28
Bundesverband Solarwirtschaft e.V. (BSW-Solar) Fire safety in planning, installation and maintenance of PV systems Watford, July 12th, 2011

D. Wedepohl_Fire Safety in Planning and Installation and Maintenance of PV Systems

  • Upload
    bre

  • View
    265

  • Download
    1

Embed Size (px)

Citation preview

Bundesverband Solarwirtschaft e.V. (BSW-Solar)

Fire safety in planning, installation and

maintenance of PV systems

Watford, July 12th, 2011

DisclaimerThese slides show selected aspects of the technical guidelines developed in the project

"Fire Safety Guidelines for Planning, Installation and Maintenance of PV Systems."

Nevertheless, please bear in mind that no liability can be assumed for the correctness of

content and the applicability of these guidelines in individual situations. It is therefore

essential to undertake a thorough check of the conditions and regulations that apply to each

planned project. The information and recommendations provided in these technical

guidelines are based on installation scenarios and the legal framework as they currently

exist in Germany. They have been coordinated with the Consortium of Heads of Fire

Departments in Germany (Arbeitsgemeinschaft der Leiter der Berufsfeuerwehren in

Deutschland - AGBF Bund). The guidelines have been compiled with the support of the

German Solar Industry (BSW-Solar), the German Association of Planners and Technical

Experts in Preventive Fire Protection (Bundesvereinigung der Fachplaner und

Sachverständigen im vorbeugenden Brandschutz e.V. – BFSB), the Munich Fire

Department (Berufsfeuerwehr München), the International Solar Energy Society, German

Section (Deutsche Gesellschaft für Sonnenenergie e.V. - DGS) and the Central Association

of German Electrical and Information Technology Industry (Zentralverband der Deutschen

Elektro- und Informationstechnischen Handwerke - ZVEH).

© BSW-Solar

2

Overview

• Brief introduction of BSW-Solar

• Development of the technical guidelines

• Planning, installation and maintenance of PV systems - fundamentals

• The four tenets of fire safety for planning, installation and maintenance

– Structural fire protection

– Protection from exposed voltage inside the building

– Access for fire extinguishing operations outside the building

– Information for emergency workers

• Conclusion and outlook

© BSW-Solar

3

4

Why does the German experience matter?

Development of the German PV market4

06/6/2011 ©

BSW-Solar

3 3 3 3 4 7 12 10 12 42 78 118 139

670

951843

1.271

1.809

3.806

7.408

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010*

annually installed cumulated installed

Market Data Photovoltaics in Germany 2010*

Newly installed power 7,400 MWp

Total installed power 17,200 MWp

Solar electricity produced 12,000 GWh

No. of all systems installed 860,000

Employees 130,000(Source: BSW -Solar)

* Preliminary figures, rounded, 3/2011

Milestones

1991: First Feed-in Law (FIT with low tariffs)

1991-1995: 1,000 roofs program (grants)

1999-2003: 100,000 roofs program (loans)

2000: Renewable Energy Sources Act (EEG) (FIT)

2004 +2009: Amendment (revision) of EEG (FIT)

2010: Amendment (revision) of EEG (FIT)

PV electricity growing

German PV-electricity production in GWh (2010/2011)

