Upload
all4-inc
View
571
Download
2
Tags:
Embed Size (px)
Citation preview
Continuing Evolution of New Source Review
2010 Mid-Atlantic Environmental and Energy
Conference and Trade Show Camp Hill, PA
April 14, 2010
John Egan and Colin McCallAll4 Inc.
2
Agenda Brief major new source review primer Case study example of current issues:
• Applicability analysis• Excluded emissions• Tracking against projections
PM2.5 and GHG meet major NSR Aggregation and offsets for non-
attainment
3
Major NSR Permits
Major new source review (NSR) is the air permitting program for major new sources and major modifications.
Two different Major NSR programs:• Prevention of Significant Deterioration
(PSD) for sources in NAAQS attainment areas
• Non-attainment New Source Review (NNSR) for sources in NAAQS non-attainment areas
4
NAAQS
Pollutant Averaging Time Primary Standard Secondary Standard
Particulate Matter PM10, 24 hr 150 g/m3 150 g/m3
Sulfur Dioxide (SO2) annual 80 g/m3 (0.03 ppm) ----
24 hr 365 g/m3 (0.14 ppm)
----
3 hr ---- 1,300 g/m3 (0.5 ppm)
--
Nitrogen Dioxide (NO2)
annual 100 g/m3 (0.053 ppm)
100 g/m3 (0.053 ppm)
Ozone (O3) 8 hr 0.075 ppm 0.075 ppm
Carbon Monoxide (CO)
8 hr 9 ppm (10 g/m3) ----
1 hr 35 ppm (40 g/m3) ----
Lead (Pb) 3-month rolling avg. 0.15 g/m3 ----
1 hr 100 ppb (new std form)
1 hr Coming Soon
PM2.5, annual 15 g/m3 15 g/m3 PM2.5, 24 hr 35 g/m3 35 g/m3
5
NSR Major Modifications In order to trigger a major
modification under PSD or NNSR:• Facility must be an existing major source
and project must result in a significant emissions increase, or
• Project must be a major source Different major source thresholds
and significance levels under PSD and NNSR
6
NSR Major Modifications Major modifications under both PSD and
NNSR can include:• New emissions units• Physical changes to existing emissions
units or to non-emissions units• Change in the method of operation of
existing emissions units (e.g., debottlenecking)
• Removal of previous permit restrictions• Use of fuels or raw materials that the unit
could not previously use
7
Example – How Major NSR Works
The Project• Existing combination fuel boiler
Fires primarily wood and coal• Modification:
Increase steam rate (more power) Burn more wood (biomass) Install new over fire air system
8
Considerations Use NSR Reform:
• Actual-to-projected actual calculations For this discussion assume:
• Historic decrease in coal use• Only five years of historic data available• No baseline adjustments required • Located in an attainment area• Able to avoid PSD for all pollutants• Focus on SO2 only
9
SO2 Applicability Analysis Potential to emit (PTE) rate = 500 TPY (no
change) Baseline period selected is 2003/2004 Baseline actual emission (BAE) rate = 300
TPY Projected actual emission (PAE) rate = 325
TPY• PAE – BAE = 25 TPY (< 40 TPY PSD significance threshold for
SO2)
10
SO2 Baseline/Future
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014-20180
50
100
150
200
250
300
350
400
450
500
Baseline and Projected Future Actual SO2 Emissions 2003-2018
YEAR
Emis
sion
s (T
PY)
Baseline + 40 TPY
Baseline 300 TPY
Project Occurs 2008
Potential to Emit
Baseline Actual Emissions Projected Actual Emissions
11
Excluded Emissions
§52.21(b)(41)(ii)(c) states that in determining PAE the source shall exclude emissions following the project that the unit could have accommodated during the baseline period and that are unrelated to the project, including demand growth.
12
Excluded Emissions For example if PAE is 380 TPY:
PAE – BAE = 380 – 300 = 80 TPY If boiler operated at a rate that resulted in
30 tons of SO2 during May 2004, a reasonable argument may exist that the boiler could have accommodated 360 TPY during baseline period (i.e., 30 tons/month x 12 months)
Any increase in SO2 cannot be due to the project
13
Excluded Emissions Applicability analysis per §52.21(a)(2)
and §52.21(b)(41)(ii)(c) definition of PAE:
Excluded emissions (EE) = CHA – BAE360 – 300 = 60 TPY
Project increase = PAE – EE – BAE380 – 60 – 300 = 20 TPY
Currently a controversial topic with U.S. EPA
14
Excluded Emissions Do they matter?
