12
natural power prepared by PEN Y CYMOEDD NEATH PORT TALBOT RHONDDA CYNON TAF SOUTH WALES SUPPLEMENTARY ENVIRONMENTAL INFORMATION NON-TECHNICAL SUMMARY August 2010

Pen y Cymoedd, Supplementary Environmental Information

Embed Size (px)

Citation preview

Page 1: Pen y Cymoedd, Supplementary Environmental Information

natural power

prepared by

PEN Y CYMOEDDNEATH PORT TALBOTRHONDDA CYNON TAFSOUTH WALES

SUPPLEMENTARY ENviRONMENTAL iNFORMATiON NON-TECHNiCAL SUMMARY

August 2010

Page 2: Pen y Cymoedd, Supplementary Environmental Information

i

CONTENTS PAGE

1.0 INTRODUCTION .......................................................................................................................................... 1

Overview ............................................................................................................................................................... 1

2.0 ECOLOGICAL SURVEYS ............................................................................................................................ 1

Nightjar Survey 2009 ............................................................................................................................................ 1

Bat Survey 2009 ................................................................................................................................................... 2

3.0 PRIVATE WATER SUPPLY ASSESSMENTS ............................................................................................. 3

4.0 TRAFFIC ASSESSMENT AND SAFETY ..................................................................................................... 3

5.0 GRID CORRIDOR SURVEYS ...................................................................................................................... 3

Hydrological Assessment ..................................................................................................................................... 4

Archaeological Assessment ................................................................................................................................. 5

6.0 REDUCING THE IMPACT ON THE CRAIG Y LLYN SSSI .......................................................................... 5

7.0 FURTHER MINIMISING THE IMPACT ON PEAT DURING CONSTRUCTION .......................................... 6

8.0 HABITAT MANAGEMENT AND RESTORATION PROPOSALS ................................................................. 7

Page 3: Pen y Cymoedd, Supplementary Environmental Information

ii

Page 4: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

1

1.0 INTRODUCTION

Overview

1.1 This is the non-technical summary of the Supplementary Environmental Information (SEI) submitted to

the Department of Energy and Climate Change in respect of the Pen y Cymoedd Wind Farm.

1.2 On 17 November 2009, an application for consent for the Pen y Cymoedd Wind Farm was submitted to

the Department of Energy and Climate Change under Section 36 of the Electricity Act 1989. That

application was accompanied by an Environmental Statement (ES) and non-technical summary (NTS).

Full details of the application and ES are set out in those documents.

1.3 At the time of submission of the application and ES, it was agreed that additional environmental

information would be provided in respect of ecology (nightjars and bats) and the underground grid

connection.

1.4 This document is a summary of the SEI, which provides additional information on the natural and

human environment of the area where the Pen y Cymoedd Wind Farm would be situated. It also

provides further information on the construction, operational and decommissioning phases of the

development and the measures that will be put into place to reduce the impacts as described in the ES,

with specific regards to peat and to avoid damage to the Craig y Llyn Site of Special Scientific Interest,

as well as a revised landscape scale proposal for habitat management.

2.0 ECOLOGICAL SURVEYS

Nightjar Survey 2009

2.1 The ES contained the results of Nightjar studies undertaken in 2008. These studies concluded that

there would not be a significant loss of nightjar habitat.

2.2 To provide an impact assessment and accurate baseline against which to monitor nightjar and establish

flight heights with greater accuracy, further survey and radio tracking studies were undertaken in 2009

using the same methods and expert ecologists as in 2008. The primary aim of this continued study was

to establish the risk to nightjars of collision with wind turbines.

2.3 The results of this additional study show that nightjars are generally only active for about 1.5 hours

around dusk and 2 hours around dawn i.e. 3.5 hours per day. Outside of this time nightjars are resting.

Page 5: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

2

2.4 The additional study confirmed the findings of the ES. Nightjars were rarely recorded flying at blade

height, and indeed, spent very little time airborne at all. Given that most flight observations were of

birds flying low, and that the birds are only active on site for a very short period of time each day, it is

concluded that collision risk in general is very low.

2.5 In response to concerns from The Royal Society for the Protection of Birds that noise from the turbines

may mask the nightjar's ‘churring’ calls, a literature search was undertaken. Subsequently, in the

absence of any published information of such an effect being experienced, and based upon the

ecologist’s expert opinion, any impact as a result of noise disturbance is considered not to be

significant.

