44
PM Generation Methods and WO Projections (PPP06) PMs, Procedures, and Projects Track

PPP06 - PM Generation Methods and WO Projections

Embed Size (px)

DESCRIPTION

See an overview of the differences between automatic and manual generation of preventive maintenance schedules, and preview the Work Order Projections feature.

Citation preview

Page 1: PPP06 - PM Generation Methods and WO Projections

PM Generation Methods and WO Projections (PPP06)

PMs Procedures and Projects Track

1 Open Internet Explorer 2 Type into the address bar wwwmaintenanceconnectioncom 3 Click Log In button 4 Enter the following

Member ID PPP_CHECKPOINT Password Checkpoint2014

Note During the seminar please do not ldquoSaverdquo while following along with a specific example unless directed to do so by your course instructor

Wireless SSID CHECKPOINT Wireless Password CHECKPOINT

Logon Instructions

Presenter Name Brandon Palana

Background information

bull Role and expertise at Maintenance Connection

bull Fun Fact

Presenter Bio

PM Generation Defined

Generating PM Schedules

Work Order Projections

Agenda

PM Generation Overview

Automatic Generation

Manual Generation

PM Generation Preferences

PM Generation Defined

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 2: PPP06 - PM Generation Methods and WO Projections

1 Open Internet Explorer 2 Type into the address bar wwwmaintenanceconnectioncom 3 Click Log In button 4 Enter the following

Member ID PPP_CHECKPOINT Password Checkpoint2014

Note During the seminar please do not ldquoSaverdquo while following along with a specific example unless directed to do so by your course instructor

Wireless SSID CHECKPOINT Wireless Password CHECKPOINT

Logon Instructions

Presenter Name Brandon Palana

Background information

bull Role and expertise at Maintenance Connection

bull Fun Fact

Presenter Bio

PM Generation Defined

Generating PM Schedules

Work Order Projections

Agenda

PM Generation Overview

Automatic Generation

Manual Generation

PM Generation Preferences

PM Generation Defined

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 3: PPP06 - PM Generation Methods and WO Projections

Presenter Name Brandon Palana

Background information

bull Role and expertise at Maintenance Connection

bull Fun Fact

Presenter Bio

PM Generation Defined

Generating PM Schedules

Work Order Projections

Agenda

PM Generation Overview

Automatic Generation

Manual Generation

PM Generation Preferences

PM Generation Defined

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 4: PPP06 - PM Generation Methods and WO Projections

PM Generation Defined

Generating PM Schedules

Work Order Projections

Agenda

PM Generation Overview

Automatic Generation

Manual Generation

PM Generation Preferences

PM Generation Defined

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 5: PPP06 - PM Generation Methods and WO Projections

PM Generation Overview

Automatic Generation

Manual Generation

PM Generation Preferences

PM Generation Defined

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 6: PPP06 - PM Generation Methods and WO Projections

Schedules are used to generate Work Orders based on information from Automation tab

PM Generation Dialog used to manually generate and perform actions

PM Generation Overview

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 7: PPP06 - PM Generation Methods and WO Projections

Work Orders generated at night for automatic PM schedules

Can be set to automatically generate a specified number of days before due date

Automatic Generation

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 8: PPP06 - PM Generation Methods and WO Projections

Can be set to display notification on Home Page a specified number of days before due date

bull Notification appears under Preventive Maintenance Info section

Manual Generation

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 9: PPP06 - PM Generation Methods and WO Projections

Settings to generate for

bull Specific Repair Centers (or All)

bull Due or through date in future

bull Only on selected Work Days

Manual Generation (contrsquod)

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 10: PPP06 - PM Generation Methods and WO Projections

Manual Generation potential problems

bull Home Page notification may not be removed

bull ldquoAnother User is Generatinghelliprdquo

bull Automated generations may not generate

bull May not complete in reasonable time

Manual Generation (contrsquod)

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 11: PPP06 - PM Generation Methods and WO Projections

Tips for optimum processing

bull Limit Repair Centers

bull Generate for shorter periods of time

bull Generate one PM schedule at a time

Manual Generation (contrsquod)

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 12: PPP06 - PM Generation Methods and WO Projections

Three important Preferences

bull Generate Work Orders in background

bull Work Days (for when manually generating)

bull Suppress PM generation for Assets not In-Service

PM Generation Preferences

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 13: PPP06 - PM Generation Methods and WO Projections

Generate Work Orders Dialog

Preview

History

Undo PM Generation

Advanced

Generating PM Schedules

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 14: PPP06 - PM Generation Methods and WO Projections

Accessible from

bull PM record

bull Actions menu

bull PM Home Page

Generate Work Orders Dialog

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 15: PPP06 - PM Generation Methods and WO Projections

Repair Centers

bull Select Available Repair Center(s) to add

bull Selected Repair Center(s) will have Work Orders generated for it

Generate Work Orders Dialog (contrsquod)

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 16: PPP06 - PM Generation Methods and WO Projections

Generate into future

bull Only generate Work Orders due

bull Generate through future date

Generate Work Orders Dialog (contrsquod)