5Quelle: UNB, EEX, eigene Berechnungen BSW-Solar

PV-electricity production: + 88 percent in the first 6 months compared to 2010

2011 PV will cover 3 percent of demand in Germany

237

4 4 8

78 2

1.134 1.157

1.429

1.670

1.3721.263

98 1

4 4 2

274370

711

1.665

2 .243

2 .597

2 .173

0

500

1.000

1.500

2.000

2.500

3.000

Jan Feb Mrz Apr Mai Jun Jul Aug Sep Okt Nov Dez

in G

Wh

2010

2011

6German Solar Industry Association

TASK To represent the German solar industry in the solar

thermal and photovoltaic sector

VISION A global sustainable energy supply provided by solar

(renewable) energy

ACTIVITIES Lobbying, political advice, public relations, market

observation, standardization

EXPERIENCE Active in the solar energy sector for over 30 years

MEMBERS More than 900 solar producers, suppliers, wholesalers,

installers and other companies active in the solar

business

HEADQUARTERS Berlin

6

06/6/2011 ©

BSW-Solar

Development of the technical guidelines

• Motives: public discussions, uncertainty among all parties concerned,

contradictory information

• 2009: Project kickoff workshop

• Project "PV Fire Prevention and Fire Fighting” – Covered by Adrian

• Objective: Bundling of answers on the topic; developing packages of

measures

• Participants: Fire departments, fire protection experts, manufacturers

of components, planners, installers, insurance companies and

associations, employer's liability insurance association

© BSW-Solar

7

Planning, installation and maintenance

of PV systems – fundamentals(a)

• Construction and mounting of substructure

based on EN1991 et al.,

• electrical installation,

based on DIN VDE 0100-712, DINVDE 0100-410 et al.,

• protection against lightning,

based on DIN VDE 0185-305 parts1-4 et al.,

• commissioning test,

based on DIN VDE 0100-600, DIN EN 62446 and BGV A3 §5 et al.,

• identification and documentation, system handover and briefing,

based on DIN EN 62446, §633 BGB, §12 VOB/B et al.,

• maintenance,

in accordance with DIN 31051, DIN VDE 0105-100 and BGV A3 et al. © BSW-Solar

8

Bundesverband Solarwirtschaft e.V. (BSW-Solar)

Technical Guidelines for Installers

David Wedepohl, Juni 2011

Planning, installation and maintenance

of PV systems – fundamentals(b)

Electrical cable systems present the following risks:

emergence of fire, as a result of the electrical installation

flammable wiring (fire load)

spread of fire (thermal conduction)

© BSW-Solar

10

The four tenets – brief overview

1. Structural fire protection – prevent the fire from spreading

2. Protection from exposed conductors inside the building

3. Access for fire extinguishing operations outside the building

4. Information for emergency workers

© BSW-Solar

11

1

42

3

1. Structural fire protection (a)

• Primary goal: preventing a fire from spreading to neighboring fire

compartments

Mechanisms of fire progagation © BSW-Solar

12

1. Structural fire protection (b)

• Basic principle: The function of firewalls and dividing walls may not be

diminished.

• Requirements from relevant building regulations: classification as "rigid

roofing" and use of materials with a B2 building materials category

("Normal Combustibility") according to DIN 4102.

• Distances between rooftop constructions and firewalls depend on the

fire behavior of the respective materials.

Unterschiedliche Ausführung von Brandwänden

© BSW-Solar

13

1. Structural fire protection (c)

• Conclusion for installation of PV systems:

– Modules or cables may not be built over/across firewalls (cable

channels must be shielded in accordance with MLAR guidelines)

– Firewalls must extend at least 30 cm above the upper edge

of the PV generator or

– Clearance distances to firewalls must be observed

• Recommended clearance distance for systems with parallel arrays on

rooftops:

– distance between firewalls or dividing wall and the entire generator

construction: 1.25 meters

– If modules fulfill requirements for rigid roofing and the substructure

is made of non-combustible material, the distance can be reduced

to 0.5 meters.

• Systems integrated into the roof, which meet requirements for rigid

roofing, can be built up to the edge of the firewall.

© BSW-Solar

14

2. Protection from exposed conductors

inside the building (a)

Protection target:

• As a rule, the installation of PV systems

may not, in case of fire, lead to exposed

DC voltage conductors inside the

building; it must be possible for rescue

and firefighting operations to be safely

carried out in the building.

• This is achieved through:

– structural or

– technical or

– organizational

measures.

© BSW-Solar

15

2. Protection from exposed conductors

inside the building (b)

Possibility 1

• Safe routing of non-disconnectable

DC power cables in the building through:

– in-wall cabling (according to MLAR)

– sheathing of DC cabling

with fireproof cladding

– routing of DC cabling through

fireproof conduits and ducts

© BSW-Solar

16

Example of fireproof conduit

made by Adolf Würth GmbH

& Co. KG

2. Protection from exposed conductors

inside the building (c)

Important:

When power cables are routed through existing conduits, these must be

clearly marked. According to building law, a disused flue is considered a

cable/services conduit.