Bat Survey 2009

2.6 The four transect routes surveyed in September 2008 were once again surveyed in September 2009,

following the same guidance and methodologies employed in the main ES. The purpose of this further

survey was to compare results with the previous year in terms of the amount of bat activity.

2.7 Each transect again picked up bat activity within the forest during September 2009. The vast majority of

bats or bat passes recorded were from common pipistrelles. Occasional soprano pipistrelle and Myotis

bats were detected. Guidelines on the consideration of bats in relation to wind farms classify

populations of Myotis species as being of low risk from wind farms, with pipistrelles classed as being of

medium risk from wind farms.

2.8 Bat activity within the forest is mostly seen at forest edges which are a favoured feeding area of many

bat species. In conifer forests, where forest roads cut through forested areas, this provides ideal

sheltered feeding for pipistrelles, who will feed on the midges that are also extremely common in conifer

forests. Areas of clear felled trees or unplanted areas tend to see less bat activity.

2.9 Opening up the forest to site turbines will create more ‘forest edge’ or sheltered feeding areas for the

bats. To mitigate against the likelihood of these bats coming into contact with turbine blades, the

minimum separation distance of 50 metres, recommended in guidance between turbine blade and forest

edge, will be maintained.

2.10 The results of the 2009 surveys confirm the 2008 survey results and conclusions. The species

identified most frequently on the site were common pipistrelle. No species classed as being of high risk

from wind farms were detected during these further surveys. It is unlikely that the development will

have any significant impacts on the local bat populations. Ongoing monitoring will continue during the

operational life of the wind farm and, if impacts were to occur, further mitigation would be considered.

Page 6: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

3

3.0 PRIVATE WATER SUPPLY ASSESSMENTS

3.1 The main ES concluded that there would be no significant impact on private water supplies. However,

the developer carried out more detailed assessments on each of the seven properties identified during

the main surveys, and a further property was identified following concerns raised during the community

consultation process. Hydrology specialists visited each of the properties and made an assessment

aiming to identify the potential risks from the proposed Pen y Cymoedd Wind Farm on the quality and

quantity of water serving the private water supplies.

3.2 The assessments concluded that the risk to all but two of the properties would be negligible. The two

exceptions having a low risk.

3.3 The SEI includes commitments to actions that the developer will take at construction to reduce the

potential for a detrimental impact on the water supplies. As a result of these commitments, residual

minor effects on the hydrological environment will be short term and temporary, and are unlikely to

result in any long term/fundamental changes to the quality and quantity of water serving the supplies.

Ongoing monitoring will be carried out to ensure this is the case.

4.0 TRAFFIC ASSESSMENT AND SAFETY

4.1 On the 18th of March 2009, a test drive by a lorry with a representative abnormal load took place with a

police escort to identify where any highway modifications would be required. As the majority of the

proposed delivery route is on major roads with two or more lanes, the results of this report identify only

four locations where minor road modifications are expected to be required. The minor modifications

include the temporary removal of road signs and the widening of junctions to make sure that the

delivery of turbine components will not cause unnecessary impact on other road users. The finer detail

of the expected modifications will be described in a Traffic Management Plan, a document which is

normally agreed with the relevant authorities prior to delivery of any turbine components. The Traffic

Management Plan will also detail the proposed timescales and schedules for the larger turbine

components, e.g. tower sections and blades, in order to inform relevant authorities and members of the

public when the deliveries are likely to take place.

5.0 GRID CORRIDOR SURVEYS

5.1 To minimise environmental effects, Nuon took the decision to bury the electricity export cables

underground between the on-site substation in the forest and the off-site substation where the wind

farm is expected to connect to the National Grid at the Hirwaun Industrial Estate. As this decision was

taken towards the end of the EIA process, hydrological and archaeological surveys were not complete

when the main ES was submitted.

Page 7: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

4

Hydrological Assessment

5.2 An assessment of the potential hydrological, hydrogeological and geological effects associated with the

underground grid connection route has been undertaken.

5.3 The chemical quality of the watercourses sampled by the Environment Agency (EA) within the site and

the main rivers near the site is assessed as being close to chemically unpolluted. The biological quality

is good and the area is known to support spawning fish. The nitrate and phosphate levels are also low

and nutrients found in the watercourses can occur naturally and are not necessarily bad for the

environment. In the past, the area was affected by industrial and minewater discharges which caused

increasing water acidity and impoverished the ecosystem.

