Upload
jisc-rsc-eastern
View
819
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Presentation by Alan Beresford of EcoCooling on the Application of Evaporative Cooling in Data Centres and Server Rooms
Citation preview
EcoCoolingThe Application of Evaporative Cooling
in Data Centres and Server Rooms
Alan BeresfordManaging Director
Evaporative Cooling of Server Rooms
• Why is an alternative cooling method needed?• How an EcoCooling Computer Room
Evaporative Cooler (CREC) works• How a CREC meets the requirements of modern
IT equipment• How to size an installation• Control• Operation and Maintenance• Installation Examples
Why is an alternative cooling method needed?
• Electricity is a major cost• Cooling typically takes half of the electricity of a
data centre• It is believed the IT sector has a bigger carbon
footprint than air travel• Many data centres have exhausted the power
supply. Reducing cooling energy use releases power for servers!
• There are fears of legislation/taxation being applied to energy use in data centres
Power Usage Effectiveness
• Power Usage Effectiveness– The ratio of total power
consumed to the IT power– Most data centres in the UK
operate at 2.0 to1.5– With DX cooling it is difficult to
beat 1.6– Chilled water systems can
achieve 1.4
• The EcoCooling CREC has a .05 effect on PUE
• Data Centres and Server rooms using CREC’s typically have a PUE of 1.1 to 1.2
• The application of EcoCooling CREC’s can halve the energy use of many Data Centres
IT L
oad
Co
olin
g
IT L
oad
Typical
PUE 2.2
Co
olin
gIT
Lo
ad
Good
PUE 1.6
EcoCooling
PUE 1.1 to 1.2
How a CREC works
Da
ta R
ack
Damper
Constant flow and temperature
Evaporative Cooling
How a CREC works
Constant air flow`
Controlled temperature and
pressure
EcoCoolingCREC
Fresh air input to system
Exhaust air recycled
Attemperation damper
Evaporative cooling during
hot periods
Hot air exhausted to outside
How a CREC works
A 100kW server room needs 8.4m3/s
Use Q=mCpΔT to calculate mass flow
rate
Sizing and Energy – 100kW Example
This is the server load
Temperature rise through server
CREC energy use is less than 10% of DX
CREC energy use is 4.2 kW
Fridge energy use is 50 kW
Sizing and Energy – 100kW Example
A good DX system will achieve a COP of
2.0
A CREC uses 0.5 kW/m3s-1
218 tonnes carbon savings per year
Annual Cost Saving of £32,000
CREC system will use 37,000 kWhrs/yr
Sizing and Energy – 100kW Example
24/7 operation is 8760 hours per year
DX system will use 430,000 kWhrs/yr
Not 10kW but 8.4m3/s
This is the number of coolers required
No redundancy, N+1 or 2N
Sizing and Energy – 100kW Example
This is the flow rate of a CREC
The is the design capacity
Each grill is designed for .5m3/s
17 grills!
What are we trying to achieve?
• Conditions where servers and IT equipment is stable and reliable
• Lowest capital, energy and operating costs of cooling infrastructure
• Lowest possible environmental impact• Appropriate levels of security and resilience• Simplicity of operation and maintenance!
Temperature and Humidity Standards
Temperature
RH
0%
50%
100%
0C 10C 20C 30C 40C
Server Fan Energy
Condensation
Equipment Failure
Static
Cooling Costs
Tape Stability
CAF Development
EcoCooler Performance
Air off temperature will not exceed 23C in London
30C days are very rare
Red line is ambient
temperature
Blue line is cooled air from EcoCooler
In the North this will not exceed
20C
Temperature and Humidity Standards
0oC 5oC 10oC 15oC 20oC 25oC 30oC 35oC 40oC 45oC 50oC 55oC-5oC
10%
20%
30%
40
%
50
%
60
%
70
%
80
%
Manufacturer Specifications10-35C 5-80%RH
ASHRAE 2008 Class 1 Allowable15-32C 16.5CDP 20-80%RH
ASHRAE 2008 Class 118-27C 5.5-15CDP 60%RH
CIBSE19-23C 45-55%RH
Dry Bulb Temperature
RelativeHumidityEcoCooling Capability
EcoCooling is 100% temperature compliant and 99%
RH compliant
Close control is not required
ASHRAE Class 1 is a good guide`
Accepting this performance
can reduce the cooling energy
use by over 90%
Control
• PLC control system for up to 6 CRECS– Crouzet (Schneider)– Boolean logic analogue
control
• Control parameters– Fan speed– Cooling mode– Links to refrigeration
equipment– Fire alarm link– Suppressant dampers– Suppressant purge
• Ethernet and Modbus communication available
Control
All control is directed through the CREC
control panel whch can control up to six CREC’s
Control
Selectable menu items and set point adjustment
is by the push buttons and LED display
Control
External and internal temperatures (with
optional pressure) are constantly monitored
CREC speed and cooling mode is controlled
Fire alarm link disables CREC’s and enables
refrigeration equipment and closes suppressant
dampers
Control
C1 C2 C3 C4
Mains Water
Drain
DrainValve
Initiate Cooling Mode
Initiate water supplyDrain Water Supply
SP – 2CSP – 4CSP – 6C5C
Cooling Mode Disabled
SP
Water supply is automatically
drained for frost protection
Cooling mode is only enabled
when necessary
Ability to cope with very hot days
PowerSavings
Simple Redundancy
SimpleMaintenance
No F Gas Compliance Costs
Low cost spare parts holding
External Access for maintenance
Increase in available power
CarbonSavings
No internal space needs
Operational Advantages
Maintenance
3 monthly service
Service takes approximately 1hr-Clean pads-Clean insect screens-Clean sump-Run test sequence
Cooling pads have a lifetime >3yrs
Consignment stock of spare parts option
Cambridge University
0
20
40
60
80
100
120
140
Jul Aug Sep Oct Nov Dec Jan
kW
IT Load
Cooling Energy
EcoCooling
• Specialist designer and supplier of evaporative coolers
• Established in 2002• UK stock of coolers and all
spare parts• Patented processes for IT
cooling• Un-rivalled technical
expertise in all forms of cooling
• Sector leader in application of evaporative cooling in data centres
• Over 3000 EcoCoolers installed in the UK
Summary
• Modern IT equipment is robust and does not require “close” control
• An EcoCooling system can reduce data centre and server room cooling energy use and costs by over 90%
• EcoCooling CREC’s make a PUE of 1.1 possible with conventional buildings, racks and servers.