45
Kuala Lumpur, 10 – 14 August 2009 Flood Defence Systems Flood Defence Systems Jan T.L. Yap - AguaJaring Jan T.L. Yap - AguaJaring Integrated Flood Integrated Flood Management Management

Flood Defence Systems(97)

Embed Size (px)

Citation preview

Page 1: Flood Defence Systems(97)

Kuala Lumpur, 10 – 14 August 2009

Flood Defence SystemsFlood Defence SystemsJan T.L. Yap - AguaJaringJan T.L. Yap - AguaJaring

Integrated Flood ManagementIntegrated Flood Management

Page 2: Flood Defence Systems(97)
Page 3: Flood Defence Systems(97)
Page 4: Flood Defence Systems(97)
Page 5: Flood Defence Systems(97)
Page 6: Flood Defence Systems(97)
Page 7: Flood Defence Systems(97)
Page 8: Flood Defence Systems(97)
Page 9: Flood Defence Systems(97)
Page 10: Flood Defence Systems(97)

Flood Embankment in Action

Page 11: Flood Defence Systems(97)

Flooded Flood Plain

Page 12: Flood Defence Systems(97)

Failed Flood Embankment

Page 13: Flood Defence Systems(97)

Piping through Embankment

Page 14: Flood Defence Systems(97)

Confined Seepage

Page 15: Flood Defence Systems(97)

Strengthening Flood Embankment

Page 16: Flood Defence Systems(97)

Good Performanced Embankment

Page 17: Flood Defence Systems(97)

Failed First-line Embankment

Page 18: Flood Defence Systems(97)

Emergency Intervention - Blow-up

Page 19: Flood Defence Systems(97)
Page 20: Flood Defence Systems(97)

Kuala Lumpur, 10 – 14 August 2009

Flood Defence SystemsFlood Defence Systems

Philosophy of Risk Management

Failure MechanismsFailure TreeProbabilistic Design

Page 21: Flood Defence Systems(97)

Overview design methods of embankments

• Initialy: pure based on experiences. Crest level established with reference to the highest known water level;

• In the 50s: applying statistical techniques to determine the “Design

Water Level” → Deterministic design method using fixed design values for the various parameters;

• Since the 70s – 80s: Probabilistic Design Method → using stochastic character of the various load and strength parameters →

based on an analysis of failure mechanism and their probabilities.

Page 22: Flood Defence Systems(97)

Review deterministic design methods

• Crest level only one of the design parameters of embankment profile. Slope, crest width & berms: stability, maintenance, construction and usage of crest;

• Hydraulic conditions & soil mechanics parameters essential for embankment stability → limited degree of accuracy → Safety factors applied based on experience, tradition and intuitive judgement;

• Only determined per embankment stretch or section, while it is in fact part of a flood defence system → many stretches of different characteristics, and many structures like sluices & water gates and …….. protecting different regions: number of inhabitants, invested capital, strategic utilities, future land use, etc.

Page 23: Flood Defence Systems(97)

Components of a flood defence system

Page 24: Flood Defence Systems(97)

Shortcomings deterministic design methods

• Various embankment sections in a defence system do not provide same degree of safety;

• It is not known which failure mechanism gives the greatest contribution to the probability of failure of an embankment section;

• The overall length of the embankment system has no influence upon the design of the embankment section;

• Magnitude of damage or loss has no influence on the design;

• The actual probability of inundation (flooding) of the protected area is not known

Page 25: Flood Defence Systems(97)

Principle of Risk Analysis

Risk = Probability x Consequence

• Probability of an undesirable event: explosion, inundation, etc.

• Consequence of the occurrence of that event: → economic loss, damage, loss of life, etc.

Risk Analysis: the whole set of activities asimed at

Quantifying

the probability of an undesirable event ..and .. the consequence of the occurrence of that event.

Page 26: Flood Defence Systems(97)

Advantages of Probabilistic Approaches

• The flood system is analysed and described as a whole;

• Components of the system can be better inter-related, i.e. less over- and under-designing;

• Various uncertainties are rationally incorporated in the assessment of the safety of the system;

• Better insight into the sensitivity of probability of failure of the system related to the various uncertainties;

• Better insight into the priority for improving the flood defence system (maintenance).

Page 27: Flood Defence Systems(97)

More …..

Page 28: Flood Defence Systems(97)

Failure tree analysis

Page 29: Flood Defence Systems(97)

Probability of Failure

Page 30: Flood Defence Systems(97)

Design Point

Page 31: Flood Defence Systems(97)

Kuala Lumpur, 10 – 14 August 2009

Flood Defence SystemsFlood Defence Systems

Reducing Flood Damages

Flood FightingFlood ProofingTemporary & Demountable Flood Defence Structures

Page 32: Flood Defence Systems(97)

Emergency Measures - Flood Fighting

Page 33: Flood Defence Systems(97)

Controling Under-seepage

Page 34: Flood Defence Systems(97)

Sand Migration due to Underseepage

Page 35: Flood Defence Systems(97)

Road System as Floodway

Page 36: Flood Defence Systems(97)

Temporary Flood Wall

Page 37: Flood Defence Systems(97)

Emergency Flood Wall

Page 38: Flood Defence Systems(97)

Emergency Flood Wall (2)

Page 39: Flood Defence Systems(97)

Local Flood Fighting

Page 40: Flood Defence Systems(97)

Flood Proofing to Reduce Damage

Page 41: Flood Defence Systems(97)

Columns for Emergency Flood Walls

Page 42: Flood Defence Systems(97)

Movable Flood Wall

Page 43: Flood Defence Systems(97)

Floating Houses

Page 44: Flood Defence Systems(97)

Floating Houses (2)

Page 45: Flood Defence Systems(97)

Kuala Lumpur, 10 – 14 August 2009

Thank you……Thank you……