Upload
nasapmc
View
13.816
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Citation preview
All Subsystems Are Not Created EqualAlternative Scheduling Approaches for Spacecraft Subsystem Development
Dewey E. Barlowcorina c. k. battista
February 2012 Orlando, FL
All Subsystems Are Not Created Equal
Contents
• Current NASA Environment• Technology Readiness Level (TRL) Considerations• Technology Race Analogy• AO Process Implications• Potential Solutions
• Staggered Starts• MIN TRL6 First• Staggered Finishes
• Recommendations• Conclusion
All Subsystems Are Not Created Equal
Current NASA Environment
Used by permission.
All Subsystems Are Not Created Equal
Current NASA Environment (7120.5)
Figure 3.1 – NASA Project Lifecycle
TRL Considerations
All Subsystems Are Not Created Equal
When many subsystems are involved, the fact that the completion of an entire spacecraft is more likely to be delayed due to the slippage in the development of one
immature subsystem is supported by historical evidence
TRL Considerations
It is difficult at best to predict the timeframes required for new and emerging technology because:
•We have limited relevant historical data•Even when relevant historical data exists, past performance may not be an
accurate indicator of future performance since new independent variables are constantly being introduced
•Technology development is often an iterative process - We find out what works often by eliminating what does not (Thomas Edison and the light bulb)
•Resource units are not highly correlated with duration
All Subsystems Are Not Created Equal
TRL Considerations
Since schedule requirements for technology development activities are subject to variation and difficult to predict, how do we expect low TRL hardware to stay on pace
with proven technologies?
All Subsystems Are Not Created Equal
TRL Considerations
Forcing low TRL subsystems to keep pace with proven technologies can induce inefficiency in execution, create schedule risk, and contribute to cost and schedule overruns
All Subsystems Are Not Created Equal
AO Process Implications
All Subsystems Are Not Created Equal
Compressing an already critical subsystem or instrument’s critical path may provide an overly optimistic and ultimately unachievable timeframe for
development. Subsystems that have the most schedule risk have the least amount of available schedule reserve
AO Process Implications
All Subsystems Are Not Created Equal
NASA projects are expected to comply with generally-accepted schedule reserve guidelines so development timeframes for these already compressed
low TRL subsystems are reduced even further
Potential Solution 1 – Staggered Starts (SS)
All Subsystems Are Not Created Equal
What if we started with an unconstrained environment and allowed the subsystems and instrument teams to define their schedule requirements given known resource
constraints and using adequate calculated schedule reserve commensurate with the level of technical and execution risk?
Potential Solution 1 – Staggered Starts (SS)
All Subsystems Are Not Created Equal
Staggered Starts allows each subsystem to develop on their own schedule and achieve compliance with 7120.5 through delta mission level reviews and waivers
Potential Solution 2 – MIN TRL First
All Subsystems Are Not Created Equal
The subsystems and instruments that are not at TRL 6 would be required to engage in technology development and demonstration activities to achieve TRL 6 prior to engaging
all subsystems
Potential Solution 3 – Staggered Finishes
All Subsystems Are Not Created Equal
Staggered Finishes allows each subsystem to develop on their own schedule/deliver early and achieve compliance with 7120.5 through delta mission level reviews and waivers
Potential Solutions – Summary
All Subsystems Are Not Created Equal
All solutions involve some level of decoupling and decompression of subsystem schedules
Recommendations
All Subsystems Are Not Created Equal
1 – Perform schedule risk assessments at the subsystem level to predict probable range of deliveries
Recommendations
All Subsystems Are Not Created Equal
2 – Analyze data from schedule risk assessments to detect groupings or patterns
Conclusion
All Subsystems Are Not Created Equal
3 – Select the appropriate schedule approach
All Subsystems Are Not Created Equal
ExampleLow TRL
The Initial TRL Estimate Influences the Parameters of Probability Distribution on Delivery
M
O – OptimisticM – Most LikelyP – PessimisticT – Target (say 70%)
O P
T
High TRL
M
O P
T
All Subsystems Are Not Created Equal
OPLExample
The Aggregate Probability Distribution Targets May Offer Patterns to Help Plan Subsystem Schedule Development Approaches
PDU
FSW
PSE NMSRF
Late Start Common Start Early Start