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 17: PPP06 - PM Generation Methods and WO Projections

Work Order scheduling

bull Non-Work Days (preferences)

bull Manual settings

Generate Work Orders Dialog (contrsquod)

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 18: PPP06 - PM Generation Methods and WO Projections

Generates list of Work Orders based on settings designated

Verify Work Order generations prior to actual generation

Preview

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 19: PPP06 - PM Generation Methods and WO Projections

List of generation history and detail

bull Name

bull Generated Date

bull WOs Generated and WOs Current

bull Undone

History

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 20: PPP06 - PM Generation Methods and WO Projections

Reverse or undo generation of Work Orders

Most recent generations must be undone prior to other generations

Undo PM Generation

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 21: PPP06 - PM Generation Methods and WO Projections

Processing Indicator can lock when PMs are manually generated

Reset processing indicator flag when PMs are not generating correctly

Advanced

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 22: PPP06 - PM Generation Methods and WO Projections

In this example a Monthly HVAC PM Schedule will go through the manual generation process

Manual PM Generation Example

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 23: PPP06 - PM Generation Methods and WO Projections

Schedule is set for every one month

Manual PM Generation Example (contrsquod)

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 24: PPP06 - PM Generation Methods and WO Projections

Automation tab set to display notification on home page three days before PM is due

Manual PM Generation Example (contrsquod)

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 25: PPP06 - PM Generation Methods and WO Projections

HVAC Assets have been added

Manual PM Generation Example (contrsquod)

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 26: PPP06 - PM Generation Methods and WO Projections

Generate Work Orders 3 months in advance

Manual PM Generation Example (contrsquod)

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 27: PPP06 - PM Generation Methods and WO Projections

Preview shows total of 9 Work Orders with Target Dates for next 3 months

Manual PM Generation Example (contrsquod)

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 28: PPP06 - PM Generation Methods and WO Projections

Work Order Projections Overview

Generate Work Order Projections File

Work Order Projection Reports

Delete Work Order Projections File

Work Order Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 29: PPP06 - PM Generation Methods and WO Projections

Supports management of maintenance resources

Anticipate WO generation based on PM schedules

Work Order Projections Overview

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 30: PPP06 - PM Generation Methods and WO Projections

Creates file of projections for viewing or analyzing using reports

Labor materials and other cost projections

One file maintained by each user

Work Order Projections Overview (contrsquod)

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 31: PPP06 - PM Generation Methods and WO Projections

Work Order Projection warning

Time out will cause

bull PM Assets Tab will show WO generated from projection as last generated WO

bull Last Generated Date used for determining date to generate next work order will be inaccurate

Work Order Projections Overview (contrsquod)

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 32: PPP06 - PM Generation Methods and WO Projections

Same controls as Generate Work Orders Dialog

Projection Info will create a name for projection file

Generate Work Order Projections File

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 33: PPP06 - PM Generation Methods and WO Projections

Projections generate similarly to PMs

Preview Dialog will display showing summary of Work Orders

Generate Work Order Projections File (contrsquod)

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 34: PPP06 - PM Generation Methods and WO Projections

Reporter can be used for summarizing costs labor utilization etc

Work Order (Projections) group contains Projection reports

Work Order Projection Reports

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 35: PPP06 - PM Generation Methods and WO Projections

Example of Work Order Projection Report

Work Order Projection Reports (contrsquod)

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 36: PPP06 - PM Generation Methods and WO Projections

Access Generate Work Order Projections Dialog

Select Delete button to delete current Projections file

Delete Work Order Projections File

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 37: PPP06 - PM Generation Methods and WO Projections

In this example an HVAC Monthly Check PM will have a Work Order Projection run for it to analyze Labor and Material Projection Reports

Work Order Projection Example

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 38: PPP06 - PM Generation Methods and WO Projections

Labor and Material Estimates have been added to Procedure for HVAC Monthly Check PM

Work Order Projection Example (contrsquod)

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 39: PPP06 - PM Generation Methods and WO Projections

Generate Work Order Projection

Work Order Projection Example (contrsquod)

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 40: PPP06 - PM Generation Methods and WO Projections

Work Order Projection by Labor Report

Work Order Projection Example (contrsquod)

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 41: PPP06 - PM Generation Methods and WO Projections

Work Order Projection with Materials Report

Work Order Projection Example (contrsquod)

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 42: PPP06 - PM Generation Methods and WO Projections

For access to documentation and tutorials reference wwwmcuserconnectcom

MC User Connect

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 43: PPP06 - PM Generation Methods and WO Projections

MCUC Documentation Tutorials Article PDF Video Tutorial

User Guide

PM and Projection Troubleshooting Guide

Generate Work Orders from PM Schedule

Generate Work Order Projections

Additional Resources

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip

Page 44: PPP06 - PM Generation Methods and WO Projections

Did you know you can take a Quiz to test your knowledge of todayrsquos content

bull Check it out on MC User Connect (wwwmcuserconnectcom)

bull Located in the MC eLearning folder PMs Procedures and Projects Course Quizzes

Test Your Knowledgehellip