KINGSTON POINT RAIL TRAIL FEASIBILITY STUDY

Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Embed Size (px)

DESCRIPTION

Lindsay Zefting, planner and engineer at Alta Planning + Design, presented the final report of the Kingston Point Rail Trail Feasibility Study, which reviewed a proposed trail from midtown Kingston to the Rondout Creek.

Citation preview

Page 1: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

KINGSTON POINT RAIL TRAIL FEASIBILITY STUDY

Page 2: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Kingston Point Rail Trail

Page 3: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Existing Planning Documents• Ulster County Non-Motorized Plan• Ulster-Delaware Rail Trail Feasibility

Study• Management Plan for the Kingston

Point Rail Trail• City of Kingston Action Plan• Kingston Local Waterfront

Revitalization Program and Implementation Plan

• City of Kingston Comprehensive Plan• Kingston Urban Cultural Park• Complete Streets SWOT Analysis

Page 4: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Opportunities and Constraints

Page 5: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Opportunities and Constraints

Page 6: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Opportunities and Constraints

Page 7: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Engineering & Environmental Assessment

• Existing right-of-way encroachments are minimal• Minimal environmental impacts and no remediation

necessary• Stormwater is a concern since the corridor is the low point;

can be addressed with natural swales along the trail• Structures along the corridor remain in good condition• There are several at-grade crossings where improvements will

be needed to ensure safe conditions• Safety concerns include the length of the tunnel, some steep

slopes and some crossings• Vegetative barriers provide screening for the trail

Page 8: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 9: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 10: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 11: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 12: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 13: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 14: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 15: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 16: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Conceptual Trail Design

Page 17: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Trail Conceptual Design

Page 18: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Trail Section• 10’ wide

asphalt path• 2’ shoulders• 8-10’ vertical

clearance• 14’ horizontal

clearance

Figure courtesy of Iowa DOT

Page 19: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Rail with Trail Alternatives

Page 20: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Rail with Trail Alternatives

Page 21: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

Implementation Steps• Public Support

– committee and community engagement• Funding

– Federal, state, and local funding sources, grant applications• Detailed Design

– Construction documents• Permits

– Erosion and Sediment Control Plan – NYSDOT Use and Occupancy Permit

• Construction– Grading, compaction, paving / structural repairs as needed

• Performance Measures– User counts, area economic improvements, and land uses

Total Cost ~ $1.6 Million- Trail, trailheads, and structural repairs included

Page 22: Kingston Greenline & Ulster County Trails Summit - KPRT Feasibility Study

Kingston Point Rail Trail Engineering and Environmental Assessment

THANK YOU