Institutionalization of Energy Managementin public sector buildings in Bosnia and Herzegovina

Sanjin AvdićSector Leader, Energy and Environment

UNDP CO BiH

Page 2: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

Understanding Bosnia and Herzegovina

• Complex administrative structure

• Reflection to the energy and environment sector

• Low RES utilization (high potential for biomass, hydro, wind and solar); high energy conservation potential (a strategic approach to EE is missing)

• Challenges for BiH to fulfill its obligations (multilateral agreements – UNFCCC, En Comm Treaty...)

• Laws, by-laws, regulations, mechanisms... (intangible)!

• Infrastructure projects (tangible)!

Page 3: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

tangibletangibleintangible &

tangibleintangible &

tangible

UNDP CO BiH - CORELATION OVERVIEW OF PAST AND PRESENT ACTIVITES

Page 4: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„PILOT PROJECTS“ 2010 - 2013

•A total of 38 replicable EE/RES pilot projects in public sector implemented

•2.9m € total value of EE/RES investments

•Government share – 1.4m €

•Annual public budget savings – 500.000 €/a

•Average return on investment – 5.8 years

•Annual CO2 reduction – 2,200 t/CO2 a

•A total of 664 man/months of employment achieved by implementation of EE/RES measures that created €350,000 worth in salaries

Page 5: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„INSTITUTIONALIZATION of ENERGY MANAGEMENT“ in 2013

•Initiation of GED project – GREEN ECONOMIC DEVELOPMENT

Project goals:

1.to institutionalize energy management - to develop and achieve a reliable and sustainable energy monitoring and reporting system

2.to create a systematic approach to energy mngt and EE/RES investment decision making

3.to enable preconditions for launching public works / generate employment

THE KEY – creating an favorable environmentfor investments in energy efficiency/RES in public sector buildings!

Page 6: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

APPROACH

bottom-upapproach

comprehensiveapproach

Page 7: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„INSTITUTIONALIZATION of ENERGY MANAGEMENT“ in 2013

Cooperation with our Partners:

•State Ministry of Foreign Trade and Economic Relations (MoFTER)•Ministry of Spatial Planning, Civil Engineering and Ecology of Republic of Srpska•Environmental Protection and Energy Efficiency Fund of RS•Ministry of Education and Culture of RS•Ministry of Spatial Planning of Federation of Bosnia and Herzegovina (FBiH)•Environmental Protection Fund of FBiH•Unsko – Sanski Canton, Tuzlanski Canton

Page 8: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„INSTITUTIONALIZATION of ENERGY MANAGEMENT“ in 2013

• Development of a systematic approach to energy mngt and EE investment decision making of Environmental Fund of FBiH

Three RES/fuel switch projects

(fossil to biomass)

Page 9: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„INSTITUTIONALIZATION of ENERGY MANAGEMENT“ in 2013

• Systematic approach to energy mngt and EE investment decision making

applications received

1st shortlisting & EMIS

2st shortlisting & detailed energy audits

decision made to invest into four projects(two have been planned!)

Page 10: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

„INSTITUTIONALIZATION of ENERGY MANAGEMENT“ 2014 - 2018

Project partners:

•Environmental Fund of FBiH (EE related project cooperation from mid-2013)

•Environmental and Energy Efficiecny Fund of RS (EE related project cooperation expected in mid-2014)

Activities:

•Coopeation on five-year Programme on EE/RES in both Entities (FBiH & RS)

•Programme “Capacity building and cost reduction in public sector buildings in FBIH/RS through increased energy efficiency, energy management and reduction of emissions“

Page 11: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

Five Programme Components

Page 12: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

Compatible / aligning activities

Page 13: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

Compatible / aligning activities

• CC Adap & LEDS of BiH – First official BiH state level adopted document on energy/environment

• Provides the basis for EE/RES public sector building projects (incl. district heating, electricity generation and transport)

• Provides the basis for potenatial NAMAs projects

• NAMA body in BiH (to be established)!

• MRV and Biomass agreement templates – GEF 4 project

Page 14: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

UNDP CO BiH - CORELATION OVERVIEW OF PAST AND PRESENT ACTIVITES

• Goal to create a self-sustainable energy mngt system by combining the tangible (infrastructure project) and intangible (processes, mechanisms, regulations)

Page 15: 10 undp bi h sust energy in see - sanjin avdic undp co bih 071213

Thank you for your attention!

Sanjin AvdićSector Leader, Energy and Environment

UNDP CO BiH

[email protected]+387 62 334 096