Agile estimations and Planning
Cornel FATULESCU
agile coach
Did It Ever Happen to You?
• Who the ... made this estimation?
• Sorry it will take me than … hours!
• I hope we’ll deliver tomorrow.
• I can’t tell you how much time it will take!
• We don’t have time for testing
• …
2
Usual solution
3
Classical IT services supplier scenario
4
Sales Start-up Ongoing project
Some experts
Some members of newly created
team
The team
Basic knowledge
Some knowledge
might be lost
Grooming sessions
Release Planning
Capitalize RFP
Knowledge
DoR DoD
Estimations
Initial Release Planning
Product Vision
Initial Backlog
Goals
Problem 1 How to
estimate features?
Problem 2 How to plan?
How to estimate features ?
• What does the team need for each feature in order to increment it?
• How features become part of the increment?
• Estimate the features!
5
Definition of Ready
Definition of Done
Relative Estimations
Feature metamorphosis flow!
6
Suggestion Assumed Estimated Ready In Progress Pre-
Production Production
Done
Feature metamorphosis flow!
7
Suggestion Assumed Estimated Ready In Progress Pre-
Production Production
Done
? ? ? ?
Release Planning
End of Release
…
…
…
…
…
…
…
…
…
…
…
…
…
…
…
…
…
… …
… …
…
Sample of Definition of Ready for a feature
8
Story clarified
Tasks identified
Story estimated
Acceptance criteria
Clear dependencies
Scrum Team accepts the story
Responsible for acceptance
User story complies INVEST rules
…
Sample of Definition of Done for a feature
9
Design complete
Development complete
Code commented
Static code quality analysis
Unit testing is done
Code Refactoring
Code checkin
Continuous build
Tests
Documentation Ready
Peer reviews
Jira is updated
Story is accepted
Why relative estimations?
• Product Owner: How long it will take to deliver feature A?
• 1st team member : 3 Days
• 2nd team member: 6 Days
10
Both estimations
might be right!
Why relative estimations?
• Product Owner: How long it will take Compared to feature B we’ve done the last time?
• 1st team member : 3 times more
• 2nd team member: I agree, 3 times more
11
Measure the size, calculate the time
12
Velocity = 𝛥𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒
𝛥𝑡𝑖𝑚𝑒
𝛥𝑡𝑖𝑚𝑒 = 𝛥𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒
𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦
Measure the size, calculate the time
13
Velocity = 𝛥𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒
𝛥𝑡𝑖𝑚𝑒
𝛥𝑡𝑖𝑚𝑒 = 𝛥𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒
𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦
http://www.mountaingoatsoftware.com/blog/its-effort-not-complexity
It’s effort, not complexity
14
“In a class a few years back, I was given a wonderful example of this. Suppose a team consists of a little kid and a brain surgeon. Their product backlog includes two items: lick 1,000 stamps and perform a simple brain surgery–snip and done. These items are chosen to presumably take the same amount of time. If you disagree, simply adjust the number of stamps in the example. Despite their vastly different complexities, the two items should be given the same number of story points–each is expected to take the same amount of time.”
-Mike Cohn
http://www.mountaingoatsoftware.com/blog/its-effort-not-complexity
Visualize the estimations
15
To estimate
Feature 2
Feature 5
Feature 6
Feature 7
Feature 8
Feature 9
Feature 11
1 SP
Feature 1
Feature 43
Feature 32
Feature 21
Feature 23
2 SPs
Feature 3
Feature 4
Feature 18
3 SPs
Feature 10
Feature 88
5 SPs
Feature 13
Feature 15
8 SPs
Feature 22
5 SPs 6 SPs 6 SPs 10 SPs 8 SPs 35 SPs
How to plan?
16
Our concern?
Release Planning Process
Sprint DoR, DoD
Release DoR, DoD
What is release planning?
17
• It is a process not an event!
Release Planning
at project start-up
Sprint 1 Sprint 2 Sprint 3
Through Grooming Sessions
In Scrum no more than 10% of the
Sprint
Usually more effort needed
than in a sprint
Sample of Definition of Ready for a sprint
18
Sprint goal
The Sprint Backlog is prioritized
No hidden work
Calculated capacity
Team accepted the Sprint Backlog
All stories meet definition of ready
List of stories for regression testing
Sample of Definition of Done for a sprint
19
Release Build
Functional testing done
Regression testing done
Acceptance testing done by the Product Owner
Closure
Sprint Context
20
Team size
Focus factor
Sprint size
Calendar days
Velocity
6 People
70%
2 weeks
10 Days
16 SPs
Estimate 1 SP
21
• Estimate in hours several features
– Ex: Feature 1
• Estimated initially at 3 SPs
• Estimated in man days at 6 days
• =>1 SP = 2 days
• Ask the team directly how they evaluate 1SP?