5.4 The EA has records of several public water abstractions within the vicinity but no private water supplies

were identified within 500 m either side of the grid connection corridor. The public water supply

abstractions were considered sensitive to the development as they are susceptible to changes in quality

and quantity that can be caused by the construction, operation and decommissioning of the grid

connection. The appraisal has also established that the grid connection corridor is located in an area

that is not susceptible to flooding.

5.5 The appraisal also established that the upper areas of the grid connection corridor are underlain by

peat. Peat is very sensitive to construction activities, as poor construction practice and sediment

management can have detrimental impacts on the stability and hydrology of the overlying peat.

5.6 A comprehensive suite of mitigation measures has been incorporated into the SEI following the

identification of the key issues and risks. In addition, an Environmental Management Plan and Pollution

Prevention Plan and specific mitigation techniques for the construction, operation and decommissioning

phases will be implemented to protect the groundwater and surface water resources from pollution.

5.7 Ongoing monitoring will be incorporated to provide reassurance that the established mitigation

measures are effective and that the development is not having a significant adverse impact upon the

environment. The ongoing monitoring will also indicate whether further investigation is required and,

where pollution is identified, additional mitigation measures can be implemented to prevent, reduce or

remove any impacts on the water environment.

5.8 Overall, the effects on the hydrological, hydrogeological and geological regime in the area of the Pen y

Cymoedd Wind Farm grid connection are considered to be negligible and not significant.

Page 8: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

5

Archaeological Assessment

5.9 The Glamorgan-Gwent Archaeological Trust, Projects Division (GGAT Projects) have undertaken an

assessment of the archaeological effects of the proposed cable connection to the off-site substation.

The assessment reviewed information held by the regional Historic Environment Record and the

National Monument Record, as well as cartographic and documentary sources.

5.10 There are nine sites of archaeological interest identified within the grid connection study area. Of these,

only one, Ffos Toncenglau Dyke, is a Scheduled Ancient Monument (SAM). The others are minor sites

of only local interest.

5.11 To mitigate the effect on the Ffos Toncenglau Dyke, the cable trench will, if possible, be located in the

middle of the existing forest track and the dyke suitably fenced. Such measures will ensure there will

be no effect on the dyke. If locating the trench within the forestry track is not possible, the entirety of

the cable trench within the scheduled area will be subject to full archaeological excavation prior to any

development starting. In accordance with the monument’s scheduled status, the developer will consult

Cadw prior to the commencement of development, and obtain Scheduled Monument Consent in

addition to deemed planning permission. Mitigation measures could include an archaeological watching

brief, field excavation or full excavation prior to any construction activities taking place. Such measures

will ensure that there will be no effect to the dyke.

5.12 Similar mitigation measures, including consultation with Cadw, will be undertaken in relation to the other

historical sites. Such measures will ensure there will be no impact on these sites.

5.13 The Rhondda Historic Landscape falls within the study region which represents one of the largest and

best-known mining conurbations and coalfield communities in Britain. As a result of this, an

Assessment of Significant Impacts of Development in Historic Landscapes (ASIDOHL 2) was carried

out. The overall significance of the impact of the grid connection corridor on the Rhondda Landscape of

Special Historic Interest is considered to be moderate.

5.14 The overall conclusion of the assessment is that with appropriate mitigation, including monitoring

through the construction period, any direct effects on the known archaeological resource in the vicinity

of the corridor will be reduced to none. It is also not considered that the development would greatly

reduce the capacity for understanding or appreciating the landscapes historical meaning or significance.

6.0 REDUCING THE IMPACT ON THE CRAIG Y LLYN SSSI

6.1 As described in the main ES, an existing forestry track crosses the southern area of the Craig y Llyn

Site of Special Scientific Interest (SSSI). The SSSI is designated primarily for its hollows, high cliffs,

ravines, flushes and associated montane vegetation. The boundary includes an upland section of acid

Page 9: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

6

grassland, which extends to the western edge of the A4061, the main road that links the Rhondda and

Neath Valleys. It is proposed that the wind farm infrastructure (track upgrade and grid connection

cabling) will be installed within the existing track margins.

6.2 The conclusion of the ecological survey from the main ES was that the upgrading of the forest track and

the burial of the twin 132 kV cables could be done sufficiently within the existing track margins so as to

not significantly affect the SSSI.

