

Yes (RECmax)

Gujarat

Final

6.00 % + 1.00 %

Yet to be notified

NA

Yes (RECmax)

Haryana

Final

1.50 % + 0.50 %

Yes

Yes

Yes (RECmax)

Himachal Pradesh

Final

10.00 % + 0.25 %

Yes

Yes

Yes (RECmax)

J&K

Final

4.75 %+0.25 %

Yes

Yes

Yes (RECmax)

Jharkhand

Final

3.00 % + 1.00 %

Yes (>5MW)

Yes

Yes (RECmax)

Karnataka

Final

10 % + 0.25 % (BESCOM,MESCOM,CHESCO

M), 7 % + 0.25 % for others

Yes (>5MW)

5% RPO

Yes (>5MW)

5% RPO

Yes (RECmax)

Kerala

Final

3.35 %+0.25 %

Yes

Yes

Yes (RECmax)

Madhya Pradesh

Final

3.40 % + 0.60 %

Yes

Yes

Yes (RECmax)

Arunachal Pradesh Final 4.1 % +0.1 % Yes Yes Yes (RECmax)

Maharashtra

Final

7.75 % + 0.25 %

Yes

Yes

Yes (RECmax)

Meghalaya

Final

0.60 % + 0.40 %

Yes

Yes

Yes (RECmax)

Orissa

Final

5.35 % + 0.15 %

Yes(>5MW)

Yes

Yes (RECmax)

Punjab

Final

2.83 %+0.07 %

Yes

Yes

Yes (RECmax)

Rajasthan

Final

7.10 % + JNNSM

Yes

Yes

Yes (RECmax)

Tamil Nadu

Final

8.95 % + 0.05 %

Yes

Yes

Yes (RECmax)

Tripura

Final

0.90 % + 0.10 %

Yes (>5MW)

Yes

Yes (RECmax)

Uttrakhand

Final

4.5 % + 0.025 % Yes

Yes

Yes (RECmax)

Uttar Pradesh

Final

5.00 %+ 1.00 %

Yes

Yes

Yes (RECmax)

West Bengal

Final

4 % + NA

NA

NA

Draft Proposed now.

JERC for Goa and UTs

Final

2.60 % + 0.40 % Yes

Yes

Yes (RECmax)

JERC for Manipur and Mizoram

Final

4.75 % + 0.25% (Man) 6.75% + 0.25% (Miz)

Yes

Yes

Yes (RECmax)

Nagaland

Final

7.75 % + 0.25%

Yes

Yes

Yes (RECmax)

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 9: Re connect newsletter xxvi

Page 9

www.reconnectenergy.com

Dear Readers, Our previous newsletters are available at our website www.reconnectenergy.com and can be downloaded from : http://www.reconnectenergy.com/rec/index.php/newsletters-on-rec-mechanism.html The summary of our previous newsletters we have published is available below. • Volume XV: November 2011

Renewable Purchase Obligation – A Demand - Supply Analysis • Volume XVI: December 2011

Analysis of Draft RPO of Andhra Pradesh + REC Market Update

• Volume XVII: January 2012 Voluntary Market for RECs

• Volume XVIII: February 2012

Off Grid Projects and REC: A new socio-development tool? • Volume XIX: March 2012

Applicability of RPO on Co-Generation Projects (An Update) • Volume XX: April 2012

Analysis of the Energy Savings Certificate Markets

• Volume XXI: May 2012 Trading of First Solar RECs - Interview with Mr Vikalp Mundra of M&B Switchgear Ltd

• Volume XXII: June 2012 Waste-to-energy projects and REC Mechanism, and REC trading updates

• Volume XXIII: July 2012

Analysis of report on RPO trajectory and impact

• Volume XXIV: August 2012 RPO Compliance: The Shifting Focus

• Volume XXV: September 2012 Analysis on Andhra Pradesh State Solar Policy

Past Newsletters

Feedback: We wholeheartedly thank you for providing your valuable feed-back on our last newsletter. Your feedback on the newsletter keeps us motivated and would certainly help us to improve the quality of it. Kindly keep writing to us. We are eager hear your views. Best Regards, Team - REConnect

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 10: Re connect newsletter xxvi

Page 10

www.reconnectenergy.com

Services Provided by REConnect

Detailed Services in REC Space Services for RE Generators

Services for Obligated Entities (Distribution Companies / Open Access Consumers / Captive Consumers)

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

Page 11: Re connect newsletter xxvi

Page 11

www.reconnectenergy.com

REConnect is a venture focused on the Renewable Energy Cer-

tificates, Energy Efficiency and Electricity Portfolio Man-

agement.

REConnect’s team has extensive experience in the environ-

mental markets both in India and internationally:

• Worked in the international carbon markets for several

years and has expertise in the consulting and trading of

emissions reductions

• Extensive knowledge about various Renewable Energy

Certificate and Energy Efficiency Certificate markets in

USA, Europe and Australia etc.

• Worked with Indian Energy Exchange (IEX), India’s leading

power exchange, and have extensive knowledge and ex-

perience of power markets

• Alumnus of Columbia University, an Ivy League University

in USA, and IIT Bombay

• Highly experienced core team worked with organizations

like J P Morgan, Indian Energy Exchange, LEK Energy

Consulting (UK) and Asia Carbon.

Contact REConnectContact REConnectContact REConnectContact REConnect

New Delh iNew Delh iNew Delh iNew Delh i Vibhav NuwalV ibhav NuwalV ibhav NuwalV ibhav Nuwal v ibhav.nuwal@reconnectenergy .com +91 88006 79988

BangaloreBangaloreBangaloreBangalore Vishal PandyaVishal PandyaVishal PandyaVishal Pandya v ishal .pandya@reconnectenergy .com +91 96202 21101 Anurag Dhyani Anurag Dhyani Anurag Dhyani Anurag Dhyani (Solar Markets)(Solar Markets)(Solar Markets)(Solar Markets) Anurag.Dhyani@reconnectenergy .com +91 77603 00499

MumbaiMumbaiMumbaiMumbai Ramkumar KRamkumar KRamkumar KRamkumar K ramkumar@reconnectenergy .com +91 99303 59992

ChennaiChennaiChennaiChennai Rajesh VaidyulaRajesh VaidyulaRajesh VaidyulaRajesh Vaidyula ra jesh.va idyula@reconnectenergy .com +91 99404 78306 Suresh Kumar Suresh Kumar Suresh Kumar Suresh Kumar ( for RPO)( for RPO)( for RPO)( for RPO) suresh.kumar@reconnectenergy .com +91 99727 24727

AhmedabadAhmedabadAhmedabadAhmedabad Mohit TyagiMohi t TyagiMohi t TyagiMohi t Tyagi mohi t . tyag i@reconnectenergy .com +91 9099002333

About REConnect

Regulatory Updates REC Trade Report REC Project Statistics Green News About REConnect Index UP Sugar Co-Gen

Volume: XII Month: June ’12 Contents of this newsletter are for informational purposes only

O

P

E

N

A

C

C

E

S

S

Vol. XXVI

2200 MW+2200 MW+2200 MW+2200 MW+

Portfolio under REC

16 States16 States16 States16 States

Projects under REC

Over 50%Over 50%Over 50%Over 50%

Market Share in REC Trade

7 States7 States7 States7 States

Physical Presence

Volume: XXVI Month: October’12 Contents of this newsletter are for informational purposes only