• Experience and measure
Calculate Sprints Velocity
22
Sprint 1 Sprint 2 Sprint 3
Person days in sprint = calendar days * team size
60 60 60
Ideal person days in sprint = person days in sprint * focus factor
42 42 42
Sprint ideal man days 1st sprint = (1-40%) * ideal person days 2nd sprint = (1-20%) * ideal person days 3rd sprint = ideal person days
25 33 42
Velocity = Sprint ideal man days/1 SP 16 22 28
Team size Focus Factor Sprint Size Calendar Days
1 SP?
6 70% 2 weeks 10 Days 1.5 Man Days
Simulate sprints
23
Backlog 5 SPs
3 SPs
8 SPs
13 SPs
1 SP
2 SP
1 SP
Sprint 1 3 SPs
1 SP
1 SP
5 SPs
2 SPs
2 SPs
1 SPs
Sprint 2
5 SPs
3 SPs
5 SPs
2 SPs
5 SPs
2 SPs
Sprint 3 3 SPs
5 SPs
3 SPs
5 SPs
1 SP
5 SPs
2 SPs
5 SPs
…
1st Sprint Velocity 16
SPs
2nd Sprint Velocity 22
SPs
2nd Sprint Velocity 28
SPs
Measure and re-estimate 1 SP?
24
• Ex: 1st sprint estimated at 16 SPs velocity
– After execution we deliver 12 SPs
– Do reverse calculations from the previous slides
Sprint 1 Sprint 2 Sprint 3 1 SP?
Before starting 1st Sprint 16 22 28 1.5
After 1st Sprint 12 16 21 2
After 2nd Sprint 12 16 21 2
Criteria for ordering the backlog
25
• 1st The risk which the story should diminish
• 2nd The uncertainty on client needs which the story should reduce
• 3rd The contribution to the product quality
• 4th The dependencies between stories
• 5th The utility of a story
Dealing with uncertainty
26
Demo inspired from http://blog.bobcravens.com/2011/05/4-principles-to-estimation-applied-to-software-development/
Estimate how long will the walking take?
Walking from Iasi to Bucharest
28
• Distance Iasi – Bucharest = 417 km
• Average walking velocity = 5.0 (km/h)
– http://en.wikipedia.org/wiki/Walking
• We estimate walking 8 hours per day
• ~ 10.5 days of walking from Iasi to Bucharest
Walking from Iasi to Bucharest
29
• Initial uncertainty is probably in hours or days
We walk from Iasi to Roman
Walking from Iasi to Bucharest
31
• Distance Iasi – Roman = ~86 km
• Real walking velocity = 4.0 (km/h)
• We’ve walked 6 hours per day
• ~ 3.6 days of walking from Iasi to Roman
Estimate from Roman to Bucharest?
Walking from Roman to Bucharest
33
• Distance Roman – Bucharest = ~331 km
• Estimated walking velocity = 4.0 (km/h)
• Estimated walking hours per day = 6
• ~ 14.8 days of walking from Roman to Bucharest
• Initial cycle time = 10.5 days of walking
• Total cycle time = 18.4 days of walking
Burn-down chart Iasi-Bucharest
34
What about agile planning poker?
35
• The most common estimation method known in the agile community
• The interest is in the discussions
What about agile planning poker?
36
• The most common estimation method known in the agile community
• The interest is in the discussions
Estimation issues hide higher problems!
37
-10
0
10
20
30
40
50
60
D1 D2 D3 D4 D5 D6 D7 D8 D9 D10
RAF
Ideal RAF
Sprint Backlog
38
1st Story 13 2nd Story 13 3rd Story 8 4th Story 8 5th Story 13
Observed issues
39
• Just technical stories/no user stories
• Stories didn’t correspond to INVEST criteria
• Waterfall approach in iterations
• Lack of Definition of Ready
• Definition of Done was not respected
• …
Start from the need of information
40
• Clients want to know when it will be ready, the budget…
– Ex: Continuous pulling systems like Kanban
=>use average Cycle Time instead
• TODO in another knowledge sharing session!
Cornel FATULESCU
agile coach Planning is Everything. Plans are Nothing.