6.3 Prior to construction, detailed construction method statements and a Water Management Plan will be

produced, following consultation with the local authority and Environment Agency Wales (EAW). These

documents will detail the most appropriate construction methods and water management techniques to

reduce the impact on the hydrological environment and will take into account up-to-date and relevant

industry guidance. The documents will be agreed with the relevant authorities, prior to construction and

will ultimately govern the construction methods that will be used.

6.4 Methods implemented to reduce the potential for impact on the SSSI will include not allowing any

rubbish to accumulate or plant to be refuelled within the SSSI boundary or wider catchment. In

addition, no excavated material will be allowed to accumulate outside of the existing track margins. The

use of settlement traps, silt fences and straw bales will be used to reduce and prevent excavated

material, such as soil particles, from entering streams.

6.5 The methods mentioned above, along with ongoing survey by ecology and hydrology specialists, should

ensure that damage to the SSSI and its qualifying features will be avoided.

7.0 FURTHER MINIMISING THE IMPACT ON PEAT DURING

CONSTRUCTION

7.1 As described in the main ES, prior to being planted by forestry, a proportion of the site upon which the

development is being proposed was overlain with peat and would have functioned as a mosaic of

habitats including blanket bog and dry heath. It is widely recognised that forestry has an adverse effect

on these increasingly important habitats.

7.2 The submitted design of the wind farm avoided the areas of more favourable habitat that still had some

existing blanket bog habitat, with the exception of a 0.625 hectare (ha) area in the east of the site.

However, some impact on peat under conifer plantation was unavoidable. In order to give confidence

that this impact would be minimised as far as possible, the developer is committed to the

implementation of a protocol, which will further consider the impact on peat, with a specific objective to

reduce that impact when confirming the final location of each turbine and it’s associated infrastructure.

This protocol will be implemented between the felling and construction phase of the development.

Page 10: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

7

7.3 The surveys and process that will inform this protocol will be drafted and agreed with environmental

bodies such as the County Borough Ecologists and Countryside Council for Wales, Forestry

Commission Wales and Environment Agency Wales. The information gathered through the

implementation of this protocol will also be shared with the Working Group responsible for the delivery

of the Habitat Management Plan as discussed in the next section.

8.0 HABITAT MANAGEMENT AND RESTORATION PROPOSALS

8.1 In July 2009, Forestry Commission Wales produced its Woodland Strategy for Wales. The strategy

gives a clear commitment that, ‘where there is a clear ecosystem service benefit, existing non native

woodlands are restored to open habitat’. The publication of this strategy has allowed a review of the

restoration proposals to take place. As a result of this review the habitat management and restoration

proposals have increased from approximately 400 ha to approximately 1500 ha.

8.2 The areas that will be managed and the methods by which they are identified and managed will be

drafted and agreed with a Project Board, which will include representatives from Countryside Council

for Wales, Neath Port Talbot and Rhondda Cynon Taf County Borough Councils, Forestry Commission

Wales, the Royal Society for Protection of Birds and Cadw. The results of the surveys will inform the

detail of a live document, subject to review and revision throughout the life of the wind farm (called a

Habitat Management Plan).

8.3 The Project Board shall consider and advise the detail of the Habitat Management Plan, expected to

concentrate, where possible, on the following principal objectives:

Regeneration of peat body functionality.

Promotion of blanket mire and dry heath habitat.

Promotion of native woodland.

Management of stream corridors.

Promotion of feeding habitat for honey buzzard in the Resolven Forest area.

Promotion of appropriate management for nightjar.

Promotion of public enjoyment, understanding and involvements with delivery of the Habitat

Management Plan.

Page 11: Pen y Cymoedd, Supplementary Environmental Information

Pen y Cymoedd Wind Farm SEI: Non-Technical Summary

8

8.4 The developer will commit to providing £3 million of funding for habitat management over the life of the

wind farm and it is expected that the Project Board will be able to identify new opportunities throughout

the lifetime of the wind farm, working towards ongoing landscape scale management beyond the

current proposals.

Page 12: Pen y Cymoedd, Supplementary Environmental Information

natural power

NUON RenewablesLlys KearnsJersey MarineSwanseaSA1 8QL

+44 (0) 1792 455 004www.nuonrenewables.comwww.penycymoeddwindfarm.info

Natural Power Consultants LtdOffice 9, Aberystwyth TechniumY LanfaAberystwythCeredigionSY23 1AS

+44 (0) 1970 636 869www.naturalpower.com