• In first case project increase was less than significant regardless of CHA emissions
• In second case CHA made project not significant
• Also if the project involved other units that emit SO2 they could affect applicability analysis and/or future reporting
Note that the rule says “shall exclude”
15
Permit Language Requirement to monitor, calculate, and
record annual boiler SO2 emission rate for 10 years following project due to:• Applicability approach• Increased steaming capacity • Reasonable possibility of significant increase per
§52.21(r) due to 25 TPY increase not counting excluded emissions
Requirement to submit report if annual emissions exceed BAE by a significant amount and differ from documented projection
16
Future Tracked Emissions 2009, 2010, 2011 annual SO2 emission
rate is less than BAE + 40 TPY: • No report required
In 2011 scarcity of biomass results in greater coal use and annual emissions exceed preconstruction projection
17
Future Tracked Emissions
2009 2010 2011 20120
50
100
150
200
250
300
350
400
450
500
Projected Actual and Actual SO2 Emissions 2009-2012
Projected Actual
Actual
YEAR
Emis
sion
s (T
PY)
Potential to Emit
Baseline + 40 TPY
Baseline 300 TPY
18
Future Tracked Emissions By 2012 increased coal use results in
annual emissions exceeding both the BAE + 40 TPY and preconstruction projection:• Report required• Justification that emissions are within the
scope of the project• Possibly use excludable emissions from
baseline period to support
19
Other Thoughts What if in 2012 we decide to fire TDF
instead of more coal?• Likely considered a modification if not
allowed in permit• New applicability analysis required• Baseline may need to change• CHA emissions may be important• May not be excludable
20
More Thoughts The more complicated the project the
greater the potential for confusion and non-compliance. For example say the project required wood yard upgrades and netting for PM10:• Required to track PM10 for project and could
have units greater than and less than projections and not need to report
• What happens if one unit included in a multi-unit project isn’t changed?
• How does the next project get permitted?
21
Final Project Thoughts What happens if actual emissions
exceed BAE + 40 TPY due to the project?
Maybe PTE isn’t so bad…
22
PSD/NNSR for Fine Particulate (PM2.5)
Several unique PSD/NNSR issues:• Difficulty quantifying emissions• PSD air quality modeling challenges• NNSR applicability and offset
challenges Impacts to project viability, schedule,
and design
23
Quantifying PM2.5 Emissions PSD/NNSR will require establishing
emission limits with a margin of compliance
Published emission factors not widely available, particularly for condensables
Vendor emission factors are often lacking
Test methods available but may not be appropriate in certain instances
24
PM2.5 PSD Air Quality Modeling
Significant impact levels (SILs) not finalized
NAAQS demonstration will be difficult:• Adding facility-wide modeled
concentrations to nearby monitored concentrations
• Current background concentrations are above or near the 24-hour and annual NAAQS level already
24-hour concentrations could be temporally paired in certain situations
25
PM2.5 NAAQS Considerations
35
PM2.
5 24-
hour
Con
cent
ratio
n (
g/m
3 )
28
NAAQS Level
Monitored Background Value
7 g/m3 available for modeling
26
PM2.5 NNSR Applicability Challenges
Pennsylvania specific: 10-year deminimis aggregation
Projects with minor emission increases must be summed with other increases and decreases that occurred with a 10-year lookback
If a project triggers NNSR requirements, the clock is “reset” with respect to aggregation
27
PM2.5 Deminimis Aggregation Example
Major facility with the following historic permitting activities:• New project (2 tpy)• 2007: New storage pile (1.3 tpy)• 2005: New boiler (2.4 tpy)• 2004: Boiler uptime improvement (3.5
tpy)• 2002: New outdoor vent (0.9 tpy)
Total of 10.1 tpy would need to be offset Same process applies to SO2 (40 tpy
threshold)
28
PM2.5 Offset Challenges PM2.5 emission reduction credits (ERCs) are
in short supply Interpollutant trading will help ERCs are to be obtained from the same
nonattainment area of the project location, otherwise air quality modeling is required
Significant limits on the spatial separation between the sources generating the PM2.5 ERCs and the project location
29
ERC Equivalency Demonstration
Project Location
ERC Location
30
Finding PM2.5 ERCs
Direct PM2.5 ERCs are selling in PA for between $3,000 – $10,000 per ton with very limited sales of ERCs from which to judge
Determine the amount of ERCs needed early in their planning process
Begin looking for available ERCs as soon as possible
Internal reductions of PM2.5 should be given serious consideration
31
New NAAQS Levels
1-Hour NO2 NAAQS: 100 ppb Extremely stringent for a 1-hour
averaging time standard. No proposed SIL, awaiting guidance.
Proposed 1-Hour SO2 NAAQS with similar issues as the NO2 NAAQS
No grandfathering of PSD permit applications that have not received final approval (even with draft permits)
Challenge for NAAQS demonstrations that correspond to Title V renewals
32
New NAAQS Levels
Any major facility will have difficulty demonstrating compliance using facility-wide modeling
Strategic approaches to permitting: Look for emission reductions where they are
available (to either avoid major source permitting or to decrease modeled impacts)
33
GHG Tailoring Rule
“Major Sources” of GHGs Regulated GHG pollutants PSD implications and timing
U.S. EPA will begin regulating GHGs for stationary sources in January 2011
No grandfathering for permit applications that have not been issued
Addressing GHGs in construction permit emissions inventories and control technology requirements (BACT, etc.)
34
Conclusions
NSR applicability process is still evolving
Implications of new NAAQS are immediate and far reaching
GHGs can’t be ignored Environmental considerations will impact
planning and design Pay attention to these issues and try
not to be surprised
35
Questions?John and Colin
All4 Inc.2393 Kimberton Road
P.O. Box 299Kimberton, PA 19442
610.933.5246 x14 and x20
www.all4inc.com