© BSW-Solar

17

Non-disconnectable DC

power cables inside the

building that are longer than

1 meter should have fire-

resistant routing

2. Protection from exposed conductors

inside the building (d)

Possibility 2

• Routing of DC cables OUTSIDE the building.

In this case, the following must be observed:

– DC power cables must be easy for emergency workers to identify

(e.g. in the "General Plan for Emergency Workers")

– During operations, no damage to cable or insulation may come

about

– Routing of DC power cables away from, or separated from, escape

routes and access routes for emergency workers

– Routing of DC power cables away from areas where water may

collect

© BSW-Solar

18

2. Protection from exposed conductors

inside the building (e)

Possibility 3

• Inverters located outdoors or directly at building entry points. This

means: Inside the building, there are only disconnectable AC cables.

In this case, the following must be observed:

– Inverters must be installed away from escape routes and access

routes for emergency workers

– Inverters must be installed so they are protected from the weather

– Required IP Code must be observed

© BSW-Solar

19

2. Protection from exposed conductors

inside the building (f)

Possibility 4

• DC disconnect switch in the string cable/main cable

In this case, the following must be observed:

– Long-term reliability, consistent with weather and climate

conditions

– Failsafe behavior of switch

– Safeguard system to prevent restart

– Trip-switch at building's main power supply

– Switch state clearly identifiable

– Clear identification of switch

and disconnected areas

– Synchronous switching of

inverter circuit breaker due to

hazard of discharge surge

– … © BSW-Solar

20

Protection (installation examples)

© BSW-Solar

21

3. Access for fire extinguishing

operations outside the building (a)

• Prerequisite for firefighting operations:

Emergency workers must have access to fire source

¬ Inside attack: Protection against exposed conductors inside the

building

¬ Outside attack: Access to roof

• Escape routes

– serve primarily as possibilities of escape and rescue

– serve additionally as access routes for emergency workers

• Observe minimum requirements for access and clearance

Allow 1 meter safety clearance from electrically conductive

components (in accordance with DIN VDE 0132)

e.g. size of "fire escape window": clearance width 90 cm and

clearance height 120 cm© BSW-Solar

22

3. Access for fire extinguishing

operations outside the building (b)

• Different access possibilities to roof

© BSW-Solar

23

Access via north side without panels Access via gable window

Access strips on roof covered on both sides or mono-pitch roof without gable window

3. Access for fire extinguishing

operations outside the building (c)

• Different access possibilities to roof

© BSW-Solar

24

For smaller flat roofs without any other

access possibilities - access strip on the

long side (one access strip is

recommended for arrays up to 20 m wide)

For large flat roofs, access should be

guaranteed for each fire compartment (in

general, 40 x 40 meters) all around the

generators. The width of access strips should

be no less than 1 meter.

4. Information for emergency workers

• Provide emergency workers with a

quick overview

– near the building's junction box

• Indicator sign

• General plan for

emergency workers

– Supplement existing fire

response plans with PV

installation information

© BSW-Solar

25

Key information- Areas containing voltage-carrying components

- Safe and protected areas

- Location of DC disconnect-switch

Conclusion

• Simple measures are enough to ensure fire safety in the planning,

installation and maintenance of PV systems.

• There is currently no single answer to all questions regarding every

installation scenario A close monitoring of the installation situation

by planners and installers is necessary

• Planners and installers are called upon to put into practice the

recommended technical guidelines for fire safety in planning,

installation and maintenance

© BSW-Solar

26

Outlook

• Further dissemination and application of technical guidelines

• Missing answers to individual questions are currently being sought via

norms and standards or by the industry itself

• Industry is working on solutions to disconnectability

of DC circuit testing specifications

are necessary to prevent subsequent

dismantling of unsuitable solutions

• Building regulations requirements:

"rigid roofing" and at least

Class B2 building materials

("Normal Combustibility")

according to DIN 4102

© BSW-Solar

27

Thank you

for your attention!

Contact:

David Wedepohl, Departmental Director Market & Communikation

[email protected]

Christian Brennig, Project Manager Technology

[email protected]

© BSW-Solar

28